OFFICE OF
SCIENCE
Review of Critical Decision 3b for the
Large Liquid Argon Detector for Neutrino Physics (MicroBooNE)
Fermi National Accelerator LaboratoryFebruary 29 – March 1, 2012
Kurt W. FisherReview Committee Chair
Office of Science, U.S. Department of Energyhttp://www.science.doe.gov/opa/
OFFICE OF
SCIENCEReview Committee Participants
Department of Energy Subcommittee 1- Cryostat and Cryo-systemKurt W. Fisher, DOE, Chairperson *Joel Fuerst, ANL
Bruce Strauss, DOE/SC
Subcommittee 2- Detector and Electronics *Bill Wisniewski, SLAC
Karen Byrum, ANL
Observers Subcommittee 3- Infrastructure and InstallationAlan Harris, DOE/FSO *Victor Guarino, ANLTed Lavine, DOE/SC Eli Rosenberg, DOE/SC Subcommittee 4- Management, Cost, Schedule Paul Philp, DOE/FSO and ES&H *Jeff Sims, ANL
Gil Gilchriese, LBNLEthan Merrill, DOE/SC
2
OFFICE OF
SCIENCE
3
Department of EnergyOffice of the Secretary
Dr. Steven Chu, Secretary
Deputy Secretary* Daniel B. Poneman
Associate Deputy SecretaryMelvin G. Williams, Jr.
Office of the Under Secretary
for Nuclear Security
Thomas P. D’AgostinoUnder Secretary
For Nuclear Security
*The Deputy Secretary also serves as the Chief Operating Officer.
06 December, 2011
Energy InformationAdministration
Bonneville PowerAdministration
Southwestern PowerAdministration
Southeastern PowerAdministration
Western Area PowerAdministration
Intelligence andCounterintelligence
Assistant Secretary forPolicy and International
Affairs
Assistant Secretary forCongressional and
Intergovernmental Affairs
General Counsel
Chief FinancialOfficer
Chief Human CapitalOfficer
Chief InformationOfficer
Public Affairs
Economic ImpactAnd Diversity
Deputy Administratorfor Defense Programs
Deputy Under Secretaryfor Counter-terrorism
Associate Administratorfor Emergency
Operations
Associate Administratorfor Acquisition &
Project Management
Associate Administratorfor Defense Nuclear
Nonproliferation
Deputy Administratorfor Naval Reactors
Associate Administratorfor Defense Nuclear
Security
Office of the Under Secretary
for Science
VacantUnder Secretary
for Science
Office of Science
Advanced ScientificComputing Research
Basic Energy Sciences
Biological andEnvironmental Research
Fusion Energy Science
High Energy Physics
Nuclear Physics
Office of the Under Secretary
VacantUnder Secretary
Associate Administratorfor External Affairs
Workforce DevelopmentFor Teachers/Scientists
Management
Health Safety andSecurity
Hearings and Appeals
Advanced ResearchProjects Agency-Energy
Loans ProgramOffice
American Recovery &Reinvestment Act Office
Federal EnergyRegulatory Commission
Inspector General
Assistant Secretaryfor Environmental
Management
Assistant Secretaryfor
Fossil Energy
Legacy Management
Indian EnergyPolicy and Programs
Assistant Secretaryfor Energy Efficiency
and Renewable Energy
Assistant Secretaryfor Electrical Delivery and
Energy Reliability
Assistant Secretaryfor
Nuclear Energy
Associate Administratorfor Info. Management
& CIO
Associate Administratorfor Management &
Budget
Associate Administratorfor Safety & Health
Technology TransferCoordinator
Chief of Staff
National NuclearSecurity Administration
Hearings and Appeals
4
OFFICE OF
SCIENCEOffice of Science
Chicago Office
Roxanne Purucker
Office of the Director (SC-1)William F. Brinkman
Advanced ScientificComp. Research (SC-21)
Daniel Hitchcock
Workforce Development for Teachers/
Scientists (SC-27)
P. Dehmer (A)Basic Energy
Sciences (SC-22)Harriet Kung
Fusion EnergySciences (SC-24)
