Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
West York Area School District Wallace Elementary
June 5, 2015
Construction Manager: Quandel Construction Group, Inc. 3003 North Front Street, Suite 201 Harrisburg, PA 17110 717.657.0909
Architect: Gilbert Architects 626 North Charlotte Street Lancaster, PA 717.291.1077
EX
ECU
TIV
E SU
MM
AR
Y R
EPO
RT
NO
. 11
EXEC
UTI
VE
SUM
MA
RY
REP
OR
T N
O.
11
WEST YORK AREA SCHOOL DISTRICT
Wallace Elementary June 5, 2015
1 | Executive Summary Report No. 11
2 | Progress Photos
3 | Proposed Change Order Log
4 | Prime Contractor Invoice Log
5 | Wallace Phasing Key
TABLE OF CONTENTS
EXECUTIVE SUMMARY REPORT NO. 11
WEST YORK AREA SCHOOL DISTRICT WALLACE ELEMENTARY
June 5, 2015
SCHEDULE STATUS
Construction start date (NTP): July 1, 2014 Project completion date: August 16, 2015 Original Substantial Completion date: August 16, 2015 Contract duration: 411 days Extension of time requested: 0 days Number of days expended: 339 days Extension of time approved: 0 days Percent complete by time: 82.5% Current Substantial Completion date: August 16, 2015 Lost weather days: 23 days
STATUS: West Wing Renovations Overhead rough-ins are completed along with roof replacement. Gypsum wall board installation is almost completed
and painting has started. Casework installation is scheduled to begin installation the week of June 15, 2015. Classrooms are scheduled to be completed for the District to begin move-in on June 29, 2015.
Kitchen Area Demolition of the Kitchen Area started on June 5, 2015. Sitework Binder paving on the new parking lot is completed. Sidewalk installation is ongoing. BUDGET STATUS
Contract amount: $ 10,280,706.00 Total billed to date (thru May) $ 8,246,096.94 Approved change orders: $ 49,322.00 Paid to date: $ 7,875,308.07 Revised contract amount: $ 10,330,028.00 Percent complete by cost: 79.8 % Pending changes: $ 6,641.00 Remaining Contingency: $ 257,555.00 PENDING ISSUES
There are no pending issues at this time.
PROGRESS PHOTOS | Wallace Elementary
New Classroom Addition New Classroom Addition
New Entrance New Parking Lot
PROGRESS PHOTOS | Wallace Elementary
New Sidewalk Installation CMU Wall Installation
Corridor Rough-ins West Wing Rough-ins
AMOUNTS
PC NO DESCRIPTION
CONTRACTORS
IMPACTED
ESTIMATED
and / or
SUBMITTED
PENDING
and/or
IN REVIEW
Recommend
Approval APPROVED CO NO STATUS
1 Relocate Electric Line Lobar 2,217.00 2,076.00 01-001 Approved
2 Revise Door B146 Frame Lobar 2,426.00 0.00 NA Void
3 Replace Sanitary Sewer Line Lobar 19,807.00 14,741.00 01-002 Approved
4 Infill Existing Coal Chutes Lobar 2,400.00 2,400.00 Release T&M
5 Revise Waterline Service Lobar (4,276.00) (7,721.00) 01-006 Approved
6 Reroute Existing Electrical Conduits Lobar Electric 22,000.00 16,121.00 04-001 Approved
7 Revisions to Door B159 Lobar 1,031.00 1,031.00 01-004 Approved
8
Provide Power and FA to Coiling Door per
ASI No. 5 Lobar Electric 1,120.00 0.00 NA Utilized Electrical Alllowances
9 Provide Power to Unit Heater in B107 Lobar Electric 380.00 0.00 NA Utilized Electrical Alllowances
10 Markerboard Revisions Lobar 10,776.00 10,776.00 01-003 Approved
11 Add Light Fixture in B160 Lobar Electric 948.00 0.00 NA Utilized Electrical Alllowances
12
Provide Additional Electrical Devices per
ASI No. 007 Lobar Electric 6,885.00 0.00 NA Utilized Electrical Alllowances
13 Kitchen Equipment Revisions Lobar (6,500.00) (6,500.00) 01-005 Approved
14 Add Ceiling at Heat Pump Rooms Lobar 1,157.00 1,157.00 01-007 Approved
15 Provide Additional Valves Carl Frantz 550.00 0.00 NA Utilized Plumbing Allowances
16 Panel BA Relocation Lobar Electric 8,974.00 8,974.00 Approved T&M
17 Paint Room Lobar 2,907.00 0.00 NA Utilized Plumbing Allowances
18 Provide Additional Water Line Tie-Ins Carl Frantz 2,907.00 0.00 NA Utilized Plumbing Allowances
19
Provide Additional Feed for Circulator
Pump Lobar Electric 1,240.00 1,240.00 Approved. Co to be issued.
