Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
OFF GRID SOLAR POWER SOLUTION FOR TTK
PRESTIGE DETAILED PROJECT REPORT
Page 2 of 31
TABLE OF CONTENTS
GLOSSARY OF TERMS .................................................................................................................................... 3
EXECUTIVE SUMMARY .................................................................................................................................. 5
INTRODUCTION ............................................................................................................................................. 7
MANAGEMENT OBJECTIVES FOR INSTALLING SOLAR POWER ................................................................... 10
DEMAND ANALYSIS & JUSTIFICATION OF THE PROJECT ............................................................................. 12
SYNOPSIS OF THE PROJECT ......................................................................................................................... 15
OPERATION METHODOLOGY ..................................................................................................................... 19
IMPLEMENTATION METHODOLOGY .......................................................................................................... 23
ABOUT SUN BEST ........................................................................................................................................ 34
CONCLUSION ............................................................................................................................................... 38
Page 3 of 31
GLOSSARY OF TERMS
Photovoltaic: The physical effect of direct Conversion of light (sunlight) to electrical energy.
PV Cell: The smallest photovoltaic (PV) element that generates
electricity from light.
PV Module: A collection of interconnected PV cells, encapsulated between protective materials such as glass and back
sheet (Poly Vinyl Fluoride) or glass and glass, and mounted in an aluminum frame. This is a hermetically
sealed unit.
Array: Several strings of modules with the same orientation and tilt angle, located together.
Inverter: An electronic device that converts direct current electricity into alternating current electricity suitable
for feeding directly to the electrical grid or to normal AC loads.
Insolation: It is a measure of solar radiation energy received on a
given surface area in a given time. It is commonly expressed as average irradiance in watts per square meter (W/m²) or kilowatt-hours per square meter per
day (kWh/ (m² day)) (or hours/day).
Mounting Structure: Device used to hold modules in place, at desired angle
& direction.
Power Evacuation: Power generated from Solar PV Power Plant is transmitted to a point (sub-station) where it is
distributed for consumer use.
Sub-station: The place where the generated power from solar is synchronized with utility grid and metered.
Control Room: Room housing control equipment.
Cable: A conductor with one or more strands bound together,
used for transmitting electrical energy.
Junction Box: Inputs of several strings are connected to this box and taken as single output.
Page 4 of 31
Current: A flow of electricity through a conductor measured in Amps.
Voltage: The rate at which energy is drawn from a source that produces a flow of electricity in a circuit; expressed in
volts. It is the difference of electrical potential between two points of an electrical or electronic circuit, expressed in volts. It is the measurement of the
potential for an electric field to cause an electric current in an electrical conductor.
Lightning Arrestor: Device used to protect all the components from
lightning strikes.
Transformer: An electrical device by which alternating current of one
voltage is changed to another voltage.
Grid: A system of high/ low tension cables by which electrical power is distributed throughout a region.
Page 5 of 31
EXECUTIVE SUMMARY
TTK Prestige has a manufacturing unit in Myleripalayam near Coimbatore.
The factory has a limited sanctioned load of 490KVA from TNEB while the peak
connected load is 810KVA. The additional power is currently being met by a set
of 2 x 320KVA & 1 x 1010KVA Diesel Generators. With the cost of diesel rising
rapidly, the company is planning to install a solar power plant that will power
100 KW load during sunny period with battery back up so as to minimize the
use of at least one 320KVA DG and get considerable savings on diesel costs.
This DPR provides technical details and overall costs/calculation for the
feasibility of the project. The proposed solution will provide solar power as a
standalone off-grid solution to power 100 KW load of the factory during sunny
Page 6 of 31
period with battery backup. The system will able to provide 75 -80% of load.
With this the objective to avoid running the 320KVA DG will be met for at least
290 days per year.
The layout of the proposed solar power plant is given in the figure below:
100
100 KVA
Solar output 100 KW
Page 7 of 31
The following table gives the summary of the proposed project:
Targeted Load Factory Loads
Connected Load 810KVA (648 KW)
Proposed Solar Plant 100 KW
Area Required 10,000 Sq Ft of Un-shaded Space
(space available above Factory Polish area & Canteen roof)
Annual Solar Energy Generation 1.66 Lakh Units Per Year
Solar Project Cost*** Rs.165.1 Lakhs*
Government subsidy** Rs. 49.53 Lakhs
Tax benefit Rs. 47.94 Lakhs
Net investment Rs. 68.04 Lakhs
ROI without subsidy for diesel replacement
3.95 Years
ROI with subsidy for diesel replacement
2.26 Years
.
