Upload
damian-rose
View
216
Download
0
Tags:
Embed Size (px)
Citation preview
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
Module 6Specifications and Special Provisions
Traffic Control Plan Development Course
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
2
MnDOT Standard Specification for Construction Book (Spec Book)The “Spec Book” contains standard
specifications used and referred to in – Plans– Special Provisions
2014 Spec Book– includes numerous modifications to the
2005 Spec BookMnDOT produces a new Spec Book
on a 5 year cycle
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
3
Spec Book
Format of the Spec Book– The Spec Book is made of three
divisions:• Division I - General Requirements and
Covenants• Division II - Construction Details• Division III - Materials
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
4
Spec Book
DIVISION I — General Requirements and Covenants– Each Division I Specification number
begins with “1” (1101 – 1911)– Nine (9) sections– Section 1404 of Division I contains
information on Maintenance of Traffic
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
5
Spec Book
1404
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
6
Spec Book
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
7
Spec Book
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
8
1504 - Coordination of Plans and Specifications
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
9
Spec Book
DIVISION II — Construction Details– Each Division II Specification number
begins with “2” (2021 - 2582)– Six sections
1. General (2021 - 2051)2. Grading (2101 - 2131)3. Base Construction (2211- 2232)4. Pavement Construction (2301 - 2399)5. Bridges and Structures (2401 - 2481)6. Miscellaneous (2501 - 2582)
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
10
Spec Book
– Each section is generally divided into the following sections:1. Description2. Materials3. Construction Requirements4. Method of Measurement5. Basis of Payment
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
11
Spec Book
DIVISION III — Materials– Each Division III Specification number
begins with “3” (3101 - 3973)– Division is divided into eighteen
sections
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
12
MnDOT Contract Proposal
Contents– Each MnDOT project has a proposal– The proposal contains items such as:
• Addendums• Notices to Bidders• Appendices• Special Provisions (by division, for
example: Division A, Divisions S, Division SS, Division SL, Division ST, etc.)
• Attachments• Contract Schedule (Bid Prices)
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
13
Special Provisions
Special Provisions are defined as:– “Additions and revisions to the
Standard and Supplemental Specifications covering conditions peculiar to an individual project”
– Special Provisions are just that: “SPECIAL” provisions
– If an item(s) is adequately addressed or specified in the Spec Book, Standard Plates, Plan, or other Contract documents, then that item(s) should not be duplicated within the Special Provisions
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
14
Special Provisions
Topics that are always covered by Special Provisions include– Construction Start Dates– Completion Dates– Traffic Control– Special Pay Items
The Special Provisions need to cover every special pay item from the Plan
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
15
Special Provisions
Division S is for general projectsSpecial Provisions may be formatted into
more than one S section– Time and Traffic (Division S)
• S-1 Contact Information• S-2 (1404) Maintenance of Traffic and (2563) Traffic
Control• S-3 (1710) Traffic Control Devices• S-4 (1806) Determination and Extension of Contract
Time• S-5 (1807) Failure to Complete The Work on Time• S-6 (2563) Traffic Control Supervisor
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
16
Special Provisions
The following sections can be found in the Special Provisions:– Opening Descriptive Paragraph– General Section– Materials– Construction Requirements– Measurement and Payment
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
Special Provisions
Special Provision Boiler Plates– Standard special provisions have been
developed for use on MnDOT Construction projects
– The following is a handout of the “boilerplate” special provisions
17
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsInnovative Contracting incorporates
new practices to supplement traditional low-bid, design-bid-build contracting
Innovative Contracting Guidelines
18
Page 6-61
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsTypes of Processes
– A+B Bidding• A+B bidding reduces contract time on
projects• Contractors bid the time to complete the
project and a dollar amount for work items• The contract is awarded to the lowest
combination of time and cost.
19
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsTypes of Processes
– Lane-Rental• Lane-rental reduces impacts to the
traveling public by minimizing the time lanes are closed
• Contractors are charged a fee for closing lanes and shoulders due to construction activities
• The concept focuses on the time that the public is affected, NOT the overall contract time
20
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsTypes of Processes
– Incentives/Disincentives• The contractor is paid for early completion
of a project as provided for in the contract• If the contractor completes the project
later than the time allowed, disincentive money is subtracted from payments due
21
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsTypes of Processes
– Constructability Reviews• The industry provides valuable feedback
into key areas that the Agency may not be able to quantify during the project development process
• Feedback on preliminary plans has the potential to significantly reduce project costs and construction timelines
22
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsTypes of Processes
– Locked Incentive Date• A locked incentive date provides an
incentive if the contractor completes the work done early
• Contractors are not allowed any extensions in the completion date, regardless if extensions are owner caused or not
23
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsTypes of Processes
– Design-Build• Design and construction phases overlap,
allowing faster overall project delivery
24
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsTypes of Processes
– Pay-for-Performance• Pay-for-performance specifications rely on
final outcomes measured against performance criteria set forth in the contract
• If the contractor fails to meet minimum performance criteria, payment is withheld and corrective action is required
25
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsTypes of Processes
– Warranties• Warranties require contractors to
guarantee all or portions of a construction project to be free of defects in materials and workmanship for a period of time
• The contractor is required to correct deficiencies that occur during the warranty period.
26
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsTypes of Processes
– Critical Path Method (CPM Schedules)• Critical Path Method (CPM) schedules are
excellent tools for both the contractor and MnDOT to monitor contract time during a construction project
27
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy Innovative Contracting
MethodsMore Info
– A+B– Lane-Rental– Incentives/Disincentives– Constructability Reviews– Locked incentive Date– Design Build– Pay-for-Performance– Warranties– Critical Path Method
28
Offi
ce o
f Tr
affi
c, S
afe
ty a
nd
Tech
nolo
gy
End
Questions?Training CertificatesEmail ListEvaluation Forms
29