Observation Report 2500 NE 65th Avenue * Vancouver WA 98661-6812 P 360.750.7500 - F 360.750.9706 Project: Davenport Elementary-Middle School
Date: August 16, 2018
Weather conditions: Warm and smokey
Discussions: The following pages show the progress made this week (August 13, 2018 through August 16, 2018). All of the trusses have been placed. Roofing is complete at the old covered play area and the upper roof of the new Middle School wing. The sheathing at the 2 locations (kitchen and music room) has dried some in the past week and a half but it still continues to hold moisture. It was decided that this sheathing will be removed and allow the underneath to dry. Interior work to finish up next week. Dolly Ramminger, CCM Project Manager
CSG is a program of Educational Service District 112
Dolly Ramminger, Project Manager ESD 101 4202 S Regal St. Spokane, WA 99223 P: 509.789.3784 - F: 509.323.2758