October 2013 Monthly Progress Report of NCRMP-TPQA

Embed Size (px)

Citation preview

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    1/160

    Co n s u l t a n c y Se r v i ce s f o r T h i r d P a r t y

    Q u a l i t y A u d i t

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    2/160

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    CONTENTS

    1.0 Project Background 2

    2.0 Out Line Tasks to be carried out 3

    3.0 Findings of the Site Reports 5

    3.1 Summary of Audit opinion 6

    3 2 Corrective actions 8

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    3/160

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    1. Project Background

    Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road

    network in the state, the nine coastal districts cover 26,000 km of road length. Every year during the

    period of April-May and September-December, cyclonic situations set in to the Bay of Bengal. With

    the recent changes in climatic conditions, the catastrophic events are increasing resulting in very

    devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging from

    1892 to 1989, there were as many as 67 cyclones within the State.

    It is essential to provide safe residential accommodation to the vulnerable population during any

    eventuality or disaster due to natural calamities such as cyclones and associated tidal waves and

    storm surges. The project is formulated based on experiences of Government of Andhra Pradesh in

    mitigating such disasters during the past and also keeping in view the existing facilities available in

    the project area in Andhra Pradesh.

    The Government of India has applied for a credit of US$ 255 Million equivalent from the

    International Development Association (IDA) toward the cost of National Cyclone Risk Mitigation

    Project (NCRMP), and it intends to apply the proceeds to payments for goods, works, related

    services and consulting services under this Project.

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    4/160

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    2. Outline of tasks to be carried outThe scopes of services for the Third Party Quality Audit (TPQA) assignment are

    A. The consultant will prepare an inception report within 30 days from signing of the contract that

    details the method agreed during negotiations to be employed in performing the services.

    B. Assist SPIU in resolving issues related to Non compliances.

    C. The field testing being conducted by the implementation staff will be observed and when doubts

    arise in such observations another sample will be taken and will be tested independently to verify

    whether it is as per the standards or not.

    D. The consultant will review civil work components of the cyclone shelters and related roads &

    bridges of these buildings and compliances and non-compliances will be reported regularly to PIU

    and line department.

    E. Consultants will visit the sites for each stage of work and audit

    F. The consultant will visit the construction sites randomly without prior information to the

    implementing agency, along with the regular site visits. The consultant will be submitting weekly

    reports before the 3rd day of the following week Monthly reports quarterly reports annual

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    5/160

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    I. The consultant will participate in the workshops / trainings administrated by the PIUs / line

    departments, quarterly and also as and when called for to give their inputs and also to act as

    resource persons as and when needed.

    J. The competency of the implementation staff will be verified and reported to SPIU and suitable

    suggestions will be made.

    K. The work plans of the implementation agency will be observed and suitable modifications will be

    suggested basing on the past experiences in the sites.

    L. The consultant will prescribe suitable formats for progress reporting and the same formats will

    be used to report regularly.

    M. The consultant will advise on the required site audit procedures for individual duties and

    responsibilities, including detailed inspection schedules and check lists.

    N. The Third Party Quality Audit will carry out additional tests, where a prime facie doubt arises

    related to quality of works and / or compliance of standards using mobile laboratory available

    with the consultant or nearby approved laboratories. The consultant shall advise few more labs

    for testing suitably, which after the approval of the SPIU / line departments, can be used for

    testing

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    6/160

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    issues etc. The Consultant will also make presentations on audit findings at the designated

    forums as and when required by the client.

    3.0 Findings of the Site Reports:

    Third Party Quality Audit engineers are inspecting the NCRMP works at regular intervals. The

    inspections are being carried out as per the TOR of the agreement.

    During inspections, TPQA engineers are verifying the test records, adequacy of machinery

    and work force, safety measures taken and site related problems if any. They are also carrying out

    all the field tests on the materials, on work done or being done. Some minor corrective measures

    which can be attended immediately are being got done in the presence of TPQA engineers, during

    their inspections. Samples are collected for laboratory testing for tests like California Bearing Ratio

    (CBR) tests on sub base and sub grade materials, confirmatory Safe Bearing Capacity (SBC) for

    buildings and bridges, mechanical and chemical properties of steel and tests on cement whenever

    doubt arises about the quality of cement. Measurements are also being verified with reference to the

    d ing Spe i l ttention i being p id fo e ifi tion of einfo ement det il on ete nd

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    7/160

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    The summary of site visits, NCRs issued during the month and Quality Control Tests done are

    tabulated hereunder.

    Sl. No. DistrictNo of Sitevisits by

    TPQA

    Number ofNCR Issued

    Quality control Testsdone

    Passed Failed

    1 Srikakulam 26 0 29 1

    2 Vizianagaram 7 0 7 0

    3 Visakhapatnam 8 0 4 0

    4 East Godavari 25 0 83 0

    5 West Godavari 21 0 35 0

    6 Krishna 40 0 60 0

    7 Guntur 29 0 4 0

    8 Prakasam 39 0 82 0

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    8/160

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Summary of TPQA observations requiring attention of SPIU in Quality Audit Reports.

    Sl.No

    Description of item Remarks

    1 Action Taken ReportsATRs for QCRs are not received from line departmental officers. Allthe others are delaying them. Prompt submission of ATRs will servethe purpose of issuing QCR.

    2

    Contractors work program andEnvironmental and SocialManagement Framework (ESMF)plan.

    Despite requesting several times, TPQA is not receiving or shownthe work program and ESMF for any work. TPQA supplied themodel format for ESMF plan also. Necessary guidance will beextended by TPQA in preparation of the plan if necessary.

    3 Quality control lab

    Contractor is not establishing QC lab for many road works. Forsmall road works, necessary field testing equipment shall be made

    available at site by the contractor so that the field officers can alsoconduct the QC tests. One QC lab for one package of road works ata central location shall be provided.

    4 Site inspection register

    At some places, site inspection registers are not maintained.Instructions of the inspecting officers are not being written in theregister. Some inspecting officers are issuing inspection reports.These reports are to be attached in the register.

    On man oads elect ical pole a e nea the ca iage a The a e

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    9/160

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    3.2 Corrective actions:

    Corrective actions for all the likely non-compliances are suggested as per standard specifications

    adopted in the contract documents in the Quality assurance Plan submitted. Accordingly for various

    non-compliances, corrective actions are suggested and getting implemented. Some of the corrective

    actions are discussed hereunder:

    1. Gradation non - compliance: In collection of aggregates for GSB Granular Sub Base), WMM (WetMix Macadam), WBM (Water Bound Macadam), OGPC (Open Grade Premix Carpet), Seal Coat, SDBC

    (Semi Dense Bituminous Concrete) and concrete fine aggregate collections, whenever gradation is

    not satisfied, corrective actions were suggested by TPQA to make the gradation compliant with the

    specified one. Generally, it was done by adding the missing or deficient sizes and re-breaking higher

    sized materials.

    2. Density - compliance: Whenever relative compaction is deficient in compacted layers of

    earthwork, shoulders, GSB layers, WBM layers or WMM layers, re-compaction is done by scarifying,

    watering to OMC (Optimum Moisture Content) and compaction to achieve the specified relative

    compaction

    3. Deficiency in thickness: NCRs were issued when thickness of GSB, WBM, WMM or sub-grade layer

    thickness is found to be less than the specified thickness. After the suggested corrective action is

    done, the NCR s are being closed after verification.

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    10/160

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    District wise Summary of Work Progress

    Sl. No. DistrictUp to10%

    11 to40%

    41 to70%

    71 to100%

    WorksNot

    started

    Worksdeleted

    TotalNo ofworks

    1 Srikakulam 14 19 2 7 3 4 49

    2 Vizianagarm 2 1 2 1 0 0 6

    3 Visakhapatnam 1 0 2 8 0 0 11

    4 East Godavari 5 10 3 4 3 0 25

    5 West Godavari 1 25 3 2 2 0 33

    6 Krishna 15 16 7 10 2 0 50

    7 Guntur 2 2 0 2 3 0 9

    8 Prakasam 4 10 4 17 0 0 35

    9 Nellore 1 15 5 18 0 0 39

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    11/160

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4.0 Activities of Third Party Quality Audit Consultant.

    All the activities of TPQA consultant, such as status of TPQA visits, Quality Audit reports, NCR status

    reports, status of Quality Control tests and other reports are summarized in the tables and furnished

    in this Monthly Progress Report as detailed below.

    Status of NCRMP Year-1 works are given in Table-1

    Spillover works statement for the Year-1 works are given in Table-2

    Details of Spillover works for the year-1 works are given in Table-3

    Agreements communicated for NCRMP Year-2 works statement given in Table-4

    Overall statement of Agreements communicated Year-2 works + Spillover Year-1 works

    statement is given in Table-5

    Final QCRs to be submitted for the Year-1 works statement is given in Table-6

    Status of works communicated agreements and spill over works abstract is given in Table-7

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    12/160

    RHB

    RCS

    MPCS

    B

    ridges

    Roa

    ds(R&B)

    Total

    RHB

    RCS

    MPCS

    B

    ridges

    Roa

    ds(R&B)

    Total

    RHB

    RCS

    MPCS

    B

    ridges

    Roa

    ds(R&B)

    Total

    1 Srikakulam 6 8 2 4 1 21 6 8 0 3 1 18 12 0 0 2 1 0 3 0

    2 Vizianagaram - - - 2 1 3 0 0 0 2 1 3 3 0 0 0 0 0 0 0

    3 Visakhapatnam 8 6 7 - - 21 8 6 6 0 0 20 14 0 0 0 0 0 0 1

    4 East Godavari 2 8 3 - - 13 2 7 2 0 0 11 8 0 0 1 0 0 1 1

    5 West Godavari 10 - - - - 10 10 0 0 0 0 10 10 0 0 0 0 0 0 0

    6 Krishna 5 3 - - - 8 5 3 0 0 0 8 8 0 0 0 0 0 0 0

    7 Guntur 3 12 - 2 - 17 3 12 0 1 0 16 11 0 0 0 1 0 1 0

    8 Prakasham 14 7 2 1 - 24 14 7 2 1 0 24 24 0 0 0 0 0 0 0

    9 Nellore 16 10 - - - 26 16 8 0 0 0 24 24 0 2 0 0 0 2 0

    Total 64 54 14 9 2 143 64 51 10 7 2 134 114 0 2 3 2 0 7 2

    Total No. of works entrusted in Year-1 = 143 nos No. of works deleted = 2 nos

    No. of works completed by 14.04.2013 = 129 nos Spillover works in to Year 2 = 143 2 129 = 12 nos

    No.ofworksdeleted

    No.

    ofFinalReports

    Submitted

    Status of NCRMP Year-1 works as on 14.04.2013 TABLE - 1

    S.no

    District

    No. of works(Under Concluded

    Agreements)No. of works Completed No. of works under Progress

    Page 11 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    13/160

    Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works

    1 Srikakulam 1 2 0 0 2 3 3 5 1 1 0 0 4 6

    2 Vizianagaram 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    3 Visakhapatnam 1 1 0 0 0 0 1 1 0 0 0 0 1 1

    4 East Godavari 1 1 0 0 0 0 1 1 0 0 0 0 1 1

    5 West Godavari 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    6 Krishna 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    7 Guntur 0 0 1 1 0 0 1 1 1 1 0 0 2 2

    8 Prakasam 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    9 Nellore 0 0 1 2 0 0 1 2 0 0 0 0 1 2

    3 4 2 3 2 3 7 10 2 2 0 0 9 12Total

    Abstract of pending Spill over (NCRMP Year-1) works (which were not completed by 14.04.2013) TABLE - 2

    Sl.