Edmund Synakowski
High EnergyPhysics (SC-25)James Siegrist
Biological & Environ. Research (SC-23)
Sharlene Weatherwax
Nuclear Physics(SC-26)
Timothy Hallman (A) Acting
12/2011
Deputy Directorfor Science Programs (SC-2)
Patricia Dehmer
Deputy Directorfor Resource Management (SC-4)
Jeffrey Salmon
Deputy Directorfor Field Operations (SC-3)
Joseph McBrearty
Office of Project
Assessment (SC-28)Daniel
Lehman
Office of Budget (SC-41)
Kathleen Klausing
Office of Scientific and Tech. Info. (SC-44)
Walt Warnick
Office of SC Program Direction (SC-46)
Rebecca Kelley
Office of Grants/ Cont. Support (SC-43)Linda Shariati
Office of Business Policy
& Ops (SC-45)
J. Salmon (A)
SC Communications & Public Affairs
(SC-4)Dolline Hatchett
Ames SOCynthia Baebler
Thomas Jeff. SOJoe Arango
Stanford SOPaul Golan
Pacific NWest SORoger Snyder
Princeton SOMaria Dikeakos
Oak Ridge SOJohnny Moore
Fermi SOMichael Weis
Brookhaven SOMichael Holland
Berkeley SOAundra Richards
Argonne SOJoanna Livengood
SCIntegratedSupportCenter
Office of Lab
Policy & Evaluat.(SC-32)D. Streit
Office of Safety,
Security & Infra.(SC-31)
M. Jones
Human Resources & Admin.(SC-45.3)
Cynthia Mays
Small BusinessInnovationResearch(SC-29)
Manny Oliver
Oak Ridge Office
J. Eschenberg (A)
5
OFFICE OF
SCIENCECharge Questions
1. Final Design: Is the design sufficiently mature so that the project can continue with procurement and fabrication? Baseline Cost and Schedule: Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? Is the contingency adequate for the risks?
2. Management: Evaluate the management structure as to its adequacy to deliver the proposed final design within the baselines as identified in the PEP. Has there been adequate progress on the fabrication activities approved under CD-3a?
3. Has the project responded satisfactorily to the recommendations from the previous independent project review?
6
OFFICE OF
SCIENCEReport Outline/ Writing Assignments
Executive Summary Fisher
1. Introduction Lavine
2. Technical Status (Charge Questions 1, 3)
2.1 Cryostat and Cryo-System Fuerst*/Strauss
2.1.1 Findings
2.1.2 Comments
2.1.3 Recommendations
2.2 Detector Wisniewski*/Byrum
3. Infrastructure and Installation (Charge Questions 1, 2, 3) Guarino*
4. Management , Cost, Schedule and ES&H(Charge Questions 2, 3)
Sims*/Gilchriese/Merrill
*Lead
7
OFFICE OF
SCIENCEExpectations
Present closeout reports in PowerPoint. Forward your sections for each review report
(in MSWord format) to Casey Clark, [email protected],
by March 5, 8:00 a.m. (EDT).
OFFICE OF
SCIENCE2.1 Cryostat and Cryo-SystemFuerst, ANL/Strauss, DOE/SC
1. Final Design: Is the design sufficiently mature so that the project can continue with procurement and fabrication? Baseline Cost and Schedule: Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? Is the contingency adequate for the risks? Yes.
3. Has the project responded satisfactorily to the recommendations from the previous independent project review? Yes
8
OFFICE OF
SCIENCE2.1 Cryostat and Cryo-SystemFuerst, ANL/Strauss, DOE/SC
9
Findings• LAr pumps, cooldown compressor, and heat exchanger (long-
lead procurements) are on order.• The cryostat bid package is complete.• The LAr fill is not a KPP.• “Piston purge” has proven successful in LAPD and will be used
instead of evacuation for initial cryostat purification.• The welded (vs. flanged) cryostat head design choice has been
made.• A thorough Hazard Analysis Review exists including cryogenics
ODH.