Page 8 of 31
INTRODUCTION
Power is a vital input for economic development and sustenance of modern
economy. However, providing adequate and clean power to face the ever-
growing environmental degradation has been a great challenge of the current
century. Renewable energy does not pollute the environment; the way burning
of fossil fuels does. Renewable energy sources are limitless and will not be
exhausted though fossil fuel will be gradually exhausted in course of time.
The financial cost of Renewable energy applications is not always cheap but if
the environmental costs of using fossil are accounted for, renewable energy
wins hands-down. There are also indirect savings on health costs as there
are no harmful emissions.
India is a tropical country and has abundant Solar Isolation throughout the
country for most part of the year. Since the seasonal variation is marginal
solar energy can be harnessed economically throughout the year.
Shortage of power is a critical problem faced by Indian industries, and with the
Indian industry growing at a hectic pace, this deficit is even more harmful.
Major industries are energy intensive in nature and thus power costs form the
most critical cost component.
Many large companies have resorted to having their own captive power plants.
Many industries rely to a large extent on diesel for additional power. With the
cost of diesel increasing rapidly, it is becoming economically unviable to
continue to run on diesel generators. With the prices of Solar PV becoming
attractive, several industries are considering solar energy to replace their diesel
generators.
Page 9 of 31
In Summary, the benefits of using solar PV are:
Solar power will reduce the cost of production as it is cheaper than
diesel with a payback of around 2.26 years.
Solar power will augment the needs of peak power needs of the factory
Incentives are available from the Government for setting up solar power
plants like Subsidy, Accelerated Depreciation & Renewable Energy
Certificates
Solar power will help in meeting the Solar Purchas Obligation of the
TN state government.
Power from the sun is clean, silent, limitless and free
Photovoltaic process release no CO2, SO2 or NO2 gases which are
normally associated with burning finite fossil fuel reserves and do not
contribute to global warming
Photovoltaic’s are now a proven technology which is inherently
safe as opposed to other fossil fuel based electricity generating
technologies
Increase the grid reliability (i.e. voltage and frequency)
Reduce the transmission line losses
Page 10 of 31
MANAGEMENT OBJECTIVES FOR INSTALLING SOLAR POWER
HIGH COST OF RUNNING DIESEL GENERATORS IMPACTING
BOTTOM LINE
TTK Prestige has a sanctioned load of 490 KVA while the connected load is as
high as 810KVA. In order to overcome the demand the factory is using a set of
2 x 320KVA & 1 x 1010KVA Diesel Generators. Over the last 10 years diesel
prices have increased by 158% at a compound rate of approximately 16% per
annum. With diesel prices becoming deregulated, the cost of using diesel is
expected to go up rapidly. At current bulk purchase prices, the cost of using
diesel is around Rs. 20 per unit. At this cost the payback by using solar to
replace DG is very attractive at around 2.26 years.
The chart below depicts the increase in retail price of diesel over the last
decade. Ref: www.mypetrolprice.com
Page 11 of 31
SOLAR PURCHASE OBLIGATION
In its recent Policy statement TN Government has introduced a Solar Purchase
Obligation of 6% for all HT consumers with effect from Jan 2014. The
obligated consumers may fulfill the SPO by:
Generating captive solar power in TN equivalent or more than their SPO
Buying equivalent to or more than their SPO from other third party
developers in TN
Buying RECs generated by solar projects in TN
Purchasing power from TANGEDCO at Solar Tariff
ENVIRONMENTAL CONCERNS
The company policy is to ensure healthy, safe and secure environment for its
employees. The Green Energy produced by solar power will not only help the
company in meeting its energy demands but would also help in meeting
international standards.
Page 12 of 31
DEMAND ANALYSIS & JUSTIFICATION OF THE PROJECT
SOLAR POWER POTENTIAL IN INDIA
India is located in a sunny belt of the earth, receiving abundant radiant energy
from the sun. The daily average global radiation is around 5.0 kWh/m2 in north-
eastern and hilly areas to about 7.0 kWh/m2 in western regions and hot dessert areas
with the sunshine hours ranging between 2300 and 3200 per year. In most parts of
India, clear sunny weather is experienced for 250 to 300 days a year. The annual global
radiation varies from 1600 to 2200 kWh/m2.
