Nyota Minerals Limited (‘Nyota’ or the ‘Company’) Quarterly Report to 31 March 2012 Nyota Minerals Limited (ASX/AIM: NYO), the gold exploration and development company in East Africa, is pleased to announce its Quarterly Report for the period ended 31 March 2012. HIGHLIGHTS Tulu Kapi Project, Ethiopia A new Mineral Resource estimate was announced for Tulu Kapi of 17.97 million tonnes @ 2.90g/t gold containing 1,672,000 ounces of gold; o Comprises an upgrade and increase in the Indicated category of 82 per cent to 831,000 ounces of gold @ 3.01g/t gold; and o An Inferred Resource of 841,000 ounces of gold @ 2.79g/t gold; A detailed drill programme at Tulu Kapi aimed at converting additional Inferred Resources to Indicated Resources will commence during Q2, 2012. The impact of this work to further increase resources will be seen in a resource update during H2 2012; The Company’s operational focus has been to complete the studies required for the Definitive Feasibility Study (“DFS”) including drilling for hydrogeological, geotechnical and metallurgical reasons, metallurgical sampling for variability test work, the evaluation of sources of aggregate and the environmental and social studies; The DFS is progressing well and is on schedule for completion in the second half of 2012; Proximal and Satellite zones Comprehensive gold in soil geochemical coverage has been completed over the most prospective areas within the Proximal and Satellite zones around Tulu Kapi. The major discovery is the Komto – Guji trend, a gossanous body extending over a strike length of approximately 2.8km to the west of the Tulu Kapi deposit; Due to the requirement for drilling to focus on DFS related work, focus has been on analysis and evaluation work on the Proximal and Satellite zones, although within the capacity restraints Nyota has still been able to undertake a level of drilling on the Guji Prospect; Regional exploration Drilling commenced on the Bendokoro Prospect; the initial programme was completed after the period end and all assay results are pending; o Visible gold identified in drill core consistent with surface rock samples of up to 8.81g/t;

Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

  • Upload
    ledat

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

 

Nyota Minerals Limited (‘Nyota’ or the ‘Company’) 

Quarterly Report to 31 March 2012 

Nyota Minerals  Limited  (ASX/AIM: NYO),  the  gold  exploration  and development  company  in  East Africa, is pleased to announce its Quarterly Report for the period ended 31 March 2012. 

HIGHLIGHTS 

Tulu Kapi Project, Ethiopia 

• A  new Mineral  Resource  estimate  was  announced  for  Tulu  Kapi  of  17.97 million  tonnes @ 2.90g/t gold containing 1,672,000 ounces of gold; 

o Comprises  an  upgrade  and  increase  in  the  Indicated  category  of  82  per  cent  to 831,000 ounces of gold @ 3.01g/t gold; and 

o An Inferred Resource of 841,000 ounces of gold @ 2.79g/t gold; 

• A detailed drill programme at Tulu Kapi  aimed at  converting additional  Inferred Resources  to Indicated Resources will commence during Q2, 2012. The impact of this work to further increase resources will be seen in a resource update during H2 2012;  

• The Company’s operational  focus has been to complete the studies required  for the Definitive Feasibility  Study  (“DFS”)  including  drilling  for  hydrogeological,  geotechnical  and metallurgical reasons, metallurgical sampling for variability test work, the evaluation of sources of aggregate and the environmental and social studies; 

• The DFS is progressing well and is on schedule for completion in the second half of 2012; 

Proximal and Satellite zones 

• Comprehensive  gold  in  soil  geochemical  coverage  has  been  completed  over  the  most prospective  areas  within  the  Proximal  and  Satellite  zones  around  Tulu  Kapi.  The  major discovery  is  the  Komto  – Guji  trend,  a  gossanous  body  extending  over  a  strike  length  of approximately 2.8km to the west of the Tulu Kapi deposit; 

• Due to the requirement for drilling to focus on DFS related work, focus has been on analysis and  evaluation  work  on  the  Proximal  and  Satellite  zones,  although  within  the  capacity restraints Nyota has still been able to undertake a level of drilling on the Guji Prospect; 