OFFICE OF
SCIENCE2.1 Cryostat and Cryo-SystemFuerst, ANL/Strauss, DOE/SC
10
Comments• There may be additional risk associated with failure of the long-
lead cryogenic rotating machinery in the absence of on-hand spare parts.
• The cryostat bid package should continue to be expedited to enhance the schedule.
• A strategy for LAr removal should be considered.
Recommendations1) By 15MAR2012, consider ordering the recommended spare
parts kit (or a reasonable subset thereof) for the cooldown compressor.
OFFICE OF
SCIENCE
11
3. Infrastructure and InstallationGuarino, ANL
1. Final Design: Is the design sufficiently mature so that the project can continue with procurement and fabrication? YES Baseline Cost and Schedule: Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? Is the contingency adequate for the risks? YES
2. Management: Evaluate the management structure as to its adequacy to deliver the proposed final design within the baselines as identified in the PEP. Has there been adequate progress on the fabrication activities approved under CD-3a? YES
3. Has the project responded satisfactorily to the recommendations from the previous independent project review? YES
OFFICE OF
SCIENCE3. Infrastructure and Installation
Guarino, ANL
12
FindingsThe group has performed a many tests of wire strength and has changed the diameter of the pins and applied tension as a result. A cold test of the wire assembly has been performed. The infrastructure for TPC assembly is well underway.The group has a good plan for TPC installation and cryogenics assemblyThe group has solid QA procedures and processes defined.
CommentsThe TPC assembly manpower relies on university labor and approximately 1FTE of a FNAL technician. For continuity, efficiency, and quality the group should consider using a minimum of 2 dedicated techs throughout the TPC assembly process.The re-welding of the flange and potential damage to the electronics is a concern and some testing might be warranted
RecommendationsNone
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
13
Detector & Electronics review scope includes PMT (WBS 1.8), TPC (1.4), Front End Electronics (1.5); Electronics Readout (1.11), DAQ / Monitoring & Slow Control (1.9) and some of infrastructure. PMT, TPC and Electronics Readout are in-kind contributions funded by NSF. FEE and DAQ are DOE funded.
The Committee commends the team on continued progress since the last review.
1. Final Design: Is the design sufficiently mature so that the project can continue with procurement and fabrication? Baseline Cost and Schedule: Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? Is the contingency adequate for the risks?
The design is sufficiently mature to continue with procurement and fabrication. Cost performance since the last review has been good, using little contingency and allowing fractional contingency on work remaining to increase. Contingency is adequate to the risks.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
14
3. Has the project responded satisfactorily to the recommendations from the previous independent project review?
There were no recommendations for the experimental team at the last review. However, there were Comments. The team has addressed these as if they were recommendations, and have made satisfactory response.
Findings: PMT has continued to make progress. Key components are in hand,
with all remaining materials to be purchased soon. Costs are close to estimates. SHV connectors have been found to be unreliable when cold. New
cabling solutions, possibly with no intermediate cold connections, are under consideration.
Optical simulations have been performed and indicate that typically 10 PE can be seen in most of the TPC volume.
All PMTs have been tested in air.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
15
Findings: PMT:
The PMT LN2 test stand is in now in use. 4 PMTs can be tested simultaneously. Gain vs HV is measured using an LED calibrator.
Cold test procedures passed safety review, allowing unattended cold tests to be performed.
Cold tests are expected to be complete by the start of CY2012Q4 A long full PMT unit test is planned to follow. WLS degradation on the plate has been found to be due to light, not
humidity. Care will be taken to limit exposure to light after plate painting; in particular, the assembly tent lights will be UV filtered.
