Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
TECHNO ECONOMIC FEASIBILITY REPORTFor
Change in Configuration & Expansion of 1.4 MTPA Integrated Steel Plant
of
SHYAM METALICS & ENERGY LTDPandloi, PO-Rengali, Sambalpur, Odisha
Prepared by
GLOBAL TECH ENVIRO EXPERTS PVT. LTD.C-23, BJB NAGAR
BHUBANESWAR-751014PH. NO.-06742433487
Email:- [email protected]
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
1
CONTENTS
Contents .............................................................................................................. 1
CHAPTER-1 .......................................................................................................... 4
EXECUTIVE SUMMARY ........................................................................................... 4
CHAPTER-2 .......................................................................................................... 6
INTRODUCTION OF THE PROJECT ........................................................................... 6
2.1 IDENTIFICATION OF THE PROJECT & PROJECT PROPONENT: .......................... 6
2.2 BRIEF DESCRIPTION OF NATURE OF THE PROPOSED PROJECT ....................... 6
2.3 NEED OF THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND OR
REGION ............................................................................................................ 6
2.4 DEMAND –SUPPLY GAP .............................................................................. 7
2.5 IMPORTS VS. INDIGENOUS PRODUCTION & EXPORT POSSIBILITY .................. 8
2.6 EMPLOYMENT GENERATION (DIRECT & INDIRECT) DUE TO THE PROJECT ........ 9
CHAPTER-3 ........................................................................................................ 10
PROJECT DESCRIPTION ....................................................................................... 10
3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECTS
IF ANY. ........................................................................................................... 10
3.2 LOCATION .............................................................................................. 10
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS ....................................... 15
3.8 RESOURCE OPTIMISATION/RECYCLING AND REUSE ENVISAGED IN THE
PROJECT ......................................................................................................... 24
3.9 AVAILABILITY OF WATER ITS SOURCE, ENERGY/POWER REQUIREMENT AND
SOURCE .......................................................................................................... 24
3.9.1 WATER REQUIREMENT: ....................................................................... 24
3.9.2 POWER REQUIREMENT FOR THE PROJECT .............................................. 26
CHAPTER -4........................................................................................................ 28
PROPOSED INFRASTRUCTURE AND EMP ................................................................. 28
4.1 CONNECTIVITY ....................................................................................... 28
4.2 LAND FORM, LAND OWNERSHIP ................................................................ 28
4.3 TOPOGRAPHY ......................................................................................... 28
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
2
4.4 SOIL CLASSIFICATION: ........................................................................... 29
4.5 CLIMATIC DATA FROM SECONDARY SOURCE .............................................. 29
CHAPTER -5........................................................................................................ 30
PLANNING BRIEF................................................................................................. 30
5.1 PLANNING CONCEPT ............................................................................... 30
5.2 PERIPHERAL DEVELOPMENT PLAN ............................................................. 30
5.3 LAND USE PLANNING ............................................................................... 30
5.4 BENEFITS TO THE REGION AND THE COUNTRY ........................................... 31
CHAPTER -6........................................................................................................ 32
PROPOSED INFRASTRUCTURE .............................................................................. 32
6.1 INDUSTRIAL AREA DISTRIBUTION ............................................................. 32
6.2 GREENBELT DEVELOPMENT ...................................................................... 32
6.3 CONNECTIVITY ....................................................................................... 32
6.4 DRINKING WATER MANAGEMENT: ............................................................. 32
6.5 INDUSTRIAL WASTE MANAGEMENT ........................................................... 32
6.6 POWER REQUIREMENT ......................................................................... 33
6.6 INDUSTRIAL POLLUTION CONTROL ........................................................... 33
Pollution Control Equipments .......................................................................... 36
6.6.2 WATER POLLUTION CONTROL ............................................................ 37
6.7 MAN POWER REQUIREMENT ..................................................................... 37
CHAPTER -7........................................................................................................ 38
REHABILITATION & RESETTLEMENT ...................................................................... 38
REHABILITATION & RESETTLEMENT ................................................................... 38
CHAPTER -8........................................................................................................ 39
PROJECT SCHEDULE ............................................................................................ 39
8.1 IMPLEMENTATION SCHEDULE ................................................................... 39
8.2 ESTIMATED PROJECT COST ...................................................................... 39
CHAPTER-9 ........................................................................................................ 40
ANALYSIS OF PROPOSAL (FINAL RECOMMENDATION) ............................................. 40
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
3
9.1 FINANCIAL & SOCIAL BENEFITS ............................................................... 40
9.2 SOCIAL INFRASTRUCTURE ....................................................................... 40
9.3 EMPLOYMENT POTENTIAL ........................................................................ 40
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
4
CHAPTER-1
EXECUTIVE SUMMARY
M/s Shyam Metalics & Energy Ltd steel project is located at Pandoloi, in Sambalpur
district of Odisha. The project site is at latitude 210 40’ 50.43’’ N and longitude 840
02’ 30.63’’ E, MSL 208m. The project is located on state Highway joining Sambalpur-
Rourkela, NH-6 and 42 exist at a distance of about 25km from the site. SH-10 is passing
by the side of the project. The project is by the side of Railway line of Sambalpur-
Jharsuguda section. The nearest railway station Rengali is 8 km away from project site.
The company was initially having DRI Kilns, IFs and rolling mill and proposed expansion
and granted prior EC to setup1) 4x500 TPD DRI kilns, 2) 2x450m3 MBF, 3)3 Lakh TPA
Pellet Plant, 4)1x96m2 Sinter Plant, 5)4x8T, 4x12T IFs, 2x80/90T EAF, 6)6Lakh TPA
Rolling Mill, 7)2x6, 2x9 & 3x11 MVA Ferroalloy plant, 8)5Lakh 50 thousand Coke Oven
Plant, 9)15Lakh TPA Coal washery, 10) 60,000 TPA Lime Plant, 11)3,53,500 TPA Bloom
Caster and 12) 200 MW power Plant.
The company started production installing some of the facilities approved under EC
within its validity period and has taken validity extended vide F.No. J-11011/495/2006-
IA II (I)of MoEFCC, dated 2nd December, 2016. The company mean while intents to
setup additional 10 Lakh TPA Iron Ore Pellet Plant with existing approved 3Lakh TPA
pellet plant, and to reduce Power generation by 50 MW (from approved EC quantity of
225 MW to 175 MW), so as to keep all emissions and effluents within the approved scope
of existing EC, so as to be within the scope of 7(ii) of EIA Notification 2006.
The project is “primary ferrous” metallurgical unit belonging to schedule 3(a) category A
Water will be drawn from Hirakud Reservoir of river Mahanadi. Fresh water requirement
after the proposed change has been estimated to be 55702 KLD against 62612 KLD as
approved in EC and there will be a reduction of 6910 KLD.
Power requirement after the change has been estimated to be project is estimated to be
about 216.12 MW, whereas captive power generation will be reduced from 225 MW to
175 MW. Balance power will be purchased from state supply.
In the existing plant, the haulage roads are been installed with sprinklers and road
leading to material handling and storage have been concretized for control of fugitive
emission. Across the railway siding, 44 nos. of sprinklers are been installed which
drastically reduces the fugitive emissions due to transportation and handling.
Land
The total land required for the project is 294.84 ha out of which 127.05 ha has been
acquired and the balance acquisition is in process
Manpower
The total manpower is different categories were as follows in accorded EC and there will
not be any significant change in it with proposed change.
Executives = 155
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
5
Non-Executives = 2905
Total = 3060
Project cost
The estimated expansion project cost in approved EC was 3,868 crore.