Page 13 of 31
PROJECT LOCATION IN TAMILNADU
Tamilnadu has high solar insolation (5.6 to 6.0 kWh/sq mt) with more than
300 clear sunny days in a year. With substantial solar insolation and declining
solar power costs there is a remarkable opportunity in the solar energy domain.
Page 14 of 31
Page 15 of 31
SYNOPSIS OF THE PROJECT
AVAILABLE DATA
Location of the Plant Mayileripalayam, Coimbatore
Site Coordinates Lat: 10.87
Long: 77.00
Sanctioned Load 490KVA
Connected Load 810KVA
Power Cut 5 Hrs
Avg TNEB Bill over last 7 months Rs. 4.5 Lakhs per month
Avg. Cost of Grid Per Unit Rs. 7.5 Per Unit
Avg. Cost of Diesel Per Unit *Rs. 18 Per Unit
Roof Area Available Factory Policsh Area: 1860 Sq Mt
(20,020 Sq Ft)
Canteen Area: 1050Sq MT (11302
Sq Ft)
Total Area: 31,322 Sq Ft
* The bulk price of diesel is currently at Rs.60/liter. The 320KVA generator
consumes around 40 liters per hour which is equivalent to Rs. 83.5 Lakhs per
year. As this solution is designed to replace the 320DG for most of the year, we
have taken this annual cost of diesel for 320KVA DG for calculating the
payback.
Page 16 of 31
ESTIMATED SOLAR POWER GENERATION FROM THE PROPOSED
PLANTS
As per the historical data available with Central Energy Regulatory
Commission (CERC) of India solar power plants based in India have
demonstrated a PLF of 19%. At 19% PLF the annual solar power generation for
100KW solar plant is 166 MWh.
PAYBACK ANALYSIS
ASSUMPTIONS
As the solution is primarily designed to avoid running the 320KVA DG,
the payback of the solution is based on comparing the solar costs with
the diesel cost
Base Price of diesel is taken at Rs. 60/liter which is the current market
price for bulk consumers
Diesel cost is increased by 10% every year as per historical data given
above.
Maintenance of Diesel Generator (as given by the company managers)
has been taken at Rs. 0.50/kWH.
Based on the bills of the last 6 months, the average cost of electricity
from TNEB is Rs. 7.5/unit
Last year the electricity prices were increases by average 37%. TN
government is likely to increase the price of electricity on an annual basis
to tide over the financial crisis of TNEB. On a conservative basis, it is
assumed that electricity price will increase by 8% to 10% per year over
the coming few years.
Page 17 of 31
AMC cost for solar plant is 1% of the Capital Cost. AMC is increase by
5% every year.
80% Accelerated Depreciation for the 1st year has been taken into
account for solar projects.
PAYBACK CHART FOR 100 KW SOLAR PLANT – SOLAR VS DIESEL
Annual Solar Energy Generation 1.66Lakh Units Per Year
Solar savings (1.66 Lakh Units Per Year x Rs. 18/Unit)
Rs.29.88 Lakhs
Solar Project Cost*** Rs.165.1 Lakhs*
Government subsidy** Rs. 49.53 Lakhs
Tax benefit Rs. 47.94 Lakhs
Net investment Rs. 68.04 Lakhs
ROI without subsidy for diesel
replacement
3.95 Years
ROI with subsidy for diesel replacement
2.26 Years
Page 18 of 31
SOLUTION DESIGN FOR 100KW OFF GRID SOLAR SYSTEM
Solar Photovoltaic power generator consists of solar modules in series and
parallel connections; these convert solar radiations into DC electrical power at
the predetermined range of Voltages whenever sufficient solar radiation is
available. The individual crystalline solar cells are connected together in
module (in series connection), which are hermetically sealed to survive in
rugged weather conditions and ensures optimum performance during its long
life. In order to achieve a higher system voltage, modules are installed in a row
arrangement, called a string. A higher system voltage has the advantage of
lesser installation work, higher efficiency of the entire plant and usage of
smaller cross section cables. Calculated no. of strings is connected in parallel
by cables in Junction Boxes. These junction boxes not only act as a
junction point but also monitor each string output which will be fed to the
central monitoring and analysis system. Outputs from many such junction
boxes are connected in parallel in the Main Combiner Box (MCB). This Main
Combiner Box output is fed to the Off Grid Inverter to invert solar
generated DC power in to conventional 3 phase AC power. O f f Grid
Inverter operate on MPPT (Maximum power point tracking) mode to ensure
maximum output from the solar generators at di f f erent ambien t
conditions. These inverters use higher system voltages to reach very high
efficiency of 98%. Furthermore, installations can be expanded with additions
of more modules without problems.