Fabrication will commence in CY2013Q1, under the current schedule, with PMT unit assembly complete in Q4.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
16
Findings: TPC:
Work since the last review has been focused on completing drawings for the TPC components, winding machines and tension devices.
The first wire winding machine has been assembled and tested. Teams at Yale and Syracuse have been trained. The first machine is now at Syracuse ready for use. This is about a month later than expected at the time of the last review. Yale’s line will start in a month
The wire carriers have been refined (thicker pins, bigger resistors, smaller caps, simpler connections
A wire catcher system will not be used. Instead, the QA program was expanded. In the process, a cold test of the full-length wire carrier assembly has been successfully performed, and no breakage found up to 2.5kg (tension below yield point).
Milestones were adjusted to reflect sequential release of TPC component part POs, allowing revision of parts for the Cathode. Anode parts are in fab, and field cage tubes out for quote.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
17
Findings: TPC:
Wire winding is expected to be complete by CY2012Q4, with other parts fab’d on the same time scale, and delivered to Fermilab.
There appears to be adequate manpower to complete the task. Wire breakage is not expected to be a problems after the extensive test program and under the QA program. There is a tension safety factor of 4.5 (RT) to 6 (LN2).
Front end electronics: FEE prototype cycle 1 development was finished and successfully
tested. Development of the cycle 2 prototype, which is the pre-production prototype, is almost complete, with preparations for testing the electronics for a full TPC feed-through in progress. Many boards have already been fab’d and tested toward this goal. A 2nd prototype TPC signal feed-through has been produced, as well as cables, and a power supply candidate ordered.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
18
Findings: Front end electronics:
The CMOS front end ASIC 3rd version was received in late Oct. 2011. Thirty-eight were warm tested. Eight, mounted on a motherboard, have been cold tested through more than 50 LN2 immersions. The ASIC was found to function with increased gain and lower noise.
A 4th ASIC cycle will be submitted in early March to address fabrication issues: channel-to-channel variations for two chips is +/-4% (higher than expected); defects seen at one edge of the chips; chip level yield of ~60% with single channel yield of 97%. More conservative design rules will be used. Options are being considered to mitigate the cost and schedule impact of this unexpected extra ASIC cycle.
Readout Electronics: The Front End Module was tested with TPC FEE prototypes. ADC data
was received correctly, calibration triggers could be propagated through the system. Baseline noise, cross-talk and linearity were measured.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
19
Findings: Readout Electronics:
The PMT electronics chain, which operates at a higher frequency, was also tested: the shaper can send data to the PMT ADC, where it was successfully digitized; the FEM can receive that data and generate a trigger. Proto 2 tests are on the horizon.
Production of components has begun, with completion expected February 2013.
DAQ is responsible for assembling events into a file, as well as monitoring and control, run control, calibration sequencing, file management.
Glomation has been selected as the slow monitoring and control hub. PCIe functionality, network, and calibration process were specified.
PCIe testing is being carried out on Fermilab and Nevis test stands. Calibration Hardware Interface code was developed. Event building is largely finished, including MicroBooNE specific fake
data files.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
20
Findings: DAQ:
Processes for Online monitoring and EPICs issues are understood, with IOCs accessing shared memory.
Relying on experience from PHENIX, ATLAS, NOvA, DoubleChooz and D0.
The D0 Assembly Building test stand is imminent. CD resources have been identified. The consequent rework of the
schedule is in progress, and was unavailable to the Committee. Hardware costs and purchase sequencing are well understood.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
21
Comments: PMT has continued to make progress. Most components are in hand,
and the schedule of work moving forward is not demanding, but does merit continuing attention.
TPC has been very aggressive in understanding wire issues. Cold tests have been performed on the full length wire system. The stringing tension has been reduced to provide more headroom at room temperatures and at LN2 temperatures. The team has put heavy emphasis on QA. The Committee commends the team on this work. In light of what has been learned in this program, the decision to dispense with the complications of a wire catcher system is reasonable.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
22
Comments: The TPC group is aware of the consequences of an approximate 4
month shut down if a wire should break once the experiment is taking data.
