Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Oakwood CSO Control Facility and Pump Station (PC-755)
June 24, 2013
Mirza Rabbaig, DWSD
Mark TenBroek, CDM Smith
Project Purpose
• Address capacity issues in original sewer system: – Oakwood District sewers built by Oakwood Village
– DWSD inherited these sewers
– Sewers undersized for combined sewer flows
• Install relief sewers in Oakwood Sewer District: – Mitigate chronic basement and street flooding issue
– Address 140 flooding complaints from 1994-1996
• DWSD design process: – Began to evaluate district in 2000
– Determined street flooding caused drainage system
– DWSD has designed new relief sewer system
Project Purpose
• Provide Combined Sewage Overflow (CSO) control:
– Treat water before discharge to Rouge River
– Improve Rouge River water quality
– Facility required by MDEQ
• Provide increased pumping capacity:
– Additional relief sewers under design for district (PCS-79)
– Current pump station - 650 cfs
– New pump station - 1,660 cfs
Benefits from Project
• Improve Rouge River water quality
• Remain compliant with MDEQ permit
• Reduce street flooding in district
• Reduce basement flooding in district
• Convey sanitary wastewater to wastewater treatment plant
• Remove older obsolete pump station
Ple
as
an
t Stre
et
Liddesdale
Liebold
Deacon Site Plan
Project Work Area
Perspective view looking Northwest Perspective view looking Northeast
Perspective view looking North Perspective view looking Southeast
Design Rendering
CSO Basin Pump Station
Facilities
Scre
ens
Early Foundation Construction (2008)
Unique Features
• Slurry Wall – Deep facility construction
• Pump Hydraulics – Physical model study
• Chemical Mixing – Reduced maintenance compared to mixers
typically used
• Ground Level Basin – Improved dewatering control
• Perforated Plate Screens – Six perforated plate screens
Slurry Wall Construction
• Pump station proposed rectangular trench style wet well
• Wet well base slab slightly above underlying rock
• Artesian aquifer in rock, causing concerns with uplift forces
• Circular caisson construction not deemed feasible
• Slurry wall construction selected, while not commonly used in
Southeast Michigan
Slurry Wall Excavator
Slurry Supporting the Slot Excavation
Reinforcement Dropped into Excavation
Concrete is Tremie Placed and Slurry is Displaced
Pump Station Work Area
Wet Well Support During Construction
Pump Station Hydraulics Required Physical Model
• Wet well relatively small compared to peak pumping capacity
– 1,660 cfs
– 8 vertical turbine pumps
• Concerned with swirl that could cause pump problems
• Commissioned physical model
– Initial during design
– Updated during construction when inlet conditions changed
• Resulted in small modifications to protect pumps
Model Included Both Pump Station Wet Wells and Inlets from the Upstream Junction Chamber
The Model Incorporates All Important Physical Features
Dye Used to Identify Problem Swirl and Determine Corrective Actions
Pump Arrival
Pumps Placed in Wet Well
Pump Station Motor Floor
Completed Motor Floor
Disinfection Solution Added at Pump Discharge
• Most CSO basins add chemical using mixers to properly distribute
disinfectant
• Oakwood places disinfectant in the pump discharge lines
• Simplified chemical application control since each storm pump is
matched with a chemical pump
Pump Station Intermediate Level
Ground Level CSO Basin
• Most DWSD CSO basins are gravity flow through style
• Hydraulics in the Oakwood District required pumping
• Decided to construct basin partially above ground:
– Reduced excavation costs
– Fewer dewatering issues
– Allows mostly gravity dewatering
Basin Pile Foundation Construction
CSO Screening and Basin Area
CSO Basin Effluent Weirs
Basin Flushing Lanes
Influent Screening using Perforated Plate Screens
• Provides removal of small material
• Includes bypass channels should screens become blinded with
excessive material
• Screen discharge includes screening washer and discharge to a
dumpster
Perforated Plate Screen Installation
Project Summary
• Slurry wall construction installed quickly
• Pumping systems have worked well, in spite of small wet well
• Chemical application has worked effectively
• Flushing system has removed solids with single flush
• No problems have been encountered with screen blinding
• Project PPC 1-year sampling period has been completed
• Final PPC report to be submitted this fall
Completed Facility
Acknowledgements
Detroit Water & Sewerage Department (DWSD)
• Sue McCormick DWSD Director
• Mirza Rabbaig CSO Program Manager
CDM Michigan Inc. (CDM Smith) Engineering Partners
Applied Science, Inc. Hamilton Anderson Associates
JE Associates PMA Consultants, LLC
SOMAT Inc. Spalding DeDecker Associates
Sigma Associates Superior Engineering, Inc.
Tucker Young Jackson Tull, Inc.
L D’Agostini & Sons (LDS) Construction Contractor
• Gino L. D’Agostini, Jr. Project Manager