Regional exploration  

• Drilling commenced on the Bendokoro Prospect; the initial programme was completed after the period end and all assay results are pending; 

o Visible  gold  identified  in  drill  core  consistent with  surface  rock  samples  of  up  to 8.81g/t; 

Page 2: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

• Additional  geological  mapping  and  interpretation  at  Boka  Sirba  has  been  completed following  the  identification  of  gold  in  the  quartzite  meta‐sediments.  Drilling  has  been deferred whilst a new geological interpretation is evaluated.  Further sampling and possibly trenching is planned along the strike length of the unit before a drilling campaign is initiated; 

Corporate 

• Cash on Balance Sheet at end of Quarter: A$22.5m;  

• This  represents an  increase of A$8.2m  from  the end of  the prior quarter and  includes  the proceeds of the placing approved at General Meeting on 7 March 2012 of GBP9.66m; and 

• Neil Maclachlan was  appointed  as Non‐executive  Chairman  on  21 March  2012.   Neil  has extensive experience  in both  the City and  the mining  industry and has been appointed  to further  develop  the  Company  as  Nyota moves  from  being  an  exploration  company  to  a development and production company. 

Richard Chase, Chief Executive Officer commented, “The  last quarter has been exceptionally busy for Nyota and my thanks go to all our employees and our consultants who have worked hard to keep both the feasibility study and the exploration on track. Tulu  Kapi  remains  the  greatest  call  on  our  resources  and  our  cash,  but  the  initial  signs  from  the Bendokoro drilling are even more encouraging than I had previously thought and the identification of an additional gold‐bearing  lithology at Boka Sirba  is a significant discovery; even  if  it frustrates our desire to get started with drilling there. The evidence before me leads me to believe that 2012 will be transformational for Nyota.”  

TULU KAPI PROJECT  

Updated Mineral Resource Estimate  

On  9 March  2012,  Nyota  announced  an  updated Mineral  Resource  for  Tulu  Kapi,  prepared  in accordance with  the guidelines of  the  JORC Code  (2004) and estimated  independently by Wardell Armstrong International.   The new Mineral Resource benefits  from  significantly more  geological detail  than  that previously available and  incorporates all  the drill holes  for which gold analyses had been  received up  to and including the beginning of March,  2012 (Figure 1).  This Mineral Resource estimation will be used as the basis of the Ore Reserve estimation, at the end of June, to be included in the Feasibility Study.  The new Mineral Resource estimate was increased to 17.97 million tonnes @ 2.90g/t gold containing 1,672,000  ounces  gold:  comprising  an upgrade  and  increase  in  the  Indicated  category  of  82%  to 831,000  ounces  of  gold @  3.01g/t  gold  and  an  Inferred  Resource  of  841,000  ounces  of  gold @ 2.79g/t gold.   This resource  includes all the drill holes for which assay results had been received by the end of January 2012 and is summarised in the table below. 

Page 3: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

  

Tulu Kapi Resource Estimate ‐ In‐Situ Model (WAI, March 2012 compared with WAI, June 2011) 

(Prepared in accordance with the guidelines of the JORC Code (2004) 

   June 2011  March 2012 

Mineralisation Type  Saprolite  Fresh  Total  Saprolite Fresh  Total 

Cut Off Grade (g/t)  0.4  0.5  0.4 / 0.5 0.4  0.5  0.4 / 0.5 

Difference

Tonnage (kt)  277  4,394  4,671  425  8,157  8,583  +83% 

Au (g/t)  2.42  3.08  3.04  1.87  3.07  3.01  ‐1% 

kg  670  13,531 14,200  796  25,056 25,852  +82% Indicated 

Metal k.oz  22  435  457  26  806  831  +82% 

     

Tonnage (kt)  811  10,481 11,291  395  8,989  9,385  ‐18% 

Au (g/t)  2.02  2.82  2.76  1.57  2.84  2.79  +1% 

kg  1,636  29,548 31,184  622  25,534 26,157  ‐16% Inferred 

Metal k.oz  53  950  1,003  20  821  841  ‐16% 

 Note:  Nyota holds an interest of 100% in the Tulu Kapi asset.  The Ethiopian Government will be entitled to a 

5% interest in the project on grant of a mining licence. 