The current TPC cost projection is consistent with the approved baseline. The group identifies the biggest risk to be one of the wire winding assemblies not working and wire breakage rate being larger than expected. Mitigation in both cases relies on the team working longer and spreading the load between the two groups.
While there appears to be enough manpower available, a detailed schedule utilizing this manpower is missing.
Solid progress continues in Readout Electronics. The full chain prototype readout is an important forward step and its success is welcome.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
23
Comments: DAQ has made good progress on design. Purchase planning has
received adequate attention. ‘Construction’ is starting. The status of manpower after the negotiations with CD, as well as the consequent schedule changes, was not clear to the committee. The team is encouraged to develop a clearer path forward here.
Front End Electronics has in general made good progress in moving forward, developing the front end boards through to the pre-production stage. The ASIC presents complications in this picture.
Since the 3rd version of the CMOS ASIC would be acceptable, though not preferred, for the needs of the experiment, the suite of tests to fully characterize this version of the ASIC should be carried out on the remaining chips. This will mitigate the risk if the 4th version has serious problems: there will at least be one solution available for production. The schedule consequences on the project’s schedule should be evaluated.
OFFICE OF
SCIENCE2.2 Detector and ElectronicsWisniewski, SLAC/Byrum, ANL
24
Recommendations1. Execute the complete suite of tests to fully characterize Version 3 of the
ASIC. 2. Understand the effects of Version 4 of the ASIC on the project
schedule.3. Conduct a design review of the ASIC before submission of the
production run.
4. Approve CD-3b
OFFICE OF
SCIENCE
25
MicroBooNE Project StatusSims, ANL/Gilchriese, LBNL/
Merrill, DOE/SC
PROJECT STATUS as of January 2012Project Type MIE / Line Item / Cooperative AgreementCD-1 Planned: Actual: 7/9/2010CD-2 Planned: Actual: 9/27/2011CD-3a Planned: Actual: 9/27/2011CD-3b Baseline: June 2012 Actual: CD-4 Baseline: Sept 2015 Actual: TPC Percent Complete Planned: 30.8% Actual: 29.3%TPC Cost to Date $4.629M
TPC Committed to Date $4.989M TPC $19.9MTEC $14.76MContingency Cost (w/Mgmt Reserve) $4.286M 38% to goContingency Schedule on CD-4 18 months 41.9%CPI Cumulative 0.99
SPI Cumulative 0.95
OFFICE OF
SCIENCE
26
4. Management, Cost, Schedule and ES&H
Sims, ANL/Gilchriese, LBNL/Merrill, DOE/SC
2. Management: Evaluate the management structure as to its adequacy to deliver the proposed final design within the baselines as identified in the PEP. Has there been adequate progress on the fabrication activities approved under CD-3a? Yes, CD-3a scope appears to be on schedule.
3. Has the project responded satisfactorily to the recommendations from the previous independent project review? Yes. CR-019 for ASIC replan is still in progress
OFFICE OF
SCIENCE
27
4. Management, Cost, Schedule and ES&H
Sims, ANL/Gilchriese, LBNL/Merrill, DOE/SC
4.1 Findings
• The GPP funded facility LARTF is under construction and ahead of schedule with
nearly 6 months of float off the Microboone critical path
• The OPC scope is substantially complete.
• The project presented the change request that is being prepared to revise the logic
and durations related to front end electronics. This change may reduce the current 18
months of project float on CD-4 to 12 months.
• The TEC scope design is complete and the cryostat related items are in the
solicitation phase.
• A detailed analysis of schedule and cost using Monte Carlo was performed which
confirmed the current cost and schedule contingency.