Now with 50 MW reduction in power plant, there will be significant reduction in
equipment cost in the order of about 150 crores, Cost of 9 Lakh TPA Iron ore pellet plant
will almost be of the same value, so differential project cost for implementation will be
about 25 crores.
Hence the total project cost will be around Rs 3893 crores
Project completion schedule
After getting CTE from SPCB, Odisha, the construction work can be started to complete
the project in two years of time.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
6
CHAPTER-2
INTRODUCTION OF THE PROJECT
M/s Shyam Metalics & Energy Ltd is spread over in an area of 295.04 ha of land in
Pandoloi village in Sambalpur district of Odisha.
The company is at present producing TMT rods in DRI-IF-Rolling mill route. The unit has
taken Environmental Clearance for its expansion for 14,44,286 TPA steel product
through DRI-MBF-EAF/IF-CCM route. Pellet Plant, Coke Oven, Coal Washery and CPP
from waste heat recovery as well as FBC.
At present the company is proposing to set up 9 Lakh TPA pellet plant which was not in
the scope of existing Environmental clearance. Along with this the company is proposing
for reduction in power generation from 225 MW to 175 MW. This power generation being
from coal based FBC (117 MW), there will be substantial reduction in pollutant emission
to atmosphere.
The emission from proposed changes being within the approved scope of EC, SPCB can
approve the change and issue consents.
2.1 IDENTIFICATION OF THE PROJECT & PROJECT PROPONENT:
The project is an integrated steel project, having scope for Coal washery, Coke oven,
Iron Ore palletization, Sinter, Hot Metal through both DRI and IF route, Rolling mill and
Ferro alloy production.
The company received EC vide letter dated 10th December, 2008 and subsequently
extended EC validity vide letter from MoEFCC, dated 2nd December,2016.
The project is primary ferrous metallurgical unit belonging to schedule 3(a) category A
Mr. B.K. Panda is project coordinator on behalf of M/s Shyam DRI Power Ltd (SDPL).
2.2 BRIEF DESCRIPTION OF NATURE OF THE PROPOSED PROJECT
The Proposed expansion cum modification project is a brown field primary metallurgical
(ferrous) project, in which the capacity of Pellet Plant will be enhanced to 1200000 TPA
from 300000 TPA, total CPP capacity will be reduced from 225 MW to 175 MW along with
reduction in Coal Washery throughput from 1500000 TPA to 1000000 TPA. Along the
same line, considering the market potential
2.3 NEED OF THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY
AND OR REGION
Steel is traditionally considered the backbone of national economic development. It is a
major input into sectors which support economic growth such as infrastructure,
machinery, power and railways, as well as being important for fast growing sectors, in
particular automobiles and consumer durables.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
7
The steel industry in India is currently at an inflexion point brought about by ambitious
capacity expansion plans, entry of new players and increased competition on one hand
and consistently rising and shifting demand patterns on the other.
This rise in demand is expected to be driven by the construction, automobile and
consumer durables sectors
In the construction sector, Government spending in infrastructure is expected to surge
during the twelfth plan period, thus driving up demand for steel used in construction.
Most steel producers are planning major capacity expansions through both Greenfield
and Brownfield expansions. This, coupled with the entry of new players will result in a
significant rise in steel production over the next ten years.
TMT rods as being manufactured by the company are most suitable in construction due
to its high workability.
The other proposed product of M/s Shyam Metalics & Energy Ltd are ferroalloys like Fe-
Mn, Si-Mn, Fe-Cr and Fe-Si, which has various uses for quality steel production.
The above stated facts indicate importance steel as well as Ferro alloys products in the
development of a country. As Odisha has rich source of all the ores from Hematite to
Chromatite to Manganese ore, the project bear a lot of significance for development of
state as well as the nation.
Thus proposed integrated steel project has make in India importance to the country &
the region.
2.4 DEMAND –SUPPLY GAP
Due to pressure from the construction sector, the demand for longs will continue to
dominate the steel industry, while on the supply side, flats are expected to dominate
In the optimistic scenario, all crude steel capacity expansion targets announced by steel
companies are aggregated. Under this scenario, it was estimated that crude steel
capacity will be 259.11 MT in 2020-21. However, this will be possible only if the crude
steel capacity targets, as announced by steel producers are met. However, for 2020-21,
this scenario estimates a more reasonable capacity of 210.11 MT.
Base Case Scenario: The base case scenario gives a lower bound crude steel capacity
estimate. It accounts for delays in commissions of projects due to problems associated
with land acquisition, obtaining environmental clearances, raw material availability, etc.
The effect of these delays on the date of commissioning of projects was assessed
through interviews with experts and a review of secondary literature. According to this
scenario, crude steel capacity in the country in 2020-21 will be 178.8 MT.
Currently, demand for finished steel in India is estimated to be around 70 MT. This is
expected to more than double to 166 MT by 2020-21. This demand will mainly be driven
by the construction (real estate and infrastructure), automobile and consumer durables
sectors. It must be noted that this figure includes only domestic demand for steel.
Demand from international markets will further push this figure up.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
8
2.5 IMPORTS VS. INDIGENOUS PRODUCTION & EXPORT POSSIBILITY
On liberalization of the Indian steel sector with effect from 24.5.92, iron and steel
industry was included in the list of „high priority‟ industries for automatic approval for
foreign equity investment up to 51%. This limit has since been increased to 100%.
The import regime for iron and steel has undergone major liberalization moving
gradually from a controlled import by way of import licensing, foreign exchange release,
canalization and high import tariffs to total freeing of iron and steel imports from
licensing, canalization and lowering of import duty levels. Export of iron and steel items
has also been freely allowed. Import duty on capital goods was reduced from 55% to
25%. Duties on raw materials for steel production were reduced. These measures
reduced the capital costs and production costs of steel plants.
Imports
Iron & steel are freely importable as per the extant policy.
Data on import of total finished steel (alloy + non alloy) is given below for last
five years:
Indian steel industry : Imports (in million tonnes)
Category 2010-
11
2011-
12
2012-
13
2013-
14
2014-
15
Total Finished Steel (alloy + non alloy) 6.66 6.86 7.93 5.45 9.32
Source: Joint Plant Committee
Exports
Iron & steel are freely exportable.
Data on export of total finished steel (alloy + non alloy) is given below for last
five years:
Indian steel industry : Exports (in million tonnes)
Category 2010-11 2011-12 2012-13 2013-14 2014-15
Total Finished Steel (alloy + non alloy) 3.64 4.59 5.37 5.98 5.59
Source: Joint Plant Committee
Above figures are indicative of constant increase of steel export from India and likely to
increase further in coming years.
The New Industrial policy opened up the Indian iron and steel industry for
private investment by (a) removing it from the list of industries reserved for public
sector and (b) exempting it from compulsory licensing. Imports of foreign technology as
well as foreign direct investment are now freely permitted up to certain limits under an
automatic route. Ministry of Steel plays the role of a facilitator, providing broad
directions and assistance to new and existing steel plants, in the liberalized scenario.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
9
2.6 EMPLOYMENT GENERATION (DIRECT & INDIRECT) DUE TO THE
PROJECT
Manpower
The total manpower in different categories were as follows in accorded EC and there will
not be any significant change in it with proposed change.
Executives = 155
Non-Executives = 2905
Total = 3060
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
10
CHAPTER-3
PROJECT DESCRIPTION
3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND
INTERDEPENDENT PROJECTS IF ANY.
The project is a primary metallurgical (ferrous) expansion project of M/s Shyma Metalics
& Energy Ltd. Coming under category-A, schedule 3(a).