    No.District

    PR R&B I & CADTOTAL

    MPCS RCS RHB TOTAL Bridges Saline Embankment

    Page 12 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    14/160

    Sl.

    NoDistrict

    Categ

    ory

    Packages allotted under

    Phase - 1s.no Names of works under each package

    Agreement

    No. / Date

    Work

    StatusRemarks

    1 1Road from R&B road Mobagam to

    Duubakavanipeta via Gajapathinagaram

    /2010-11, Dt.

    30.04.2011completed completed

    2 2Road from Talasamudram to Dola

    Regulator

    /2010-11, Dt.

    30.04.2011completed completed

    3 NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

    3 Road from R&B road Edulavalasa - Killamto Jonnam via Talasamudram

    /2011-12, Dt.30.04.2011

    completed completed

    4R&B

    bridge

    NCRMP/B-W/AP/Br/R&B/

    01/Uppugedda/0024

    Construction of High level bridge across

    Uppugedda at KM 7/6 of Srikakulam

    muncipal limits to Pukkalapeta via

    Killipalem

    47/2010-

    2011,Dt17.12.2

    010

    Work in

    Progress

    Deck Slab completed. Retaining wall and

    finishing works are in progress

    5 5Construction of Cyclone shelter at

    Kollipadu

    G.o rt No 451

    dt 06.04.2010

    Work in

    Progress

    Brick work, Plastering and Flooring are under

    progress

    6 6 Construction of Cyclone Shelter at RunkuG.o rt No 451

    dt 06.04.2010

    Work in

    Progress1st floor Brick work in progress

    7 Visakhapatnam

    MPCS NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

    1 Construction of CS at Venkayyapalem /2011-12, Dt.03.10.2011

    Completed Finishing works nearing completion

    8East

    GodavariMPCS

    NCRMP/B-W/AP/MPCS/PRED/

    04/ Uppalaguptam/0021

    Construction of CS at Pedaraghavulapeta

    of Uppalaguptam Mandal

    78/2011-12

    Dt:17.10.2011Completed

    9 BridgesNCRMP/B-W/AP/Br/R&B/

    07/Bapatla/0114

    Reconstruction of HLB @Km2/4 of Bapatla -

    Pandurangapuram Road across perali drain

    78/2010-11

    1.12.2010

    Work is in

    progress

    For approach road, GSB & WMM Works

    completed, traffic allowed. Finishing works

    nearing completion

    10 RCSNCRMP/B-W/AP/RCS/PRED/

    07/PV Palem/0016

    Road from R&B Road Alluru to

    Yadavapalem

    2011-2012

    1.11.2011completed work completed, FQCR Submitted

    11 3Road from @ 56/8 to C.K road to

    Periyavettu kuppam CS14.09.2012

    work in

    progressWBM Gr-III completed.

    12 2Providing BT road to Pedapannamgadu in

    Tada Mandal14.09.2012

    Work

    completed

    Black topping completed. Only road furniture

    is to be fixed

    NCRMP/B-W/AP/RCS/PRED/

    09/Tada/009RCS

    SPSR

    Nellore

    STATUS OF SPILL OVER (NCRMP YEAR-1) WORKS AS ON 31.10.2013 TABLE - 3

    Srikaulam

    RHB

    NCRMP/B-W/AP/RHB/PRED/

    01/Polaki/006

    MPCSNCRMP/B-W/AP/MPCS/PRED/

    01/Santhabommalli/005

    Guntur

    Page 13 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    15/160

    Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works

    1 Srikakulam 11 22 4 11 4 10 19 43 0 0 0 0 19 43

    2 Vizianagaram 1 1 1 5 0 0 2 6 0 0 0 0 2 6

    3 Visakhapatnam 1 1 3 4 3 5 7 10 0 0 0 0 7 10

    4 East Godavari 3 5 6 9 5 8 14 22 2 2 0 0 16 24

    5 West Godavari 0 0 4 9 8 24 12 33 0 0 0 0 12 33

    6 Krishna 0 0 8 26 8 23 16 49 1 1 0 0 17 50

    7 Guntur 2 2 2 3 1 1 5 6 1 1 0 0 6 7

    8 Prakasam 0 0 3 11 8 23 11 34 1 1 0 0 12 35

    9 Nellore 0 0 10 18 9 19 19 37 0 0 0 0 19 37

    18 31 41 96 46 113 105 240 5 5 0 0 110 245Total

    Details of Agreements Communicated by SPIU to TPQA Consultant to the end of October 2013 TABLE - 4

    R&B I & CADTOTAL

    MPCS RCS RHB

    PR

    TOTAL Bridges Saline EmbankmentDistrictSl.

    No.

    Page 14 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    16/160

    TABLE - 5

    Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works

    1 Srikakulam 12 24 4 11 6 13 22 48 1 1 0 0 23 49

    2 Vizianagaram 1 1 1 5 0 0 2 6 0 0 0 0 2 6

    3 Visakhapatnam 2 2 3 4 3 5 8 11 0 0 0 0 8 11

    4 East Godavari 4 6 6 9 5 8 15 23 2 2 0 0 17 25

    5 West Godavari 0 0 4 9 8 24 12 33 0 0 0 0 12 33

    6 Krishna 0 0 8 26 8 23 16 49 1 1 0 0 17 50

    7 Guntur 2 2 3 4 1 1 6 7 2 2 0 0 8 9

    8 Prakasam 0 0 3 11 8 23 11 34 1 1 0 0 12 35

    9 Nellore 0 0 11 20 9 19 20 39 0 0 0 0 20 39

    21 35 43 99 48 116 112 250 7 7 0 0 119 257Total

    RCS RHB

    Details of Agreements Communicated by SPIU to TPQA Consultant to the end of October 2013 + Spill over works of Year-1

    Sl.

    No.District

    PR I & CAD

    TOTALMPCS

    Saline

    Embankment

    R&B

    TOTAL Bridges

    Page 15 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    17/160

    Sl.

    No

    Dist

    rict

    Categ

    ory

    Packages allotted under

    Phase - 1s.no Names of works under each package Work Status Remarks

    1 1 Road from DPN R&B road to Uddandapalem Work completed Approval of working estimate awaited

    2 2 Road from K. Umilada Junction to Koduru (Link Road) Work completed Approval of working estimate awaited

    3 3Road from Borubhadra, Malagam to Kollipadu via

    Seepuram, Gantapeta Work completed Approval of working estimate awaited

    4 1 Construction of CS at Gajapathinagaram Work completedCopy of Approved working estimate &

    ATRs not recived

    5 2 Construction of CS at Ratnayampeta Work completedCopy of Approved working estimate &

    ATRs not recived

    6 3 Construction of CS at Patimeeda Work completedCopy of Approved working estimate &

    ATRs not recived

    7 4 Construction of CS at Mullaparra Work completedCopy of Approved working estimate &

    ATRs not recived

    8 5 Construction of CS at Bangarampeta Work completedCopy of Approved working estimate &

    ATRs not recived

    9 RCSNCRMP/B-W/AP/RCS/

    PRED/04/Uppalaguptam/0031

    Road from R&B Road to Chinaraghavulapeta Cyclone

    ShelterWork completed

    Approval of working estimate waited &

    ATRs not received

    10NCRMP/B-W /AP/MPCS/

    PRED/04/ Thondangi/0012

    Construction of Cyclone Shelter at Lakshmanudipeta in

    ThondangiWork completed working estimate approval not received

    11NCRMP/B-W /AP/MPCS/PRED/

    04/Thondangi/0013 Construction of Cyclone Shelter at Avulamanda Work completed working estimate approval not received

    12 1Road from Ganapavaram R&B Road to

    PedamarpuvaripalemWork completed Approval Working Estimate received

    13 2 Road from R&B Road to Chinapuluguvaripalem Work completed Approval Working Estimate received

    No. of works for which Final QCRs submitted = 116 nos ; No. of works for which Final QCRs to be submitted = 13 nos

    Note: Quality Audit was done for all the items of the above completed works. Pre-final QCRs were also submitted. Approval of working estimatesincorporating the deviations are awaited. Immediately after the receipt of approved working estimates from the departmental officers and ATRs in few cases,

    final QCRs will be submitted.