20 Add Switches in Stairwells Lobar Electric 1,673.00 1,673.00 Approved. Co to be issued.
21 Relocate Additional Electrical Conduits Lobar Electric 1,438.00 0.00 NA Allowance Item
22
Add Sprinkler Heads at Heat Pump
Closets Triangle 4,241.00 4,241.00 In review
23
Add Ceilings at Heat Pump Closets in the
Existing Building per RFI No. 63 Lobar 5,754.00 5,754.00 01-008 Approved
24 Add Receptacles for Condensate Pumps Lobar Electric 2,090.00 0.00 NA Allowance Item
25 Add Light Fixture in A104 Lobar Electric Need Pricing
26 Add Fiber between MDF and IDF Lobar Electric Need Pricing
27 Add Elevator Indicator Light Power Lobar Electric Need Pricing
28 Add Gypsum Bulkheads Lobar Need Pricing
29 Add Ventilation to IDF Room Matchline Need Pricing
30 Provide Additional Tampers per RFI No. 64 Lobar Electric Need Pricing
Totals 92,145.00 6,641.00 0.00 49,322.00
Original Contract 10,280,706$
Approved Change Orders 49,322$
Revised Contract Value 10,330,028$
Original Contingency 306,877$ 2.98%
Approved Change Orders 49,322$ 0.48%
Remaining Project Contingency 257,555$
West York Area School DistrictWallace Elementary
CHANGE ORDER LOG
6/4/2015 Page 1 of 1
WALLACE ELEMENTARY SCHOOL
PRIME CONTRACTOR INVOICE LOG
INVOICES THROUGH THE END OF 5/31/2015
Contractor Invo
ice
No
.
Original
Contract
Approved
Changes
Contract Sum to
Date
Total Complete &
Stored to Date Retainage
Total Earned less
Retainage
Previous
Certificate for
Payment
Current Payment
Due Balance To Finish
Lobar, Inc. 11 5,637,700.00$ 21,314.00$ 5,659,014.00$ 4,686,791.05$ 234,339.55$ 4,452,451.50$ 4,212,101.12$ 240,350.38$ 1,206,562.50$
Carl E. Frantz, Inc. 11 713,646.00$ -$ 713,646.00$ 541,075.00$ 27,053.75$ 514,021.25$ 493,814.75$ 20,206.50$ 199,624.75$
Matchline Mechanical 11 2,018,000.00$ -$ 2,018,000.00$ 1,867,485.00$ 93,374.25$ 1,774,110.75$ 1,749,581.75$ 24,529.00$ 243,889.25$
Lobar Electrical, Inc. 11 1,595,000.00$ 28,008.00$ 1,623,008.00$ 1,346,866.78$ 67,343.34$ 1,279,523.44$ 1,208,220.45$ 71,302.99$ 343,484.56$
Triangle Fire Protection 10 316,360.00$ -$ 316,360.00$ 251,100.00$ 25,110.00$ 225,990.00$ 211,590.00$ 14,400.00$ 90,370.00$
Totals 10,280,706.00$ 49,322.00$ 10,330,028.00$ 8,693,317.83$ 447,220.89$ 8,246,096.94$ 7,875,308.07$ 370,788.87$ 2,083,931.06$
84.2% 79.8%
Bid & Plan Con D Adjustments +/- Total after Adjustment Payments Balance
Structure $10,280,706.00 $49,322.00 $10,330,028.00 ($7,875,308.07) $2,454,719.93
Architect's Fee $511,461.00 $2,574.30 $514,035.30 ($425,367.92) $88,667.38
Moveable Furniture & Euqipment $204,584.00 $0.00 $204,584.00 ($23,436.00) $181,148.00
Additional Construction Related Cost** $884,477.00 $0.00 $884,477.00 ($971,253.27) ($86,776.27)
** Has OCIP Insurance Included
Finance Cost $108,092.00 $0.00 $108,092.00 $0.00 $108,092.00
Balance Remaining $2,745,851.04
Wallace Elementary Cost to Date
Project Recap - June 2015
Removed for student safety. Contact the board secretary for a copy of this page.
West York Area School District High School
June 5, 2015
Construction Manager: Quandel Construction Group, Inc. 3003 North Front Street, Suite 201 Harrisburg, PA 17110 717.657.0909
Architect: Gilbert Architects 626 North Charlotte Street Lancaster, PA 717.291.1077
EX
ECU
TIV
E SU
MM
AR
Y R
EPO
RT
NO
. 8
EXEC
UTI
VE
SUM
MA
RY
REP
OR
T N
O.