This project is independent plant without any interlink or interdependence.
3.2 LOCATION
M/s Shyam Metalics & Energy Ltd steel project is located at Pandoloi, in Sambalpur
district of Odisha. The project site is at latitude 210 40’ 50.43’’ N and longitude 840
02’ 30.63’’ E, MSL 208m. The project is located on state Highway joining Sambalpur-
Rourkela, NH-6 and 42 exist at a distance of about 25km from the site. SH-10 is passing
by the side of the project. The project is by the side of Railway line of Sambalpur-
Jharsuguda section. The nearest railway station Rengali is 8 km away from project site.
3.3 Satellite imagery of M/s Shyam Metalics & Energy Ltd
ALTERNATE SITES CONSIDERED AND THE BASIS OF SELECTING THE PROPOSED
SITE, PARTICULARLY THE ENVIRONMENTAL CONSIDERATIONS GONE INTO
SHOULD BE HIGHLIGHTED.
The existing Project site is running on 295 ha of land and all the expansion jobs are
being carried out on this land and so no alternate sites have been taken in to
consideration.
3.4 SIZE OR MAGNITUDE OF OPERATION
The Project after this proposed expansion will be a 1.4 MTPA integrated steel project
manufacturing various steel products within the existing permissible EC limits.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
11
Table 3.1 Project configuration and Product mix of existing and changed facilities.
A B C D E F G H
Sl. No
Facilities Configurations Prior to EC
Configurations Approved in EC
Present Operation status with CTO
Facilities Yet To be commissioned as per EC
Changes to EC Configuration Proposed
Additional Unit Configuration
Final Configuration
Final capacity In TPA
1 DRI Kilns 2x350 TPD +
2x100 TPD
4x500 TPD 2x350 TPD+
2x100 TPD +
2x500 TPD
2x500 TPD No Change Nil (2 x 350 TPD,
2 x 100 TPD,
4 x 500 TPD)
8,00,000
2 MBF Nil 2x450m3 Nil 2x450m3 No Change Nil 2x450m3 7,42,500
3 I/O
Pelletization
Nil 3 Lakh TPA 3 Lakh TPA Nil Capacity
Enhancement of 3
Lakh TPA to 6 Lakh
TPA.
6Lakh TPA 12 Lakh TPA 12,00,000
4 Sinter Nil 1x96m2 Nil 1x96m2 No Change Nil 1x96m2 8,82,000
5 S M S 4x18T IF 4x8T + 4x12T
IF
2x80/90 T EAF
with matching
LRF
4x18T + 4x8T
+ 2x12T IF
2x12T IF
2x80/90 T EAF
with matching
LRF
Change in EAF from
2 x 80/90 T to 1 x
80 T
11 x 18 T IF (15x18T +
8x8T +
4x12T) along
with 1 x 80
EAF with
matching LRF
14,44,286
6 C C M Nil 1x6 strand &
1x2 strand
1x3 & 1x2
strand
1x3 strand No Change Nil Nil 6,60,000
7 Rolling Mill 60,000 TPA 6 Lakh TPA 60,000 TPA 6 Lakh TPA No change in
production
capacity, but Wire
rods, structural,
Pipe flats & HR
Coils are to be
introduced.
TMT 100000 TPA;
Structural Mill
60000 TPA;
Pipe Mill 30000
Nil TMT 1
100000 TPA;
Structural Mill
60000 TPA;
Pipe Mill
30000 TPA;
WRM1 & 2
400000 TPA
and TMT 2
Bar 70000
TPA
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
12
TPA;
WRM1 & 2 400000
TPA
7 Ferro alloy
plants
Nil 2x6, 2x9 &
3x11 MVA
2x6, 2x9 &
3x11 MVA
Nil No Change Nil Nil 2,50,000
8 Coke oven Nil 5 Lakh
50 thousand
TPA
Nil 5 Lakh
50 thousand
TPA
No Change Nil Nil 5,50,000
9 Coal
washery
3 Lakh TPA 15 Lakh TPA 3 Lakh TPA 7Lakh TPA Reduced
throughput with
introduction of
Foreign Coal as
substitute
Nil 10,00,000
TPA Capacity
10,00,000
10 Lime Plant Nil 60,000 TPA Nil 60,000 TPA No Change Nil Nil 60,000
11 Bloom
caster
Nil 3,53,500 TPA Nil 3,53,000 No Change Nil Nil 3,53,500
12 C P P 15
MW(WHRB)
10 MW (FBC)
200 MW 37 MW(WHRB)
70 MW(FBC)
68 MW
(FBC)
No more additional
Power Plant &
reduction id AFBC
Power by 50 MW
Nil WHRB 58 MW
+ FBC 117
MW = 175
MW
175 MW
Source: SDPL
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
13
Therefore a comparison of existing vs proposed changes in the configuration is
represented in the table below. The total changes is within the EC approved quantity of
steel production for 14,44,286 TPA from this integrated Steel Plant.
Sl. No. Plant Unit
EC Status Existing / Proposed
Changes
Unit Description with configuration Capacity in TPA
1
Pellet
Existing
Pellet Plant 300000
2 PGP 5 x 2850 NM3/hr
1
Proposed
PelletPlant 1200000
2 PGP 20 x 2850 NMQ/hr
3
DRI
Existing DRI (2 x 350 TPD, 2 x 100 TPD, 4x500 TPD*)
800000
3 Proposed
DRI (2 x 350 TPD, 2 x 100 TPD, 4x500 TPD)
800000
4 Power Plant
Existing Power Plant* 225 MW
4 Proposed Power Plant 175 MW
5
SMS
Existing (EC granted for
(210000 +1200000
=1410000 TPA)
EAF ( 2x80/90 T ) 1234286
IF (4 x18T)+ (4 x8) +(4 x 12) 210000
5 Proposed EAF (1 x 80T) 673406
IF (15x18T + 8x8T + 4x12T) 770880
6 SINTER
Existing 882000 ( 1x 96 m2) 882000
6 Proposed 882000 ( 1x 96 m2) 882000
7
MBF
Existing 2x450 m3 with 2.357 factor for 350 days
742500
7 Proposed 2x450 m3 with 2.357 factor for 350 days
742500
8
Rolling Mill
Existing
TMT 60000
Structural Mill 60000
Pipe Mill* 30000
WRM I* 235000
WRM II* 235000
8 Proposed
TMT 170000
Structural Mill 60000
Pipe Mill 30000
WRM I 200000
WRM II 200000
9 SAF
Existing Ferro Alloys Plant (SAF) 250000
9 Proposed Ferro Alloys Plant (SAF) 250000
10 Coal
Washery
Existing Coal Washery 1800000
10 Proposed Coal Washery 1000000
11 Coke Oven Plant
Existing Coke Oven* 550000
11 Proposed Coke Oven 550000
Source: Sam DRI
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
14
Fig 2.1 LAYOUT PLAN OF THE INTEGRATED PROJECT
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
15
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS
The changes proposed on accorded EC are increase of Iron Ore pellet production by
10lakh TPA and reduction of power generation by 50 MW.
Project description & Process details will remain same as described in existing EC.
Iron Ore agglomeration by Sintering and Palletization from beneficiated Iron Ore from
market, will be fed to DRI Kilns, Blast Furnaces and EAFs to produce hot metal, which
will be converted to liquid steel in LFs and cast to blooms and Billets. TMT rods etc. will
be manufactured for sale.
Ferroalloy Plants to manufacture Fe-Mn, Si-Mn, Fe-Si and Fe-Cr for internal use and sale.
