OFFICE OF
SCIENCE2.3 Infrastructure and Installation
Sims, Edwards
1. Does the conceptual design and planned implementation satisfy the performance specifications required to meet the project objectives? Yes
5. Is the DOE project scope well defined within the DOE and NSF funded collaboration? Are all the other parts of the project understood to be the responsibility of the other collaborators? Yes, however more effort is needed to develop the exact scope of the installation work.
6. Is the documentation required by DOE O413.3A in order and ready for approval of the Critical Decision 1? Yes
Experimental Infrastructure- WBS 1.6Findings • The infrastructure program is based on science experiment requirements.
ODH (exiting /egress) is a key focus of the conceptual design.• Three alternates were investigated in conceptual design. Reuse of the
MBD (Mini BooNE Detector) Hall was chosen. • WBS 1.6 is estimated to cost $3M ($2.1 construction contract) plus $1.2M
(40%) contingency.
2
OFFICE OF
SCIENCE2.3 Infrastructure and Installation
Sims, Edwards
Experimental Infrastructure- WBS 1.6 (Continued)Findings• Construction is planned to begin in February 2012 and take 9 months to
complete. • MBD Hall decommissioning (roof removal and tank removal) is not in the
MicroBooNE project scope. • Design and project development for this decommissioning work has not
begun and costs for the decommissioning work are not well understood.Comments• The WBS 1.6 team is very experienced and the conceptual design is
appropriately mature for CD-1.• The lack of progress on the design of the MBD Hall decommissioning
project adds risk to WBS 1.6 because of potential uncertainties in the interface scope, cost and schedule.
• The project should avoid starting the site preparation (wall extension and new roof) activities in the winter weather periods.
3
OFFICE OF
SCIENCE2.3 Infrastructure and Installation
Sims, Edwards
Experimental Infrastructure- WBS 1.6 (Continued)Comments• Discrepancies were discovered when comparing the cost tables and basis
of estimate (BoE) documents that were presented. The team should make a concerted effort to compile and present a consistent set of cost tables and BoE prior to the CD-1 ESAAB
• The project needs to fully understand the scope and schedule of the MBD Hall decommissioning project (soil, roof, equipment and tank removal).
• The MicroBooNE project should in turn utilize the developed decommissioning scope, cost and schedule to refine the WBS 1.6 plan and reconfirm the viability of the selected alternative (reuse of the MBD Hall).
• Consider the potential cost and schedule advantages of issuing a single contract for decommissioning and MicroBoone infrastructure and outfitting (WBS 1.6).
4
OFFICE OF
SCIENCE2.3 Infrastructure and Installation
Sims, Edwards
Experimental Infrastructure- WBS 1.6 (Continued)Recommendations1. Initiate with Fermilab Management a Mini BoonE Detector Hall
decommissioning plan and implement by CD-2.
OFFICE OF
SCIENCE2.3 Infrastructure and Installation
Sims, Edwards
5
Experiment Installation - WBS 1.7Findings• WBS well organized with documentation, planning, preassembly,
installation & commissioning all included• The Installation technical team (pool at FNAL) is well experienced • It was stated that Installation planning and interface definitions will be
completed through meetings with minutes (to capture agreements).• Cost estimate was done “bottoms up” and includes $499K in FNAL labor
and $270K in M&S (or $769K base) plus 38% ($302K) contingency • The costs for Installation have increased 50% since the Directors review
last November • Installation is on the critical path – it is where all elements come together
and is also driven by the civil site being ready.• The risks identified were damage to detector elements during pre assembly
and transportation to the detector hall as well as the MiniBooNE hall not being ready and conflicts in availability of key installation personnel.
OFFICE OF
SCIENCE2.3 Infrastructure and Installation
Sims, Edwards
6
Experiment Installation - WBS 1.7 (Continued)Comments• The WBS 1.7 team is very experienced and the conceptual design is
appropriately mature for CD-1.• Assembly and Installation is an integration task and it will require a
great deal of communication – meetings, workshops and reviews with formalized documentation and agreements.
• Capturing the full scope of installation, including well defined interfaces, is difficult when the experiment has not yet been fully defined in some detail
• Given this situation, the cost estimate appears to be somewhat optimistic.
• The estimates may be improved if a database of the vast Fermilab cost knowledge from past assembly/installation efforts was made available.
• Contingency appears to be optimistic at this point (pre CD-2 definition) • The schedule durations are perhaps adequate, but only if you can
assume that the resources are available as planned/needed
OFFICE OF
SCIENCE2.3 Infrastructure and Installation
Sims, Edwards
7
Experiment Installation - WBS 1.7 (Continued)
Recommendations
1) Develop an integrated approach to capture and review plans, hazards and mitigations, associated with installation before CD-2
2) Re-evaluate the cost and schedule, after more design and installation
planning progress has been made, in preparation for CD-2