Attached is an updated briefing for today's conference call
Thanks
From:Sent: Tuesday, September 30, 2008 2:57 PMRequired:
FLOSSMAN, LOREN W;
Optional:
Subject: Updated: Weekly meeting with IBWCWhen: Thursday, October 02, 2008 1:00 PM-2:00 PM.Where: 1 (800) 238-0210, Passcode #342193
Access number: 1 (800) 238-0210
Passcode #342193
(b) (6)
(b) (6)
(b) (6)
(b) (6)
(b) (6)
(b) (6)
(b) (6)
(b) (6)
(b) (6)
7/31/2019 Oct 2 2008 Mtg CBP IBWC -Likely to Drop O-1 O-2 0-3 -
2/8
F r Of cia e On yFor Official Use Only
SBI Tactical Infrastructure ProgramIBWC Issues
October 2nd, 2008
009226
7/31/2019 Oct 2 2008 Mtg CBP IBWC -Likely to Drop O-1 O-2 0-3 -
3/8
2
Major Issues
Fence in Floodplain
Fence on Levees
Hidalgo County
Miscellaneous Items
009227
7/31/2019 Oct 2 2008 Mtg CBP IBWC -Likely to Drop O-1 O-2 0-3 -
4/8
3
Fence in Floodplain
Segments O-1 (3.8 miles), O-2 (8.8 miles) & O-3 (1.9 miles)
DHS likely to drop fence segments from PF225
Segment M-2A (0.75 miles)
Baker modeled the retaining wall proposed for M-2A (in the flood plain) andconcluded it will not impact the floodplain
IBWC approved the construction of M-2A in the floodplain on 22 Aug
No Issues letter drafted and forwarded to Commissioner for signature.
Segment L-1 (0.20 miles)
009228
(b) (7)(E)
7/31/2019 Oct 2 2008 Mtg CBP IBWC -Likely to Drop O-1 O-2 0-3 -
5/8
4
Fence in Floodplain
Segment O-21 (0.53 miles)
CBP would now like IBWC to design and construct levee wall similar to Hidalgo
using CBP funds
Segment CV-1A CBP to install permanent fencing along canal, outside of the spillway and weir
footprints for the dam. CBP still desires to locate temporary barriers across the
weir until such time de-silting has been accomplished. USIBWC requires letter from
CBP Commissioner prior to placement of temporary barriers.
Draft letter forwarded to DHS??
009229
7/31/2019 Oct 2 2008 Mtg CBP IBWC -Likely to Drop O-1 O-2 0-3 -
6/8
5
Fence on/near Levee
Segments L-1A and L-1B (6 miles)
Projects have been removed from PF225
CBP would now like IBWC to design and construct a levee wall within these segments
CBP preparing written request
Segment K-1B (0.7 miles) Project has been canceled
Segment K-2C
Current alignment has been determined to not be constructible; now looking at installing at the north toe of thelevee (i.e. our original proposed location)
Segment O-21
Segment O-21 currently the only segment in which CBP believes sections of fence may need to encroach on
the 15 ft desired buffer north of the levee The contract documents for all RGV segments in which fence is proposed north of the levee:
The minimum 15 ft buffer
Contractor to stake out fence alignment prior to construction
IBWC review/approval of staked-out alignment prior to construction
Station 35+00 to Station 40+00 USIBWC concurs with location closer than 15 ft from toe. Contractor must stake out area priorto construction and obtain USIBWC review/no issues.
Station 220+00 to Station 224+00 USIBWC will coordinate with owner of unauthorized structures to have them removed. DHSto maintain 15 ft offset.
Station 236+00 to Station 259+00 USIBWC concurs with less than 15 ft offset at station 236, if required to avoid tower.USIBWC currently surveying our right-of-way between stations 236 & 259 to determine if existing fencing is within right-of-wayand 15 ft offset could be obtained within our right-of-way (OPEN ITEM).
Station 369+37.50 to Station 397+77.50 Nye Plantation segment; CBP terminated this work for FY 2008. No further actionrequired.
USIBWC understands that all other fence segments will provide a 15 ft offset from toe of levee. USIBWC will provide CBP withletter regarding our decision on abovementioned segments.
009230
7/31/2019 Oct 2 2008 Mtg CBP IBWC -Likely to Drop O-1 O-2 0-3 -
7/8
6
Hidalgo County
SBI has decided to provide Hidalgo County additional funding to complete
segments O-4A, O-4C, O-6A, O-6B/C, O-8 and O-9 Phase II
SBI evaluating the feasibility of constructing pedestrian fence on either side
of the HCWD#1 pump station (O-4B)SBI owes IBWC:
Draft letter from CBP on coordination efforts with property owners potentially
directly impacted by the levee wall project is being routed for Mr. Giddens
signature
009231
7/31/2019 Oct 2 2008 Mtg CBP IBWC -Likely to Drop O-1 O-2 0-3 -
8/8
7
Miscellaneous Items
Tracking of IBWC Design Approvals
On-going; both CBP/Corps & IBWC tracking status
Segment K-1A (1.1 mile)
CBP moving forward with design assuming floating fence (PV-3) in TXDOT
right of way
Proposed alignment/draft RFP submitted to IBWC
Need to discuss IBWC requested gate
Laredo Cane Control Project CBP submitted letter to IBWC on June 22nd describing the proposed project
US IBWC has informed MX IBWC of proposed pilot project (1.7 miles)
Cane removal activities scheduled to begin on October 1st
009232