Page 19 of 31
OPERATION METHODOLOGY
The proposed solution is designed with 100KW Solar Panels, 100 KW Off
Grid Power Conditioning Unit (PCU) & 1700Ah /240V Battery bank. The
load connected will be 100KW. During the day, solar power will be
supplied directly to the 100KW load and in parallel, the battery bank will
also get charged. When the solar power is low, the power to the loads will
be supplemented with battery power.
The system will be provided with communication ports which will enable
local and remote monitoring and control.
POWER PLANT CONFIGURATION
S.NO ITEM Qty
1 Solar Poly PV Modules (in 200W-250W range)* 100KW
2 Module Mounting Structure As per site
area
3 100KVA Off Grid PCU 3 Phase with MPPT Controller 1 No
4 1700Ah/240V VRLA Battery Bank 1 No
5 Array Junction Boxes, Main Junction Boxes, DC
Distribution Board
Suitable
Number
6 String Monitoring & SCADA Suitable
Number
7 AC Distribution Board 1 No
8 1C x 4 Sq mm PVC Cu. Cable (Array to AJB), 1C x 25
Sq mm PVC Cu. Cable (AJB to MJB, 31/2C 16 Sq mm
PVC Cu Cable (Inverter Output to Load)
Suitable qty
9 UG Cable from Main Junction Box to Bus Bar* 100 mts
Page 20 of 31
10 Earthing Kits Suitable
Numbers
11 Lighting Arrestors Suitable
Numbers
The products will meet all international and domestic certification and quality
standards approved by MNRE like TUV, IEC, MNRE, BIS, UL & MCS.
*As per the government of India regulation, the SPV panels supplied are to be
Indian origin having standards IEC 61215 / IS14286.
OFF GRID POWER CONDITIONING UNIT (PCU)
The Off Grid PCU is designed to integrate renewable sources like solar with
batteries to provide a completely standalone power plant. The PCU output
is designed to operate independently without any other power source and
replace the existing DG. The units are fitted with data logger, web server, a
graphical display for showing operating data and a USB port for installing
firmware updates. These inverters are sophisticated bi-directional power
conditioners featuring advanced fast control algorithms which
accommodate a range of power sources and storage technologies. This
ensures high quality power output under varied or cloudy conditions and
supports high levels of solar penetration, including zero diesel fuel
consumption power systems. If and when required it can also be integrated
with the DG
EARTHING & LIGHITNG PROTECTION
The Earthing of all outdoor equipment and provision of associated earthing
systems, electrodes and connections shall be in accordance with the
recommendations in the latest IEEE 80/IS 3043.
Page 21 of 31
GROUNDING SYSTEM
The grounding design calculation shall conform to ANSI / IEEE Standard
80-2000. Earth electrodes shall be provided throughout the plant areas along
with the main earth grid. The number of earth electrodes shall be according to
achieve the total earth grid resistance less than one (1) ohm. Earth electrodes
shall be provided in earth pits. The earth pits shall be of two types namely
treated with test links and untreated. Earth electrodes shall be of heavy duty
GI pipes, 40mm dia and 3 meter long. The main buried grid conductors shall
be connected to all the earth electrodes to form a total earth grid.
GROUNDING MATERIAL
Galvanized steel flats of required size shall be used as per approved design.
Treated earth pits shall conform to relevant INDIAN Standards. The earth
grid shall be installed specified / approved depth of minimum 600mm.
EQUIPMENT EARTHING
The frames of all electrical equipment and structural steel work shall
be earthed by connection to earth grid by branches of same cross sectional
area of the earth grid.
LIGHTINING PROTECTION SYSTEM
Power plant needs protection against Lighting. The system will be designed
as per IS: 2309 and Indian Electricity Rules.
Page 22 of 31
Vertical air termination of 40mm diameter, 3 M long shall be provided
above highest point of array to provide radius of protection full array.
