Upload
mostafa-0088
View
42
Download
0
Tags:
Embed Size (px)
DESCRIPTION
s
Citation preview
http://jvc.sagepub.com/Journal of Vibration and Control
http://jvc.sagepub.com/content/early/2012/07/18/1077546312439911The online version of this article can be found at:
DOI: 10.1177/1077546312439911
published online 18 July 2012Journal of Vibration and ControlM Taji, M Ataei, K Goshtasbi and M Osanloo
ODM: a new approach for open pit mine blasting evaluation
Published by:
http://www.sagepublications.com
can be found at:Journal of Vibration and ControlAdditional services and information for
http://jvc.sagepub.com/cgi/alertsEmail Alerts:
http://jvc.sagepub.com/subscriptionsSubscriptions:
http://www.sagepub.com/journalsReprints.navReprints:
http://www.sagepub.com/journalsPermissions.navPermissions:
What is This?
- Jul 18, 2012OnlineFirst Version of Record >>
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:05pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
Article
ODM: a new approach for open pit mineblasting evaluation
M Taji1, M Ataei2, K Goshtasbi3 and M Osanloo4
Abstract
In open pit mines, the blasting operation should be effectively optimized at the lowest possible total cost, providing
technical specifications and the required safety norms. The optimization demand measurement (ODM) value of blast
should be evaluated by considering blast results and other mine unit operations, comprehensively. The present research
proceeds by taking into consideration seven blast results including degree of fragmentation, muckpile, overbreak, boul-
ders, bench floor and toe conditions, environmental considerations and misfires. Consequently, these results have been
rated and classified. In the ODM, a value could be assigned to each blast, with lower values corresponding to better
results of the blasting operation. The ODM procedure indicates a relationship between blasting results, drilling and
loading performances. The specific mine unit operations index and the blast block situation rating are introduced in
order to determine the ODM value. The blast results evaluation and its effects on the mining operation are analyzed by
utilizing the blast results matrix [z], the performance matrix [P] and the ODM matrix [O]. Based on the results as well as
considering optimization, blasts are classified into five modes: very good, good, relatively weak, weak and very weak.
Thereafter, the ODM procedure is applied to the blasting operation at an Iranian iron ore open pit mine (Chador Malu),
with nine blast blocks. In summary, this approach could help design engineers to recognize the optimization demand of
the blasting operation at different mining conditions.
Keywords
Optimization demand measurement (ODM), open pit mine blasting operation, blast block situation rating (BBSR), blast
results matrix, performance index
Received: 7 February 2010; accepted: 9 May 2010
1. Introduction
To optimize blasts, the analysis of blasting results isnecessary in an open pit mine. The data interpretationmight cause successive modifications of the design par-ameters of a mine operation (Lilly, 2007). To achieve aneffective optimal open pit mine blasting operation aswell as its global evaluation, the main blast resultshave to be analyzed. The process could lead researchersto three important questions. First, what are the pre-sent blasting operation conditions? Second, what pos-ition should be given to the present blasting operation?Third, which design will yield better results?
Since 1966, many researchers have studied the evalu-ation of blasting operation results. In Table 1 the mostfamous and important studies that have been presenteduntil now have been reviewed. The table shows manyindexes for evaluating blast operation. Some of them
such as the degree of fragmentation (DF) and specificcharge (Sc) have been widely used in evaluation.However, some less-common indexes such as the digg-ability of loading machines (DL), explosive cost (EC)and energy consumption (En.Cs), have also beensuggested. These indexes are not independent param-eters but are based on some the parameters such asbench floor conditions and boulder characteristics.
1Science and Research Branch, Islamic Azad University (IAU), Tehran, Iran2Faculty of Mining, Petroleum and Geophysics, Shahrood University of
Technology, Iran3Tarbiat Modares University, Faculty of Engineering, Tehran, Iran4Amirkabir University, Faculty of Mining, Petroleum and Geophysics,
Tehran, Iran
Corresponding author:
M Taji, Science and Research Branch, Islamic Azad University (IAU),
Tehran, Iran
Email: [email protected]
Journal of Vibration and Control
0(0) 1–15
! The Author(s) 2012
Reprints and permissions:
sagepub.co.uk/journalsPermissions.nav
DOI: 10.1177/1077546312439911
jvc.sagepub.com
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:05pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
Some indexes such as loading equipment productivity(LP), specific drilling (Sd), environmental considerations(E.Co) and secondary blasting (SB) are important but inprevious studies have not been studied comprehensively.
In order to develop a rational and economical opti-mization of blasting operations, the present study hassuggested a new approach to measure the blast results.In brief, the proposed optimization demand measure-ment (ODM) is a quantitative procedure used to assessthe degree of optimization demand for open pit mineblasting operation.
2. ODM procedure
The ODM is based on a systematic approach and inte-grates knowledge from theoretical analysis, experiencesand monitoring, so can be utilized to compute and deter-mine the ODM values for different blast block situation(BBSs). The BBS is determined and classified based on theblasthole water ratio, the number and type of free face, theratio of length to width of the blast block and type of blastblock material. The blast block situation rating (BBSR)considers blast working conditions to rationally compareblast blocks. So, it could be enter blast operation special
Table 1. The most famous and important studies regarding the evaluation of blast operation
Reference EC OC El.Cs En.Cs TC Sc Sd DL Pe LP Cr.P MT Mu DF E.Co SB Di
Hammes (1966) # #
Mackenzie (1965) # # # #
Da Gama (1990) # # # # #
Nielsen and Kristiansen (1996),
Nielsen and Lownds (1997)
# # # # #
Williamson et al. (1983) # # # #
Hodjigeorgiou and Scoble (1988) # # # #
Taqieddin (1989) # # # # #
Hunter et al. (1990) # #
Stagg et al. (1992) # #
Eloranta (1993, 1995, 1997) # # # # #
Da Gama and Lopez Jimeno (1993) # # #
Fuerstenau et al. (1995) # # # # # #
Mckee et al. (1995) # # #
Cunningham (2005) #
Adler et al. (1996a, 1996b) # # # #
Moody et al. (1996) # #
Frimpong et al. (1996) # # #
Eloranta (2001a, 2001b, 2007) # # # # # # #
Kanchibotla et al. (1998, 1999) # # # # # # #
Workman (2000,2001) # # # #
Harris et al. (2001) # # #
Grundstrom et al. (2001) # # # #
Singh and Yalcin (2002) # #
Workman and Eloranta (2008) # # # # #
Singh et al. (2003) # # #
Hamdi and du Mouza (2005) # #
Mosher (2005) # #
Kojovic (2005) # #
Morin and Ficarazzo (2006) # # #
Singh and Narendrula (2006) # # # #
Ryu et al. (2006) # # # #
Bremer et al. (2007) # # # #
AOG (2007, 2009) # # # # #
Calder and Workman (2008,2009) # # # # # #
EC: explosive cost, OC: operational (blasting, drilling or loading) cost, El.Cs: electrical consumption, En.Cs: energy consumption, TC: total costs of
mining, Sc: specific charge, Sd: specific drilling, DL: diggability of loading machines, Pe: expert personnel LP: loading equipment productivity, Cr.P:
crusher productivity and delays at the crusher, MT: mill throughput, Mu: condition of muckpile, DF: degree of fragmentation and required size
distribution of fragmented rocks, E.Co: environmental considerations, SB: secondary blasting, Di: dilution constrains.
