ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
ASHLAND COUNTY 1
Ashland County Projects PID
Number Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor Maintenance of Traffic
98252 ASD/HUR
SR 511/SR 162 0.00/19.98
Chip Seal SR 511, from SR 39 to US 30. SR 162, from US 250 to New London
Corp. Limit 08/09/18
05/01/19 07/19/19
$582,292.06 Melway Paving
Traffic maintained by flaggers
94432 ASD SR 95
01.20 Bridge Deck Replacement
In the Village of Perrysville 10/01/18 06/03/19 08/30/19
$954,845.11 Shelly & Sands
60 day detour
94430 ASD US 42
00.15 Bridge
Replacement Near Richland County line, over
Brindle Creek 10/11/18
02/04/19 06/28/19
$859,765.21 V O Menuez &
Son 60 day detour
96318 ASD/MED
SR 58/SR 301 00.61/08.61
Minor Rehabilitation
Beginning at the Ashland City Corp limit to Lorain County line.
Beginning just south of Spencer Mills Rd and ending at the Lorain
County line.
11/08/18 04/01/19 09/28/19
$4,919,991.15 Shelly & Sands
Traffic maintained by flaggers
107013 Mohican State
Park Parking Lot
Upgrade Mohican Lodge Parking Lot 01/24/19
03/01/19 05/14/19
$351,352.10 Barbicas
Construction
Traffic maintained by flaggers with parking lot
closures as needed
98573 ASD SR 60/96 16.22/05.63
Resurfacing From the southern Ashland City
Corp. limit to US 250 Bypass. From SR 60 to US 42/250
05/23/19 06/30/19 08/31/19
$1,028,000.00 Unknown
Traffic maintained by flaggers
88847
ASD SR 179 05.64
Bridge Replacement
Just south of Twp. Rd. 2252, over Gharst Run
07/11/19 09/02/19 11/02/19
$495,000.00 Unknown
60 day detour
90912 ASD US 224
11.12 Culvert
Replacement US 224, just east of SR 58 09/26/19
01/01/20 12/31/20
$350,000.00 Unknown
Traffic maintained at all times
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
ASHLAND COUNTY 2
108920 ASD SR 3 05.63
Smooth Seal
From the Village of Loudonville, in
Ashland County, to the City of Wooster, in Wayne County
09/26/19 04/01/20 11/30/20
$3,199,000.00
Unknown
Traffic maintained by flaggers
102960 ASD FY 2020 Smooth
Seal
US 250, the City of Ashland Corp limit to Bailey Lakes. US 60, from Village of Haysville to US 30. SR
179, from the Holmes County line to SR 60
12/12/19 04/01/20 11/30/20
$3,059,000.00 Unknown
Traffic maintained by flaggers
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
ASHLAND COUNTY 3
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
ERIE COUNTY 4
Crawford County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor
Maintenance of Traffic
77480 CRA US 30
04.02 Minor
Rehabilitation The Bucyrus Bypass, from CR 330 to
Lower Leesville Rd. 01/10/19
04/01/19 09/27/19
$6,953,000.00 Unknown
Traffic maintained at all times
30 day detours for ramps at SR 98
45 day detour for Homles Center Rd.
101356 CRA SR 4
06.72 Resurfacing
SR 4, from the southern Corp. limit of Bucyrus to South Sandusky Ave.