Captive Power will be generated from Waste heat of flue gas from DRI Kilns, Coke Oven
gas and steam from FBCs.
There will be Coal washery to feed washed Coal to Coke Oven plant and middling to FBC.
The detailed process flow diagram for the integrated Steel Plant is represented in
Figure….
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
16
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
17
A. Pellet Plant
Pelletization process consists of number of key stages. Concentrate is fed along with a
mixture of Bentonite and other chemical additives (such as lime stone, coal and coke
breeze) and moisture, into balling devices like drum or disc to produce green pellets 9-
11 mm dia. These pellets are loaded on to a moving grate and form a packed bed.
Increasingly hot process gas is blown through it to dry and fire the pellets at 13000C.
Then ambient air cools them back to room temperature.
Grate kiln process which will be adapted by M/s Shyam Metalics& Energy Ltd,will have
three machines in series; a travelling grate, a rotary kiln and an annular cooler. Overall
the grate kiln system can be independently controlled, e.g. the speed of the grate can be
slowed to allow more drying time of the green balls. The kiln speed can be modified to
keep a constant residence time for proper induration.
Since iron ore slurry from beneficiation plant is used for pallet making, water content of
the concentrate from the thickener is about 50%. In order to reduce moisture content
ceramic vacuum disc filters are used and water content is reduced to 11% and water is
recycled.
Slurry with 11% moisture is conveyed to the feed silo. From the silo the slurry will be
transferred by belt conveyor to buffer bunker in the drying unit. Drying will be provided
with one set of Ø 3.74×22m barrel drying machine with handling capacity with 150t/hr.
water content of concentrate will be reduced to around 7% after drying and transferred
to proportioning bin. Coal and bentonite will be received by trucks and stored separately
in the yard.
Fuel coal with sizes from 0-30mm will be transferred by belt conveyor from coal store
bunker to coal preparation area, where vertical coal mill be used to grind the coal to size
of 200 mesh(fraction more than 80%). Finally grinded coal will be transferred to the
burner in the coal injection tower. The capacity of vertical mill will be 6-10t/hr and type
HRM 1100. Crushed coal of 200 mesh will be transferred to coal injection pipe at the
head of induction unit and burnt by air through blowers.
Pre-determined quantity of concentrate bentonite, limestone / dolomite, coal is sent to
intensive mixer to produce a homogeneous mixture.
B. Rolling Mill
The company now proposes manufacture of total 6,60,000 TPA rolled product
Revamp existing 60,00 TPA rolling mill to manufacture 1,00,000 TPA rolled TMT
product.
Set up 2x2,00,000 TPA wire rod mills.
Set up 1x 60,000 TPA structural mill
Set up 1x30,000 TPA Pipe mill
Set up 1x70,000 TPA TMT rod mill
I Reheating of Billets
Billets are charged from one end to a 20 TPH oil fired reheating furnace by a suitably
rated pusher and discharged at the other after being heated and soaked to desired
rolling temperature level at 1200oC. In order to avoid de-carbonization on heating, the
billet are heated slowly and uniformly up to 800oC and then rapidly to the rolling
temperature level of 1200oC.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
18
II. Roughing Mill
The roughing mill contains 510 PCD 3Hi one reversing stand and one vertical edging
stand. Billet is first rolled in the first stand of roughing mill train. To and from rolling of
bottom and top pass in first stand shall be carried out till a definite section shall be
obtained in sixth pass and the Billet will be then allowed to pass through the bottom
pass of intermediate mill stand.
III. Vertical Edging Stand
The vertical edging stand will be used to produce strips with very fine plane edges. Two
nos. edging stand is incorporated in the mill. First one will be in the roughing group and
the second one will be in the intermediate group. The second stand will have 5%
concave type roll edging.
IV. Intermediate Mill
The intermediate mill contains 410 PCD 2Hi three stand and one vertical edging stand.
From the roughing mill the Billet will be then allowed to one pass through first stand of
Intermediate mill, next one pass through second stand & the next one pass through third
stand. The three intermediate stands is continuous stand. The Billet coming out from
third stand of intermediate mill will be then allowed to the first stand of Finishing mill.
V. Finishing Mill
The Continuous mill containing 310 PCD 4Hi two stands is the Finishing mill. The strip /
skelp coming out of 3rd stand shall be allowed to enter to the continuous finishing stands
driven by a proper drive. One (1) pass in each finishing stand shall be used. The finished
strip / skelp coming out of mill stand shall be collected in the coiler. These coils will be
supplied to the tube mill.
C. Coal Washery
Coal Washing is a process of separation mainly based on difference in specific gravity of
coal and associated impurities like shale, sand and stones etc so that we get relatively
pure marketable coal with add on calorific value of the coal. Coal washing separates non-
combustible material from useful combustible material. Coal washing uses gravity
separation, flotation and a technology, which uses dense media. In India dense medium
cyclones are most popular as it gives very high separation efficiency Mostly magnetite is
used as dense media. Magnetite having specific gravity in the range of 4.8 to 5.4 is used
in washery for washing process which is ground to –325 mesh and mixed with water to
maintain the desired gravity in HM Bath or HM Cyclone for separation of coal from its
impurities.
Indian coal has a very high NGM (Near Gravity Material) value and it is difficult to wash
it. Dense medium cyclone provides best solution for Indian coal. With around 221 billion
tons of non coking coal deposits, India has huge advantage in developing coal-based
sponge iron technology in India. A country having no significant resources of either
coking coal or natural gas can leverage washed and beneficiated coal causing value
addition of coal by way of reduction in ash percentage.
Beneficiated coking coals find use in manufacturing of hard coke for steel making.
Beneficiated washed Non-coking coal find use mainly for power generation.
Beneficiated Non-coking coal can be used by Cement plants, Sponge Iron plants
and other industrial plants.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
19
M/s SMEL intends to beneficiate non-coking coal from IB Valley in Odisha, to upgrade its
quality for use in rotary kilns for DRI (Sponge Iron) production. The Middlings and other
products are to be further used in the proposed power plant. They are planning to set up
a plant of capacity 10,00,000 TPA that would accept (–) 20 mm coal for washing while
crushing and screening stage would accept –300 mm coal. They needed a solution for
reduction in ash of raw coal from various mines of IB valley from 38-60% to 27-36%
with surface moisture of 11-14%.
The heavy media cyclone washery consists of the following sub-systems -
Receiving and Sizing Section
Heavy Media Coal washing system
Media handling and recovery system
Process water handling and recovery system.
Receiving and Sizing Section
Raw coal is fed to a Raw Coal Hopper (Surge Bunker) for feeding to the washery. This
hopper is provided with a Grizzly of 200 mm. A Vibratory feeder draws the coal from the
hopper and feeds to a Primary Crusher preceded by a fixed screen for scalping the feed
to the primary crusher. The Primary crusher is operated in open circuit and envisaged to
reduce the size of the coal to 75 mm. This is followed by a second stage of crushing and
is set up in close circuit with a screen to ensure low generation of fines and close size
control for the products from the washery. The Vibratory screen classifies the material at
20 mm and the oversize material is sent to the crusher for crushing down to –20 mm.
The crushed fraction is re circulated back to the screen. The undersize of the screen (-
20+0 mm) is directed towards the surge bunker for feeding to the washing section.