2 Journal of Vibration and Control 0(0)
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:05pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
characteristics such as: (1) the solutions to overcome theblasthole water problems, (2) initiation and priming sys-tems by considering the effect of blast block size and shapeand the number of free face, (3) the necessity of blendingprograms or fragmentation degree limitations by consider-ing the effect of blast block material type (ore, waste, oreand waste). To develop the ODM, the blast blocks needsto be divided into five classes or representative blast blocksbased on BBSR. S1 shows water presence or the blastholewater ratio and S2 indicates the number of free face/pres-ence of the buffer of broken rock, resting on one of the freefaces from the previous blast. So, S3 and S4 indicate theratio of length to width of the blast block and type of blastblock material, respectively. Every blast block posited inthe BBSR class is numbered by 1, 2, . . . , j, . . . ,m, respect-ively. In principle, the BBSR helps to optimize blastdemand assessment according to very similar blast work-ing conditions.
To apply the ODM in open pit mines, the followingpoints are emphasized.
1. In an open pit mine, the properties of blast are likely tobe different from one to other blocks. In other words,the blast results will be different for each block. Hence,the optimization and ODM values for different blastblocks will be different. To develop the ODM, firstdetermine the BBSR class of the blast block.
2. When the blast results are determined and rated,their contributions to the ODM values are expressedby a dimensionless numerical value (Saaty, 1980;Wang et al., 2005) based on the general principlesand experiences from the open pit mine blasting spe-cialists, equipment operators and mining engineers.
3. A m � 1 matrix [z] can be compiled by using theblast results and their assigned values.
4. In fact, the weight and importance of each blastresult is different. To determine the weight andimportance of each blast result, we should developa performance index.
5. By transforming the specific mine unit operationsindex (Suo) measured in each blast block into theform of the specific mine unit operation ratios, a1�m matrix, i.e. the specific mine unit operationratio or performance matrix [P] can be obtained.
6. By multiplying [z] and [P], a m�m matrix [O] isachieved. The elements Ojj along the leading diag-onal of the matrix [O] are the ODM values for the jthblast block. Figure 1 demonstrates a flowchart of theODM procedure.
2.1. Blast results
As mentioned previously, the seven main blast resultsare based on theoretical analyses as well as engineering
practice to discuss empirical assignments These are thefragmentation degree, the muckpile, the overbreak,bench floor and toe conditions, boulders, environ-mental considerations of the blasting operation andcondition of misfires (Jimeno et al., 1995; Katsabaniset al., 2005). The seven blast results are divided intoclasses with numerical values of 1 to 20. A blast resulthigher assignment value indicates a low optimal and ahigher degree of optimization demand in the blockblasting.
2.1.1. The degree of fragmentation (�FR). The fragmenta-tion degree is one of the most important factors ofblasting operation outputs. Apart from the classifica-tion of size distribution or screening of the muckpile intreatment plants, there is no method which enables aquantitative evaluation of fragmentation in conditionsthat would be trustworthy. The fragmentation degree(zFR) is divided into six classes. According to Table 2,these numbers show the numerical assigned value ofoptimization demand for the blast block in an openpit mine blasting operation.
BBSRj
Blast results matrix [ζ]
ζFL ζBOζOVζMUζFR ζEN ζMI
Classification of (ζj)
Specific mine unit operation index
Performance matrix [P]
ODM matrix [O]
ODM values
Calculation of specific charge, specific drilling and specific loading of every blast block
Relative evaluation of blast operation:
Figure 1. Flowchart of the ODM procedure.
Taji et al. 3
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:06pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
2.1.2. Condition of the muckpile (�MU). Table 3 shows thatthe optimum geometry, height (Hm) and displacementof the muckpile depends on the applied digging andloading system.
2.1.3. The overbreak condition (�OV). A typical overbreakcondition and remaining rock after blasting is given inFigure 2. It shows damage and problems in the diggingand loading system as well as around the blast block
Table 2. The degree of fragmentation (zFR)
Class I II III IV V VI
Fragmentation
efficiency (%)
>95 85–95 75–85 65–75 50–65 <50
Qualitative Excellent Very good Good Moderate Unsuitable Very poor
zFR 1 4 8 12 16 20
Table 3. Condition of the muckpile (zMU)
Class Description
zMU
a b
I � Need to clean up more area 1 7
� The productivity is low (shovel)
� Loading safety is good
� Loading operation is easy
II � Irregular profile 4 12
� Need to clean up more area
� The productivity is low (shovel)
� Loading safety is good
III � Moderate clean up area 7 1
� The productivity is good (shovel)
� Loading safety is good
IV � High necessity of clean up * 10 16
� Need to clean up more area
� The productivity is very low (shovel) ** 12 20
� Loading safety is very good
V � Low clean up area 16 4
� The productivity is excellent (shovel)
� Loading safety is dangerous (loader)
VI � Muckpile displacement is very low 20 10
� Shovel operation to face wall clean up is difficult
aUsing loading equipment with access height lower than bench height (maximum access height is 2/3 bench height).bUsing loading equipment with access height comparable to bench height.*Suitable bench width.**Low bench width.
4 Journal of Vibration and Control 0(0)
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:06pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
drilling operation. Table 4 indicates the assignedoptimization demand value of the overbreak (zOV).