The March  2012  Resource  Estimate  update  saw  a  significant  increase  in  the  Indicated  Resource resulting from a greater degree of confidence in the continuity of mineralisation.  The balance of the Resource  currently classified as  Inferred has been broadly defined by drilling and  therefore  scope exists  for  the  conversion  of  the  bulk  of  these  ounces  to  an  Indicated  status  over  the  next  few months.    It should be noted  that where  the orebody extends  to  its natural  limits,  it  is not always possible to define the termination of individual mineralised structures and as a result a proportion of the Resource will always remain in the Inferred category. The objective over the next 6 months is to convert sufficient Resources to an Indicated status to be able to commence mine development with an Ore Reserve estimate of >1m oz Au contained.  

Wardell  Armstrong  International  and  the  Nyota  geological  team  are working  on  a  detailed  drill programme  for  further  infill  reverse  circulation  (“RC”)  drilling  designed  to  convert  these  Inferred Resources to an Indicated status in the shortest possible timeframe. This programme is scheduled to commence  in Q2 and due  to  the superior  infrastructure of  the Tulu Kapi project area, drilling will continue throughout the rainy season which spans May to October. 

Page 4: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

Further Exploration 

It  is  important to note that the Tulu Kapi deposit remains open to the north, northeast, southwest and at depth. Consequently, drilling to define the limits of the deposit and add further ounces to the Resource is on‐going.  

The  likely  short‐term  addition  to  the  Resource will  be  from  the  north  and  northeast  extensions, where sufficient drilling has already  taken place  to confidently outline  targets  ready  for  infill. One example  is  the UNDP  target where  an  additional  two  shallow  zones of mineralisation  have been identified and the last of seven drill holes targeting these are being drilled. 

Only once drilling and interpretation is complete will it be possible to state whether these resources will be  incorporated  into  the existing proposed pit outline or whether  they will  form smaller scale satellite pits adjacent to the main Tulu Kapi pit.     

Drilling  to extend  the high‐grade  feeder  style mineralisation at depth, which  requires holes  to be drilled to an average depth of 650m and  takes approximately 20 working days to complete, will be deferred while potential near‐surface gold ounces remain to be drilled out.  

An exploration update was announced on 20 January 2012. Please refer to that announcement for individual drillhole results and their context. 

Both a new geological model and a new ore genesis model have been produced  for Tulu Kapi and neighbouring  targets.  The  models  are  the  result  of  interpretation  of  a  substantial  database accumulated over  the past  two  years by Nyota,  the  generation of general  theories  regarding  the emplacement of mineralisation  into the Tulu Kapi syenite and  latterly the review of these  in‐house theories  by  experienced  external  geological  consultants  with  particular  expertise  in  the interpretation of geological  settings. The pinning down of  the ore genesis model  in particular has had a significant bearing on the development of Proximal and Satellite Targets around Tulu Kapi.  If the validity of  the models  can be proven  from  follow‐up activities over  the next  few months,  the expectation  is  that  subsequent exploration  can be more  focussed and  the overall exploration  risk profile reduced.  

Mining Licence Application 

On 18  January 2012 Nyota was made  aware  that  the Ministry of Mines  required  an Ore Reserve estimated  according  to  an  internationally  acceptable  standard  (eg:  JORC)  as  a  pre‐condition  of issuing a Mining Licence.   This cleared‐up an ambiguity  in  the Regulations  that pre‐date  the 2010 Mining Operations Proclamation (the “Mining Act”).   

In order for Nyota to meet this new requirement it is necessary for the on‐going studies for the DFS to be ostensibly complete such that the JORC requirement for “Modifying Factors” to be taken in to account can be satisfied. The working target agreed with the Government for this is 30 June 2012. 

Definitive Feasibility Study  

The DFS is progressing well and is on schedule for completion in the second half of 2012.  

