35
Numerical Simulation of Basal Aquifer Depressurization in the Presence of Dissolved Gas – An Update Rudy Maji, Ph.D. Karl Lawrence, Ph.D. Ken Baxter, M.Sc., P.Geol. Scott Morton, P.Geol.

Numerical Simulation of Basal Aquifer Depressurization in the … · 2020. 12. 16. · FEFLOW Model Reduction in effective permeability is continuous (i.e. at every timestep) Implemented

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

  • Numerical Simulation of Basal Aquifer Depressurization in the Presence of Dissolved Gas – An Update

    Rudy Maji, Ph.D. Karl Lawrence, Ph.D. Ken Baxter, M.Sc., P.Geol. Scott Morton, P.Geol.

  • What to Take Away From this Presentation

    Reservoir modelling typically considers multiphase flow;

    Groundwater modelling has only dealt with single phase flow;

    A regional scale reservoir model is required to address the dissolved gas issues during basal aquifer depressurization in advance of mining;

    Originally, this challenge was addressed through a modified application of MODFLOW (finite difference approach);

    This presentation provides the results of a better approach developed using FEFLOW (finite element approach).

    April-16-14 2

  • Outline

    Background

    Key Questions to be Answered

    Ground Water Modelling Approach Model Construction Model Calibration Prediction Results

    Summary and Conclusions

    April-16-14 3

  • Background

    April-16-14 4

  • Background – Project Location

    Calgary, Alberta, Canada

    Fort McMurray, Alberta, Canada

    April-16-14 5

  • Background - CNRL Horizon Oil Sands Project

    Located about 75 km north of Fort McMurray in northeastern Alberta

    Open pit mining operation and oil sands plant for extracting and upgrading bitumen from the McMurray Oil sands deposit.

    April-16-14 6

  • Background - CNRL Horizon Oil Sands Project

    Prior to mining the piezometric elevations within primary aquifer varied between 276 m to 280 m asl

    An aquifer depressurization plan consisting of 6 pumping wells were planned around the South Pit to depressurize the basal aquifer

    April-16-14 7

  • Background - CNRL Horizon Oil Sands Project

    DP network operational since 2009

    In early 2012, the DP well network consisted of 35 vertical in-pit pumping wells and 2 horizontal pumping wells

    Depressurization has been achieved in the area of active mining.

    2006 DP Well Network Planning

    2009 DP Well Network Operational

    2010-2011 Mine Sequence Excavation

    April-16-14 8

  • Background – Why? Gas Locking

    If there are substantial amounts of dissolved gas in the groundwater, “gas-locking” may occur during the depressurization of aquifer

    Pore pressure reductions lower the gas solubility;

    When pressure reduces below critical value (“bubble pressure point”), exsolution occurs;

    Presence of gas ↑ effective specific storage or ↓ effective permeability;

    Permeability reduction results in steeper drawdown curves and reduced depressurization extent.

    April-16-14 9

  • Background – Effects of Gas Locking

    Reduction in DP well efficiency – depressurization is limited locally;

    Additional DP wells may be required to achieve the target water level elevations.

    Cost and schedule implications.

    April-16-14 10

  • Background – Basal Aquifer Isopach

    Mining starts from the west edge of the pit

    South Pit Contours

    April-16-14 11

  • Background – Key Indicators

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    55

    60

    65

    700 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450 480 510 540 570 600 630 660 690 720 750 780 810 840

    Elapsed Time (min)

    Dra

    wd

    ow

    n (

    m)

    DP-03 Datalogger OBW @ DP-03 Datalogger OBW @ DP-03 Manual DP-03 Manual

    Separation between pumping well and observation well = 31.0 m

    Q1 = 157 m3/d (24 igpm)

    Q2 = 333 m3/d (51 gpm)Q3 = 655 m3/d (100 igpm)Q4 = 982 m3/d (150 igpm)

    Available drawdown to pump intake = 65.1m

    Q1

    Q2

    Q3

    Q4

    April-16-14 12

  • Key Questions

    April-16-14 13

  • Key Questions to be Answered

    How many wells are required to be installed in the DP network?

    How much water to be handled?

    April-16-14 14

  • Modelling Approaches

    April-16-14 15

  • Groundwater Modelling Approaches

    Develop Regional Model in Multiphase Flow Modelling Framework. Numerically complex; Computationally memory extensive.

    Develop Alternative Model to Build the Solution for Gas Locking Problem

    in the Single-Phase Modelling Framework; Easy to solve using an existing regional model; Computationally less intense.

    Regional Model in Visual MODFLOW; Regional Model in FEFLOW.

    April-16-14 16

  • Single Phase Flow Modelling - MODFLOW

    MODFLOW model was revised to account for dissolved gas issues The hydraulic conductivity values were revised based on the

    simulated pressure at discrete time steps.

    April-16-14 17

  • MODFLOW Approach – Discrete Reduction

    210

    220

    230

    240

    250

    260

    270

    280

    290

    300

    0 50 100 150 200 250 300 350

    Corr

    ecte

    d H

    ead

    (mas

    l)

    Time (min)

    SIM-NO GAS LOCKING

    DP-03-MEASURED

    DP-03-SIM

    DISCRETE STEPS

    OBW4-MEASURED

    OBW4-SIM

    18 April-16-14

  • Single Phase Flow Modelling - FEFLOW

    An external module was developed in FEFLOW Automated update of hydraulic conductivity during each timestep

    based on: Aquifer pressures; and Relative permeability relationship.