2.1.4. The bench floor and toe condition (�FL). Figure 3shows a typical bench floor and toe remaining rock,where ‘HF’ is the average increased height of benchfloor and ‘J’ is subdrilling. The optimization demandnumerical values of the bench floor and toe conditionare evaluated from Table 5.
2.1.5. Boulders and oversize characteristics in the muckpile
(�BO). Important factors in boulder evaluation in themuckpile are: the amount of boulders in the muckpileas a volume percentage (MBO%), loading operationsafety degree, effect on productivity and loading equip-ment delay as shovel loading rate, secondary breakagemethods, the necessity of secondary blasting, positionof boulders in the muckpile (as shown in Figure 4),boulders size and probability of secondary breakagein the next blast blocks, delay at the crusher and theloading equipment and flexibility of breakage methodto extraction. The classification of boulders and over-size conditions (zBO), are given in Table 6.
2.1.6. Environmental considerations (�EN). The environ-mental considerations for blasting consist of airblast,ground vibration, noise, flying rock, dust and fumes.These often causes environmental and productionproblems such as decreasing productivity and increas-ing equipment damage, increasing risk of loss, buildingdamages, labor and operator injures and finally increas-ing mining costs. Some of the factors should be con-sidered for evaluating of environmental considerationsof blasting operation include: (1) the presence of officebuildings, mine shops, warehouses and their distancefrom the pit; (2) the position and location of the dor-mitory, urban areas; (3) the distance between the mainroads, haul roads, service roads, in-pit roads to theblasting site; (4) the position and location of the radio
Tab
le4.
The
rem
ainin
gro
ckan
dove
rbre
akco
nditio
n(z
OV)
Cla
ssI
IIIII
IVV
VI
VII
IIX
Desc
ription�
There
issm
ooth
wal
lw
ithout
dam
age
and
crac
kin
g
�T
here
issm
ooth
wal
lw
ith
low
crac
kin
g
�T
here
are
a
little
bac
kbre
ak,
sidebre
akan
d
tensi
on
crac
k
�d b
a<
Bor
d si<
S*
�d b
a<
Ban
d
d si<
S
�d b
a<
B
and/o
rd s
i<S
�d b
a>
Bor
d si>
S�
d ba>
Bor
d si>
S
�N
ot
nece
ssar
y
tofa
cesc
alin
g
�N
ot
nece
ssar
y
tofa
cesc
alin
g
�D
rilli
ng
loca
tion
isre
lative
lysa
fe
�D
rill
equip
ment
loca
tion
is
rela
tive
ly
safe
�D
rill
equip
ment
loca
tion
is
rela
tive
ly
dan
gero
us
�D
rilli
ng
and
bla
stin
gar
enot
poss
ible
but
rock
extr
action
carr
y
out
by
load
ing
equip
ment
�Fa
cesc
alin
gby
load
ing
equip
ment
are
not
poss
ible
�Fa
cesc
alin
gby
load
ing
equip
ment
isnot
poss
ible
�D
rilli
ng
loca
tion
issa
fe
�Fa
cesc
alin
g
by
load
ing
equip
ment
iseas
y
�D
rilli
ng
and
face
scal
ing
by
load
ing
equip
ment
are
rela
tive
lyeas
y
�D
rilli
ng
and
face
scal
ing
by
load
ing
equip
ment
are
rela
tive
lydiff
icult
�D
rilli
ng
and
bla
stin
g
are
not
poss
ible
but
rock
extr
action
carr
y
out
by
mech
anic
al
equip
ment
asdoze
r
�D
rilli
ng
and
bla
stin
g
are
not
poss
ible
but
rock
extr
action
carr
ied
out
by
mech
anic
al
equip
ment
such
asa
doze
r
z OV
13
58
11
14
17
20
*B:burd
en,S:
spac
ing.
Figure 2. A typical overbreak condition and the remaining rock
after blasting.
Taji et al. 5
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:06pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
station, power house, power main lines, power station;(5) the presence of the historical construction, the envir-onmental protected location and their distance from theblasting site and related regulations; (6) yearly weatherconditions and their variances and degree of alter-ations; (7) general direction and position of the wind;(8) flexibility and changeability of mine facilities loca-tion and access ways; (9) bench width; (10) dilution andore grades limitations and the blast block selectionbased on these factors; (11) required degree of the cer-tain block blasting to provide production schedulingobjectives and selective mining; (12) flexibility of pro-duction constraints and blasting time scheduling underdifferent atmospheric conditions; (13) general shape ofthe pit and adjacent mining sites constraints; (14) pre-sent mine equipment; (15) Capability of equipment toreach a safety zone; (16) bench and pit slopes stabilityconditions in blasting practices (Pal Roy, 2005).
The blasting site sensitivity is classified into threemajor groups: usual sensitiveness, relatively sensitiveand sensitive. According to the above-mentioned 16 fac-tors, usual sensitiveness shows that the facilities loca-tions, the main roads, power and energy main linesand urban distances from the blasting site are suitable.The in-pit roads are flexible and changeable. There areno air noise limitations because the suitability of dormi-tory and urban areas are probable. The yearly weatherconditions are desirable. The drilling, loading andhauling equipment usage are probable. The productionscheduling has high flexibility in bad climate conditions.The bench and pit slopes stability conditions are goodand predictable. Blending reasons are not significant.
The environmental influences and impacts of theblasting operation are classified into three positionsi.e. acceptable, relatively acceptable, and relativelyunacceptable, which are indicated in Table 7.
Table 8 shows the blasting operations’ environmen-tal considerations (zEN), based on the considered fac-tors in the environmental outputs of blasting operationand the sensitivity degree as well as blasting site condi-tions (usual, relatively sensitive and sensitive).
2.1.7. The presence and condition of misfire (�MI). If misfireoccurs, only few employees shall remain in the blastedsite. The blaster shall determine after each blast that nomisfire has occurred. Under most conditions the safestway to dispose of a misfire is ‘reshoot’. The misfireprognosis ability is of two types: (1) properly, certainor suitable; (2) improperly, uncertain or unsuitable.Table 9 shows the misfires conditions are classifiedbased on prognosis ability, the misfire number andposition.