Work during the period included: 

Page 5: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

• Completion of the process plant design and layout and the advancement of instrumentation, electrical and civil engineering design work.  

o Requests for quotations have now been submitted to contractors. 

• Surveys  for  the  roads  and other  infrastructure  and  an  airborne  LIDAR  topographic  survey over a 56km2

 area of influence. 

• Additional metallurgical  samples  for  variability  test‐work  across  the  ore  body  using  the designed process flow sheet. 

• Geotechnical studies and design work for the open pit, tailings storage facility, water dams and process plant.  

o 21 drill holes were completed using a variety of techniques appropriate specifically to geotechnical studies and 69 test pits were dug;  

o Laboratory test work on the samples is on‐going. 

• Hydrogeological  investigations.  These  consumed  considerable  time  and  resources. Work included drilling and logging 12 holes in the proposed mine area and 8 holes in the proposed fresh water storage dam area. A lack of suitable equipment in‐country caused delays and has led to the postponement of pump‐testing until equipment is imported and is on‐site.   

• Baseline  environmental  and  social  studies  are  largely  complete.  Implementation  of  the project  requires  population  resettlement  and work  is  in  progress  to  locate  suitable  host resettlement  lands.  Resettlement  in  Ethiopia  requires  a  collaborative  effort  led  by  the Government and a good relationship has been developed with all levels of government. The assessment of the positive and negative impacts on both affected and host communities and the measures to maintain livelihoods will commence once this step is complete. 

PROXIMAL AND SATELLITE TARGETS  

With  the  emphasis  on  DFS  work  and  more  specifically  drilling  related  to  hydrogeological  and geotechnical investigations drill rig capacity for further exploration has been limited.   Exploration work during  the quarter  focussed on completing a detailed geological map  showing a more thorough coverage of the area within a 15km radius of Tulu Kapi based on close‐spaced soil geochemical surveys. These surveys have better defined known targets and resulted in the discovery of new  targets warranting  further  follow up. These new  targets generally  represent extensions  to previously known anomalies or the  joining up of two separate anomalies  into one  larger target.   A case  in point  is  the Komto‐Guji Trend Target.   Here, mapping,  in conjunction with  the soil  sample programme, has delineated a mineralized  ferruginous  schist and  limonitic quartz breccia, within a meta‐sedimentary/meta‐volcanic  unit.  The  gossan  bodies  are  lenticular,  typically  100m wide  and several  hundred  meters  long  and  discontinuous  over  an  estimated  2.8km  strike  length.  The exploration  team  responsible  for  follow up currently envisage  the Komto‐Guji Trend as a possible future bulk mineable deposit.  Access to the Komto–Guji Trend is good and it is envisaged that drill 

Page 6: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

access  roads be constructed during  the dry season  to allow  for a more extensive drill programme during the wet season (Figure 2).  

Komto  

The December exploration program called for detailed mapping of the prospective Guji Shear Zone, along which the Komto target was selected based on historical exploration results.   

Follow‐up mapping of  Komto  shows  a brecciated pyritized meta‐sediment  capped by  ferruginous gossan with a strike extend of 2km and coincidental with geophysical  (IP/Resistivity) anomalies. A programme  of  trenching  and  a  string  of  RC  holes  is  planned  to  straddle  the  soil  /  rock  chip  / geophysical anomaly.  

Guji  For resource delineation  in the proximal exploration areas the emphasis  is initially on those targets that  can  generate high‐grade easily  accessible  feed  to be processed  through  the Tulu Kapi plant, further  improving  project  economics.  The  Guji  Prospect  was  therefore  identified  as  a  priority because previous drilling had delineated anomalous gold contents in the saprolite from surface and because it is located 6km by existing road from Tulu Kapi.  