STRUCTURAL MOUNTING EQUIPMENT*
SR.NO. ITEM
1.0 Type Ground / Roof Mounting
2.0 Material MS Galvanized
3.0 Overall dimension As per design
4.0 Coating Hot dip (Galvanized) Minimum of 130 Micron size
5.0 Wind rating 150 km / hr
6.0 Tilt angle 15°
7.0 Fixing type SS 304 Fasteners
*Mounting for panels only included. The support frame for solar SPV panels
which is made of Zinc coated hot dipped galvanized iron frames of height ½ m
and 1 m on the other side – any higher support or basic frames + civil works
have to be done by the use under our directions.
The panel mounting structure including the solar panels will weigh 20 Kgs per
sq mt. In some locations, the roofs may require reinforcement to increase the
load bearing weight to support the mounting structures. Structural and civil
costs to increase the load bearing weight of the roofs to support the solar panel
structure is not included in the scope of work. For ground mounted systems
the cost of clearing the land has not been included in the scope of work.
Page 23 of 31
IMPLEMENTATION METHODOLOGY
The most essential aspect regarding the implementation of this project is to
ensure that the project is successfully completed within the schedule. A
good planning, scheduling, and monitoring program is imperat ive to
complete the project on time and without cost overruns.
The project zero date start once the kick- off meeting has taken place and
contract has been signed.
PROJECT IMPLEMETATION STRATEGY
It is envisaged that the project will have the below mentioned phase
of activities. These phases are not mutually exclusive; to implement the
project on fast track basis some degree of overlapping is envisaged.
Issuing letter of Indent
Applying to government with all papers for subsidy
Payment from the user to start the project through Bank LC
Procurement of Project Material and transfer them to site
Site preparation including Civil – wherever necessary like mounting on
the roof, support frame to be done by the user as per our directions
Installation of the system at the site
Trial Runs
Training & handing over of the system to the user including system
monitoring.
Page 24 of 31
PROJECT SCHEDULE
Page 25 of 31
PROJECT COSTS & COMMERCIAL TERMS
BASIS FOR COST ESTIMATION
The capital cost of the plant has been estimated taking into account
supply of complete system including solar panels, inverters, batteries,
cables, electrical accessories, mounting structure & other equipment
required for the system.
Currently MNRE provides 30% capital subsidy up to 100KW for
installation of solar power systems by commercial organizations.
MNRE Subsidy is available only when Indian made solar panels are used.
The below price is for reputed Indian made solar panels of ISO 9000
standards
Packing, forwarding, inland transportation and insurance for all
equipment and systems including spares have been considered.
Erection, testing and commissioning charges have been included.
Current Applicable Taxes have been included.
Civil works is not considered and is assumed that land or roof is ready for
installing solar panel steel mounting structures.
Power plant life is considered as 25 years.
Page 26 of 31
GENERAL TERMS AND CONDITIONS
-:GENERAL AND COMMERCIAL TERMS & CONDITIONS:-
Taxes & Duties
Included
Packing:
Prices are inclusive of Packing.
Packing shall be done as per our standard practice.
Freight & Insurance Our offer includes freight and insurance charges.
Validity of Offer:
This offer is valid for 60 days from the date of offer and thereafter subject to our reconfirmation.
Terms of Payment:
1. Letter of intent – to facilitate the government approval which will take around 6 -10 weeks.
2. 75% advance with confirm PO ( as all materials will be Supplied against full payment only)
3. 20% after delivery of materials 4. Balance 5% will be released after 3 weeks of
successful running of the unit.
Delivery period & Installation period
12 -14 weeks after approval from Government
Delivery / Completion
Period:
The Delivery/Completion shall be reasonably extended if:-
- The technical or commercial data required by us to execute the order including advance payment are not made available in time or if subsequent changes, which delay the delivery, are made by the purchaser.
- If the purchaser is behind the schedule with the work he has to carryout or is late in fulfilling the contractual obligations.
Limitation to Liability:
In no event shall we be liable for any consequential damages and/or losses arising out and connected with this supply order in any manner what-so-ever.
Our liability in respect of any defect or failure of the equipment supplied or for any loss, injury, damage
Page 27 of 31
attributable thereto, is limited to making good by replacing or repairing defects which under proper use appear therein (provided the equipment is installed, operated, maintained as per our instruction manual) and arise solely from faulty design, materials or workmanship within warrantee period. At the termination of which period, all liability on our part shall cease.