2.2. Structure of the blast results matrix [�]
The blast results matrix is constructed by means of theblasting outputs. Let us suppose that the numbers ofblast blocks and the blast results are m and n, respect-ively, then the matrix will be a m� n matrix, the jth rowof which is occupied by seven blast results for the jthblast block. In fact, �j is the sum of zFR, zMU, zOV, zFL,zBO, zEN and zMI. The possible minimum and maximumzj are 7 and 140, respectively. The seven blast results andtheir matrix can be shown in the following form:
�½ � ¼
�FR1�MU1
�OV1�FL1
�BO1�EN1
�MI1
�FR2�MU2
�OV2�FL2
�BO2�EN2
�MI2
�FR3�MU3
�OV3�FL3
�BO3�EN3
�MI3
..
.::::
�FRm�MUm
�OVm�FLm
�BOm�ENm
�MIm
266666664
377777775
¼
�1
�2
�3
..
.
�m
26666666664
37777777775
ð1Þ
As shown in Table 10, the overall blast results valuesare classified into five classes.
3. Relative evaluating of blast operation
3.1. The performance matrix [P]
To consider weight and importance of each the blastresults introduced the performance index (Pj). If themeasured specific mine unit operations index in thejth blast block is Suoj (kg:hr=m8), the performanceindex can be defined as
Suoj ¼ Scj:Sdj:Slj ð2Þ
pj ¼SuojPmj¼1 Suoj
j ¼ 1, 2, . . . ,m ð3Þ
Figure 3. A typical bench floor and toe remaining rock.
6 Journal of Vibration and Control 0(0)
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:06pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
Tab
le5.
The
bench
floor
and
toe
conditio
n(z
FL)
Cla
ssI
IIIII
IVV
VI
VII
IIX
IXX
II
Desc
ription�
Bench
floor
isle
vele
d
�B
ench
floor
isle
vele
d
�B
ench
floor
isle
vele
dan
d
its
surf
ace
is
pla
nar
or
undula
ting
�B
ench
floor
isle
vele
dan
d
its
surf
ace
is
rough
�B
ench
floor
isle
vele
dan
d
its
surf
ace
is
rough
�B
ench
floor
isunle
vele
d
�B
ench
floor
isir
regu
lar
and
unle
vele
dw
ith
har
dto
e
�B
ench
floor
isunle
vele
dan
d
its
surf
ace
is
undula
ting
�B
ench
floor
isunle
vele
dan
dits
surf
ace
isro
ugh
�B
ench
floor
isunle
vele
dan
d
its
surf
ace
isst
epped
�B
ench
floor
leve
ling
isnot
nece
ssar
y
�Load
ing
equip
ment
pro
duct
ivity
isve
ry
good
for
floor
dig
ging
and
load
ing
�H
F<
1/ 4
J�
HF<
1/ 4
J�
HF¼
(1/ 4�
2/ 3
)J�
HF¼
(1/ 4�
2/ 3
)J�
HF>
2/ 3
J�
HF>
2/ 3
J�
HF>
2/ 3
J�
HF>
2/ 3
J
�T
here
isno
bench
floor
bre
akin
g
�B
ench
floor
bre
akin
gis
low
�Load
ing
equip
ment
pro
duct
ivity
isgo
od
for
dig
ging
and
leve
ling
�B
ench
floor
extr
action
is
not
nece
ssar
y*
�B
ench
floor
Extr
action
and
dig
ging
carr
ied
out
by
load
ing
equip
ment**
�D
iggi
ng
and
leve
ling
by
load
ing
equip
ment
is
diff
icult
�N
ece
ssar
yto
dig
ging
and
leve
ling
by
doze
r
�N
ece
ssar
yto
dig
ging
by
doze
r
�To
elo
cate
d
betw
een
hole
s
�To
elo
cate
d
betw
een
hole
s
and
infr
ont
of
hole
s
�T
he
dri
lling
pro
duct
ivity
is
good
�T
he
dri
lling
pro
duct
ivity
is
rela
tive
lygo
od
�Load
ing
pro
duct
ivity
tocl
ean
up
islo
w
�Load
ing
pro
duct
ivity
to
clean
up
islo
w
�B
ench
floor
leve
ling
by
shove
l
isdiff
icult
�B
ench
floor
leve
ling
isnot
poss
ible
by
load
ing
equip
ment
but
bla
stin
gis
nece
ssar
y
�B
ench
floor
leve
ling
isnot
poss
ible
by
load
ing
equip
ment
but
bla
stin
gis
nece
ssar
y
z FL
13
57
911
13
15
17
20
*Bench
floor
leve
ling
could
be
carr
ied
out
duri
ng
bott
om
blo
ckbla
stin
g.
**It
may
need
tobe
bla
sted.
Taji et al. 7
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:06pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
wherePj is a dimensionless numerical value, and the sum-mation ofPj for all blast blocks is 1. For a relative assess-ment, the use ofPj can reduce the effects of themeasuringerrors on the possible ODMvalues. Here Scj, Sdj, and Sljare specific charge (kg=m3), specific drilling ðm=m3Þ andspecific loading ðhr=m3Þ, respectively. These are mea-sured based on the volume of in situ rock in the jthblast block. In reality, specific loading is arrived by divid-ing the loading equipment total access time (hours) to thetotal volume of the jth blast block (m3).
For m number of blast blocks and n number of theblasting results, the specific mine unit operations indexratio or performance matrix [P] is a 1�m matrix, i.e.
P½ � ¼ P1 P2 � � � Pm
� �ð4Þ
3.2. The ODM matrix [O]
By multiplying the blast results matrix [z] and the per-formance matrix [P], the ODM matrix [O] can be com-puted as
O½ � ¼ �½ � P½ � ð5Þ
and a subsequent result is
O½ � ¼
o11 o12 . . . o1m�1 o1mo21 o22... . .
. ...
om�11 . . . om�1m�1om1 . . . omm
266664
377775
ð6Þ
where
ODM1 ¼ O11 ¼ �1P1
ODM2 ¼ O22 ¼ �2P2
..
.
ODMm ¼ Omm ¼ �mPm
8>>><>>>:
ð7Þ
The m number of elements along the leading diag-onal of the matrix [O] are the ODM values of the mnumber of blast blocks. A larger ODM value for a blastblock indicates a lower optimization effect of the blastblock. Table 11 shows the ODM classification and their
analysis. The ‘r’ value in Table 11 is calculated asfollows:
r ¼U� L
5ð8Þ
where U and L represent maximum and minimum Pj �j ,respectively.