OFFICE OF
SCIENCE
28
4. Management, Cost, Schedule and ES&H
Sims, ANL/Gilchriese, LBNL/Merrill, DOE/SC
4.1 Findings
• Quality Assurance modules with detailed procedures and requirements for each level
2 work package were presented.
• There are 36 active risks that are updated quarterly.
• A Project Hazard Analysis and Environment Safety and Health Plan have been
developed for all assembly and installation activities.
• Project schedule has been updated incorporating all changes through February 2012
• The project schedule has ~400 total remaining activities, ~ 60 activities on the
critical path, and ~100 activities within 30 days of the critical path.
• Critical Path has shifted to Front End Electronics followed by Installation.
• MIE funding in FY12 is $6.0M. The program will convert FY11 carry over
(approximately $3M) to MIE funds to meet planned obligations
• The project has processed ~$100K in changes since CD-2/3a in September 2011
OFFICE OF
SCIENCE
29
4. Management, Cost, Schedule and ES&H
Sims, ANL/Gilchriese, LBNL/Merrill, DOE/SC
4.2 Comments
• The project management team is complete and functioning very well. The team
should be commended on its vigilance in project management processes.
• The management structure and team appears adequate to deliver the baseline
design.
• There has been adequate progress on the activities approved under CD-3a.
• As of January, contingency of about $4M remains for an ETC of about $11M.
• There appears to be adequate float between the forecast project completion and the
CD4 milestone, even after including the delays expected from a fourth round of
front-end ASIC fabrication and testing that is not yet in the baseline schedule.
• QA processes and plans are well developed for a project of this scope
OFFICE OF
SCIENCE
30
4. Management, Cost, Schedule and ES&H
Sims, ANL/Gilchriese, LBNL/Merrill, DOE/SC
4.2 Comments
• Additional resource loading of student and scientific staff is needed, primarily in the
areas of assembly and installation labor.
• CR-19 related to the ASIC front end electronics should be processed promptly.
• A call on remaining contingency could be as high as $0.9M (25 % of current
contingency) for the procurement and testing of front-end ASIC round 4. Almost all
of this results from personnel costs (project management, engineering) maintained
for approximately an additional 6 months to complete the project. With project
management excluded contingency is approximately 30% on remaining work.
• Contingency needs should be re-evaluated after major procurements are placed in
FY2012.
OFFICE OF
SCIENCE
31
4. Management, Cost, Schedule and ES&H
Sims, ANL/Gilchriese, LBNL/Merrill, DOE/SC
4.2 Comments
• A risk review and status effort should be performed about once per month as the
project progresses. The status should use the risk registry, include mitigation steps
from the risk owners and address risks by both timeliness and impact.
• The QA modules should be signed by the L2 and related managers to ensure
concurrence and acceptance.
• The current prediction of completion of the LARTF as much 6 months ahead of the
project critical path is commendable. The project should leverage this float to
prepare the LARTF with MicroBooNE specific needs.
• The assembly and installation L2 managers must be very vigilant to ensure the
visiting team members are properly trained and adhere to Fermilab safety
procedures .
• Develop a plan to utilize potential unused contingency at the end of the project.
OFFICE OF
SCIENCE
32
4. Management, Cost, Schedule and ES&H
Sims, ANL/Gilchriese, LBNL/Merrill, DOE/SC
4.2 Comments
• 25% of project activities are on or near critical path. This should be monitored to
ensure the percentage does not increase.
• The project is cautioned against over-reliance on the risk simulations
OFFICE OF
SCIENCE
33
4. Management, Cost, Schedule and ES&H
Sims, ANL/Gilchriese, LBNL/Merrill, DOE/SC
4.3 Recommendations
1. Update the schedule and cost to include the impact of the run 4 ASIC fabrication
and test cycle and initiate change control actions to make the updated schedule/cost
the basis prior to CD-3b.
2. Sign off on Quality Assurance modules by L2 and related managers should be
completed prior to CD-3b