Division of Design and ConstructionP.O.Box 758160
Fairbanks, Ak 99775-8160(907) 474-5299
UNIVERSITY OF ALASKA FAIRBANKSCONSTRUCTION PROJECTS 2020February 21, 20200 560 1,120 1,680 2,240 2,800
Feet
AERIAL DATED: JUNE 2019
TANANA LOOP
ALUMNI DR
Campus Wide General Classroom RenovationManager: Bob CrenshawPaint and carpet renewal for rooms TBDConstruction scheduled June - August 2019
2
Campus Wide Hardware UpgradesManager: Cameron WohlfordConvert Campus to new key system. Upgrade broken doors and obsolete hardware to be compatiable with new key system.Construction scheduled 2019 -2020
YUKON DRIVE
5
4
3
Campus Wide Hardware UpgradesManager: Cameron WohlfordConvert Campus to new key system. Upgrade broken doors and obsolete hardware to be compatiable with new key system.Construction scheduled 2019 -2020
CAMPUSWIDE PROJECTS
Campus Wide Floor RecoatsManager: Noel RathbunRecoat floors at Wood Center Ballroom,SRC Dance Floor, Davis Concert Hall Stage, and Patty Gym.Construction scheduled July - Aug 2020
26. Campus Wide Elevator Repairs and Renewal Manager: Joe Krizek Repair elevators in Duckering including replacement of controls, equipment and finishes. Construction scheduled May - Dec 2020
OFF CAMPUS PROJECTS
2. Elvey Curtain Wall Repair Manager: Nick Middelstadt Repair joint between the Elvey curtain wall and roof to stop the active leak into the interior of the building. Construction scheduled May - Aug 2020
1. Campus Wide Exterior Building Entry Upgrades Manager: Cameron Wohlford Install electronic card access to exterior building entries to comply with emerging national safety standards. Construction scheduled May - Aug 2020
4. AHRB Osteo Prep Lab Manager: Bob Crenshaw Construct lab room for bone specimen preparation in Arctic Health Research Building, related to the UA Museum of the North collections. Construction scheduled Feb - April 20205. West Ridge Deer Yard Logistics and Storage Manager: Matthew Armour Remove multiple sheds and outbuildings in the "Deer Yard" and place gravel fill to create level areas for storage containers, vehicles, and other research storage needs. Construction scheduled April - June 2020
3. Utilities Cooling/Heating Loop Piping Upgrade Manager: Piotr Kawka Replace chilled water and district heating piping between Signers' Hall parking lot and the Rasmuson Library. Repair Damaged Line. Construction scheduled Aug 2020
6. Butrovich Computing Center Back-Up Power Installation Manager: Cameron Wohlford Install back-up power systems including a backup power generator for the UA Statewide Computing Center in the basement of Butrovich. Construction scheduled March - June 2020
6
7. Campus Wide Facility Demolition Manager: Noel Rathbun Demolish Facility Services Storage Building and Museum of the North bones, prep area. Construction scheduled May - Aug 20208. LARS Arctic Ground Squirrel Breeding Colony Manager: Noel Rathbun Build habitat on the northwest side of farm north of large animal holding facility. Construction scheduled April - June 2020
9. Wickersham Hall Repairs & Renovation Manager: Bob Crenshaw Replace carpet, paint the rooms, replace plumbing serving toilets/lavatories. Construction scheduled May - Aug 2020
9
10. Constitution Hall Renovations Manager: Bob Crenshaw Revitalize exterior entry doors, stairs, and ADA ramp on south side. Construction scheduled April - Sept 2020
10
11. Gruening Ground Floor Refresh Manager: Bob Crenshaw Refresh ground floor finishes (flooring, ceilings, paint). Construction scheduled May - Oct 202012. Gruening 7th Floor Renovation Manager: Bob Crenshaw Repurpose offices on Level 7 for School of Education student study/intensive learning community space. Construction scheduled May - Oct 202013. Denali Lane Storm Drains Manager: Cameron Wohlford Replace the storm drains, culvert, and paving on Denali Lane from Tanana Loop to Lathrop Hall. Construction scheduled May 2020
14
14. South Chandalar/Tanana Road Improvements Manager: Cameron Wohlford Rebuild South Chandalar and Tanana Loop storm drains, and improve pedestrian safety with new sidewalks, intersections, and lighting. Construction scheduled April - Aug 2020
1211
15. Pub Lighting Replacement Manager: Philip Schaefer Replace pub lighting with LED. Construction scheduled May 202016. Alumni Stair Lighting Replacement Manager: Philip Schaefer Install lights on stair system between Alumni Drive and Tanana Loop. Construction scheduled June 2020
16
15
17
17. Wood Center Sculpture Pole Manager: Bob Crenshaw Repair pole mounting base. Clean and reseal pole. Construction scheduled Spring 2020
Campus Wide Alaska Native Arts and Culture Facilities RenovationManager: Karl PettersonRenovate existing spaces and provide equipment atmultiple UAF campuses around the state to sustain and increase Alaska Native artistic and cultural heritage.Construction scheduled May - Nov 2020
Rural & Remote Campuses Fuel System CorrectionsManager: Karl PettersonCorrect fuel tank and piping deficiencies at multiplerural UAF campuses located around the state.Construction scheduled May - August 2020Chuckchi Campus Fire Alarm ReplacementManager: Karl PettersonReplace the fire alarm system at the Chuckchi Campus. Existing system is functional however it has been obsoleted by the manufacturer and replacement parts will not be able to be procured. Construction scheduled May - August 2020
Campus Wide Hardware UpgradesManager: Cameron WohlfordConvert campus to new key system. Upgrade doorhardware to be compatiable with new key system and safety standards.Construction scheduled 2020 -2021
CTC Garage Fire Department ConnectionManager: Noel RathbunDesign and replace piping associated with the Barnette Street parking garagefire deparment connection.Construction scheduled May 2020
13
1
8
19. Irving 1 Hydronic Repairs Manager: Nick Middelstadt Overhaul of heating distribution system for better heat delivery and prevention of air-locking. Construction scheduled May - Aug 2020
19
PENDING
Campus Wide Facility DemolitionManager: Noel Rathbun Demolish Ester Dome Building.Construction scheduled May - Aug 2020
20. Patty Ice Arena Adaptation Manager: Piotr Kawka Upgrade Patty Ice to conform to NCAA standards. Construction scheduled May - Aug 202021. Campus Wide Fire Alarm Upgrades Manager: Nick Middelstadt Design replacement fire alarm system for Brooks, Bunnell, and Chapman Buildings. Construction scheduled May - Aug 202022. U-Park ADA Operator Install Manager: Bob Crenshaw Modify entry to be ADA compliant. Construction scheduled July - Aug 202023. Copper Lane Soil Remediation Manager: Noel Rathbun Remove petroleum based contaminated soil derived from heating oil tank leak. Construction scheduled July - Aug 202024. Salisbury Theatre Fire Curtain Manager: Nick Middelstadt Replace fire rated curtain between stage and seating area. Construction scheduled July - Aug 2020
25. Bookstore Paint and Carpet Manager: Bob Crenshaw Replace carpet and paint in the bookstore merchandise area. Construction scheduled June - July 2020
143
25
24
7
22
23
20
2121
21
27. Bunnell North Star College Manager: Cameron Wohlford Repurpose room 302 into a collaborative learning space. Construction scheduled May - Aug 2020
26
27
Yankovich Road