    NCRMP/B-W/AP/MPCS/PRED

    /03/Payakaraopeta/003

    NCRMP/B-W/AP/MPCS/PRED

    /03/Nakkapalli/002

    List of Works which are completed and final QCRs to be submitted by TPQA (awaiting approval of W.E/R.E) TABLE - 6

    NCRMP/B-W/AP/RHB/PRED/

    01/Santhabommali/003

    MPCS

    Visakhapatnam

    Srikakulam

    RHB

    EastGodavari

    MPCS

    RCSNCRMP/B-W/AP/RCS/PRED/

    07/Karlapalem/002Guntur

    Page 16 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    18/160

    PR

    R&B-Bridges

    I&CADD

    Started

    Notstarte

    d

    Progress

    Complete

    d

    Deleted

    CivilEngine

    ers

    visits

    Env&Social

    visits

    ElectricalEngg

    visits

    TotalVisits

    Issued

    Closed

    Pending

    CivilAudit

    Reports

    Social&Env

    Auditreports

    ElectricalAudit

    reports

    1 Srikakulam 48 1 0 49 42 3 39 3 4 322 23 10 355 581 15 12 3 37 23 8

    2 Vizianagaram 6 0 0 6 6 0 6 0 0 61 9 0 70 133 1 1 0 9 9 0

    3 Visakhapatnam 11 0 0 11 11 0 8 3 0 168 9 14 191 606 10 2 8 29 9 14

    4 East Godavari 23 2 0 25 22 3 19 3 0 152 8 8 168 536 1 1 0 18 8 7

    5 West Godavari 33 0 0 33 31 2 31 0 0 245 41 0 286 386 20 20 0 27 42 0

    6 Krishna 49 1 0 50 48 2 48 0 0 257 24 0 281 292 12 5 7 34 23 0

    7 Guntur 7 2 0 9 6 3 5 1 0 173 0 0 173 74 1 1 0 7 0 0

    8 Prakasam 34 1 0 35 35 0 35 0 0 346 18 0 364 1071 19 14 5 62 18 0

    9 Nellore 39 0 0 39 39 0 38 1 0 329 24 0 353 1329 17 12 5 52 24 0

    250 7 0 257 240 13 229 11 4 2053 156 32 2241 5008 96 68 28 275 156 29Total

    ABSTRACT STATUS OF NCRMP WORKS PROGRESS AS ON 31.10.2013 TABLE - 7

    Cummulative Visits of TPQA

    Cummulative Audit

    Reports submitted

    by TPQA

    Sl.

    No.District

    Work Entrusted Status of Works

    TotalNo.

    ofQCtests

    cond

    ucted

    NCRs By TPQA

    Reviewo

    fContract

    Document

    Page 17 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    19/160

    Annexure - A

    Status of Works

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    20/160

    RATE OF PROGRESS OF WORKS No of works

    up to 10% 45

    11 to 40% 98

    41 to 70% 28

    71 to 100% 69

    Works Not Started 13

    Deleted 4

    Total No of Works 257

    Consolidated Abstract Status of NCRMP Works as on 31.10.2013

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    21/160

    RATE OF PROGRESS OF WORKS No of works

    up to 10% 4

    11 to 40% 10

    41 to 70% 4

    71 to 100% 17

    Works Not Started 0

    Total No of works 35

    Abstract Status of NCRMP Works in Prakasam District

    31.10.2013

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    22/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    1

    Y2-228

    Road from R&B road to

    Motupalli CS870 57.22 GSB In Progress 7.50 13%

    2

    Y2-229 Road from Km1/2+186 ofChinaganjam Railway gate-

    Bapaianagar ZP Road to

    Ramachandranagar H/o

    Kothapalem

    836 44.54 GSB Completed 7.00 16%

    3

    Y2-230

    Motupalli R&B Road to

    Nirikshanagiri (via)

    Rudramambapuram CS in

    Motupalli G.P.

    2276 102.57 GSB In Progress 15.50 15%

    4

    Y2-231

    Road from R&B road to

    Mattigunta CS363 13.21 GSB In Progress 2.00 15%

    5

    Y2-232 Vedullapalli Vodarevu R&B

    road to CS at

    Vijayalakshmipuram

    482 15.78 Earth Work in Progress 2.00 13%

    6

    Y2-233 Pakala PR Road to

    Chellammagaripattapupale

    m CS

    1200 55.59

    GSB Completed, WBM

    Grade-II Completed, CD

    Completed & CC

    Completed

    32.00 58%

    7

    Y2-234 Pakala PR road to

    Potthaiahgaripalem CS,

    Kranthinagar Revu.

    2150 102.15GSB Completed, CC

    Completed65.00 64%

    8

    Y2-235

    Woollapalem R&B road to

    Devalampallipalem CS1200 47.81 Earth Work in Progress 5.00 10%

    9

    Y2-236

    Road from Tangutur to

    Ananthavaram640 41.70

    GSB Completed, CC

    Pavement in Progress11.50 28%

    10

    Y2-238

    Road from Z.P. road to

    Srirampattapupalem2040 111.73

    GSB Completed, CC

    Completed, Shoulders in

    Progress

    106.00 95%

    11

    Y2-239

    Road from ZP road to

    Pallipalem of Chakicharala800 56.54

    GSB Completed, CC

    Completed, WBM Grade-

    II, WBM Grade-III &

    OGPC + SC Completed,

    Shoulders in Progress

    54.00 96%

    Status of NCRMP works in Prakasam District 31.10.2013

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory Agreement

    Amount

    (Lakhs)/

    Date

    DFC

    Milestone/ Financial Targets

    (%)Sl.No

    of

    work

    Projectcode

    Name of the Work

    1

    NCRMP/B-W/

    AP/RCS/

    PRED/08/

    Chinaganjam &

    Chirala/006

    RCS 233.00 /

    25.03.1325.05.14

    24.08.13

    Earth work,

    GSB, WBM

    (32%)

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    24.01.14

    CC, WBM,

    Shoulders

    (54%)

    24.05.14

    CC,

    Shoulders,

    BT & Road

    Furniture

    (100%)

    15.0

    5.1

    3

    34.00 13%

    For the

    package,

    progress of

    works is slow

    and not as

    per Milestone

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons

    for non-

    started

    works

    TPQA

    observationStage of work

    Value of

    work

    done in

    % of

    work

    done

    for the

    work

    13.12.13

    WBM Gr-II,

    CC & CD

    Works

    (54%)

    13.05.14

    WBM Gr-

    III, BT,

    Shoulders,

    Earth work

    & Road

    Furniture

    (100%)

    02.0

    4.1

    3

    113.50 23%

    For the

    Package,

    progress of

    works is slow

    and not as

    per Milestone

    2

    NCRMP/B-W/

    AP/RCS/

    PRED/08/

    S.Konda &

    Tangutur/010

    RCS 247.00 /

    14.03.1314.05.14

    13.08.13

    Earth work

    & GSB

    (32%)

    10.12.13

    GSB, WBM

    Gr-II, CC-

    1km (42%)

    10.03.14

    CC-

    1.390km,

    BT,

    Shoulders,

    Earth Work

    & Road

    Furniture

    (100%)

    15.0

    3.1

    3

    160.00 95%

    For the

    package,

    progress of

    works is

    ahead of

    Milestones.

    3

    NCRMP/B-W/

    AP/RCS/

    PRED/08/

    Ulavapadu

    /009

    RCS 169.00 /

    11.03.1310.03.14

    10.08.13

    Earth

    Work, CD

    Works

    (29%)

    Page 21 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    23/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory Agreement

    Amount

    (Lakhs)/

    Date

    DFC

    Milestone/ Financial Targets

    (%)Sl.No

    of

    work

    Projectcode

    Name of the WorkLength

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons

    for non-

    started

    works

    TPQA

    observationStage of work

    Value of

    work

    done in

    % of

    work

    done

    for the

    work

    12

    Y2-387

    R&B Road to

    Pulavaripalem600 36.71

    GSB Completed, CC

    Completed, Shoulders in

    Progress

    35.00 95%

    13

    Y2-388

    Road from Chinnaganjam

    Rly gate to Bapaiahnagar5577 187.50 168.75 90%

    14

    Y2-389

    Road from R & B road to

    Kothaplem1925 83.06 62.00 75%

    15

    Y2-390

    Motupalli R & B Road to

    Krishna Nagar360 23.37 GSB In Progress 3.00 13%

    16

    Y2-391

    Road from R & B Road to

    Yanadi Sangam850 48.19 Earth Work in Progress 5.00 10%

    17

    Y2-392 Jeedichetlapalem R&B

    road to

    Kunkuduchetlapalem

    2170 126.27 Earth Work in Progress 13.00 10%

    18

    Y

    2-397

    KEM R&B road to

    Chinapattapupalem900 43.13 34.50 80%

    19

    Y2-398 Salt Road from Madnur ZP

    road to

    Pedapattapupalem

    973 53.69 48.50 90%

    20

    Y2-399

    Madnur ZP road to

    Swarnandhrapattapupalem800 43.11 39.50 92%

    21

    Y2-400

    Madnur ZP road to

    Bapujiyanadi colony285 16.57

    GSB Completed, CC

    Completed, Shoulders in

    Progress

    15.50 94%

    22

    Y2-401 Salt Road from Madnur ZP

    road to Namburi yanadi

    colony

    975 47.89 39.00 81%

    23

    Y2

    -402 Salt Road from Madnur ZP

    road to Thotagunta

    yanadi colony

    1100 51.75 41.50 80%

    7

    NCRMP/B-W/

    AP/RHB/

    PRED/08/

    Tangutur/021

    RHB 143.00 /

    14.04.1310.04.14

    10.09.13

    Earth work,

    GSB (20%)

    10.01.14

    WBM, CD

    Works &

    CC (55%)

    10.04.14

    Shoulders,

    BT & Road

    Furniture

    (100%)

    24

    Y2-403

    Road from Tangutur to

    Tallapalem (via)

    Velagapudi (Km 4/5 to

    7/465)

    2965 143.00

    05.0

    4.1

    3 GSB Completed, CC

    Completed & WBM Grade-

    II in Progress

    66.00 63% 66.00 46%

    Progress of

    work is as per

    Milestone

    For the

    package

    Progress of

    works are

    slow and not

    as per

    Milestone

    5

    NCRMP/B-W/

    AP/RHB/

    PRED/08/

    Chinaganjam

    /013

    RHB 197.00 /

    19.03.1318.03.14

    18.08.13

    Earth work

    & GSB

    (26%)

    10.11.13

    WBM, CD &

    CC works

    (54%)

    11.05.14

    BT & Road

    Furniture

    (100%) 24.0

    3.1

    3

    265.75 87%

    For the

    package

    Progress of

    works are as

    per Milestone

    GSB Completed, CC

    Completed, WBM Grade-

    II, WBM Grade-IIICompleted, Shoulders in

    Progress

    4

    NCRMP/B-W/

    AP/RHB/

    PRED/08/

    Chinaganjam

    /012

    RHB 307.00 /

    11.03.1311.05.14

    10.06.13,

    Earth Work

    & GSB

    (32%)