Heavy Media Coal washing system
The -20+0 mm coal is tapped from the belt conveyor into the desliming screen for
removal of -1.0 mm material. Deslimed coal (-20+1.0 mm) is fed to the Correct Media
Tank, which also acts as the HM cyclone feed tank. Feed coal mixed with Media is
supposed to go to the HM cyclone through HM Cyclone feed pump. Admixture of coal and
media which is fed to the HM cyclone undergoes a density separation in the cyclone
where the clean coal below the cut density reports to the overflow. The middling which is
of a higher specific gravity suppose to report to the cyclone underflow. Both these
streams contain a mixture of coal and media.
Clean Coal Dewatering Screen is Double Deck Screen (5 mm & 0.5 mm). 20-5 mm
material is taken out directly and 5-0.5 mm material is passed through a centrifuge to
dewater the product
D. Induction Furnace
Steel melting scrap, direct reduced iron and pig iron/cast irons are the input raw
materials for an induction furnace. The ratio of these items and the technology of
melting these input materials varies according to the availability of raw materials and
location of the plant. Further selected raw materials is required for the production of
specific quality steel. For better and efficient operation of melting in induction furnace,
raw material charge must fulfill the following criteria.
It must be as dense as possible. Compaction of scrap is important for ensuring
uniform and rapid heating as well as for energy saving.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
20
It must be clean. Rust, oil, grease, and sand etc. should preferably be nil.
It must be metallurgically clean, i.e. free from slag lumps, oxides etc., particularly
for direct reduced iron, skull and ferro alloys.
There are no or less sharp pointed edges, particularly in case of heavy and bulky
scrap.
It must be segregated from harmful ingredients like explosives, closed containers,
evaporative substances and readily available in chargeable sizes on the shop
floor.
Electricity is the only energy source for steel melting in the induction furnace. Induction
furnace is to run at maximum power since beginning. There are some misconception of
running furnace at low tap initially and then gradually increase to higher tap. Maximum
power input increases rate of melting and hence reduces cycle time of a heat. Power
factor to be maintained near to one.
Important aspects of operation
As liquid steel is excited by current opposite to current flowing in induction coil, it is
agitated to raise its surface in the center. Surface of liquid steel is risen higher as
frequency becomes lower, i.e. agitation of the liquid steel occurs stronger in low-
frequency furnace than in high-frequency furnace. This effect of agitation makes it
possible to ensure uniform temperature of the liquid steel and its uniform quality as well
as to promote entrapment of material charged and fusion of chemical composition
adjusting agents, specially carbon addition. On the other hand, excessive agitation may
cause such troubles as oxidative wearing of liquid steel and fusing out of refractories or
danger of spattering of liquid steel.
The composition of the slag varies depending on the specific process being used and the
type of steel being produced. The compositions of furnace and ladle slags are often very
complex. The slag which is formed is the result of complex reactions between silica, iron
oxide from steel scrap, other oxidation by products from melting, and reactions with
refractory linings. The slag consists of a complex liquid phase of oxides of iron,
manganese, magnesium and silicon, silicates and sulfides plus a host of other
compounds, which may include Alumina, calcium oxides and sulfides, rare earth oxides
and sulfides etc.
While producing the steel, the chemistry of end product is controlled. The chemical
analysis of all the input materials is done to have a decision on the charge mix. After
completing 50 % charging of the input materials, a bath sample is analyzed for chemical
composition. Based on the chemical analysis of the bath sample at this stage calculations
are made for further additions of the metallics. If the bath sample at this stage shows
high percentage of carbon, sulphur and phosphorus then the direct reduced iron content
of the charge is increased. Final bath sample is taken when 80 % melting is completed.
Based on the analysis of this sample, another adjustment is made in the charge. The
lower content of carbon in the sample is corrected by increasing the quantity of pig
iron/cast iron in the charge. Silicon and manganese in the metal is oxidized by the iron
oxide of the direct reduced iron. Sulphur is also diluted by the direct reduced iron.
Because of use of direct reduced iron the trace elements in the steel made in the
induction furnace remains under control.
The liquid steel is the desired output of the induction furnace. The quantity depends
upon the capacity of the furnace, and the quality depends upon the raw materials and
the steel composition. The tapping temperature depends upon the type of steel and the
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
21
super heat needed in the liquid steel for its end use. Tapping of steel at high
temperatures increases refractory erosion and power consumption.
Unnecessary superheating of liquid steel to high temperature costs to energy
significantly. Minimizing the overheating of molten bath saves energy. Depending on
steel specification and temperature loss during transfer of liquid steel to continuous
casting machine, superheat temperature is to be decided. In every heat, temperature of
the liquid steel bath is to be measured and monitored to get optimum energy saving.
Proper power control systems with potentiometer adjustment need to be provided for
minimizing energy losses due to overheating.
Tilting of the furnace is to effect pouring of the melt is a last operational activity before
casting. The furnace is usually tilted to achieve an angle of 90 degree or greater for
complete pouring of the liquid steel.
The various types of Induction Furnaces used for Steel making are medium frequency
and high frequency core less. Raw materials used for Steel making from IF are Sponge
Iron, Pig iron and Scrap. Alloying elements are added as per the requirement and the
induction furnaces are provided with matching billet casters
E. Power Plant
Total power production has been envisaged at 175 MW, including existing 58 MW based
on running DRI.
Sum up of 175MW: - 58 MW WHRB + 117 MW FBC power would be produced. Boilers
will have same specifications, which are as follows.
Working Pressure 66kg/cm2 abs
Super heater temperature 4850C
BFW temperature 1300C
Operating hours 365x24hrs
The boilers will be complete with evaporator steam drum, mud drum, bank of super
heaters, economizers, ID fans, ESPs and internal piping etc. Soot blowing and de super-
heating system will also be provided.
F. Electric Arc Furnace
An electric arc furnace used for steelmaking consists of a refractory-lined vessel, usually
water-cooled in larger sizes, covered with a retractable roof, and through which one or
more graphite electrodes enter the furnace. The furnace is primarily split into three
sections:
the shell, which consists of the sidewalls and lower steel "bowl";
the hearth, which consists of the refractory that lines the lower bowl;
the roof, which may be refractory-lined or water-cooled, and can be shaped as a
section of a sphere, or as a frustum(conical section).
The roof also supports the refractory delta in its center, through which one or
more graphite electrodes enter.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
22
The hearth may be hemispherical in shape, or in an eccentric bottom tapping furnace
(see below), the hearth has the shape of a halved egg. In modern melt shops, the
furnace is often raised off the ground floor, so that ladles and slag pots can easily be
maneuvered under either end of the furnace. Separate from the furnace structure is the
electrode support and electrical system, and the tilting platform on which the furnace
rests. Two configurations are possible: the electrode supports and the roof tilt with the
furnace or are fixed to the raised platform.
A typical alternating current furnace is powered by a three-phase electrical supply and
therefore has three electrodes. Electrodes are round in section, and typically in segments
with threaded couplings, so that as the electrodes wear, new segments can be added.
The arc forms between the charged material and the electrode, the charge is heated
both by current passing through the charge and by the radiant energy evolved by the
arc. The electric arc temperature reaches around 3000 °C, thus causing the lower
sections of the electrodes to glow incandescently when in operation. The electrodes are
automatically raised and lowered by a positioning system, which may use either
electric winch hoists or hydraulic cylinders. The regulating system maintains
approximately constant current and power input during the melting of the charge, even
though scrap may move under the electrodes as it melts. The mast arms holding the
electrodes can either carry heavy busbars (which may be hollow water-
cooled copper pipes carrying current to the electrode clamps) or be "hot arms", where
the whole arm carries the current, increasing efficiency. Hot arms can be made from
copper-clad steel or aluminum. Large water-cooled cables connect the bus tubes or arms
with the transformer located adjacent to the furnace. The transformer is installed in a
vault and is water-cooled.