4. The ODM application
4.1. Chador Malu mine information
The Chador Malu mine is located in Central Iran,120Km north-east of the city Yazd. The mine is con-nected with the national railway which is used for trans-porting iron ore to Isfahan Steel Plant. Chador Malumine includes five ore bodies. An estimated reserve isabout 300 million tons (NGDIR, 2009). The northernore body with 235 million tons of mineable deposit hasbeen in operation since 1995. Chador Malu is one ofthe major producers of iron ore concentrate in Iran.The annual production is 22 million tons including10 million tons of ore and 12 million tons of overbur-den and waste (R&D Department of Chador MaluMine, 2009).
4.2. The Chador Malu mine blasting parameters
The blasting accessories contain mostly detonatingcords and the rarely used nonel system. The explosivesare ANFO (dry hole) and slurry (watery hole).
4.3. ODM criteria
4.3.1. The BBSR. The BBSR of the nine Chador Malumine blast blocks classified as class 2 are as shown inTable 12.
4.3.2. The blast results matrix [�]. The numbersof blast blocks and the blast results are 9 and 7, respect-ively. In fact the blast results matrix will be 9� 1 asfollows:
�½ � ¼
8 4 11 9 9 5 34 4 3 5 3 2 18 1 8 9 7 5 112 12 14 11 11 10 312 10 17 13 13 12 118 12 8 7 5 2 14 1 5 3 3 2 18 12 11 9 7 5 58 7 5 9 9 6 3
26666666666664
37777777777775
¼
492239738843195747
26666666666664
37777777777775
ð9Þ
Figure 4. A typical muckpile area and location of the boulders
(after Jimeno et al., 1995).
8 Journal of Vibration and Control 0(0)
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:06pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
Tab
le6.
The
clas
sific
atio
nof
bould
ers
and
ove
rsiz
ed
conditio
ns
(zB
O)
Fact
ors
Cla
ss
III
III
IVV
VI
VII
IIX
IX
MB
O%
None
<3
3–5
3–5
3–5
5–10
5–10
>10
>10
Dela
yat
the
crush
er
None
None
Very
low
Very
low
Low
Modera
teM
odera
teH
igh
Very
hig
h
Dela
yat
the
load
ing
equip
ment
None
None
Very
low
Low
Modera
teH
igh
1H
igh
1H
igh
1Very
hig
h
Seco
ndar
ybla
stin
gN
one
Unnece
ssar
yU
nnece
ssar
yO
KO
KO
Knece
ssar
ynece
ssar
ynece
ssar
y
Situ
atio
nof
bould
ers
inth
em
uck
pile
None
Floor
&
front
Eve
ryar
ea
Eve
ry
area
Inte
rior
and
top
Eve
ry
area
Eve
ry
area
Most
ly
top
Eve
ry
area
Dig
ging
conditio
ns
Exce
llent
Eas
yR
ela
tive
ly
eas
y
Rela
tive
ly
eas
y
Modera
teR
ela
tive
ly
diff
icult
Rela
tive
ly
diff
icult
Diff
icult
Diff
icult
Load
ing
opera
tion
safe
ty
Exce
llent
Very
good
Very
good
Good
Rela
tive
ly
safe
Rela
tive
ly
safe
Rela
tive
ly
dan
gero
us
Dan
gero
us
Dan
gero
us
Bould
er
bre
akin
g
meth
od
None
By
load
ing
equip
ment
By
load
ing
equip
ment
Seco
ndar
y
bla
stin
g2Se
condar
y
bla
stin
g3O
nly
seco
ndar
y
bla
stin
g3
Seco
ndar
y
bla
stin
g4Se
condar
y
bla
stin
g4Se
condar
y
bla
stin
g4
Extr
action
lost
tim
e
due
tose
condar
ybre
akag
e
None
None
Very
low
Low
Modera
teH
igh
Hig
hVery
hig
hVery
hig
h
Pro
duct
ivity
of
load
ing
opera
tion
Exce
llent
Very
good
Very
good
Good
5R
ela
tive
lygo
od
6M
odera
te6
Low
7Very
low
Very
low
Pro
bab
ility
of
the
bould
ers
bre
akag
ein
the
next
bla
stblo
cks
None
None
None
Hig
hM
odera
teH
igh
Modera
teLow
None
Flexib
ility
of
bre
akag
e
meth
od
tom
uck
pile
extr
action
None
Very
good
Very
good
Good
Modera
teR
ela
tive
ly
low
Low
Low
Very
low
z BO
13
57
911
13
17
20
1Load
ing
opera
tion
vari
able
dela
yis
hig
h.
2O
rby
load
ing
equip
ment
or
mech
anic
alm
ean
s.3Fi
rst
bould
ers
should
be
colle
cted
and
subse
quently
use
din
the
seco
ndar
ybre
akag
em
eth
od.
4T
hey
need
two
or
more
bre
akag
em
eth
ods.
5Load
ing
fixed
tim
eis
less
than
5%
usu
altim
e.
6Load
ing
fixed
tim
eis
5–10%
usu
altim
e.
7Load
ing
fixed
tim
eis
more
than
10%
usu
altim
e.
Taji et al. 9
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:06pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
Table 7. Classification of the environmental influences and impacts of the blasting operation
Characteristics
The environmental influences and impacts of the blasting operation
Acceptable Relatively acceptable Relatively unacceptable Unacceptable
Production delays None Yes1 Yes4 Yes9
Facilities damage None None Permissibly High
Flying rock Permissible limit Very low Troublesome5 Very high10
Air noise Permissible limit Very low Relatively high6 High11
Ground vibration permissible limit Permissible limit More than permissible High
Bench stability Any problem Problem2 Troublesome6 Very poor12
Slopes stability Any problem Problem3 Troublesome8 Very poor
1These delays increase the direct costs for maximum amount of 10 percent of expected costs but these production delays are compensated by the end
of working shift.2Safety factor of bench and slopes stability is reduced locally.3There are not slope wedges and failure-intensive problems.4These delays cause increasing direct costs to a maximum of 30% of expected costs.5It is necessary to clean up roads from fly rocks.6The air noise is more than the permissible limit and there is ground vibration problems on the nearby building. The amount of dust is considerable.7Safety factor of the bench and slopes stability is reduced.8There are slope wedges and failures problems.9There are production delays and the equipment efficiency is reduced, especially hauling equipment, severely (its delay is more than two working shifts).