During the period a second phase of  41 RC drill holes was completed, with four holes remaining to be drilled. Results to date from the first phase have been encouraging, with  intersections  including 6.21g/t over 1m, 0.82g/t over 20m, 1.26g/t over 6m.   REGIONAL EXPLORATION – NORTHERN BLOCKS  

The exploration emphasis has been on maximising coverage of  the balance of  the Northern Block licence area to generate future drill targets and to allow for development of all‐weather road access for drill rigs ahead of the next wet season. The area to be covered is substantial and  includes 30 of the targets generated from airborne geophysical data.  

The exploration team is currently running a regional panning programme to collect bulk soil samples to produce heavy mineral concentrates  that will show  the presence of gold and  focus subsequent grid soil geochemical sampling and geological mapping. 

Bendokoro (Brantham License area) 

During  the period  fieldwork  focused  on  the Bendokoro  target.  Prior  to  drilling  an  IP  /  Resistivity geophysical ground survey was conducted, with positive findings, and 17 trenches completed across the strike of both eastern and western targets, demonstrating strike continuity further northwards. Highlights  included Trench 1: 0.58g/t over 5m; Trench 8: 1.7g/t over 7m; Trench 14: 0.57g/t over 12m and Trench 16: 1.54g/t over 5m. 

An initial programme of 11 diamond core drill holes commenced at the start of February. 

As of 31 March 9 holes for a total of 1,657 metres had been drilled and the programme is expected to be  completed by  the early May. 3 holes have  so  far been  logged,  split,  sampled, prepared  for assay and received by the laboratories in South Africa. The turnaround time for analysis is currently in the region of 3 – 4 weeks from receipt.  

Page 7: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

Drilling has been slowed by the breakdown of the drill rig and contamination of fuel supplied to the site in drums.   Steps have been taken to ensure this issue does not recur. 

Work to date has confirmed that mineralisation is contained in an inter‐bedded suite of greenstone volcano‐sedimentary rocks 10‐30 metres wide, showing pervasive pyrite and secondary chalcopyrite mineralisation. This corresponds with the gossanous outcrop mapped at surface and containing up to 10.6 g/t  in grab samples. In addition, visible gold was intersected by borehole 3, associated with pyrite  and  chalcopyrite  within  an  altered  dyke.  The  rocks  are  structurally  complex  with  tight, recumbent,  isoclinal  folds  that  plunge  gently  to  the  north‐west  and  it  is  interpreted  from  the geophysical survey as well as from structural interpretation that the eastern and western anomalies represent a structural duplication of the above suite of rocks.  

Initial  assay  returns  and  geological  interpretation will  be  required  before  further  drilling  can  be planned. 

Boka Sirba (Towchester License area) 

Detailed reconciliation of geophysical survey data, geological mapping and anomalous samples has proven that the quartzite meta‐sediments in the more distal epidote environment contain gold. This contradicts the initial model in which gold was thought to be restricted to the Boka Sirba marble unit of the endo‐skarn. 

Further work is therefore required before the intended initial drilling can commence; this is ongoing.  In addition, soil sampling and mapping continues to target extensions to the mineralised assemblage of rocks which totals more than 15km of strike length. 

CORPORATE 

Corporate Governance 

The Directors of Nyota announced at the company’s Annual General Meeting that  it would review the  composition  of  the  Board  with  the  intention  of  appointing  appropriate  independent non‐executive  directors  to  provide  guidance  on  the  development  of Nyota’s  assets  and  for  their independent input to the Board’s key committees, such as Audit and Remuneration.  

On 21 March 2012, Neil Maclachlan was appointed as Non‐executive Chairman and Melissa Sturgess retired from the Board, with Nyota retaining her expertise and knowledge on a consultancy basis for the next year.   Mr Maclachlan has extensive experience  in both  the City and  the mining  industry.  With  three  decades  of  investment  banking  experience, Mr Maclachlan  has  held  senior  positions, including with HSBC Investment Banking at Wardley Australia and James Capel & Co Ltd.  His banking experience spans Asia, Australia, and Europe.   Additionally, Mr Maclachlan was  the Executive Vice President, Asia, for Barrick Gold Corporation and a director of Golden Prospect Plc. Most recently, he was a director of Extract Resources Ltd and Kalahari Minerals Plc (“Kalahari”), where he was part of the  team  that  successfully negotiated  and  concluded  the  sale  of  Kalahari  to  Taurus Minerals,  an indirect subsidiary of China Guandong Nuclear Power Corporation, in February 2012.  In addition to his  role  as  Non‐executive  Chairman,  Mr  Maclachlan  will  join  Nyota’s  remuneration  and  audit committees.  