    RHB 256.00 /

    11.03.1310.09.14

    10.11.13

    Earth work,

    GSB (47%)

    18.12.13

    WBM, CD

    Works &

    CC (44%)

    18.03.14

    BT & Road

    Furniture

    (100%) 15.0

    5.1

    3

    21.00 12%

    For the

    package

    Progress of

    works are as

    per Milestone

    GSB Completed, CC

    Completed, WBM Grade-

    II, WBM Grade-III

    Completed, Shoulders in

    Progress

    10.04.14

    WBM Gr-II,

    WBM Gr-III

    & CD

    Works

    (65%)

    10.09.14

    CC,

    Shoulders,

    BT & Road

    Furniture

    (100%)

    20.0

    3.1

    3

    GSB Completed, CCCompleted, WBM Grade-

    II, WBM Grade-III

    Completed, Shoulders in

    Progress

    218.50 80%6

    NCRMP/B-W/

    AP/RHB/

    PRED/08/

    Kothapatnam/0

    20

    Page 22 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    24/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory Agreement

    Amount

    (Lakhs)/

    Date

    DFC

    Milestone/ Financial Targets

    (%)Sl.No

    of

    work

    Projectcode

    Name of the WorkLength

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons

    for non-

    started

    works

    TPQA

    observationStage of work

    Value of

    work

    done in

    % of

    work

    done

    for the

    work

    8

    NCRMP/B-W/

    AP/RHB/

    PRED/08/

    Tangutur/022

    RHB 131.00 /

    14.03.1313.03.14

    13.08.13

    Earth work,

    GSB (20%)

    13.12.13

    WBM Gr-II,

    CD Works

    & CC

    (55%)

    13.03.14

    Shoulders,

    BT & Road

    Furniture

    (100%)

    25

    Y2-404 Road from Tangutur-

    Ravivaripalem road @1/2

    KM to Pasukuduru.

    2900 131.00

    14.0

    4.1

    3 GSB Completed, CD

    Works Completed & CC

    Completed

    70.00 53% 70.00 53%

    Progress of

    work is as per

    Milestone

    26

    Y2-405

    Road from Kanuparthy toKukkalavaripalem

    800 39.55 GSB In Progress 8.50 21%

    27

    Y2-406

    Road from Kanuparthy to

    Yanadi Sangam1500 71.83 GSB Completed 23.00 32%

    28

    Y2-407

    Road from Kanuparthy to

    MS Pattapupalem2300 118.31 GSB Completed 39.00 33%

    29

    Y2-409 Road from KEM R&B Road

    to Vajjireddypalem -

    Pattapupalem

    1185 58.50

    GSB Completed, CC

    Completed, WBM Grade-

    II, WBM Grade-

    IIICompleted,Shoulder is

    in Progress

    44.00 75%

    30

    Y2-410

    KEM R & B road to

    Pinnivaripalem1650 62.08

    SB Completed, CCCompleted, WBM Grade-

    II, WBM Grade-III

    Completed, OGPC +

    SCCompletedShoulders in

    58.00 93%

    31

    Y2-411 Salt Road from Madnur ZP

    road to

    Chinnapattapupalem

    800 33.89

    GSB Completed, CC

    Completed, WBM Grade-

    II, WBM Grade-

    IIICompleted,Shoulder is

    in Progress

    31.50 93%

    32

    Y2-412

    KEM R & B road to E.

    Pallipalem650 29.20

    GSB Completed, CC

    Completed, Shoulders in

    Progress

    29.00 99%

    33

    Y2-413 Road from KEM R & B

    road to

    Chenchupapayapalem

    1550 56.72

    GSB Completed, CC

    Completed, WBM Grade-II, WBM Grade-III &

    OGPC + SC Completed,

    Shoulders in Progress

    53.00 93%

    11

    NCRMP/B-W/

    AP/RHB/

    PRED/08/

    Ulavapadu

    /016

    RHB 359 /

    11.03.1310.06.14

    10.09.13

    Earth work,

    GSB (12%)

    10.02.14

    WBM Gr-II,

    WBM Gr-III

    & CD

    Works

    (64%)

    10.06.14

    CC-

    Shoulders,

    BT & Road

    Furniture

    (100%)

    34

    Y2-414 Road From M.C road to

    West ST colony of

    Veerapalli

    5380 359.00

    20.0

    3.1

    3

    GSB Completed, CC in

    Progress, WBM Grade-II,

    WBM Grade-III & OGPC

    + SC in Completed.

    Shoulders in Progress

    319.00 89% 319.00 89%

    For the

    package

    progress of

    work is as per

    Milestone

    10

    NCRMP/B-W/

    AP/RHB/

    PRED/08/

    Kothapatnam

    /019

    RHB 240.00 /

    15.03.1314.06.14

    14.09.13

    Earth work,

    GSB (29%)

    9

    NCRMP/B-W/

    AP/RHB/

    PRED/08/ NG

    Padu/011

    RHB 229.00 /

    20.03.1319.06.14

    19.09.13

    Earth work,

    GSB (25%)

    19.01.14

    WBM Gr-II,

    WBM Gr-III

    & CD

    Works

    (49%)

    19.06.14

    CC,

    Shoulders,

    BT & Road

    Furniture

    (100%)

    14.02.14

    WBM Gr-II,

    WBM Gr-II,

    CC-50% &

    CD Works

    (35%)

    14.06.14

    CC-50%,

    Shoulders,

    BT & Road

    Furniture

    (100%)

    20.0

    3.1

    3

    215.50 74%

    For the

    package

    Progress of

    works are as

    per Milestone

    09.0

    4.1

    3

    70.50 19%

    For the

    package

    Progress of

    works are as

    per Milestone

    Page 23 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    25/160

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    26/160

    RATE OF PROGRESS OF WORKS No of works

    up to 10% 1

    11 to 40% 15

    41 to 70% 5

    71 to 100% 18

    Works Not Started 0

    Total No of works 39

    Abstract Status of NCRMP Works in SPSR Nellore District as on 31.10.2013

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    27/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    1

    Y2-240 Road from @ 56/8 to

    C.K road to Periyavettu

    kuppam CS

    2000 71.83

    Earth work, GSB and

    WBM Gr-II & WBM Gr-III

    are completed.

    67 93%

    2

    Y2-241 Providing BT road to

    Pedapannamgadu in

    Tada Mandal

    1015 32.47

    Earth work, GSB WBM Gr-

    II & III and BT

    completed.

    32 99%

    2

    NCRMP/B-W/

    AP/RCS/

    PRED/09/

    Alluru/012

    RCS 24.3900

    18.03.201317.09.13

    17.06.13

    Earthwork, CD

    Works, and

    GSB (9%)

    17.08.13 CC

    Pavement &

    Shoulders

    (90%)

    17.09.13

    Road

    furniture.

    (100%)

    3

    Y2-242

    Approach road to

    Labbipalem420 24.39 0.1.05.13

    GSB and CC pavement

    are completed21 86% 21 86%

    3

    NCRMP/B-W/

    AP/RCS/

    PRED/09/

    Bogole/013

    RCS 58.99

    20.03.201319.09.13

    19.07.13

    Earthwork,

    and GSB

    (35%)

    19.10.13

    WMM, CD

    Works and

    Shoulders

    (73%)

    19.12.13

    BT and

    Road

    furniture.

    (100%)

    4

    Y2-243

    Road from R & B road

    to Pathakadapalem1400 58.99 01.05.13

    Earth work for widening

    is done. GSB Progress21 36% 21 36%

    5

    Y

    2-244 Road from

    Ramudupalem on R&B

    road to Pallipalem

    3600 209.93

    Earth work, GSB and CC

    pavement are completed.

    WMM is Progress

    150 71%

    6

    Y2-245

    Road from Korutur to

    Pattapupalem2250 159.58

    Earth work, vented road

    dam, CD works &. GSB

    Completed. WMM is in

    progress

    115 72%

    5

    NCRMP/B-W/

    AP/RCS/

    PRED/09/

    Kavali/020

    RCS 166.89

    28.02.201327.02.14

    27.07.13

    5Months: Earth

    Work, GSB

    (24%)

    27.11.13

    9 Months:

    WMM, CD

    works

    (72%)

    27.02.14

    12 Months:

    BT & Road

    Furniture

    of all works

    (100%)

    7

    Y2-246 Road from 230/6 Km of

    M.C Raod to

    Pedapattapupalem

    6200 166.89 01.03.13

    Earth work for widening,

    vented road dam GSB

    completed.WMM is in

    progress

    105 63% 105 63%

    Pogress of

    work is with

    in the mile

    stones as per

    value of work

    done.

    8

    Y2-247

    Road from R&B road to

    Utukuru Pallipalem3800 141

    Earth work and GSB are

    completed.31 22%

    9

    Y2

    -248 Road Ponnapudi R&B

    Road to

    Ramachendrapuram.

    2000 132.8

    Earth work, GSB are

    completed. WMM in

    progress

    69 52%

    10Y2-249

    Ponnapudi R&B road to

    Busagadipalem1900 98

    Earth work & GSB are

    completed.21 21%

    11

    Y2-250 Road from Ponnapudi

    R&B Road to

    Lakshimipuram

    1000 54Earth work & GSB are

    completed.12 22%

    12

    Y2-251

    Road from R&B Road to

    Ramalingapuram1700 72 Earth work is completed 14 19%

    265 72%

    Progress of

    work is with

    in the mile

    stones as per

    value of work

    done.

    6

    NCRMP/B-W/

    AP/RCS/

    PRED/09/

    Vidavaluru

    /021

    RCS 497.800

    20.03.201319.06.14

    19.09.13

    6Months: Earth

    Work, GSB

    (21%)

    19.02.1411 Months:

    WMM, CC

    Pavement of

    all works,

    CD works

    (78%)

    Progress of

    work is with

    in the mile

    stones as per

    value of work

    done.

    4

    NCRMP/B-W/

    AP/RCS/

    PRED/09/ I.

    Pet/018

    RCS 369.51

    20.03.201319.06.14

    19.09.13

    Earthwork, CDWorks, CC

    Pavement and

    GSB (54%)

    19.02.14

    WMM, and

    Shoulders

    (74%)

    19.06.14

    BT andRoad

    furniture

    (100%)

    21.03.13

    19.06.1415 Months:

    BT & Road

    Furniture

    of all

    works.