The delays give increasing direct costs of more than 30% extraction expected costs.10The roads are obstructed. The personnel injuries are intensive.11The air noise and ground vibration problems are severe.12There are bench and slopes failures and wedges severe problems.
Table 8. The blasting operation environmental considerations based on the blast site sensitivity (zEN)
The blast site sensitivity and conditions
The environmental influences and impacts of blasting operation
Acceptable Relatively acceptable Relatively unacceptable Unacceptable
Usual 1 5 10 16
Relatively sensitive 2 6 12 18
Sensitive 3 7 14 20
Table 9. The misfires conditions (zMI)
Misfire conditions Class
Prognosis ability
Suitable Moderate Unsuitable
Misfire absence I 1 3 5
Few in number and/or concentrative II 9 11 13
Scattered and/or numerous III 16 18 20
Table 10. The zj classification and their analysis
Class I II III IV V
zj <25 25–50 50–75 75–100 >100
Condition Very good Good Moderate Weak Very weak
10 Journal of Vibration and Control 0(0)
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:06pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
The seven blast results adapted degree and the over-all blast results value for the nine blast blocks in theChador Malu mine are shown as radar diagrams, asdisplayed in Figure 5.
4.3.3. The performance matrix [i]. The performancematrix is computed using Equations (2), (3) and thespecific charge, specific drilling and the specific loadingmeasured based on the volume of in situ rock in thenine blast blocks. Table 13 shows the specific mine unitoperations and performance indexes in the ChadorMalu mine. The performance matrix [P] is a 1� 7matrix and can be established as follows:
4.3.4. The ODM values. By substituting Equations (9)and (10) into Equation (5), the ODM matrix [O]can be obtained. As specified in Equation (6), theODM values for the nine blast blocks are the nine elem-ents placed along the leading diagonal of the matrix[O]. The ODM and the overall blast results values fornine blast blocks in the Chador Malu mine are shownin Table 14.
4.4. Comparison analyses of the nine blast blocks
For convenience of comparison, the performance index(Pj), the overall blast results value (zj) and ODM valuefor the nine blast blocks in the Chador Malu mine areshown as radar diagrams. These are shown in Figures 6and 7. As a result, the following information can bededuced.
1. The minimum ODM value is for the blast block7. Also the minimum Pj (P7¼ 0.065) and �j(z7¼ 19) is obtained for this block, i.e. the overallblast result and the efficiency of other operations(drilling and loading unit) are very good. Thismeans that the minimal ODM value for theseblast blocks have a direct relation to their specificunit operations and blast results. Thus, it showsthe performance, condition and results of otheroperations will affect the rational analysis ofblast results.
2. The z2 and z7 are very good but the z3 and zFR3
are good. In fact, by considering the efficiency ofdrilling and loading operations and blast results,the ODM class of the blast blocks 2, 3 and 7 is I.This means that these blocks indicate very goodcondition.
3. The ODM class of the blast blocks 4 and 5 is V, i.e.the requirement degree to optimization of theseblocks is very high.
4. The degree of fragmentation of the blastblocks 1 and 6 are good. The loading system inthese blast blocks are a loader. The loaderaccess height is lower than the bench height in thismine. For this reason, the ODM classes of the blastblocks 1 and 6 are, respectively, III and IV. Thisindicates that the better fragmentation would givebetter overall blast results and mining operationefficiency.
5. Conclusions
With respect to the above discussion, it seems that aquantitative evaluation method is necessary and criticalin order to analyze a blasting operation. Consequently,the present research proposes the concept and ratingprocedure of the effective blasting results. The ODMprocedure is helpful because it enables enhanceddesign and optimization as necessary for blasting
Table 11. The ODM classification and their analysis
ODM class I II III IV V
ODMj L to Lþ r Lþ r to Lþ 2r Lþ 2r to Lþ 3r Lþ 3r to Lþ 4r Lþ 4r to U
Conditions Very good Good Relatively weak Weak Very weak
The requirement degree
to optimize
Very low Low Relatively high High Very high
Table 12. The BBSR of the 9 Chador Malu mine blast blocks
Number of
blast block 1
2 and
9
3 and
7 4 5 6 8
S1 0 0 0 þ5 �3 �2 þ5
S2 0 þ5 0 0 þ5 0 0
S3 þ3 þ3 þ5 þ3 0 þ5 þ5
S4 þ3 þ3 þ3 þ3 þ3 þ3 �3
BBSRj þ6 þ11 þ8 þ11 þ5 þ6 þ7
P½ � ¼ 0:109 0:075 0:076 0:145 0:115 0:192 0:065 0:134 0:089� �
ð10Þ
Taji et al. 11
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:06pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
Table 13. The specific mine unit operations and performance indexes for nine blast blocks in the Chador Malu mine
No. Scjkgm3
� �Sdj
mm3
� �Slj
hrm3
� �Suoj
kg:hrm8
� �pj
1 0.867 0.0309 0.0141 0.000378 0.109
2 0.847 0.0269 0.0114 0.000260 0.075
3 0.796 0.0265 0.0124 0.000262 0.076
4 0.910 0.0320 0.0172 0.000501 0.145
5 0.826 0.0265 0.0181 0.000396 0.115
6 1.094 0.0361 0.0168 0.000663 0.192
7 0.855 0.0278 0.0094 0.000223 0.065
8 0.917 0.0319 0.0159 0.000465 0.134
9 0.850 0.0283 0.0128 0.000308 0.089
Note: The loading operation for the blast blocks 1 and 6 are carried out by a loader.
Table 14. The ODM and the overall blast results values for nine blast blocks in the Chador Malu mine
The degree of fragmentation The overall blast result ODM
No. zFR Class Condition zj Class Condition Value Class Condition
The requirement
degree to optimize
1 8 III Good 49 II Good 5.3 III Relatively weak Relatively high
2 4 II Very good 22 I Very good 1.7 I Very good Very low
3 8 III Good 39 II Good 3 I Very good Very low
4 12 IV Moderate 73 III Moderate 10.6 V Very weak Very high
5 12 IV Moderate 88 IV Weak 10.1 V Very weak Very high
6 8 III Good 43 II Good 8.3 IV Weak High
7 4 II Very good 19 I Very good 1.2 I Very good Very low
8 8 III Good 57 III Moderate 7.6 IV Weak High
9 8 III Good 47 II Good 4.2 II Good Low
Figure 5. The blast results adapted degree to the overall blast result value for nine blast blocks in the Chador Malu mine. (The
dashed lines are the overall blast results value.).