8
WEST YORK AREA SCHOOL DISTRICT
High School June 5 2015
1 | Executive Summary Report No. 8
2 | Progress Photos
3 | Proposed Change Order Log
4 | Prime Contractor Invoice Log
TABLE OF CONTENTS
7
EXECUTIVE SUMMARY REPORT NO. 8
WEST YORK AREA SCHOOL DISTRICT HIGH SCHOOL
June 5, 2015
SCHEDULE STATUS
Construction start date (NTP): October 3, 2014 Project completion date: August 19, 2016 Original Substantial Completion date: August 19, 2016 Contract duration: 686 days Extension of time requested: 0 days Number of days expended: 245 days Extension of time approved: 0 days Percent complete by time: 35.7% Current Substantial Completion date: August 19, 2016 Lost weather days: 43 days
STATUS: Sitework
Infiltration Basin No. 1 is scheduled to begin in June following the last day of school. Courtyard Addition
Gypsum wall board installation is completed. EIFS and window installation is completed. Painting has started. Ceiling grid is scheduled to begin on June 23, 2015.
Classroom Addition
Stair Tower demolition is scheduled to begin on June 9, 2015. Once stair towers are demolished, remaining foundations and steel framing may be completed.
Gymnasium Addition
Foundations are completed. Structural steel installation has started. Steel installation is scheduled to be completed the end of June. Masonry installation has started and will continue through early August. Roof installation is scheduled to start on August 19, 2015.
BUDGET STATUS
Contract amount: $ 27,427,900.00 Total billed to date (thru May) $ 6,835,613.38 Approved change orders: $ 383,451.00 Paid to date: $ 5,732,987.10 Revised contract amount: $ 27,811,351.00 Percent complete by cost: 24.6% Pending changes: $ 14,709.00 Remaining Contingency: $ 458,391.00
PENDING ISSUES
There are no pending issues at this time.
PROGRESS PHOTOS | High School
Gymnasium Lower Level Steel Gymnasium Lower Level Steel
Gymnasium Lower Level Steel Gymnasium Mezzanine Steel
PROGRESS PHOTOS | High School
Gymnasium Lower Level Foundations Gymnasium Lower Level Foundations
Gymnasium Lower Level Plumbing Rough-Ins Gymnasium Retaining Wall Waterproofing
PROGRESS PHOTOS | High School
Gymnasium Retaining Wall Backfill Cardio Addition
Courtyard Addition Elevation Courtyard Addition Classroom
AMOUNTS
PC NO DESCRIPTION
CONTRACTORS
IMPACTED
ESTIMATED
and / or
SUBMITTED
PENDING
and/or
IN REVIEW
Recommend
Approval APPROVED CO NO STATUS
1 Install Temporary Storm Line eciConstruction 42,324.00 16,803.00 01-001 Approved
2 Revise Library Lighting Per RFI No. 20 Pagoda 11,847.00 2,639.00 04-004 Approved
3
Add Circuits for Gas Solenoid Valves per
RFI No. 21 Pagoda 2,127.00 2,127.00 04-001 Approved
4 Lighting Revisions per RFI No. 18 Pagoda 5,872.00 0.00 NA Utilized Contract Allowances
5 Relocate MH-2 Due to Fiber Ductbank eciConstruction 6,612.00 0.00 NA Utilized Contract Allowances
6 Demo Lights in Corridor E108 and E121 Pagoda 1,570.00 1,570.00 In review
7 Relocate 1600 Amp Main Switch Pagoda 28,199.00 28,199.00
Approved completion on a
T&M Basis
8 Add Softball Dugouts eciConstruction 91,804.00 0.00 NA Void
9 Lower Footing at 16" Stormline eciConstruction 1,533.00 0.00 NA Utilized Contract Allowances
10 Footing Revisions per RFI No. 31 eciConstruction 9,329.00 9,329.00 01-02 Approved
11 Additional Fiber Optic Line Pagoda 6,070.00 5,878.00 04-002 Approved
12 Fiber Ductbank Relocation Pagoda 6,649.00 6,360.00 04-003 Approved
13 Infiltration Test Pit Excavation eciConstruction 7,818.00 0.00 NA Utilized Contract Allowances
14 Extend Concession Stand Force Main eciConstruction 5,292.00 5,292.00 01-003 Approved
15 Revisions to Panel NEL per RFI 84 Pagoda 4,295.00 3,709.00 04-005 Approved
16 Heat Exchanger Credit per RFI No. 86 Matchline (23,671.00) (23,671.00) 02-001 Approved