    (100%)

    01.04.13 147 30%

    Progress of

    work is with

    in the mile

    stones as per

    value of work

    done.

    99 95%

    Progress of

    work is not

    within the

    mile stones

    as per value

    of work done.

    Extension of

    time has to

    be taken

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons

    for non-

    started

    works

    TPQA

    observationStage of work

    Value

    of

    work

    done

    in

    % of

    work

    done

    for the

    work

    1

    NCRMP/B-W/

    AP/RCS/

    PRED/09/Tada/009

    R

    CS 104.300

    14.09.201213.09.13

    13.2.13

    Earthwork,

    Pipe culverts,

    GSB & CCpavement

    (49%)

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    13.06.13

    WBM Gr-II,

    Gr-III and

    Shoulders

    (86%)

    13.09.13

    BT and

    Road

    furniture.

    (100%)

    15.09.12

    Status of NCRMP works in SRSP Nellore District 31.10.2013

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory Agreement

    Amount

    (Lakhs)/

    Date

    DFC

    Milestone/ Financial Targets (%)

    Sl.No

    of

    work

    Projectcode

    Name of the Work

    Page 26 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    28/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons

    for non-

    started

    works

    TPQA

    observationStage of work

    Value

    of

    work

    done

    in

    % of

    work

    done

    for the

    work

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory Agreement

    Amount

    (Lakhs)/

    Date

    DFC

    Milestone/ Financial Targets (%)

    Sl.No

    of

    work

    Projectcode

    Name of the Work

    7

    NCRMP/B-W/

    AP/RCS/

    PRED/09/

    Chillakur/ 014

    RCS 293.28

    21.03.201320.03.14

    20.09.13

    Earthwork,

    and GSB.

    (39%)

    20.12.13

    WMM, CD

    Works, CC

    Pavement &

    Shoulders

    (84%)

    19.03.14

    BT and

    Road

    furniture.

    (100%)

    13

    Y2-252 Road from R&B Road

    Lingavaram to

    Narravaripalem

    6808 293.28 22.03.13

    Earth work for widening

    is completed.GSB

    Completed.WMM is in

    Progress

    134.5 46% 134.5 46%

    8

    NCRMP/B-W/

    AP/RCS/

    PRED/09/

    Chillakur/015

    RCS 112.77

    21.03.201320.03.14

    20.08.13

    Earthwork,

    and GSB.

    (38%)

    20.12.13WMM, CD

    Works, CC

    Pavement &

    Shoulders

    (82%)

    20.03.14

    BT and

    Road

    furniture

    (100%)

    14

    Y2-253 Road from R&B road

    (via) Narravaripalrm to

    Srinivasa Satram

    2260 112.77 01.04.13

    Earth work for widening

    is completed.GSB

    Completed.WMM is in

    Progress

    61 54% 61 54%

    9

    NCRMP/B-W/

    AP/RCS/

    PRED/09/

    Kota/016

    RCS 157.200

    20.03.201319.03.14

    19.08.13

    Earthwork,

    and GSB.

    (21%)

    18.12.13

    WMM,CD

    Works, CC

    Pavement &

    Shoulders

    (56%)

    19.03.14

    BT and

    Road

    furniture

    (100%)

    15

    Y2-254 Road from R&B Road to

    Doruvukatta road (via)

    Allmpadu, Deyyaladibba

    4320 157.2

    21.03.13

    Earth work for widening,

    GSB, CC pavement ,CD

    works , WMM and BT

    completed.

    151 96% 151 96%

    16

    Y2-255 Road from Kotha Kudur

    Katepalli road to

    Patha Pattapupalem

    600 25.67Jungle clearance is in

    progress2 8%

    17

    Y2-256

    Road from C.S. Puram

    to Edurupalem2200 74.31

    From km 0.0 to km 1.2

    Earth work, GSB, WMM ,

    BT completed

    34 46%

    18

    Y2-257

    Mahlakshmi puram to

    Sagara Sangamam (via)

    Muthyalathopu

    Pattapupalem

    2600 65.66

    Earth work for widening,

    WMM and BT Completed.

    CD works completed.

    63 96%

    19

    Y2-258 Road from R&B road

    Nelaturu to

    Ananthavaram CS

    100 7.34Jungle clearance is in

    progress1 14%

    11

    NCRMP/B-W/

    AP/RCS/

    PRED/09/

    Tada/024

    RCS 97.55

    22.03.201321.03.14

    21.07.13

    Earthwork,

    and GSB.

    (35%)

    21.10.13

    WMM, CD

    Works, CC

    Pavement &

    Shoulders(79%)

    21.12.13

    BT and

    Road

    furniture

    (100%)

    20

    Y2-259 Road from @ Km 65/4

    of CK Road to Tada

    Kuppam CS

    1900 97.55 23.03.13

    Earth work for

    widening,CD, GSB and

    WMM and BT

    completed.

    90 92% 87 89%

    progress of

    work is with

    in the mile

    stones as per

    value of workdone.

    12

    NCRMP/B-W/

    AP/RHB/

    PRED/09/

    Allur/018

    RHB 120.86

    18.03.201317.03.14

    17.08.13

    Earthwork,

    and

    GSB.(16%)

    17.12.13

    WMM, CD

    Works, CC

    Pavement &

    Shoulders

    (77%)

    17.03.14

    BT and

    Road

    furniture.

    (100%)

    21

    Y2-419 Road from R.I Road to

    C.R. Palem (via)

    Sambhunipalem

    4000 120.86 01.06.13 CD works is progress. 16 13% 16 13%

    Progress of

    work is

    slightly

    behind the

    mile stones

    as per value

    of work done.

    10

    NCRMP/B-W/

    AP/RCS/

    PRED/09/

    T.P.Gudur &

    Muthukur /019

    RCS 172.98

    15.03.201314.06.14

    14.09.13

    6Months: Earth

    Work, GSB

    (17%)

    Progress ofwork is with

    in the mile

    stones as per

    value of work

    done.

    14.02.14

    11 Months:

    WMM, CD

    works, CC

    Pavement

    (76%)

    14.06.14

    15 Months:

    BT and

    Road

    Furniture

    (100%)

    01.07.13 100 58%

    progress of

    work is with

    in the mile

    stones as per

    value of work

    done.

    Page 27 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    29/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons

    for non-

    started

    works

    TPQA

    observationStage of work

    Value

    of

    work

    done

    in

    % of

    work

    done

    for the

    work

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory Agreement

    Amount

    (Lakhs)/

    Date

    DFC

    Milestone/ Financial Targets (%)

    Sl.No

    of

    work

    Projectcode

    Name of the Work

    22

    Y2-420 Salt Road from Iskapalli

    to Salt fields at Kotha

    Kurrupattapupalem

    3000 134

    Earth work, GSB & WMM

    are completed. CD works

    completed.

    105 78%

    23

    Y2-421

    Road from R&B road to

    Zuvvagu Lakshmipuram1800 84

    Earth work for widening

    done. GSB in progress12 14%

    24

    Y2-422 Road from R&B Road to

    Zuvvagu2100 31.24

    Earth work, GSB, WMM,CD works and CC Road

    are completed.

    23 74%

    25

    Y2-423 Annagaripalem R&B

    road to Pedanattu

    Pattapupalem

    2100 57.28Earth work for widening

    done. GSB completed18 31%

    26

    Y2-424

    Pedapattapupalem to

    Nandempuram2800 77.17

    Earth work, GSB and

    WMM are progress56 73%

    27

    Y2-425

    Ponnapudi-Utukur road

    to Pattapupalem2800 137

    Earth work for widening

    and GSB completed.42 31%

    28

    Y

    2-426

    Road from R&B road to

    Venkatareddypalem1100 58.63 Sub Grade in progress 15 26%

    29

    Y2-427

    Ponnapudi R&B road to

    Anjanayapuram950 52

    Earth work for widening

    and GSB is in progress.21 40%

    30

    Y2-428

    Ponnapudi Utukur

    road to Srigowripuram1100 68.0

    Earth work for widening

    and GSB is in progress.15 22%

    31

    Y2-429

    Ponnapudi Utukur

    R&B road To Kothuru800 54.86

    Earth work for widening

    and GSB completed.22 40%

    32

    Y2-430 Road from Ponnapudi

    Utukur R&B road to

    Prasanthi giri colony

    1200 68

    Earth work for widening,

    GSB,WMM & BT are

    completed.

    67 99%

    33

    Y

    2-431

    Ponnapudi R&B road to

    Venkatanarayanapuram1200 70

    Earth work for widening,

    GSB , WMM & BT are

    completed.

    69 99%

    34

    Y2-432

    Road from Ponnapudi

    R&B road to Ponnapudi500 34

    Earth work, GSB & CC

    pavement are completed34 100%

    35

    Y2-433

    Mypadu R&B Road to

    Kollimittapalem2350 126.6

    Earth work for widening,

    GSB and WMM

    completed

    105 83%

    36

    Y2-434 Nellore Mypadu R&B

    Road to West

    Pattapupalem

    900 59.64Earth work , GSB & CC

    road is completed48 80%

    82%

    Progress of

    work is with

    in the mile

    stones as per

    value of work

    done.

    207 70%

    Progress of

    work is with

    in the mile

    stones as per

    value of work

    done.

    15

    NCRMP/B-W/

    AP/RHB/

    PRED/09/

    Vidavaluru/025

    RHB 247.63

    20.03.201319.03.14

    20.08.13

    5Months: Earth

    Work, GSB

    (27%)

    19.03.14

    12 Months:

    BT & Road

    Furniture

    remaining

    all items.

    (100%)

    21.03.13 153

    74 55%

    Progress of

    work is with

    in the mile

    stones as per

    value of work

    done.

    20.12.13

    9 Months:

    WMM, CC

    Pavement of

    all works,CD works,

    (84%)

    20.03.14

    12 Months:

    BT & Road

    Furniture

    of allworks.

    (100%)

    21.03.13 56

    17

    NCRMP/B-W/

    AP/RHB/

    PRED/09/

    I.Peta/027

    RHB 186.24

    20.03.201319.03.14

    19.08.13

    5Months: Earth

    Work, GSB

    (20%)

    19.12.13

    9 Months:

    WMM, CD

    works,

    (89%)

    23%

    16

    NCRMP/B-W/

    AP/RHB/

    PRED/09/

    Vidavaluru

    /026

    RHB 294.86

    20.03.201319.06.14

    20.09.13

    6Months: Earth

    Work, GSB

    (23%)

    20.02.14

    11 Months:

    WMM, CC

    Pavement of

    all works,

    CD works,

    (88%)

    20.06.14

    15 Months:

    BT and

    Road

    Furniture

    of all

    works.