Page 8: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

In line with the Company’s stated intentions, it is expected that a further non‐executive director will be appointed before the end of the second quarter.     Placing 

On 3 February 2012, the Company announced the conditional placing of 161,000,000 new ordinary shares, 146,720,000 ordinary shares at an issue price of GBP0.06 and 14,280,000 ordinary shares at an issue price of A$0.089, to raise approximately £9.66 million before expenses (the “Placing”).  The Placing  of  these  new  shares  was  completed  after  obtaining  shareholder  approval  at  a  general meeting held on 7 March 2012.  The  Placing  was  undertaken  to  fund  continued  exploration  drilling  over  the  Northern  Blocks, progress the Tulu Kapi project post completion of the DFS and for general working capital purposes.  The Placing was supported by new and existing shareholders  including Centamin plc  ("Centamin"). Centamin  is an Arabian‐Nubian Shield  focused gold mining company whose  flagship project  is  the Sukari  Gold Mine,  located  in  the  eastern  desert  of  Egypt.  Following  the  Placing  Centamin  owns 90,000,000 Ordinary Shares, being 14.08% of the enlarged share capital of the Company. 

Management Appointments 

A new Chief Operating Officer has been appointed and took up his post  in Addis Ababa on the 16 January 2012. Patrick Goodfellow will oversee the construction of the Tulu Kapi mine and has been appointed ahead of time to give him familiarity with the DFS and to build operational capacity and develop relationships in Ethiopia in order to reduce the risk of delays in construction.  

Patrick  is  civil engineer  and his  considerable project  construction and management experience  in gold projects in Australia and latterly in gold and nickel in SE Asia and Australia.   

Also during the quarter, Anthony Rowland  joined as Business Development Manager. Anthony  is a qualified accountant and CFA charterholder and was a “Qualified Executive” for the AIM Market, or “NOMAD”, for the past five years. 

Health and Safety  

Nyota  recognizes  that  the health  and  safety of  its personnel  is  fundamental  to  the  success of  its operations.    During  the  last  quarter, with  the  considerable  increase  in  activity  at  the  Tulu  Kapi project, several lost time injuries were recorded.  The Company is committed to learning from these incidents and adapting operational methods appropriately.  Nyota strives to continually improve the health and safety of its personnel.  

Page 9: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated
Page 10: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated
Page 11: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

For further information please visit: http://www.nyotaminerals.com or enquire to: 

Richard Chase (CEO)/ Anthony Rowland (Business Development) Nyota Minerals Limited +44 (0) 20 7400 5740  [email protected]  NOMAD Richard Morrison / Jen Boorer Ambrian Partners Limited +44 (0)20 7634 4700  BROKER  Guy Wilkes Ocean Equities Limited (+44) (0) 20 7786 4370  BROKER Rory Scott Mirabaud Securities LLP  (+44) (0)20 7878 3360  FINANCIAL PR Paul Youens / Jos Simson  Tavistock Communications (+44) (0)20 7920 3150  

Competent Persons The Resource Estimate is the responsibility of Principal Geologist Che Osmond BSc MSc MCSM CGeol FGS  EurGeol.   Che  Osmond  is  a  full‐time  employee  of  Wardell  Armstrong  International,  an independent Consultancy and has sufficient experience which is relevant to the style of mineralization and type of deposit under consideration, and to the type of activity which he is undertaking to qualify as a Competent Person as defined in the June 2009 Edition of the AIM Note for Mining and Oil & Gas Companies. Che Osmond  consents  to  the  inclusion  in  the announcement of  the matters based on their  information  in the  form and context  in which  it appears and confirms that this  information  is accurate and not false or misleading. 