    April-16-14 19

  • FEFLOW Approach - Continuous Reduction

    20 April-16-14

    0

    200

    400

    600

    800

    1000

    12000

    10

    20

    30

    40

    50

    60

    70

    0 100 200 300

    Time [min]

    Pum

    ping

    Rat

    e [m

    3/da

    y]

    Draw

    dow

    n [m

    ]

    DP-03

    DP-03 - SIM

    OBW

    OBW - SIM

    Pumping Rate

  • Single Phase Flow Modelling - FEFLOW

    Gas characterization Pressurized sampling

    Multi-phase flow (reservoir) modelling CNRL

    Relative permeability relationship 30% reduction in permeability for every 10 m reduction in head below the bubble point pressure (BPP)

    April-16-14 21

  • Single Phase Flow Modelling - FEFLOW

    𝐾𝐾 = 1 − 𝑝𝐻−ℎ𝐷 × 𝐾 … obtained from the relative permeability and

    pressure saturation relationship

    p% of permeability reduction was found for D m of pressure drop

    H = 240 masl (BPP) h = head in each node K = Original Hydraulic Conductivity

    April-16-14 22

  • Calibration to a Pumping Test

    April-16-14 23

    With Gas-Locking – 30% reduction in K per 10 m

    0

    200

    400

    600

    800

    1000

    12000

    10

    20

    30

    40

    50

    60

    70

    0 100 200 300

    Time [min]

    Pum

    ping

    Rat

    e [m

    3/da

    y]

    Draw

    dow

    n [m

    ]

    DP-03

    DP-03 - SIM

    OBW

    OBW - SIM

    Pumping Rate

    Calibration (Well Head)

    Observed

    Simulated

  • Comparison Between Approaches

    FEFLOW Model

    Reduction in effective permeability is continuous (i.e. at every timestep) Implemented through external module (IFM) which is linked to FEFLOW at run-time separate module created to

    reduce K

    shorter runtimes

    minor user interaction (only need specify K reduction function)

    Visual MODFLOW Model

    Reduction in effective permeability is discrete (i.e. not at every timestep) The K field was revised at discrete timesteps based on the simulated heads and bubble point pressure model run was interrupted to

    reduce K

    longer runtimes

    major user interaction

    April-16-14 24

  • History Match

    April-16-14 25

  • History Match – Pumping Wells

    Pumping schedule irregular

    Horizontal wells are

    modelled

    40 scheduled stress (pumping) periods

    43 pumping wells

    April-16-14 26

  • History Match – DP Obs Wells (with gas-lock)

    April-16-14 27

  • History Match – DP Obs Wells (no gas-lock)

    April-16-14 28

  • History Match – DP Obs Wells (with gas-lock)

    April-16-14 29

  • History Match – DP Obs Wells (no gas-lock)

    April-16-14 30

  • History Match - Summary

    Detailed history match of operational volumes completed with irregular pumping schedule; 2 horizontal wells; 41 vertical wells; 40 scheduled stress (pumping) periods

    Suitable match obtained given approach and uncertainties

    April-16-14 31

  • Prediction Results

    April-16-14 32

  • Estimation of Flow Volumes and Number of Wells

    North South Total [m3/day [m3/day [m3/day 2012 711.23 98.46 809.69 2013 655.55 292.44 947.99 2014 482.81 555.90 1038.71 2015 457.22 662.96 1120.18

    No Gas Locking No Gas Locking – Estimate # Wells

    With Gas Locking – Estimate # Wells

    North South Total

    8 1 9

    7 3 11

    5 6 12

    5 7 12

    Number of Wells Operating

    North South Total

    24 3 27

    22 10 32

    16 19 35

    15 22 37

    Number of Wells Operating

    April-16-14 33

  • Summary and Conclusions

    April-16-14 34

  • Summary and Conclusions

    Characterization of dissolved gas during the early stage of the project is critical;

    A predictive tool has been developed to design the DP well network for gassy aquifers;

    Greater number of wells are required to depressurize a given aquifer in the presence of dissolved gas;

    The presence of dissolved gas could significantly impact the overall project schedule and budget.

    April-16-14 35

    Numerical Simulation of Basal Aquifer Depressurization in the Presence of Dissolved Gas – An UpdateWhat to Take Away From this PresentationOutlineBackgroundBackground – Project LocationBackground - CNRL Horizon Oil Sands ProjectBackground - CNRL Horizon Oil Sands ProjectBackground - CNRL Horizon Oil Sands ProjectBackground – Why? Gas LockingBackground – Effects of Gas LockingBackground – Basal Aquifer IsopachBackground – Key IndicatorsKey QuestionsKey Questions to be AnsweredModelling ApproachesGroundwater Modelling ApproachesSingle Phase Flow Modelling - MODFLOWSlide Number 18Single Phase Flow Modelling - FEFLOWFEFLOW Approach - Continuous ReductionSingle Phase Flow Modelling - FEFLOWSingle Phase Flow Modelling - FEFLOWCalibration to a Pumping TestComparison Between ApproachesHistory MatchHistory Match – Pumping WellsHistory Match – DP Obs Wells (with gas-lock)History Match – DP Obs Wells (no gas-lock)History Match – DP Obs Wells (with gas-lock)History Match – DP Obs Wells (no gas-lock)History Match - SummaryPrediction ResultsEstimation of Flow Volumes and Number of WellsSummary and ConclusionsSummary and Conclusions