    (100%)

    21.03.13

    14

    NCRMP/B-W/

    AP/RHB/

    PRED/09/

    Kavali/024

    RHB 134.45

    04.03.201303.03.14

    3.08.13

    5Months: Earth

    Work, GSB

    (32%)

    17.12.13

    WMM, CD

    Works, CC

    Pavement

    and

    Shoulders(49%)

    17.03.14

    BT and

    Road

    furniture.

    (100%)

    19.03.13

    3.12.13

    9 Months:

    WMM, CD

    works,

    shoulders

    (69%)

    03.03.14

    12 Months:

    BT & Road

    Furniture

    complete

    of work.

    (100%)

    01.06.13

    140 56%

    Progress of

    work is with

    in the mile

    stones as per

    value of work

    done.

    13

    NCRMP/B-W/

    AP/RHB/

    PRED/09/

    Allur/019

    RHB 249.24

    18.03.201317.03.14

    17.08.13

    Earthwork,

    and GSB

    (24%).

    Page 28 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    30/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons

    for non-

    started

    works

    TPQA

    observationStage of work

    Value

    of

    work

    done

    in

    % of

    work

    done

    for the

    work

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory Agreement

    Amount

    (Lakhs)/

    Date

    DFC

    Milestone/ Financial Targets (%)

    Sl.No

    of

    work

    Projectcode

    Name of the Work

    18

    NCRMP/B-W/

    AP/RHB/

    PRED/09/

    V.Chalam/021

    RHB 69.400

    08.02.201307.11.13

    7.07.13

    5Months: Earth

    Work, GSB

    (22%)

    7.11.13

    9 Months:

    WMM, CD

    works,

    (82%)

    7.02.14

    12 Months:

    BT & Road

    Furniture

    (100%).

    37

    Y2-435

    Road from

    Thirumalammapalem

    R&B Road to Gajulapalli

    Koneru

    2400 69.4 09.02.13

    From km 0/0 to km 2.00,

    Earth work, GSB, CD

    works, WMM & BT are

    completed. From Km 2.0

    to 2.4 work could not be

    completed due to court

    case.

    65 94% 65 94%

    19

    NCRMP/B-W/

    AP/RHB/

    PRED/09/

    Kota/022

    RHB 252.640

    19.03.201318.06.14

    18.09.13

    6Months: Earth

    Work, GSB

    (23%)

    18.02.13

    5 Months:

    WMM, CD

    works,

    (82%)

    18.06.14

    4 Months:

    BT & Road

    Furniture

    remaining

    all items.

    (100%)

    38

    Y2-436

    Road from R&B road

    Kothapatnam to

    Yamadinnepalem (via)

    Srinivasasatram

    6100 252.64 20.03.13

    Earth work for widening

    and GSB are completed.

    WMM work is in

    progress.

    70 28% 61 24%

    20

    NCRMP/B-W/

    AP/RHB/

    PRED/09/

    Kota/023

    RHB 53.87

    508.02.201307.11.13

    7.06.13

    4Months: Earth

    Work, GSB

    (24%)

    7.9.13

    3 Months:

    WMM, CD

    works,

    (81%)

    7.01.14

    2 Months:

    BT & Road

    Furniture

    (100%)

    39

    Y2-437 Road from at km 22/5

    of Yamadinne palem

    road to Gunnampadia

    1320 53.87 09.02.13

    Earth work for

    widening, GSB, CD

    works, WMM and BT

    Completed. CC pavement

    completed.

    52 97% 52 97%

    Progress of

    work is ahead

    of the mile

    stones as per

    value of work

    done.

    Progress of

    work is with

    in the mile

    stones as per

    value of work

    done.

    Page 29 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    31/160

    RATE OF PROGRESS OF WORKS No of works

    up to 10% 1

    11 to 40% 0

    41 to 70% 2

    71 to 100% 8

    Works Not Started 0

    Total No of works 11

    Abstract Status of NCRMP Works in Visakhapatnam District as on

    31.10.2013

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    32/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    1

    NCRMP/B-W/

    AP/MPCS/

    PRED/03/Rambillii/004

    MP

    CS 75.06

    03.10.2011

    02.07.201

    2 EOAT

    approved

    up to25.07.201

    3

    02.01.12

    Ground

    FloorPlinth

    Leve

    02.04.12

    Casting ofall slabs

    02.07.12

    Completio

    n of allitems of

    work

    1Y2-

    048 Construction of

    cyclone shelter atVenkayyapalem

    75.06

    Re start

    after getting

    approval of

    foundationre design on

    29.06.12

    All slabs, brick work,

    plastering, wood

    joinery,flooring,plumbing,

    painting completed.

    75.06 100% 75.06 100%

    Working estimate

    preparation/approval is awaiting.

    2

    NCRMP/B-W/

    AP/MPCS/

    PRED/03/ S

    Rayavaram

    /009

    MPCS 129.92

    20.04.201319.04.13

    19.09.13

    Ground

    Floor

    Plinth

    Level

    19.01.14

    Casting of

    all floors

    19.04.13

    Completio

    n of all

    items of

    work

    2

    Y2-057 Construction of CS at

    Bangarampalem I & II

    H/o Vakadu. (Type D)

    129 .92 20.04. 13

    Earthwork excavation

    started and stop due to

    site dispute. Alternate

    site is identified and

    approval is pending.

    0% 0% 0 0%

    The village

    proposed to be

    aquired for navel

    base purpose.

    Hence the field

    officers are

    informed to higher

    otherties for

    cancellation of the

    work

    3

    Y2-165

    Road from R&B road

    to

    Chinanagamayyapalem

    CS

    1525 47.29 11.03.13

    WBM Gr-II From KM

    0.000 to Km 0.800

    completed.

    Three nos. CD works

    completed.

    WBM Gr-III From KM

    0.000 to Km 0.800

    completed. OGPC +Seal

    coat from Km 0.00 to

    KM 0.800 completed.

    26 55%

    45% value of work

    is not able to do

    due to site dispute

    with forest dept.@

    4

    Y2-166

    Road from R&B road

    to Annavaram CS1100 31.15 11.03.13

    WBM Gr-II ( From

    km0.00 to 1.057 ) and

    CC Road work ( From

    km 1.057 to KM 1.107 )

    completed . WBMGr-III

    and OGPC + Seal coat

    from 0.00 to Km1.057completed.

    30 96%

    4

    NCRMP/B-W/

    AP/RCS/

    PRED/03/ S

    Rayavaraam

    /006

    RCS 56.46

    07.03.201306.12.13

    06.07.13

    Earth

    work, CC

    road

    (29.28%)

    06.10.13

    CC Road

    (67.18%)

    06.12.13

    Shoulders

    , Road

    furniture

    & CC road

    (100%)

    5

    Y2-167

    Road from R&B road

    to Revupolavaram CS1065 56.46 07.03.13

    Earth work for

    widening, CC Road

    work, shoulder works

    are completed from KM

    0.000 to KM 0.8538 and

    from KM 0.8845 KM

    1.072

    56 99% 56 99%

    55 70%3

    NCRMP/B-W/

    AP/RCS/

    PRED/03/

    Bheemili/005

    RCS 78.44

    11.03.2013

    10.07.13

    Earthwork

    , Pipe

    culverts of

    all

    works(10

    %)

    10.12.13

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commence

    ment of

    work

    Stage of work

    10.10.13

    WBM

    Gr-II,

    Gr-III and

    CC

    pavement

    of all

    work

    (54.76%)

    10.12.13

    BT,

    Shoulders

    and Road

    furniture

    complete

    of all

    works

    (100%)

    Status of NCRMP works in Visakhapatnam District as on 31.10.2013

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory

    Agreement

    Amount

    (Lakhs)/Date

    DFC

    Milestone/ Financial Targets

    (%)Sl.No

    of

    work

    Projectcode

    Name of the Work

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons

    for non-

    started

    works

    TPQA observation

    Value of

    work

    done in

    % of

    work

    done for

    the work

    Page 31 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    33/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commence

    ment of

    work

    Stage of work

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory

    Agreement

    Amount

    (Lakhs)/Date

    DFC

    Milestone/ Financial Targets

    (%)Sl.No

    of

    work

    Projectcode

    Name of the Work

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons

    for non-

    started

    works

    TPQA observation

    Value of

    work

    done in

    % of

    work

    done for

    the work

    5

    NCRMP/B-W/

    AP/RCS/

    PRED/03/

    Rambilli/007

    RCS 38.78

    11.03.201310.09.13

    10.06.13

    Earthwork

    , GSB (

    15%)

    10.08.13

    CC Road

    ( 89.45)

    10.09.13

    Wearing

    coat,

    shoulders

    and Road

    furniture

    complete( 100%)

    6

    Y2-168

    Road from R&B road

    to Kothapatnam CS650 38.78 11.03.13

    Earth work, sub

    grade,GSB, shoulders

    and CC Road work

    completed from KM

    0.000 to KM 0.610.

    39 101% 38.7 100%

    7Y2-280

    Road from R&B road

    to Rajavaram425 14.38 07.03.13

    One pipe culvert, WBM

    Gr-II, Gr-III and OGPC

    seal coat Work is

    completed From KM

    0.0 to KM 0.425

    14 94%

    .4 va lue o ne

    pipe culvert work is

    not executed as the

    field officers

    proposed that it is

    not re uired.

    8Y2-281 Road from Rajala R&B

    Road toRajaraidupalem

    1764 65.34 07.03.13

    Sub grade with selected

    earth(Gravel): From km

    0.640 to 0.750, from KM

    1.190 to Km 1.764

    completed. Earth work

    and WBM Gr-II

    completed From KM

    0.000 to KM 0.012, from

    KM 0.030 to KM 1.764.GSB : 1488 Meters

    From KM 0.030 to KM

    0.094, from KM 0.340 to

    KM 1.764 completed.

    CD works (4 nos)

    and Retaining wall

    completed.WBM Gr-III

    Rolling is progress..