02/21/19 06/01/19 08/31/19
$600,000.00 Unknown
Traffic maintained by flaggers
94434 CRA SR 97
02.64 Bridge
Replacement Bridge over Olentangy River, just
east of Galion Millsboro Rd. 03/07/19
04/01/19 12/31/19
$600,000.00 Unknown
45 day detour
104117 CRA SR 4
09.31 Resurfacing From Perry St. to SR 19 05/16/19
07/15/19 11/30/19
$1,698,000.00 Unknown
Traffic maintained by flaggers
102970 CRA Smooth Smooth Seal
SR 19, from Galion West Corp. Limit to Bucyrus East Corp. Limit. SR 4, from Bucyrus North Corp. Limit to Seneca County Line. SR 97, from
Millsboro Rd. to Morrow County Line
06/20/19 08/01/19 09/30/19
$3,093,000.00 Unknown
Traffic maintained by flaggers
90883 CRA SR 4
19.13 Bridge Repair
Just north of South Intersection of SR4/SR103, over Sycacamore Creek
08/22/19 07/01/20 08/31/20
$517,000.00 Unknown
60 day detour
101409 CRA SR 19
16.08 Minor
Rehabilitation From CR 16 to just north of CR 27 09/26/19
06/01/20 09/30/20
$2,109,000.00 Unknown
Traffic maintained at all times
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
ERIE COUNTY 5
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
ERIE COUNTY 6
Erie County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor
Maintenance of Traffic
98466 ERI US 6 03.64
Smooth Seal From Sandusky Co. line to the City
of Sandusky 08/23/18
06/03/19 08/02/19
$676,840.70 Erie Blacktop
Traffic maintained by flaggers
94444 ERI/MED Bridge Repair Various locations in Erie and
Medina Counties 01/10/19
04/01/19 08/31/19
$688,000.00 BCC
Traffic will be maintained using lane closures, short term closures will be used
on some ramps
103921 ERI US 6 13.19
Culvert West of Cedar Point Rd. 01/10/19 05/01/19 06/28/19
$150,000.00 Eclipse
14 day detour
105587 ERI SR 2 14.06
Bridge Repair
The Camp Rd. overpass, between Galloway Rd. and Rye Beach Rd./ the Hahn Rd. overpass, between
SR61 and Frailey Rd./ the Joppa Rd. overpass, between
Frailey Rd. and Barnes Rd.
10/01/19 04/01/20 10/31/20
$430,000.00 Unknown
One lane of traffic in each direction
maintained at all times, with 45 day
detours at Camp, Hahn and Joppa Rds.
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
HURON COUNTY 7
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
HURON COUNTY 8
Huron County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor
Maintenance of Traffic
87698 HUR US 20
16.26 Smooth
Seal
US 20, from the City of Norwalk Corp. limits, to just east of the
Village of Wakeman. 08/23/18
09/04/18 08/15/19
$6,968,891.89 Erie Blacktop
One lane of traffic maintained in each direction. Flagging
operations as needed
97387 HUR US 20
25.62 Bridge Repair
US 20 over the Vermilion River in Village of Wakeman
11/08/18 02/25/19 09/30/19
$1,566,224.90 Suburban
Maintenance
Two lanes of traffic maintained at all times, with the
exception of one lane of traffic maintained using signals for 30
days.
90918 HUR US 224
17.09 Bridge
Replacement East of Townsend St 01/10/19
04/01/19 10/11/19
$650,000.00 R & I
Construction
60 day detour
101524 HUR US 224
06.79 Drainage Repair US 224, at Bullhead Rd. 04/04/19
06/01/19 10/31/19
$183,000.00 Unknown
30 day detour
103922 HUR SR 269
02.70 Culvert
Replacement SR 269, just north of E. CR 32 05/16/19
07/01/19 09/02/19
$150,000.00 Unknown
30 day detour
102068 HUR US 20
12.80 Slide Repair Between SR 18 and US 250 06/06/19
08/01/19 09/30/19
$842,000.00 Unknown
Single lane closures
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
HURON COUNTY 9
101252 HUR SR 269
05.49 Resurfacing
HUR SR 269, from South Corp. limit to North Corp. in City of
Bellevue HUR SR 269, from Robert Ave. to
Center St. HUR SR 113, from East Main St.
to Lime City ERI SR 269, from the Huron County line to Potter Rd.
01/24/19 06/01/19 08/15/19
$1,040,738.85 Gerken Paving
Inc.
Traffic maintained by flaggers
90902 HUR SR 162
04.13 Bridge
Replacement Just west of Miller Rd. 09/26/19
06/08/20 08/21/20
$579,000.00 Unknown
60 day detour
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
HURON COUNTY 10
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
LORAIN COUNTY 11
Lorain County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor
Maintenance of Traffic
82632 LOR US 20
22.19 Major
Rehabilitation US 20 from Stoney Ridge Rd to
Lear Nagle Road 11/30/17
04/02/18 10/11/19
$26,874,800.65 Fechko
One lane of traffic maintained in each direction. Various
intersecting side street closures.
92013 LOR US 6
09.67 Bridge Repair
Near the intersection of US 6 and SR 57
01/25/18 04/02/18 12/31/19
$26,332,328.83 The Ruhlin Co.