The furnace is built on a tilting platform so that the liquid steel can be poured into
another vessel for transport. The operation of tilting the furnace to pour molten steel is
called "tapping". Originally, all steelmaking furnaces had a tapping spout closed with
refractory that washed out when the furnace was tilted, but often modern furnaces have
an eccentric bottom tap-hole (EBT) to reduce inclusion of nitrogen and slag in the liquid
steel. These furnaces have a tap hole that passes vertically through the hearth and shell
and is set off-center in the narrow "nose" of the egg-shaped hearth. It is filled with
refractory sand, such as olivine, when it is closed off. Modern plants may have two shells
with a single set of electrodes that can be transferred between the two; one shell
preheats scrap while the other shell is utilized for meltdown. Other DC-based furnaces
have a similar arrangement but have electrodes for each shell and one set of electronics.
3.7 RAW MATERIAL REQUIRED AFTER PROPOSED CHANGES IN PELLET PLANT
AND CAPTIVE POWER GENERATION
Table 3.2 Annual Raw material requirement
Raw Materials (TPA) Total Raw
Material in
present EC
Conditions
Total Raw
Material in
Proposed
Conditions
Mode of
Transportation
Cooking Coal 774,648 774,648 By Rail
Chromite Ore 612,500 612,500 By Rail
Iron Ore Fines 803,660 1,838,660 By Rail
Iron Ore Lumps 818,923 168,923 By Rail
Coke Fines 50,772 57,500 By Rail
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
23
Indian Coal 2,238,075 1,066,825 By Rail
Imported Coal 38,175 559,052 By Rail
Total Quantity By
Rail
5,336,753 5,078,107
Iron Scrap 72,941 107,368 By Road
Lime 3,450 13,800 By Road
Dolomite 180,685 180,685 By Road
Quartz / Quartzite 141,460 141,460 By Road
Magnesite 25,000 25,000 By Road
Bentonite 2,243 8,970 By Road
Total Quantity By
Road
425,779 477,283
In addition to the above raw materials LDO/HSD, Electrode paste, Bentonite &
lubricating oil will also be required and procured from the local market on-demand.
Product marketing area
TMT rods & Ferroalloys has market all over India and Finished products are to be
transported through pollution compatible vehicles and fully covered to avoid flying with
air force or spillage on the public roads,
Raw Material Receipt & Store
Most of the raw material shall be received by rail or road. Separate store yard for the
major raw materials such as iron ore and coal exists and will be done by the
requirement.
Mode of Transport (Raw materials & products)
Transports will be done by the environmentally compliant trucks and covered trains also.
Bharat-III/ Euro-III trucks will be used in the transportation system. The raw materials &
products shall be covered fully during the transportation to avoid spillage & fugitive
emissions on the road & rail line. Major raw materials are carried in Railway racks to
their own private siding within the premises.
Raw Material Storage & Handling
Separate store yard for the major raw materials such as iron ore lumps, iron ore fines
lime stone/ dolomite, coal and Cr & Mn Ore etc are done. The material shall be unloaded
manually from the trucks in the stock yard. The yard shall have provision to store around
one months‟ stock of material.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
24
3.8 RESOURCE OPTIMISATION/RECYCLING AND REUSE ENVISAGED
IN THE PROJECT
The project is an integrated steel project. The final products are TMT rods, channels,
angle, & blooms. Total power generation from the project will be 175 MW which shall be
produced from WHRB, Coke Oven & gas and AFBC boilers. Total product mix after the
expansion cum modification of the project is given in the following table.
Following optimization, recycle &reuse measures have been proposed.
1) Steps proposed for optimization of power
a) Utilization of waste heat from DRI kiln to produce steam there by generation of
own power and reduction of power draw from state grid.
b) Surplus BF gas to be burnt to generate power
c) Utilization of waste dolchar to generate power thereby reduce power drawl
d) MBF top gas pressure recovery turbine to be set up to generate about 30kwh
e) Solar lighting on internal roads to optimize power consumption
f) Variable Frequency drive ID fans and blowers will draw less power for same
output.
g) Silicon-controlled rectifier to dimmer high voltage for ESPs used for DRI kilns.
h) Use of capacitor Bank to increase power factor.
3.9 AVAILABILITY OF WATER ITS SOURCE, ENERGY/POWER
REQUIREMENT AND SOURCE
3.9.1 WATER REQUIREMENT:
Water will be drawn from Hirakud Reservoir of river Mahanadi. Fresh water requirement
after the proposed change has been estimated to be 55702 KLD against 62612 KLD as
approved in EC and there will be a reduction of 6910 KLD.
Sl No. Items
Water
requirement for
Existing unit (in
KLD)
Water
requirement for
Proposed unit (in
KLD)
1 CLARIFLOCCULATOR 31306 27855
2 SOFTNER 19080 16260
3 DM PLANT 2613 2032
4 DRI-I 350 350
5 DRI-II 750 750
6 FAD 1990 1990
7 SMS-I 280 280
8 SMS-II 320 320
9 SMS-III 632 632
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
25
10 SMS-IV 816 816
11 MBF 2800 2800
12
ROLLING
MILL/STRUCTURAL
MILL/PIPE MILL/WRM
830 830
13 COKE OVEN 515 515
14 DRINKING
WATER/DOMESTIC WATER 300 250
15 FIRE FIGHTING MAKEUP 30 30
TOTAL 62612 55710
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
26
3.9.2 POWER REQUIREMENT FOR THE PROJECT
Power requirement
Power requirement as envisaged in EC was 225 MW. It is now reviewed and break -up will
be as follows.
Sl.No Facility Power requirement in MW
1 DRI Kilns 8.32
2 MBF 13.3
3 Pellet plant 5.1
4 S M S 103
5 Rolling mill 12
6 Ferro alloy Plant 50
7 Coke oven 1.9
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
27
8 Coal washery 3.5
9 A/C, domestic & miscellaneous 1.5
10 Power Plant internal consumption 17.5
Total 216.12
This power load has been estimated based on full load of all the units all the time.
Captive power generation 175 MW, hence about 40 MW Power has to be purchased from
state power grid to run all the facilities.
Manpower
No change in manpower as given in EC will remain unchanged with 3060. Breakup is as
follows.
Executives 155
Non-Executives 2905
Project Cost
The estimated expansion project cost in approved EC was 3,868 crore.
Now with 50 MW reduction in power plant, there will be significant reduction in
equipment cost in the order of about 150 crores, Cost of 9 Lakh TPA Iron ore pellet plant
will almost be of same value, so additional project cost for implementation will be about
25 crores.
Hence the total project cost will be around Rs 3893 crores
Project completion schedule
After getting CTE from SPCB, Odisha, the construction work can be started to complete
the project in less than one year of time.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
28
CHAPTER -4
PROPOSED INFRASTRUCTURE AND EMP
4.1 CONNECTIVITY
M/s Shyam Metalics & Energy Ltd. has its existing Steel Plant at: Pandoloi in Sambalpur
district of Odisha. The project is located at latitude: 210 40‟ 50.43‟‟ N and longitude 840
02‟ 30.63‟‟ E, with 208m AMSL.
The location is well connected by road and Rail, and existing project transportation is
going on this infrastructure.
