202
Nuggets of Gold • Troubleshooting Tips For diagnosing vibration problems • Balancing • Alignment • Motors • Pumps • Signal Processing Considerations • DC Drives

Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Embed Size (px)

Citation preview

Page 1: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Nuggets of Gold

• Troubleshooting Tips For diagnosingvibration problems

• Balancing

• Alignment

• Motors

• Pumps

• Signal Processing Considerations

• DC Drives

Page 2: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

General ThoughtWHEN HIGH VIBRATION

IS PRESENT

1: There may be a large force

2: The structure may be weak

3: Resonance amplificationmay be present

Page 3: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Balancing1: When balancing, plot the original and trial vectors on all

bearings and orientations. When all vectors point towards thesame solution; you are in the right plane. When the vectorsdo not point towards the same solution, try another plane. If

this still doesn't work, try a multi-plane solution.

Vectors Agree In weight adjustment

Vectors disagree in weight adjustment

Page 4: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1 2 3 4 5 67 GENERATOR GENERATOR MOTOR GENERATOR GENERATOR GENERATOR

MOTOR GENERATOR SET ON DRAG LINE

ORIGINAL READINGSBRG. 1 BRG 2 BRG 3 BRG 4 BRG 5 BRG 6 BRG 10

H 7.8 45 DEG 5.4 45 DEG .8 80 DEG 1.5 220 DEG 1.7 253 DEG 2.1 245 DEG 2.6 260 DEGV 10.3 50 9.1 50 9.7 45 8.6 47 5.6 63 2.5 107 5.1 180

BALANCE SHOT ADDED TO No. 1 GENERATOR 8.25 OZ at 310 DEGREESH 5.9 37 3.9 35 .6 45 .8 270 .9 270 .8 270 1.1 45V 11.0 45 9.6 45 10.1 36 8.8 40 5.4 45 1.1 117 5.9 200

NOTE !- LEVELS WENT DOWN IN THE HORIZONTAL DIRECTION, BUT UP IN THE VERTICAL DIRECTION

UNCOUPLED GENERATORS 1 & 2 FROM MOTOR

H 6.8 25 4.5 34 1.0 350 1.6 270 1.8 270 2.0 243 2.7 236V 7.9 68 6.5 63 6.6 45 5.9 45 3.8 45 1.9 45 1.8 270

NOTE THAT EVEN UNCOUPLED, GENERATOR NO. 1 IS OPERATING WITH ALMOST 8 MILS OF VIBRATION

PERFORMED RESONANCE TEST- STRUCTURE FOUND TO BE OPERATING NEAR RESONANCE

ADDED 50 OZ BALANCE WEIGHT TO MOTOR , ALL LEVELS DROPPED TO BELOW 3 MILS.

NO. 1 NO. 2 NO. 3 NO. 4 NO. 5

SIX ROTORS WITH SEVEN SHARED BEARINGS SOLIDLY COUPLED ON A METAL DECK.

After a weight wasinstalled,Horizontals wentdown Verticals went down.

This is a strong sign that youare adding weight to wrong

plane

Page 5: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: When a rotor runs above its 1stcritical and there is an indicationof a bow, translate a portion of thestatic balance component fromthe ends to the center of the rotor.If this is not done, the rotor willrun good on a balance machinebut bad in its own bearings athigh speed. This is due tointernal bending momentsproduced by unbalance forcesacting on the axial distancebetween the mass unbalance andthe correction weights.

Page 6: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

BOWED FLEXIBLE ROTOR REQUIRING MID SPANSHOT

END PLANE SHOTS

CREATES INTERNAL BENDINGMOMENTS

WHEN A ROTOR OPERATES BELOW ITS FIRST BENDING MODE, IT ACTS LIKE ARIGID BODY AND THE BALANCE WEIGHT CAN BE ADDED ANYWHERE ALONG THEROTOR. IF, HOWEVER, THE ROTOR OPERATES ABOVE ITS BENDING MODE, ITBECOMES A FLEXIBLE ROTOR AND THE WEIGHT NEEDS TO BE PLACED OPPOSITETHE HEAVY SPOT TO PREVENT INTERNAL BENDING MOMENTS.