One lane of traffic maintained in each
direction. Up to three different closures of
US 6, that will be limited to 7 days for operating equipment
installation
84591 LOR IR 90
11.78 Bridge
Replacement I-90 WB structure over SR 2 EB 08/23/18
11/01/18 10/31/19
$2,243,732.30 J D Williamson
Single lane closures
98394 LOR SR 18
00.00 Minor
Rehabilitation From the Huron County line to the
Medina County line 09/27/18
05/01/19 07/31/19
$3,367,452.56 Karvo
Traffic maintained by flaggers
107021 LOR SR 511
00.00 Micro
Surfacing From the Ashland County line to
US 20 01/24/19
06/01/19 09/01/19
$1,059,104.21 Strawser
Construction
Traffic maintained by flaggers
102660 LOR US 20
20.47 Bridge
Replacement US 20 over Ridgeway Ditch 04/04/19
06/01/19 10/30/19
$1,462,000.00 Unknown
One lane of traffic maintained in each
direction at all times
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
LORAIN COUNTY 12
102874 LOR SR 113
11.66 Resurfacing
From the west corp. limits of the City of Elyria to SR 57
04/04/19 06/01/19 09/30/19
$2,148,000.00 Unknown
Traffic maintained by flaggers
108894 LOR/MED Micro
Surfacing
LOR SR 57 & US 20, at 4-lane divided intersection. LOR SR 83, from Medina County line to SR
303. MED SR 83, form Lodi North Corp. limit to SR 18
04/18/19 06/01/19 09/30/19
$1,283,000.00 Unknown
Traffic maintained by flaggers
84829 LOR SR 301
26.67 Major
Rehabilitation Through the City of Sheffield Lake 05/02/19
06/15/19 10/15/19
$1,413,000.00 Unknown
120 day detour, local access only
95578 LOR SR 162
00.45 Bridge
Replacement SR 162 over Winston Creek 05/02/19
07/01/19 09/02/19
$210,000.00 Unknown
30 day detour
101359 LOR US 20
19.40 Roadway
Improvement From SR 301 to Case Rd. 05/02/19
07/01/19 04/30/20
$1,465,000.00 Unknown
Traffic maintained at
all times
88874 LOR SR 511
01.25 Bridge
Replacement SR 511, over a Tributary of Buck
Creek 05/23/19
08/01/19 10/01/19
$350,000.00 Unknown
45 day detour
102027 LOR SR 254
02.03 Turn Lane Addition
SR 254 northbound at the ramp to I-90 westbound
06/06/19 08/05/19 05/29/20
$2,013,000.00 Unknown
Two lanes of traffic in each direction
maintained at all times with single lane
closures as needed
98273 LOR SMOOTH
FY2020 Smooth
Seal Various locations throughout
Lorain County 06/20/19
08/01/19 06/30/20
$2,500,000.00 Unknown
Traffic maintained by flaggers
87706 LOR IR 90
10.76 Reactive
Maintenance From the Ohio Turnpike to SR 611 07/11/19
08/01/19 11/30/19
$500,000.00 Unknown
Single lane closures
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
LORAIN COUNTY 13
101387 LOR SR 301
22.33 Resurfacing
SR 301, from SR 254 to Colorado Ave. From Colorado Ave. to
Walker Rd. SR 611, from SR 301 to Miller Rd.