12 Journal of Vibration and Control 0(0)
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:06pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
engineering. The key conclusions that can be drawnfrom this paper are as follows:
. By integrating the theoretical analyses, experiencesand monitoring, the blast results can be classified.The assigned values and their changes can be con-veniently analyzed in the form of matrices.
. The ODM provides an efficient evaluation mechan-ism for the main outcome of the blasting.
. To define and assess of the ODM values, the blastblocks should be divided into different classes basedon blast block situation rating and considering blastworking conditions.
. The seven main blast results considered include frag-mentation degree, muckpile, overbreak, bench floorand toe conditions, the boulders, the environmentalconsiderations and condition of misfires. Theyshould be classified and rated accordingly.
. In this procedure, the blast results and the efficiencyof other unit operations are analyzed together.
. The specific charge, specific drilling and specificloading indexes should be recognized as one of theobjective criteria for the ODM assessment.
In a nutshell, the ODM can help design engineers torecognize the optimization demands of each blasting atdifferent mining conditions. Using this approach, theactual evaluation of the blast results can be achievedin an open pit mine.
Acknowledgements
We are thankful to the Khandagh Tech. & Eng. Companyand the Chador Malu, the Choghart, Gole Gohar mine, Iran
for their crucial support during this study. We express ourgratitude to A Mahzun, H Mahmudabadi and staff and tech-nicians of Khandagh Co. The authors are also indebted toEng. SH Hoseinie and Dr F Sereshki of Shahrood University
of Technology and Eng. A Afsharian of the Chador Malumine for their valuable suggestions and help.
Funding
This research received no specific grant from any fundingagency in the public, commercial, or not-for-profit sectors.
References
Adler J, Du Mouza J and Arnould M (1996a) Measurement
of the fragmentation efficiency of rock mass blasting and
Figure 6. The Pj and zj radar diagram of the nine blast blocks in the Chador Malu mine.
Figure 7. The Pj , zj and ODM radar diagram of the nine blast blocks in the Chador Malu mine.
Taji et al. 13
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:07pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
its mining applications. International Journal of RockMechanics and Mining Sciences 33: 125–139.
Adler J, Du Mouza J and Arnould M (1996b) Evaluation of
blast fragmentation efficiency and its prediction by multi-variate analysis procedures. International Journal of RockMechanics and Mining Sciences and Geomechanics 33:189–196.
AOG (2007) AOG Workshop: Blast Fragmentation andMining Cost, Quebec, Canada, 18–19 August 2007,Available online 21 July 2008, http://www.AOG.com/.
AOG (2009) http://www.AOG.com/ drill to mill for mines/pdf/dix12 k71/.
Bremer D, Ethier R and Lilly D (2007) Factors driving
continuous blasting improvement at the Lafarge RavenaPlant. In: International Society of Explosives Engineers –33rd Annual Conference on Blasting Technique.
Calder and Workman (2008) An Analysis of BlastingProfitability and Productivity, Hunter Valley, NSW,28–31 October 2008, pp. 41-45, http://www.calderwork-man.com/.
Calder and Workman (2009) Optimum Blasting, A literaturereview, 4 September, http://www.calderworkman.com/.
Cunningham CVB (2005) The Kuz–Ram fragmentation
model – 20 years. In: Proceedings 3rd EFEE WorldConference on Explosives and Blasting, September,Brighton, UK, 2005. pp.201–210.
Da Gama CD (1990) Reduction of costs and environmentalimpacts in quarry rock blasting. In: Proceedings of the 3rdInternational Symposium on Rock Fragmentation byBlasting, Brisbane, 26–31 August 1990. pp.5–8.
Da Gama CD and Lopez Jimeno C (1993) Rock fragmenta-tion control for blasting cost minimization and environ-mental impact abatement. In: Proceedings of
FRAGBLAST 4, Fragmentation by Blasting, 1993.Eloranta J (1997) The efficiency of blasting versus crushing
and grinding. In: Proceedings of the Twenty Third Annual
Conference on Explosives and Blasting Technique, LasVegas, NV, February 1997. International Society ofExplosive Engineers, Cleveland, OH, pp.157–163.
Eloranta J (2007) The effect of fragmentation on miningcosts, a literature review. In: Workshop on theMeasurement of Blast Fragmentation-Cost, Quebec,Canada.
Eloranta JW (1993) Practical blast evaluation at the Minntacmine. In: Proceedings of the Nineteenth Conference ofExplosives and Blasting Technique, San Diego, CA, 31
January–4 February 1993. International Society ofExplosives Engineers, Cleveland, OH, pp.101–107.
Eloranta JW (1995) The effect of fragmentation on down-
stream processing costs. In: Proceedings of Explo95Conference, Brisbane, Queensland, Australia, 4–7September 1995. pp.25–28.
Eloranta JW (2001a) Improve milling through better powder
distribution. In: Proceedings of the twenty-seventh confer-ence of Explosives and Blasting Technique, Orlando, FL,28–31 January. International Society of Explosives
Engineers, Cleveland, OH.Eloranta JW (2001b) Optimized iron ore blast designs for
SAG/AG Mills. In: Proceedings of the International
Conference on Autogenous and Semiautogenous Grinding
Technology, Vancouver, BC, Canada, 30 September–3
October. Vol. 1, pp.262–270.
Frimpong M, Kabongo K and Davies C (1996) Diggability in
a measure of dragline effectiveness and productivity. In:
Proceedings of 22nd Annual Conference on Explosives and
Blasting Techniques. pp.95–104.Fuerstenau MC, Chi G and Bradt RC (1995) Optimization of
energy utilization and production costs in mining and ore
preparation. In: XIX International Mineral Processing
Congress, San Francisco, CA, October 1995. pp.161–164.Grundstrom C, Kanchibotla SS, Jankovic A and Thornton D
(2001) Blast fragmentation for maximising the sag mill
throughput at Porgera Gold Mine. In: Proceedings of the
Twenty-Seventh Annual Conference on Explosives and
Blasting Technique, Orlando.
Hamdi E and du Mouza J (2005) A methodology for rock
characterization and classification to improve blast results.