Page 12: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

Appendix 5B Mining exploration entity quarterly report 

 

 

 + See chapter 19 for defined terms.  17/12/2010 Appendix 5B  Page 1  

Rule 5.3 

Appendix 5B  

Mining exploration entity quarterly report Introduced 01/07/96  Origin Appendix 8  Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10  

 Name of entity 

NYOTA MINERALS LIMITED

 ABN    Quarter ended (“current quarter”) 

98 060 938 552   31 March 2012

 Consolidated statement of cash flows 

 Cash flows related to operating activities  

Current quarter $A’000 

Year to date  (9 months) 

$A’000 1.1  Receipts from product sales and related 

debtors      

1.2  Payments for  (a)  exploration & evaluation   (b)  development   (c)  production   (d)  administration 

(5,335)

(877)

(14,770)

(2,604) 1.3  Dividends received  1.4  Interest and other items of a similar nature 

received  26 110 1.5  Interest and other costs of finance paid  1.6  Income taxes paid  1.7  Other      

Net Operating Cash Flows  (6,186) (17,264)    

Cash flows related to investing activities  1.8  Payment for purchases of: 

  (a)  prospects   (b)  equity investments   (c)  other fixed assets  (72) (497)

1.9  Proceeds from sale of:   (a)  prospects   (b)  equity investments   (c)  other fixed assets 

1.10  Loans to other entities  1.11  Loans repaid by other entities  69 1.12  Other (provide details if material)     

Net investing cash flows  (72) (428) 1.13  Total operating and investing cash flows 

(carried forward)  (6,258) (17,692)

Page 13: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

Appendix 5B Mining exploration entity quarterly report  

 

 + See chapter 19 for defined terms.  Appendix 5B  Page 2  17/12/2010 

 1.13  Total operating and investing cash flows 

(brought  forward)  (6,258) (17,692)    

Cash flows related to financing activities  1.14  Proceeds from issues of shares, options, etc.  14,442 14,456 1.15  Proceeds from sale of forfeited shares  1.16  Proceeds from borrowings  1.17  Repayment of borrowings  1.18  Dividends paid  1.19  Other – capital raising costs  (380) (380)   Net financing cash flows  14,062 14,076    

Net increase (decrease) in cash held   7,804 (3,616)

1.20  Cash at beginning of quarter/year to date  14,325 25,633 1.21  Exchange rate adjustments to item 1.20  407 519

1.22  Cash at end of quarter  22,536 22,536

Payments to directors of the entity and associates of the directors Payments  to  related  entities  of  the  entity  and  associates  of  the related entities 

  Current quarter $A'000 

 1.23 

 Aggregate amount of payments to the parties included in item 1.2 

 243 

 1.24 

 Aggregate amount of loans to the parties included in item 1.10 

 

 1.25 

 Explanation necessary for an understanding of the transactions 

Non‐cash financing and investing activities 2.1  Details of financing and investing transactions which have had a material effect on 

consolidated assets and liabilities but did not involve cash flows    

  

2.2  Details of outlays made by other entities to establish or increase their share in projects in which the reporting entity has an interest 

    

Financing facilities available Add notes as necessary for an understanding of the position.  

    Amount available $A’000  

Amount used $A’000 

3.1  Loan facilities  

Nil  Nil 

3.2  Credit standby arrangements  

Nil  Nil 

Page 14: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

Appendix 5B Mining exploration entity quarterly report 

 

 

 + See chapter 19 for defined terms.  17/12/2010 Appendix 5B  Page 3  

 Estimated cash outflows for next quarter 

    $A’000 4.1  Exploration and evaluation 

 3,800

4.2  Development  

4.3  Production  

4.4  Administration  

700

   Total 

4,500

  

Reconciliation of cash Reconciliation of cash at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts is as follows. 