07/25/19 08/01/19 11/01/19
$1,663,000.00 Unknown
Traffic maintained by flaggers
94420 LOR SR 303
11.05 Minor
Rehabilitation SR 303, from Lagrange Corp. limit
to Medina County Line. 11/07/19
05/01/20 07/31/20
$2,981,000.00 Unknown
Traffic maintained by
flaggers
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
LORAIN COUNTY 14
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
MEDINA COUNTY 15
Medina County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor Maintenance of Traffic
14821 MED
N. Carpenter Road
Major Reconstruction
SR 303 to Boston Rd 02/01/18 03/12/18 08/15/20
$11,419,901.00 Shelly & Sands
One-way traffic for 240 days
99536 MED US 42
11.60/12.70 Culvert
Intersection of CR 15 and US 42/ Intersection CR 45 and US 42
09/13/18 04/15/19 06/28/19
$311,167.94 Stanley Miller Construction
14 day detour for each
location
90931 MED SR 94
18.66 Bridge
Replacement Just east of SR 606 10/25/18
06/01/19 09/30/19
$729,828.60 Lockhart Concrete
120 day detour
91092 MED IR 76
0.73 Smooth
Seal From Lake Rd. to the SR 57 Ramps 11/29/18
05/06/19 10/18/19
$3,569,993.20 Shelly & Sands
Single lane closures
100928 MED US 224
13.47 Intersection
Improvement US 224 at Westfield Center Rd, 05/23/19
07/15/19 12/15/19
$1,970,000.00 Unknown
One lane of traffic will be maintained in each direction at all times
106876 MED SMOOTH FY2019 (A)
Smooth Seal
SR 3, from Medina Corp. limit to just north of Fenn Rd., from just
south of Odessa Rd. to the Cuyahoga County line.
SR 252, from just north of SR 57 to Lorain County line.
SR 57, from SR 18 to just south of SR 252
06/06/19 06/30/19 10/31/19
$2,750,000.00 Unknown
Traffic maintained by flaggers
94436 MED SR 3
17.05 Bridge Repair SR 3 over Plum Creek 10/24/19
04/01/20 07/01/20
$700,000.00 Unknown
No impact to traffic expected
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
MEDINA COUNTY 16
94440 MED SR 303 13.90/14.96
Bridge Replacement
Culvert just west of State Rd./ Bridge just east of State Rd., west
of Summit County line 01/23/20
04/01/20 11/30/20
$1,475,000.00 Unknown
90 day detour
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
MEDINA COUNTY 17
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
RICHLAND COUNTY 18
Richland County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor
Maintenance of Traffic
88885 RIC SR 545
09.93 Bridge Repair
Bridge over Levi’s Creek, just south of Olivesburg
06/07/18
10/01/19 06/30/19
$290,235.60 Adena Corp.
30 day detour
87721 RIC IR 71
06.39/10.77 Minor
Rehabilitation IR 71, from the 6.39 to the
Ashland County line. 06/21/18
08/15/18 08/31/19
$8,566,636.00 Shelly & Sands
Single and two-lane closures
102954
HUR SR 103 / HUR SR 598 / RIC SR 13 / RIC SR 39 / RIC SR 598
Smooth Seal
Various locations in Huron and Richland Counties
07/12/18 08/01/18 08/01/19
$2,829,700.00 Kokosing
Traffic will be maintained by flaggers
94441 RIC SR 97
15.78 Bridge Deck Replacement
Just east of the intersection with Narrow Rd
10/11/18 03/01/19 05/31/19
$649,900.00 Kelstin Inc
21 day detour
94403 RIC SR 97
10.53 Minor
Rehabilitation From the Bellville Corp. limit to
SR 3,in Ashland County 03/07/19
04/15/19 10/30/19
$4,381,000.00 Unknown
Traffic maintained by flaggers
102957 RIC US 42
13.13
Minor Rehabilitation
From the City of Mansfield Corp. limit to S. Baney Rd.
03/07/19 06/01/19 10/25/19
$3,298,000.00 Unknown
Traffic maintained by flaggers
87728 RIC US 30
04.07 Minor
Rehabilitation From 4th St. to SR 309 06/20/19
08/01/19 06/30/20
$3,270,000.00 Unknown
Single lane closures
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
RICHLAND COUNTY 19
102058 RIC SR 603
00.05 Slide Repair Just west of SR 95 09/26/19
11/01/19 12/16/19
$1,242,000.00 Unknown
45 day detour
94405 RIC US 42
03.48 Minor
Rehabilitation From just south of Fox Rd., to
the Mansfield Corp. limit 10/10/19
05/01/20 08/31/20
$1,777,000.00 Unknown
Traffic maintained by flaggers
87722 RIC IR 71
00.00 Minor
Rehabilitation From the Richland County line to
the Mansfield City limits 11/07/19
05/01/20 11/01/20
$7,298,000.00 Unknown
Single and two-lane closures
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
RICHLAND COUNTY 20
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
DISTRICT WIDE PROJECTS 21
Wayne County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor Maintenance of Traffic
101400 WAY SR 83
00.00 Minor
Rehabilitation From the Holmes County
line to just north of SR 302 10/25/18
05/01/19 09/30/19
$3,551,696.85 Kokosing
Traffic maintained by flaggers
90941 WAY SR 302
02.18 Bridge
Replacement Just south of Vanover St. 01/31/19
04/01/19 07/31/19
$776,000.00 Unknown
90 day detour
98492 WAY SR 585
02.22 Minor
Rehabilitation From the City of Wooster
to SR 57 03/07/19
05/15/19 10/15/19
$2,266,000.00 Unknown
Traffic maintained by flaggers
101436 MED/WAY SR 3/SR 57
Preventative Maintenance
Micro Surfacing
From the Wayne County line to just south of IR 76. From south of Jackson Rd., to south of Crestview Dr.