    32 49%

    9

    Y2

    -282 Road from R&B road

    to Gajareddipalem via

    Venkaypalem

    2614 109.87 07.03.13

    4 Nos pipe culverts

    completed. From Km

    0/106 to Km 1/600 and

    from km 2/0 to km

    2/620 GSB,WBM Gr-

    II,Grade-III and OGPC

    + Seal coat completed.

    From KM 1.600 to Km

    2.0 and From KM 2.620

    to KM 2.720 GSB work

    completed.

    92 84%

    138 73%

    06.10.13

    Earthwork

    ,

    Pipeculver

    ts,GSB

    ( 35.8%)

    06.04.14WBM Gr-

    II,Gr-III

    and

    shoulders

    & CC

    Pavement

    ( 72.6%)

    06.06.14

    BT and

    Road

    furniture

    ( 100%)

    6

    NCRMP/B-W/

    AP/RHB/

    PRED/03/

    Payakaraopeta

    /005

    RHB 189.59

    07.03.201306.06.14

    Page 32 of 159

    Mil t / Fi i l T t T l

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    34/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commence

    ment of

    work

    Stage of work

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory

    Agreement

    Amount

    (Lakhs)/Date

    DFC

    Milestone/ Financial Targets

    (%)Sl.No

    of

    work

    Projectcode

    Name of the Work

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons

    for non-

    started

    works

    TPQA observation

    Value of

    work

    done in

    % of

    work

    done for

    the work

    7

    NCRMP/B-W/

    AP/RHB/

    PRED/03/

    Payakaraopeta

    /008

    RHB 62.04

    07.03.201306.12.13

    06.07.13

    Earth,GSB

    ,Retaining

    wall (

    22%)

    06.10.13

    CC Road

    (86%)

    06.12.13

    CC drain,

    CD works,

    Shouldersand Road

    furniture

    complete

    (100%)

    10

    Y2-28

    3 Road from Z.P Road

    Palmanpeta to

    Korlayyapeta

    1110 62.04 07.03.13

    One single row and one

    two row pipe culvert

    works completed.

    Retaining wall work

    completed for 62.55

    Meters ( 62.55m in km

    0/600 ).Earth work, GSB and CC

    pavement From Km

    0/0323 to Km 0/4021,

    from Km 0/689 to

    0/9294 and Cross Road

    from Km 0/328 to 0/498

    Completed

    60 96% 60 96%

    CC drain, body walls

    and parapet wallsfor one CD work is

    not done.

    8

    NCRMP/B-W/

    AP/RHB/

    PRED/03/

    Atchutapuram

    /009

    RHB 26.09

    07.03.201306.09.13

    06.06.13

    Earth

    work,CC

    Road

    (26.22%)

    06.08.13

    CC Road

    (70.81%)

    06.09.13

    Shoulders

    and Road

    furniture

    11

    Y2-284

    Road from R&B Road

    to Vadapalem450 26.09 07.03.13

    Shoulders and CC Road

    completed from KM

    0.000 to KM 0.4244

    26 100% 26 100%

    Page 33 of 159

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    35/160

    RATE OF PROGRESS OF WORKS No of works

    up to 10% 14

    11 to 40% 19

    41 to 70% 2

    71 to 100% 7

    Works Not Started 3

    Works Deleted 4

    Total No of works 49

    Abstract Status of NCRMP Works in Srikakulam Districtas as on 31.10.2013

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    36/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    1

    Y2-001

    Construction of CS at

    Kollipadu112.03

    Finishing work is in

    progress111 99%

    2

    Y2-002

    Construction of CS at

    Runku112.03

    Finishing work is in

    progress108 96%

    3

    Y2-005

    Construction of MPCS

    in AmalapaduDELETD

    4

    Y2-006

    Construction of MPCS

    in Angavanipeta86.4 Not started 0 0%

    Line Dept officers

    are taken position

    of required land

    from

    Gramkantam. The

    villagers wanted

    to construct the

    CS at Amalapadu.

    5

    Y2-007

    Construction of MPCS

    in Ch.BatasalavanipetaDELETED

    6

    Y2-008 Construction of MPCS

    in ChintavanipetaDELETED

    7

    Y2-009

    Construction of MPCS

    in U.Narisingapally86.4 Not started 0 0%

    8

    Y2-010 Construction of MPCS

    in Bypalli

    (Type C)

    117.38

    PCC for Footings,

    footings, pedestals

    and columns up to

    bottom of plinth

    beam are

    completed, Back

    filling in foundation

    is in progress.

    25 21%

    9

    Y2-01

    1 Construction of MPCS

    in Chinavanka

    (Type C)

    119.1

    PCC, Footings,

    Columns below

    plinth levelcompleted. Back

    filling in fondation is

    in progress.

    19 16%

    10

    Y2-012 Construction of MPCS

    in Chinakotturu

    (Type A)

    89.21

    PCC, Footings

    completed. Columns

    is in progress.

    11.5 13%

    11

    Y2-013 Construction of CS in

    Chinajuttuvanipalem

    (Type A)

    DELETED

    3

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/

    V.Kotturu/004MPCS 422.27

    9.03.13 8.09.14

    Progress of work is

    behind the mile

    stones. Contractor

    has to speed up the

    work to achive the

    progress.

    8.11.13

    Ground

    Floor

    PlinthLevel of

    all works

    (24.34%)

    8.04.14

    Casting of

    all slabs

    of allworks

    (59.64%

    Value)

    8.09.14

    Completet

    ion of all

    works

    (100%

    Value)

    55.5 17%

    219.00 98%

    2

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/

    V.Kotturu/003MPCS 475.07

    09.03.1308.09.14

    08.11.13

    Ground

    Floor

    Plinth

    Level of

    all works

    (28.72%)

    08.04.14

    Casting of

    all slabs

    of all

    works

    (65.27%

    Value)

    08.09.14

    Completet

    ion of all

    works

    (100%

    Value)

    0 0%

    1

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/

    Santhabommali

    /005

    MPCS 224.07

    17.10.11

    EOAT

    approved

    up to

    04.09.13

    16.03.12

    Ground

    Floor

    Plinth

    Level of

    all works

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    16.08.12

    Casting of

    first floor

    roof slabs

    of all

    works

    16.01.13

    Completet

    ion of all

    works

    (100%

    Value)

    Nov-11

    Status of NCRMP works in Srikakulam District as on 31.10.2013

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory

    Agreement

    Amount

    (Lakhs)/Date

    DFC

    Milestone/ Financial Targets

    (%)Sl.No

    of

    work

    Projectcode

    Name of the Work

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons for

    non-started

    works

    TPQA observationStage of work

    Value of

    work

    done in

    % of

    work

    done for

    the work

    Page 35 of 159

    e Milestone/ Financial Targets Total

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    37/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory

    Agreement

    Amount

    (Lakhs)/Date

    DFC

    Milestone/ Financial Targets

    (%)Sl.No

    of

    work

    Projectcode

    Name of the Work

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons for

    non-started

    works

    TPQA observationStage of work

    Value of

    work

    done in

    % of

    work

    done for

    the work

    4

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/

    Ranastalam

    /008

    MPCS 88.75

    15.03.1314.03.14

    14.09.13

    Ground

    Floor

    Plinth

    Level of

    all works

    (21%)

    14.2.14

    Casting of

    all slabs

    of all

    works

    (67%

    Value)

    14.06.14

    Completet

    ion of all

    works

    (100%

    Value)

    12

    Y2-018 Construction of MPCS

    in Kommaravanipeta

    (Type A)

    88.75 15.03.13

    Earth work

    excavation

    completed, PCC

    Completed.

    Reinforcement for

    footings is in

    progress.

    6.4 7% 2 2%

    5

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/

    Kavati/011MPCS 80.83

    20.03.1319.03.14

    19.08.13

    Ground

    Floor

    Plinth

    Level

    (28.51%)

    19.12.13

    Casting of

    all slabs.

    (60.23%

    Value)

    19.03.14

    Completet

    ion of all

    works

    (100%

    Value)

    13

    Y2-023 Construction of MPCS

    in Ch.Karrivanipalem

    (Type B)

    80.83 15.08.13Earth work is in

    progress1 1% 1 1%

    6

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/

    Sompeta/012MPCS 88.78

    15.03.1314.03.14

    19.08.13

    Ground

    Floor

    Plinth

    Level

    (33%)

    19.12.13

    Casting of

    all slabs.

    (67%

    Value)

    19.03.14

    Completet

    ion of all

    works

    (100%

    Value)

    14

    Y2-024 Construction of MPCS

    in Ramayyapatnam

    (Type B)

    88.78 15.03.13 PCC completed 5.5 6% 5.5 6%

    Progress of work is

    behind the mile

    stones. Contractor

    has to speed up the

    work to achive the

    progress.

    15

    Y2-025

    Construction of MPCS

    in Metturur (Type D)119.775 15.03.13

    PCC for Footings,footings, pedestals

    and columns up to

    bottom of plinth

    beam are

    completed, Back

    filling in foundation

    is in progress.

    23 19%

    16

    Y2-026 Construction of MPCS

    in Nuvvalarevu (Type

    D)

    119.775 Not started 0 0%

    Site is handed

    over to the

    contractor. The

    contractor has to

    start the work.

    8

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/

    Santhabommall

    i /014

    MPCS 116.89

    20.03.1319.03.14

    19.08.13

    GroundFloor

    Plinth

    Level

    (21%)

    19.12.13Casting of

    all slabs.

    (% Value)

    19.03.14

    Completetion of all

    works

    (100%

    Value)

    17

    Y2-027 Construction of MPCS

    in R.Sunnapally

    (Type C)

    116.89 20.03.13Earth work is in

    progress2 2% 2 2%

    The contractor

    started the earthwork excavation in

    the month of July.

    Awaiting for SBC

    result.

    Progress of behind

    themile stones.

    Contractor has to

    speed up the work

    to achive the

    progress.

    Site is handed

    over to the

    contractor. But

    the contractorstarted the earth

    work excavation

    in the month of

    August.

    Progress of work is

    behind the mile

    stones. Contractorhas to speed up the

    work to achive the

    progress.