Warrantee /
Guarantee:
Solar Module
05 Years Limited Warranty on Product and Workmanship
10 Years Limited Warranty on 90% Power Output
25 Years Limited Warranty on 80% Power Output
For Balance Supplies
12 Months Limited Warranty
Parts and Components, which are repaired or replaced during such period, are warranted for the original warranty period only and will not carry any extended warranty. If the equipment is not repairable at site the same has to be sent at our workshop on freight prepaid basis after obtaining our consent in writing and we shall make good the defect and return back to you on freight to pay basis.
The warranty shall not apply to defects resulting from:
- Willful damage or negligence, normal wear and tear,
- Installation and/or maintenance by Purchaser or a third party without supplier’s
prior written consent,
- Misuse or abuse of Equipment.
- Modifications or alterations made by Purchaser or a third party without supplier's written consent.
Right and Lein of
Property:
We shall retain the right on equipment, materials or parts supplied by us under this quotation until full value thereof as per our invoice has been fully paid to us as per terms and conditions.
Page 28 of 31
Confidentiality /
Do Not Disclose
(DND):
The information shared by us of any nature during tendering or execution of the contract may be treated truly confidential. Due respect should be taken care to respect the confidentiality of intellectual property. The Confidentiality of this offer should be maintained strictly and in no case without seeking our written permission this document can't be shared, disclosed, reproduced, copied or circulated.
Force Majeure:
We shall be under no liability if performance of contract on our part is prevented or delayed whether in whole or in part due to any of the causes beyond our reasonable control. The supplier shall not be held responsible for any delay, loss or damage arising from any cause, matter or thing beyond the supplier's / sub-supplier's reasonable control, including, without prejudice to strikes, lockouts, go-slow, delays in approval of drawing, rejection of any important part of work, default of sub supplier in supplying the parts / raw materials, lack of transportation facilities, inability to obtain necessary labour or materials, official prohibition of transit of goods,
requisition by legal authorities of personal property, movable or immovable, restriction in power supply or any other action of the government, riots, war or warlike conditions, acts of nature or God such as epidemics, floods, earthquakes, fires etc. whether such delay or impediment occurs before or after the time or extended time for dispatch or completion. In case the supply is affected by the force majeure conditions, we shall intimate the purchaser, within a reasonable time, of such occurrence and suitable extension to the delivery time shall be granted.
OTHER TERMS & CONDITIONS
1. The user will protect the patent right of the unit to the extent possible.
2. Excess material [purchased for the project] will be allowed to be taken back after the project completion
Page 29 of 31
ABOUT SUN BEST
Dr.C.Palaniappan is the Proprietor of Sun Best, has more than 30 years of
experience in solar energy both in application and promotion. He did his
doctorial thesis on solar agricultural drying at Milan University under young
scientist award in 1986.
The pioneering work done by Dr.C.Palaniappan is recognized by international
organizations like UNDP, REEEP, UNIDO,ICTP.
The solar air heating technology has been recognized by Ministry of New
Renewable Energy, Tamilnadu Energy Development Agency, National Research
Development Corporation.
Dr.C.Palaniappan has continued Research & Development activities in
collaboration with Technical University of Munich, Germany and International
Centre for Theoretical Phyiscs, Italy to bring latest technology.
Recently completed an Indo – German project with Technical university of
Munich, University of Stuttgart and Anna University. International Energy
Agency (IEA), Paris world’s authority on Renewable Energy has invited
Dr.C.Palaniappan in the task force 33 as a special invitee.
Since 2007, SUN BEST has installed around 2000 m2 of solar collector for Coir
mattresses sheet, Turmeric drying, Latex drying, paint shop, dryoff oven, fruits
and vegetables dehydration. Sun Best is promoting the solar air heater and
solar water heater to the top corporate like TTK – LIG Ltd, Orchids Pharma,
Hindustan Lifecare Limited, Murugappa group, TAFE, Visteon, Caterpillar,
Roca Bathroom Products Pvt Ltd, L & T etc.
Page 30 of 31
The green technologies developed has served more than 100 small & medium
sized companies. CO2 emission equivalent to 60,000 kW thermal has been
reduced annually.
A company dedicated to producing quality work & exemplary customers’
services backed by years of real world experience and established in Theni,
Tamilnadu.
Page 31 of 31
CONCLUSION
This DPR explains in detail the implementation of 100 KW off grid solar power
to assist TTK Prestige to reduce their DG consumption. The solution is
designed to fully replace the 320KVA DG for 290 days a year. Such off grid
solutions have been successfully used in several locations globally and we are
confident of providing a quality solution to TKK Prestige that will give them the
expected benefits.