From US 30 to South Orrville Corp. limit. From north Orrville Corp. limit to Rittman Corp. From
27.25-28.35
04/18/19 06/01/19 09/30/19
$1,166,000.00 Unknown
Traffic maintained by flaggers
102109 WAY US 30
23.33 Intersection Improvement
US 30, at Wenger Rd., in the Village of Dalton
05/02/19 07/01/19 10/31/19
$424,000.00 Unknown
One lane of traffic in each direction will be maintained at all
times
103920 WAY SR 604/301
20.65/04.50
Culvert Replacement
Just west of SR 94/ Just north of TR 409 (Massie
Rd.) 05/16/19
07/15/19 10/15/19
$240,000.00 Unknown
21 day detour for SR 604/ One lane in each direction for SR 301
88886 WAY SR 83
00.62/00.74 Bridge
Replacement
Between CR 2 (Harrison Rd.) and CR 289 (Force
Rd.) 12/12/19
05/28/20 08/31/20
$720,000.00 Unknown
75 day detour
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
DISTRICT WIDE PROJECTS 22
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
DISTRICT WIDE PROJECTS 23
District Wide Projects
PID Number
Route & Section
Work Type Location
Sale Date Est. Start
& Est. Ed
Est. Cost &
Contactor Maintenance of Traffic
104285 D03 PR FY2019
Pruning, Tree/Bush Removal
Various locations throughout District 03
07/26/18 10/03/18 12/15/19
$650,000.00 Van Curen
Traffic maintained at all times
98252 D03 CHIP FY2019
Preventive Maintenance
Ashland County: SR 511 beginning at SR 39 and ending
at US 30 Huron County: SR 162
beginning at US 250 and ending at the New London Corp line
08/09/18 05/01/19 07/19/19
$573,000.00 Melway Paving
Traffic maintained by flaggers
98254 D03 CRSEAL
FY2019 Crack Seal
Various routes and sections throughout District 03
08/20/18 09/15/18 07/31/19
$448,993.35 Scodeller
Construction Traffic maintained by flaggers
98250 D03 SMOOTH
FY2019 Smooth Seal
MED SR 42 from WAY Co. to South of Congress Rd./ MED US 42 bridge over US 224 to MED Corp./ MED US 224 from ASD
Co. to US 42/ WAY SR 42/ WAY 539 from West Salem Corp. to
SR 301
08/23/18 03/15/19 07/31/19
$3,361,688.35 Ronyak Paving
Single lane closures- traffic maintained by flaggers on specific
routes
106929 D03 PR
FY2019 (B)
Pruning, Tree/Bush Removal
Various locations throughout the District
10/25/18 12/20/18 12/15/19
$372,445.00 Van Curen
Traffic maintained at all times
90194 MED I-71/76-22.71/05.29
Lighting IR 76 Weigh Station
IR 71 Northbound Rest Area 11/08/18
03/01/19 10/31/19
$355,553.00 Perram Electric
Traffic maintained at all times
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
DISTRICT WIDE PROJECTS 24
104147 D03 GR FY2019
Guardrail Maintenance
Various locations throughout the District
12/13/18 02/01/19 01/31/20
$688,375.00 Lake Erie
Construction Traffic maintained at all times
99654 D03 TSG FY2019
Signals Various locations throughout
the District 01/24/19
03/01/19 03/01/20
$408,515.00 Asplundh
Cosntruction Traffic maintained at all times
94443 D03 BH
FY2019 (A) Bridge Repair
Various locations throughout the District
03/21/19 04/30/19 10/30/19
$536,000.00 Unknown
Traffic maintained at all times. 14 day detour for SR 83
105333 D03 LG
FY2019(A) Lighting
Various locations throughout the District
03/21/19 05/01/19 08/30/19
$150,000.00 Unknown
Traffic maintained at all times
101833 D03 PM FY2019
Loop Detector Repair
Various locations throughout the District
04/04/19 06/17/19 05/31/21