    7

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/

    V.Kotturu / 013MPCS 239.55

    15.03.1314.06.14

    14.09.13

    Ground

    Floor

    Plinth

    Level of

    all works

    (22.97%)

    14.02.14

    Casting of

    all slabs

    of all

    works

    (52.58%

    Value)

    14.06.14

    Completet

    ion of all

    works

    (100%

    Value)

    23 10%

    Page 36 of 159

    e Milestone/ Financial Targets Total

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    38/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory

    Agreement

    Amount

    (Lakhs)/Date

    DFC

    Milestone/ Financial Targets

    (%)Sl.No

    of

    work

    Projectcode

    Name of the Work

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons for

    non-started

    works

    TPQA observationStage of work

    Value of

    work

    done in

    % of

    work

    done for

    the work

    18

    Y2-028 Construction of MPCS

    in Calingapatnam

    (Type D)

    125.78 15.03.13Plinth beam

    completed38 30%

    19

    Y2-029 Construction of MPCS

    in Bandaruvanipeta

    (Type D)

    125.78 15.03.13

    Earthwork

    Excavation, PCC for

    footings, RCC

    footings, pedestals

    and columns upto

    bottom of plinth

    beam work

    completed. Back

    filling in foundation

    completed.

    30.5 24%

    10

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/

    Polaki/018MPCS 92.48

    15.03.1314.03.14

    14.08.13

    Ground

    Floor

    Plinth

    Level

    (15%)

    14.12.13

    Casting of

    all slabs

    of all

    works

    (68%

    Value)

    14.03.14

    Completet

    ion of all

    works

    (100%

    Value)

    20

    Y2-030 Construction of MPCS

    in Akkuvaram (Type

    C)

    92.48 15.03.13

    PCC completed,

    Reinforcement for

    footings is in

    progress.

    7.5 8% 7.5 8%

    Progress of work is

    behind the mile

    stones. Contractor

    has to speed up the

    work to achive the

    progress.

    21Y2-0

    31 Construction of MPCS

    in Jaganadhapuram(Type B)

    89.43 15.03.13

    PCC, Footings &

    columns below

    plinth beamcompleted and back

    filling is in progress.

    17 19%

    22

    Y2-032 Construction of MPCS

    in Kottamukkam (Type

    A)

    88.72 15.03.13

    PCC completed,

    Reinforcement,

    shuttering for

    footings completed.

    16 18%

    23

    Y2-036 Construction of MPCS

    in Patadibbalapalem

    (Type A)

    89.91

    Footings, columns

    below plinth beam

    completed

    19 21%

    24

    Y2-037 Construction of MPCS

    in Bontalakoduru

    (Type B)

    86.87Earth work

    Completed2 2%

    25Y2-145 Road from

    Chinnavanka toGopaladavooru

    3675 63.32Earth work

    completed 1 2%

    26

    Y2-146 Road from MN peta

    Road to Kondavooru

    and to CS

    500 23.50Earth work

    completed1 4%

    27

    Y2-147

    Road from R&B Road

    to S.J. Puram265 19.13

    Earth work and GSB

    completed2 10%

    28

    Y2-148

    Road from Kothapeta

    Road to Sainooru CS785 30.10

    Earth work

    completed1 3%

    5 4%

    Working estimate is

    prepared for

    changing the WBM

    layer to WMM layer,

    approval is awaiting.

    13

    NCRMP/B-W/

    AP/RCS/

    PRED/01/

    V.Kottoru/001

    RCS 136.07

    15.03.1314.03.14

    14.08.13Earth

    work,

    Pipe

    culverts,G

    SB and

    CC

    Pavement

    s of all

    works

    (44.97%)

    14.12.14WBM Gr-

    II, Gr-III,

    CD works

    and

    shoulders

    of all

    works

    (70.33%

    Value)

    14.03.14

    BT and

    Road

    furniture

    of all

    works

    (100%

    Value)

    15.03.13

    11

    NCRMP/B-W/AP/MPCS/

    PRED/01/

    Ranastalam

    /016

    MPCS 178.26

    15.03.1314.06.14

    Progress of work isbehind the mile

    stones. Contractor

    has to speed up the

    work to achive the

    progress.

    12

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/

    Etcherla/017AMPCS 176.94

    03.04.1302.07.14

    02.10.13

    Ground

    Floor

    Plinth

    Level of

    all works

    (29.19%)

    02.03.14

    Casting of

    all slabs

    of all

    works

    (63.11%

    Value)

    02.07.14

    Completet

    ion of all

    works

    (100%

    Value)

    03.04.13

    14.09.13

    GroundFloor

    Plinth

    Level of

    all works

    (26.01%)

    14.2.14

    Casting ofall slabs

    of all

    works

    (58.56%

    Value)

    14.06.14Completet

    ion of all

    works

    (100%

    Value)

    33.00 19%

    Site is handed

    over to thecontractor. But

    the contractor

    started the earth

    work excavation

    in the month of

    June

    21 12%

    Progress of work is

    behind the mile

    stones. Contractor

    has to speed up the

    work to achive the

    progress.

    9

    NCRMP/B-W/

    AP/MPCS/

    PRED/01/Gara/015

    M

    PCS 251.57

    15.03.13

    14.06.14

    14.09.13

    Ground

    Floor

    Plinth

    Level of

    all works

    (28.43%)

    14.2.14

    Casting of

    all slabs

    of all

    works

    (59.88%

    Value)

    14.06.14

    Completet

    ion of all

    works(100%

    Value)

    68.5 27%

    Progress of work

    behind the mile

    stones. Contractor

    has to speed up thework to achive the

    progress.

    Page 37 of 159

    e Milestone/ Financial Targets e Total

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    39/160

    First Second Third

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Length

    (Mts)

    AGG

    Value

    of work

    (Lakhs)

    Date of

    commen

    cement

    of work

    Sl.

    No.

    of

    Pkg

    Package Nos.

    catagory

    Agreement

    Amount

    (Lakhs)/Date

    DFC

    Milestone/ Financial Targets

    (%)Sl.No

    of

    work

    Projectcode

    Name of the Work

    Total

    Value of

    Work

    done for

    package

    (Lakhs)

    % of

    work

    done for

    the

    Package

    Reasons for

    non-started

    works

    TPQA observationStage of work

    Value of

    work

    done in

    % of

    work

    done for

    the work

    14

    NCRMP/B-W/

    AP/RCS/

    PRED/01/

    Santhabommali

    /008

    RCS 93.09

    15.03.1314.12.13

    14.07.13

    Earth

    work, GSB

    (18.18%)

    14.10.13

    WBM GR-

    II &III,

    CD works

    and CC

    pavement

    (81.46%

    Value)

    14.12.13

    BT and

    road

    furnishes

    all works

    (100%

    Value)

    29

    Y2-150 Borubhadra -

    Meghavaram Road to

    M. Maruvada

    2000 93.09 15.03.13

    Earth work and

    Culverts completd,

    GSB 400 MTS

    Laying is in

    progress.

    16 17% 16 17%

    Progress of work is

    behind the mile

    stones. Contractor

    has to speed up the

    work to achive the

    progress.

    30

    Y2-154 Yeeramukkam Rati

    R&B road to

    Dunnavooru

    350 18.79 3 3%

    31

    Y2-155 Road from

    Yeeramukkam Rati

    R&B road Geddavooru

    600 34.96 7 20%

    32

    Y2-156 Road from R&B road

    Ganguwada to road to

    Sigalaputtuga

    875 39.19 4 10%

    33

    Y2-157

    Road from R&B road

    to Akkuvaram585 30.41

    CC road completed,

    Graverl shoulder

    laying is in progress

    29.5 97%

    34

    Y2-158 Road from R&B road

    to Pathadibbalapalem3500 121.67

    Culverts,GSB

    completed, Road

    widening is in

    progress

    32 26%

    35Y2-159

    Road from R & B road

    to Pothayyapeta CS1300 40.87

    Road widening is in

    progress, culverts

    and GSB completed

    6 15%

    36

    Y2-265

    Road from B.M R&B

    Road to Simmayyapeta1350 33.52

    Road widening is in

    progress1.5 4%

    37Y2-266

    Road from R&B road

    to Marripadu400 13.77 GSB completed 3.5 25%

    38

    Y2-267

    Road from R&B Road

    to Kakarapalli1200 34.98

    Road widening is in

    progress9 26%

    39

    Y2-268

    Road from R&B road

    to Marripadu700 22.29 GSB completed 6 27%

    40

    Y2-269

    Road from R&B road

    to Pethalingapuram500 13.89

    Road widening is in

    progress0.5 4%

    38 23%

    Progress is with in

    approved mile

    stones.

    17

    NCRMP/B-W/

    AP/RHB/

    PRED/01/

    Santhabommali

    /001A

    R

    HB 118.46

    25.03.1324.06.14

    24.09.13

    Earth

    work &

    GSB of allworks

    (

    24.02.14

    WBM Gr-

    II, Gr-III

    and CDworks for

    all works

    24.06.14

    BT raod

    furnishes

    all works(100%

    Value)

    25.03.13 20.5 17%

    Progress of work is

    behind the mile

    stones. Contractor

    has to speed up thework to achive the

    progress.

    16

    NCRMP/B-W/

    AP/RCS/

    PRED/01/

    Etcherla &

    Ranasathalam

    /012

    RCS 162.54

    15.03.1314.03.14

    14.08.13Earth

    work &

    GSB of all

    works

    (23.26%)

    or 3%

    14.12.14

    WMM, CCPavement

    & CD

    works, for

    all works

    (71.70%

    Value) or

    24.60%

    14.03.14

    BT raod

    furnishes

    all works

    (100%

    Value)

    15.03.13

    15

    NCRMP/B-W/

    AP/RCS/

    PRED/01/

    Mandasa/010

    RCS 123.36

    15.03.1314.03.14

    Progress is with in

    approved mile

    stones.

    14.08.13

    Earth

    work, GSB

    of all

    works

    (20.72%)

    or

    12.15%

    14.12.14

    WMM, CC

    Pavement

    & CD

    works,

    shoulders

    for all

    works

    (88.36%

    Value) or

    38.09%

    14.03.14

    BT and

    road

    furnishes

    all works

    (100%

    Value)

    15.03.13 43.5 35%

    Road widening is in

    progress, earth

    work, culverts is in

    progress.

    Page 38 of 159

    e Milestone/ Financial Targets e Total % f

  • 8/13/2019 October 2013 Monthly Progress Report of NCRMP-TPQA

    40/160