Current quarter  $A’000 

Previous quarter $A’000 

5.1  Cash on hand and at bank  2,037 1,353

5.2  Deposits at call  20,499 12,972

5.3  Bank overdraft 

5.4  Other (provide details) 

  Total: cash at end of quarter (item 1.22)  22,536 14,325

 Changes in interests in mining tenements      Tenement 

reference Nature of interest (note (2)) 

Interest at beginning of quarter 

Interest at end of quarter 

6.1  Interests in mining tenements relinquished, reduced or lapsed   

       

6.2  Interests in mining tenements acquired or increased   

       

Page 15: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

Appendix 5B Mining exploration entity quarterly report  

 

 + See chapter 19 for defined terms.  Appendix 5B  Page 4  17/12/2010 

Issued and quoted securities at end of current quarter Description includes rate of interest and any redemption or conversion rights together with prices and dates.    Total number   Number quoted  Issue price per 

security (see note 3) (cents) 

Amount paid up per security (see note 3) (cents) 

7.1  Preference +securities  (description)  

       

7.2  Changes during quarter (a)  Increases through issues (b)  Decreases  

       

7.3  +Ordinary securities  

639,073,263

639,073,263

N/a N/a

7.4  Changes during quarter (a)  Increases through issues (b)  Decreases  

146,720,000 14,280,000

146,720,000 14,280,000

GBP0.06 A$0.089

GBP0.06 A$0.089

7.5  +Convertible debt securities (description)  

7.6  Changes during quarter   

7.7  Options  (description and conversion factor) 

5,300,000 1,280,000 7,000,000

250,000 1,250,000 3,933,334 3,933,334 3,933,332 4,000,000 1,700,000 1,800,000 2,500,000

- - - - - - - - - - - -

Exercise price $0.11 $0.13 $0.15 $0.17 $0.31 $0.35 $0.42 $0.50

GBP0.23 GBP0.175

GBP0.20 -

Expiry date 30/9/2012

31/12/2012 31/12/2012 30/06/2013 30/06/2013 31/12/2015 31/12/2015 31/12/2015

31/1/2016 30/06/15 30/06/15 30/06/15

7.8  Issued during quarter 

2,500,000

-

-

30/6/15

7.9  Exercised during quarter 

7.10  Expired/cancelled during quarter 

900,000 900,000 900,000

- $0.35 $0.42 $0.50

31/12/2015 31/12/2015 31/12/2015

7.11  Debentures (totals only) 

7.12  Unsecured notes (totals only)  

 

Page 16: Nyota Minerals Limited (‘Nyota’ or the ‘Company’) … · Drilling to extend the high‐grade feeder style mineralisation at depth, which requires holes to be drilled ... accumulated

Appendix 5B Mining exploration entity quarterly report 

 

 

 + See chapter 19 for defined terms.  17/12/2010 Appendix 5B  Page 5  

 

Compliance statement  1  This statement has been prepared under accounting policies which comply with 

accounting standards as defined in the Corporations Act or other standards acceptable to ASX (see note 5). 

 2  This statement does give a true and fair view of the matters disclosed.  

 

  Sign here:   ............................................................ Date:  30 April 2012 

Finance Director    Print name:   Michael Langoulant  

Notes  1  The quarterly report provides a basis for informing the market how the entity’s 

activities have been financed for the past quarter and the effect on its cash position.  An entity wanting to disclose additional information is encouraged to do so, in a note or notes attached to this report. 

 2  The “Nature of interest” (items 6.1 and 6.2) includes options in respect of 

interests in mining tenements acquired, exercised or lapsed during the reporting period.  If the entity is involved in a joint venture agreement and there are conditions precedent which will change its percentage interest in a mining tenement, it should disclose the change of percentage interest and conditions precedent in the list required for items 6.1 and 6.2. 

 3  Issued and quoted securities  The issue price and amount paid up is not 

required in items 7.1 and 7.3 for fully paid securities.  4  The definitions in, and provisions of, AASB 6: Exploration for and Evaluation of 

Mineral Resources and AASB 107: Statement of Cash Flows apply to this report.  5  Accounting Standards ASX will accept, for example, the use of International 

Financial Reporting Standards for foreign entities.  If the standards used do not address a topic, the Australian standard on that topic (if any) must be complied with. 

 == == == == ==