$150,000.00 Unknown
Traffic maintained at all times
98927 HUR/WAY CULVERT FY2019
Culvert Replacement
HUR US 20, just west of SR 18/ WAY SR 21, just north of the
Stark County line 04/18/19
05/01/19 10/01/19
$200,000.00 Unknown
Traffic maintained at all times
98933 D03 PM FY2019
Pavement Marking
Various locations throughout the District
05/02/19 07/01/19 07/31/20
$1,600,000.00 Unknown
Traffic maintained at all times
98256 HUR/LOR RM
FY2019 Mill and Fill
Various locations in Huron and Lorain Counties
05/16/19 08/01/19 10/31/19
$500,000.00 Unknown
Traffic maintained by flaggers
106419 D03 GR
FY2019 NHS Guardrail
Replacement
Various locations in Ashland, Lorain, Medina and Wayne
Counties 05/23/19
06/30/19 12/31/19
$666,000.00 Unknown
Traffic maintained at all times
98931 D03 RPM FY2019
Raised Pavement Markings
Various locations throughout the District
06/06/19 07/01/19 07/31/20
$200,000.00 Unknown
Traffic maintained at all time
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
DISTRICT WIDE PROJECTS 25
104286 D03 PR FY2020
Pruning, Tree/Bush Removal
Various locations throughout the District
07/25/19 10/03/19 09/30/20
$650,000.00 Unknown
Traffic maintained at all times
98275 D03 CRSEAL
FY2020 Crack Seal
Various locations throughout the District
08/22/19 09/03/19 11/02/19
$400,000.00 Unknown
Traffic maintained by flaggers
109054 D03 GR
FY2020(A) Guardrail
Maintenance Various locations throughout
the District 10/10/19
02/01/20 01/31/21
$1,250,000.00 Unknown
Traffic maintained at all times
103475 D03 PR
FY2020 (B)
Pruning, Tree/Bush Removal
Various locations throughout the District
10/24/19 12/04/19 12/04/21
$120,000.00 Unknown
Traffic maintained at all times
105359 D03 TSG FY2020
Signals Various locations throughout
the District 11/07/19
01/01/20 12/31/20
$442,000.00 Unknown
Traffic maintained at all times
98928 D03 CULVERT
FY2020 Culvert
Replacement MED US 224 just East of Lake
Rd. 11/21/19
01/01/20 12/31/20
$350,000.00 Unknown
Single lane closures
104148 D03 GR FY2020
Guardrail Maintenance
Various locations throughout the District
11/21/19 02/01/20 01/31/21
$650,000.00 Unknown
Traffic maintained at all times
95585 D03 BH
FY2020 (A) Bridge Repair
Various locations on I-71 in Ashland and Richland Counties,
and US 30 in Ashland County 12/12/19
01/01/20 12/31/20
$425,000.00 Unknown
Traffic maintained at all times
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
DISTRICT WIDE PROJECTS 26
ODOT DISTRICT 3 2019 CONSTRUCTION PROGRAM
DISTRICT WIDE PROJECTS 27
To provide easy conveyance of people
and goods from place to place, we will:
Take care of what we have;
Make our system work better;
Improve safety;
Enhance capacity
A long-term, reliable, professional and
highly productive organization
O U R M I S S I O N
O U R V I S I O N
For more information, Bob Weaver, Acting District Deputy Director at (419) 207-7058,
Mike Fair, District Construction Engineer, at (419) 207-7087; or
Public Information Office at (419) 207-7181.
Like us on Facebook: www.facebook.com/OhioDepartmentofTransportationDistrict3
Follow us on Twitter: www.twitter.com/ODOT_NorthCenOH
Statewide Traffic Information: www.Ohgo.com
For general information, call (800) 276-4188 or visit District 3’s Web site at: www.transportation.ohio.gov/dist3