4.2 LAND FORM, LAND OWNERSHIP
The total land required for the project is 294.84 ha out of which 127.05 ha has been
acquired and the balance acquisition is in process. The detailed breakup of the land is
given in the following table:
SL
NO Facilities
Total Land in
Ha
1 Plant facilities 42.0
2
Raw Material Yard &
Finished products 8.3
3
Office & other
permanent structures 0.93
4 Internal Road 1.0
5
Rain Water harvesting
system 6.2
6 Water Reservoir 3.8
7 Green Belt 97.3
8 Vacant Space 135.31
Total 294.84 ha
4.3 TOPOGRAPHY
The district has three distinctive physiographic units such as, Hilly Terrain of Bamra and
Kuchinda in the north, plateau and ridges of Rairakhol in the south-east and valley and
plains of Sambalpur Sub-division in the south east. The topography is undulating. The
area has thin alluvial cover and the soil is mainly reddish and not very much fertile. It is
a transitional zone having hard rock as well as alluvial terrain which are flat and gently
sloping.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
29
4.4 SOIL CLASSIFICATION:
The west coarse gritty soil blended with rock fragments is formed from the weathering of
pegmatites, quartz veins and conglomeratic sandstones, where as sandy soil
characteristic of granitic rocks and sandstones. This soil is of reddish colour, medium to
coarse in texture, acidic in reaction, low in nitrogen, calcium, phosphate and other plant
nutrients. Water holding capacity of this soil increases with depth as well as with the
increase of clay portions. Towards the east alluvial soil attains an enormous thickness in
the low level plains to the east. This alluvial soil is formed of alluvium brought down by
the Ajay, Damodar, Bhagirathi and numerous other rivers. These soils are sandy, well
drained and slightly acidic in nature.
The soil type of the Core zone of the study area is fine loamy typic endoaquepts in
nature. The prevailing soil types in the study area are mostly belongs to fine loamy typic
ustochrepts. The other soil types found in the study area are loamy skeletaltypic
ustochrepts, coarse loamy fluventic ustochrepts, fine loamy typic haplustalfs, fine loamy
udic ustochrepts, fine loamy udifleventivic ustochrepts
4.5 CLIMATIC DATA FROM SECONDARY SOURCE
The district experiences a warm temperate rainy climate with mild. The cold season
starts from about the middle of November and continues till the end of February. March
to May is dry summer intervened by tropical cyclones and storms. June to September is
wet summer while October and November is autumn.
Secondary information on meteorological conditions has been collected from the nearest
IMD station at Jharsuguda and IMD Book (1970-2000).
The drinking water will be met through overhead tank of existing plant
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
30
CHAPTER -5
PLANNING BRIEF
5.1 PLANNING CONCEPT
The plant is an integrated steel plant having semi-mechanized operation. It is a labor
intensive project. However, depending on the production schedule, there will be
technical labor engaged for operation.
The raw materials shall be transported through covered trucks by road up to the nearest
siding for further transportation by rail. And the finished products will be transported by
both rail and road. The transportation load will not add much to the existing load on the
said road system.
Appropriate plantation program shall be undertaken along with the developmental
program to at least cover the boundary areas with thick and tall plants for containment
of the air borne pollutants within the premises, which is duly reflected in the land use
plan.
There will not be any further infrastructural development other than needed for the
commissioning of the total project component machineries. This revised expansion shall
utilize the existing infrastructural facilities for all purposes.
5.2 PERIPHERAL DEVELOPMENT PLAN
M/s Shyam Metalics & Energy Limited will make sincere efforts to improve the socio-
economic status of the local habitants. A welfare scheme will be prepared by the
company for the socio- economic development of the area. The scheme will envisage
promotion of education in the adjoining villages by giving aid to the local schools,
providing drinking water facility and organizing health check-up programs. Local people
will be given free seedlings to develop greeneries all around. The progress of the scheme
will be reviewed periodically and further action will be taken as deeming fit. This has
already been mentioned in EIA report submitted for getting prior EC for the project.
5.3 LAND USE PLANNING
The total land required for the project is 294.84 ha out of which 127.05 ha has been
acquired and the balance acquisition is in process. The detailed breakup of the land is
given in the following table:
SL
NO Facilities
Total Land in
Ha
1 Plant facilities 42.0
2
Raw Material Yard &
Finished products 8.3
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
31
3
Office & other
permanent structures 0.93
4 Internal Road 1.0
5
Rain Water harvesting
system 6.2
6 Water Reservoir 3.8
7 Green Belt 97.3
8 Vacant Space 135.31
Total 294.84 ha
5.4 BENEFITS TO THE REGION AND THE COUNTRY
M/s Shyam Metalics & Energy Limited shall produce TMT rods, channels and angles &
Blooms that are to be utilized in construction activities and industries. The products are
in demand and production shall contribute to the GDP growth of the country.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
32
CHAPTER -6
PROPOSED INFRASTRUCTURE
6.1 INDUSTRIAL AREA DISTRIBUTION
The total land required for the project is 294.84 ha out of which 127.05 ha has been
acquired and the balance acquisition is in process.
6.2 GREENBELT DEVELOPMENT
In order to combat the air pollution, noise pollution and also to improve the aesthetic,
the company proposes to develop greenbelt, landscaping and avenue plantation. 33% of
the total area i.e. about 97.3 ha of land will be demarcated for green belt purpose.
6.3 CONNECTIVITY
M/s Shyam Metalics & Energy Ltd steel project is located at Pandoloi, in Sambalpur
district of Odisha. The project site is at latitude 210 40’ 50.43’’ N and longitude 840
02’ 30.63’’ E, MSL 208m. The project is located on state Highway joining Sambalpur-
Rourkela, NH-6 and 42 exist at a distance of about 25km from the site. SH-10 is passing
by the side of the project. The project is by the side of Railway line of Sambalpur-
Jharsuguda section. The nearest railway station Rengali is 8 km away from project site.
6.4 DRINKING WATER MANAGEMENT:
The drinking water will be met through ADDA supply. Around 15 KLD will be used for
drinking purposes.
6.5 INDUSTRIAL WASTE MANAGEMENT
Emission Management after proposed change in configuration
Two changes have been proposed in approved EC:
50 MW AFBC based power plant to be dropped; additional 6 lakh TPA I/O pellet plant to be
installed; existing 3 lakh TPA plant to be upgraded to 6 lakh TPA;additional 11 x 18 TPA IF
to be added with reduction in SMS capacity and Coal Washery.
Revised Solid waste generation & its Management
Sl.No Facility Generated
waste
Quantity in
TPA as per
EC
Revised
Quantity in
TPA
Management
1 Coal Washery Middling &
Rejects
9,98,000 6,10,000 FBC fuel
2 Coke Oven Coal Fines 28,750 28,750 8970 TPA to
Pellet Plant &
19780 TPA to
Sinter Plant
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
33
Bottom dust 4,379 4,379 Land fill
3 DRI Kilns FLY Ash 1,01,155 46,560 Brick
Manufacturing
Dolchar 5,06,000 5,06,000 AFBC Boiler fuel
4 Sinter Plant Dedusting dust 1,28,935 1,28,935 Recycling for
sinter making
5 Pellet Plant Dedusting dust 54,180 2,16,720 Used in Sinter
Plant
6 PGP Plant Tar & Tar oil 1,037 4,075 Reused in Pellet
Plant Kiln
7 MBF Dust & Fines 2,75,010 2,75,010 Used in Sinter
Plant
Slag 2,22,750 2,22,750 Cement Plant
8 S M S Slag 37,059 1,72,574 Road making &
land filling
Scrap 48,524 74368 Recycled in IF
8 FBC Fly ash 8,50,492 6,94,567 Reused in Brick
Industry
9 Ferro alloy plant Bag House
Dust
3,400 3,400 Land fill
6.6 POWER REQUIREMENT
Power requirement after expansion will be about 216 MW and captive generation will be
175 MW, hence about 40 MW will be purchased from DVC.
6.6 INDUSTRIAL POLLUTION CONTROL
Estimation of Pollution load change
6.5.1 Air pollution
Pollution Load Estimate due to Transportation:
Basis of Estimation:
Mode of Transportation Existing Proposed
By Rail Rack 5336753 5078107
By Road 425779 477283
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
34
No, of Trucks (16T) in to-
and-fro traffic
53722 59660
No. of PCU equivalents 171912 190913
Area of the Siding 28752 m2
Traffic Pollution Load Estimation:
Existing Pollutant Quantity
PM10
mg/m3
SO2
mg/m3
Nox
mg/m3
CO
mg/m3
Total No.