17 Door Hardware Revisions eciConstruction 3,893.00 3,893.00 01-004 Approved
18
Increase Elevator Breaker Size per RFI
No. 83 Pagoda 341.00 0.00 NA Utilized Contract Allowances
19 Add Electric Door Hardware per ASI No 8 eciConstruction 2,591.00 2,591.00 01-005 Approved
20
Install Waterline to Concession Stand per
ASI No. 9 Vision 18,828.00 18,828.00
Approved completion on a
T&M Basis
21 Pipe Relocation Vision 2,000.00 2,000.00 Released T&M
22A
Infiltration Basin No. 1 and No. 2 Revisions
and Rock Claim eciConstruction 201,978.00 39,177.00 01-007 Approved
22B Additional Basin Rock Excavation eciConstruction 45,000.00 45,000.00 Approved T&M per settlement
23 Bannister Street Parking Expansion eciConstruction 140,926.00 140,926.00 01-006 Approved
24
Provide Site Lighting for Bannister Parking
Lot Expansion Pagoda 73,158.00 73,158.00
Approved completion on a
T&M Basis
25 Provide Site Lighting for Tennis Courts Pagoda Need Pricing
26 Insulate Existing Roof Drains Vision 3,213.00 3,213.00
Approved completion on a
T&M Basis
27 Add Concrete Wall at West Gym Ramp eciConstruction Need Pricing
28
Revise Sprinkler heads to Concealed in
C115 Vision Need Pricing
29A Door Hardware Revisions per ASI No. 17 eciConstruction Need Pricing
29B Door Hardware Revisions per ASI No. 17 Pagoda Need Pricing
30 Add Gas Shut-off Valve in C209 Pagoda Need Pricing
31 Add Light Fixture at Courtyard Entry Pagoda Use Allowance
32 Add Electrical Rough-in for Site Sign Pagoda Need Pricing
33
Add Circuits for Plumbing Equipment per
RFI 95 Pagoda 6,263.00 6,263.00 In review
34 Revise Circuit Breaker for Elevator Pagoda 2,872.00 2,872.00 In review
35 Add GWB Bulkheads 2,004.00 2,004.00 In review
Totals 710,737.00 14,709.00 0.00 383,451.00
Original Contract 27,427,900$
Approved Change Orders 383,451$
Revised Contract Value 27,811,351$
Original Contingency 841,842$ 3.07%
Approved Change Orders 383,451$ 1.40%
Remaining Project Contingency 458,391$
West York Area School DistrictWest York High School Additions and Renovations
CHANGE ORDER LOG
6/4/2015 Page 1 of 1
WEST YORK AREA HIGH SCHOOL ADDITIONS AND RENOVATIONS
PRIME CONTRACTOR INVOICE LOG
INVOICES THROUGH THE END OF 5/31/2015
Contractor Invo
ice
No
.
Original
Contract
Approved
Changes
Contract Sum to
Date
Total Complete &
Stored to Date Retainage
Total Earned less
Retainage
Previous
Certificate for
Payment
Current Payment
Due Balance To Finish
eciConstruction 6 16,891,400.00$ 263,011.00$ 17,154,411.00$ 3,940,881.60$ 394,088.26$ 3,546,793.34$ 3,045,824.70$ 500,968.64$ 13,607,617.66$
Vision Mechanical 7 2,352,500.00$ 22,041.00$ 2,374,541.00$ 482,729.50$ 48,272.96$ 434,456.54$ 209,293.20$ 225,163.34$ 1,940,084.46$
Matchline Mechanical 6 4,568,000.00$ (23,671.00)$ 4,544,329.00$ 2,553,800.00$ 255,380.00$ 2,298,420.00$ 2,040,615.00$ 257,805.00$ 2,245,909.00$
Pagoda Electric 7 3,616,000.00$ 122,070.00$ 3,738,070.00$ 617,715.00$ 61,771.50$ 555,943.50$ 437,254.20$ 118,689.30$ 3,182,126.50$
Totals 27,427,900.00$ 383,451.00$ 27,811,351.00$ 7,595,126.10$ 759,512.72$ 6,835,613.38$ 5,732,987.10$ 1,102,626.28$ 20,975,737.62$
27.3% 24.6%
Bid & Plan Con D Adjustments +/- Total after Adjustment Payments Balance
Structure $27,427,900.00 $383,451.00 $27,811,351.00 ($5,732,987.10) $22,078,363.90
Architect's Fee $1,457,148.00 ($54,171.50) $1,402,976.50 ($1,204,990.03) $197,986.47
Moveable Furniture & Euqipment $582,985.00 $0.00 $582,985.00 ($38,301.00) $544,684.00
Additional Construction Related Cost $1,793,934.00 $0.00 $1,793,934.00 ($1,292,299.79) $501,634.21
Finance Cost $305,594.00 $0.00 $305,594.00 $0.00 $305,594.00
Balance Remaining $23,628,262.58
West York Area High School Cost to Date
Project Recap - June 2015