International Journal of Rock Mechanics and Mining
Sciences 42: 177–194.Hammes J K (1966) The economics of producing and deliver-
ing iron ore pellets from North American taconite type
resources. In: Proceedings of the 27th Annual Mining
Symposium, University of Minnesota. pp.9–16.Harris GW, Mousset JP and Daemen JK (2001)
Measurement of blast induced rock movement in surface
mines by application of magnetic geophysics. Transactions
of the Institution of Mining and Metallurgy (Section A:
Mining Industry) 108: AI72–A180.Hadjigeorgiou J and Scoble M (1988) Prediction of digging
performance in mining, Int. Journal of Surface Mining 2:
237–244.Hunter GC, Sandy DA and Miles NJ (1990) Optimisation
of blasting in a large open pit mine, Fragblast ’90.
In: Proceedings 3rd International Symposium on
Fragmentation by Blasting, Inst. Min. Metall., Victoria,
Australia, pp.21–30.Hustrulid W (1999) Blasting Principles for Open Pit Mining,
Vol.1-General Design Concepts. Rotterdam: A.A.
Balkema.Jimeno C, Jimeno E and Carcedo F (1995) Drilling and
Blasting of Rocks. Rotterdam: A.A. Balkema.Kanchibotla SS, Valery W and Morrell S (1999) Modelling
fines in blast fragmentation and its impact on crushing and
grinding. In: Proceedings Explo-99 Conference, Kalgoorlie.
Katsabanis T, Thomas C, Workman L, Palangio T and
Eloranta J (2005) From drill to mill for mines and quar-
ries. Newsletter of Advanced Optimisation Group 4(1).Kojovic T (2005) Influence of aggregate stemming in blasting
on the SAG mill performance. Minerals Engineering 18:
1398–1404.Kontoghiorghes EJ and Gatu C (2006) Optimisation,
Econometric and Financial Analysis (Advances in
Computational Management Science). Rotterdam: A.A.
Balkema.
Lilly DP (2007) A statistical approach to integrating blasting
into the mining process. In: Oxford Business and
Economics Conference, 2007.MacKenzie AS (1965) Cost of explosives - do you evaluate it
properly? In: American Mining Congress. Las Vegas, NV.
14 Journal of Vibration and Control 0(0)
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from
XML Template (2012) [13.7.2012–2:07pm] [1–15]K:/JVC/JVC 439911.3d (JVC) [PREPRINTER stage]
McKee DJ, Chitombo GP, Morrell S (1995) The relationshipbetween fragment fragmentation in mining and comminu-tion circuit throughput. Mineral Engineering 18(11),
1265–1274.Moody L, Cunningham C and Lourens H (1996) Measuring
the effect of blasting fragmentation on hard rock quarry-ing operations. In: Proceedings of FRAGBLAST5,
Fragmentation by Blasting, Montreal, Quebec, Canada,25–29 August 1996. pp.353–359.
Morin M and Ficarazzo F (2006) Monte Carlo simulation as
a tool to predict blasting fragmentation based on the Kuz–Ram model. Computers and Geosciences 32: 352–359.
Mosher JB (2005) Comminution circuits for gold ore process-
ing developments. Mineral Processing 15: 253–277.NGDIR (2009) Development planning and equipment of
Chador Malu Iron ore mine. Technical Report, http://
www.NGDIR.org.Nielsen K and Kristiansen J (1996) Blasting–crushing–grind-
ing: optimisation of an integrated comminution system.In: Mohanty B (ed.) Rock Fragmentation by Blasting—
Proceedings of Fragblast 5. Rotterdam: A.A. Balkema,pp.269–277.
Nielsen K and Lownds CM (1997) Enhancement of taconite
crushing and grinding through primary blasting.International Journal of Rock Mechanics and MiningSciences 34: 226.e1–226.e14.
Pal Roy P (2005) Rock Blasting Effects and Operations. NewDelhi: Oxford & IBH nublishing Co. Pvt. Ltd.
R&D Department of Chador Malu Mine Guidelines ofMining Operation. T4108 project final report.
Ryu DW, Shim HJ, Han CY, and Ahn SM (2006) Predictionof rock fragmentation and design of blasting pattern basedon 3-D spatial distribution of rock factor, International
journal of rock mechanics and mining sciences 46(2):326–332.
Saaty TL (1980) The Analytic Hierarchy Process. New York:
McGraw-Hill.Singh SP (2006) Fragmentation prediction during ring blast-
ing using a discrete Kuz–Ram Model. In: 16th
International Symposium on MPES, Torino, Italy, 20–22
September.
Singh SP and Yalcin T (2002) Effects of muck size distribu-
tion on scooping operations. In: Proceedings of 28th
Annual Conference on Explosives and Blasting
Techniques. pp.315–325.Singh SP, Yalcin T, Glogger M and Narendrula R (2003)
Interaction between the size distribution of the muck
and the loading equipment. In: Proceedings of the 4th
International Conference on Computer Applications in
Mineral Industries. pp.1–13.Stagg MS, Otterness RE and Siskind DE (1992) Effects of
blasting practices on fragmentation. In: Proceedings of the
33rd US Symposium on Rock Mechanics, Santa Fe, 3–5
June 1992. pp.313–322.
Taji M (2008) The classification of open pit mine blast results
by BBSR. In: Proceedings of the 1th National Symposium
on Blasting Engineering and Industrial Explosives, BEIE
2008, Electronic file No. 004.Taqieddin SA (1989) Evaluation of the efficiency of a blasting
operation designed for a dragline strip mining process.
International Journal of Rock Mechanics and Mining
Science and Geomechanics 8: 59–64.Wang Y-J, Zhang X-Z and Qi L-Q (2005) Unconstrained
optimization reformulation of the generalized nonlinear
complementarity problem and related method.
Optimization 54: 563–577.
Workman L (2001) An analysis of blasting profitability and
productivity, Hunter Valley, NSW, 28–31 Oct., pp.41–45.
Workman L and Eloranta J (2008) The effects of blasting on
Crushing and grinding efficiency and energy consumption,
3 June 2008. Available at: http://www.isee.org/Williamson S, Mckenzie C, O’Loughlin H (1983). Electric
shovel performance as a measure of blasting efficiency.
In: 1th International Symposium on Rock Fragmentation
by Blasting, Lulea University of Technology, Vol.1,
pp.76–83.
Taji et al. 15
at LESLEY UNIV LIBR on October 29, 2012jvc.sagepub.comDownloaded from