of
Vehicles
in PCU
Fugitive
emissions
TPA
Traffic
Pollution
1.71912 8.251776 5.501184 1.203384 171912 0.005054
Railway
Siding
64.39
Proposed Pollutant Quantity
PM10
mg/m3
SO2
mg/m3
Nox
mg/m3
CO
mg/m3
Total No. of
Vehicles in
PCU
Fugitive
emissions
TPA
Traffic
Pollution
1.90913 9.163824 6.109216 1.336391 190913 0.005613
Railway
Siding
77.09
Net Change in Traffic Pollutant Quantity w/o any EMP
PM10
mg/m3
SO2
mg/m3
Nox
mg/m3
CO
mg/m3
Fugitive
emissions
TPA
Traffic 0.19001 0.912048 0.608032 0.133007 0.000559
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
35
Implemented EMP Measures (As-on-date)
1. There are 44 Sprinklers installed at the Railway Siding
2. There are 64 sprinklers installed along the haulage road inside the plant premises
Net Change in Pollutant Quantity after EMP
PM10
mg/m3
SO2
mg/m3
Nox
mg/m3
CO
mg/m3
Fugitive
emissions
TPA
Traffic
Pollution
-1.33729 0.912048 0.608032 0.133007 -0.003932
Railway Siding -48.97
Ambient Air Pollution Load Estimation:
Only the units with probable emissions are considered for this evaluation
Sl.
No.
Plant Unit Existing EC
Status /
Proposed
Existing Pollutant Quantity
SPM
(TPA)
SO2
(TPA)
NOx
(TPA)
CO2
(TPA)
1
Pellet
Existing 194 382 42 1650
1 Proposed 774 563 168 6600
3
DRI
Existing 481 4800 NA 42
3 Proposed 481 3722 NA 42
4
Power Plant
Existing 1130 6288 4533 15768
4 Proposed 878 4061 3526 12264
5
SMS
Existing 101 NA NA 21
5 Proposed 75 NA NA 11
6
SINTER
Existing 7410 593 NA 78
6 Proposed 7410 593 NA 78
6 MBF Existing 33001 NA NA NA
Pollution
Railway Siding 12.70
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
36
6 Proposed 33001 NA NA NA
7
SAF
Existing 10.4 8.32 NA 5.30
7 Proposed 10.4 8.32 NA 5.30
8 Coke Oven
Plant
Existing 65.89 207.8 NA NA
8 Proposed 65.89 207.8 NA NA
Net Change in Ambient Air Pollution Load:
SPM
(TPA)
SO2 (TPA) NOx (TPA) CO2
(TPA)
Total pollution Load in
present EC Conditions
42393 12280 4575 17522
Total Pollution Load in
Proposed Conditions
42621 9156 3694 18947
Net Change in Pollution Load 228 -3124 -881 1425
Pollution Control Equipments
Sl.
No.
EC Status
Existing /
Proposed
Pollution Control
Systems
Implemented
1 Pellet Plant ESP & Bag House
2 DRI Bag House
3 Power Plant ESP Attached to
AFBC
4 SMS
Fume Extraction
System
Cyclone Separator
5 Sinter Plant Bag House
6 MBF GCP + Flaring
7 SAF Fume Extraction
System
8 Coal Washery ETP
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
37
6.6.2 WATER POLLUTION CONTROL
The waste water from canteen and office toilets will be sent to a soak pit. Canteen waste
water will be treated in a separate ETP consisting of O & G trap, settling tank, anaerobic
treatment system & gravity sand filter. Sewage from toilets will be treated in septic tank
and discharged to soak pit.
6.7 MAN POWER REQUIREMENT
The total man power requirement for plant operation on completion of the proposed
project will be around 3060 and extra 50 nos. for Security.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
38
CHAPTER -7
REHABILITATION & RESETTLEMENT
REHABILITATION & RESETTLEMENT
The proposed expansion units will be implemented in the existing plant premises. The
existing lands were already derived as industrial land. As settlement will not be affected
so, no R&R facility is anticipated.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
39
CHAPTER -8
PROJECT SCHEDULE
8.1 IMPLEMENTATION SCHEDULE
Time schedule for completion of various activities is given below in Table 8.1. The zero
date will commence after getting EC and consent to establish from SPCB.
Table 8.1: Tentative implementation schedule:
Sl.
No.
Activities Duration
1 Engineering
Concept Design 15 days
Basic Engineering 30 days
Detailed Engineering 90 days
2 Civil Work
Land development 15 days
Construction of plant & auxiliary facilities 150 days
3 Statutory Clearance for establishment
State clearance for establishment 20 days
State EC Clearance 90 days
4 Procurement
Place orders for long lead Equipments 90 days
Place orders for commodity items 30 days
Receipt of equipment 230 days
Installation of equipment & items 180 days
5 Erection & Commission
Inspection before commissioning 80 days
Commissioning & production trial run 40 days
Some works will proceed parallel and some in series. Critical Path Method (CPM) and
Project Evaluation & Review Technique (PERT) will be followed for completion of project
work. In short construction job will be completed within two years of time after getting
EC from MoEF&CC.
8.2 ESTIMATED PROJECT COST
Project Cost
The estimated expansion project cost in approved EC was 3,868 crore.
Now with 50 MW reduction in power plant, there will be significant reduction in
equipment cost in the order of about 150 crores, Cost of 9 Lakh TPA Iron ore pellet plant
will almost be of same value, so additional project cost for implementation will be about
25 crores.
Techno Economic Feasibility Report of M/s Shyam Metalics & Energy Ltd At: Pandloi, Dist: Sambalpur, Odisha
Global Tech Enviro Experts Pvt. Ltd.
40
CHAPTER-9
ANALYSIS OF PROPOSAL (FINAL RECOMMENDATION)
9.1 FINANCIAL & SOCIAL BENEFITS
The proposed expansion project is expected to bring socio-economic and environmental
benefits both at local and global level as listed below:
9.2 SOCIAL INFRASTRUCTURE
Social awareness programs will be further improved by the local authority such as
sanitation and hygiene, HIV Prevention Program.
Through this project, adult education and female education will be provided to the
illiterate adults and backward females of the villages in the project surrounding
area.
The proposed expansion project will set up training center for the male and
female youth group by considering their skills and qualification which will support
the people for self-employment.
9.3 EMPLOYMENT POTENTIAL
The project is going to create substantial employment and income. Due to this project
activity, some persons in the project area will be recruited as skilled and semi-skilled
workers by the company as per its policy. Therefore, substantial amount of employment
and income is likely to be generated for the local people. So, the project will contribute
in a positive manner towards direct employment in the project area. Some employment
potential benefits are given below:
Long term employment of up to additional 80 people in the operation phase of
the proposed expansion project.
Generating additional associated jobs due to establishment of the project.