CASE HISTORY: A STATIC BALANCE SHOT IN THE END PLANES WAS INSTALLEDON A HIGH PRESSURE TURBINE ROTOR WITH A BOW. 18 OZ WERE ADDED INEACH END, WITH ALMOST NO EFFECT. WHEN WEIGHT WAS ADDED IN THE MIDSPAN, THE ROTOR WAS EASILLY BALANCED.

IF SHOT IS DIRECTLY ACROSSFROM BOW NO BENDING MOMENTSARE CREATED.

MID SPAN SHOT

Page 7: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: When balancing 2 polemotors which are above 1000HP, beware of thermalvectors. This class of rotor willoperate well uncoupled, butwill often have high levels ofvibration when pulling fullcurrent. This is because therotor can bow as a function ofheating by the current flow.

Page 8: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Corpoven RefineryVenezuela

Page 9: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 10: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

4: During a startup, if a high speed compressorhas low response as it passes through itscritical, but the level increases steadily withRPM, without much of a phase shift, thensuspect unbalance in the coupling. On a polarplot, the response line will point straight outwardbecause the amplitude increases without anyshift in phase.

Page 11: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

COMPRESSOR WITH UNBALANCE IN COUPLING

PHASE

MAGNITUDE

UNBALANCE IN COUPLING

UNBALANCE IN ROTOR

PROBE

COUPLING IS OVERHUNG

7000 RPM COMP.BEFORE BAL.3.8 MILS 240 DEGWT. ADDED23.7 GM @ 50DEGAFTER BALANCE.6 MILS 203 DEG

45 315

135 225

0

180

BEFOREAFTER

90 270

Page 12: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

5: When balancing a large machinewith multiple rotors, if there is no otherclear indication, then on the first trialweight attempt, add weight in the rotorwith the largest inertia. Learned fromArt Crawford. Once that is done, referto balancing tip No. 1

Page 13: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1 2 3 4 5 67 GENERATOR GENERATOR MOTOR GENERATOR GENERATOR GENERATOR

MOTOR GENERATOR SET ON DRAG LINE

ORIGINAL READINGSBRG. 1 BRG 2 BRG 3 BRG 4 BRG 5 BRG 6 BRG 10

H 7.8 45 DEG 5.4 45 DEG .8 80 DEG 1.5 220 DEG 1.7 253 DEG 2.1 245 DEG 2.6 260 DEGV 10.3 50 9.1 50 9.7 45 8.6 47 5.6 63 2.5 107 5.1 180

BALANCE SHOT ADDED TO No. 1 GENERATOR 8.25 OZ at 310 DEGREESH 5.9 37 3.9 35 .6 45 .8 270 .9 270 .8 270 1.1 45V 11.0 45 9.6 45 10.1 36 8.8 40 5.4 45 1.1 117 5.9 200

NOTE !- LEVELS WENT DOWN IN THE HORIZONTAL DIRECTION, BUT UP IN THE VERTICAL DIRECTION

UNCOUPLED GENERATORS 1 & 2 FROM MOTOR

H 6.8 25 4.5 34 1.0 350 1.6 270 1.8 270 2.0 243 2.7 236V 7.9 68 6.5 63 6.6 45 5.9 45 3.8 45 1.9 45 1.8 270

NOTE THAT EVEN UNCOUPLED, GENERATOR NO. 1 IS OPERATING WITH ALMOST 8 MILS OF VIBRATION

PERFORMED RESONANCE TEST- STRUCTURE FOUND TO BE OPERATING NEAR RESONANCE

ADDED 50 OZ BALANCE WEIGHT TO MOTOR , ALL LEVELS DROPPED TO BELOW 3 MILS.

NO. 1 NO. 2 NO. 3 NO. 4 NO. 5

SIX ROTORS WITH SEVEN SHARED BEARINGS SOLIDLY COUPLED ON A METAL DECK.

Page 14: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

6: Do not attempt to balance when the phaseis moving. This is a sign that there is a rub.Machines that operate below a critical tendto bow into the rub and the rub gets worsewith time. Machines that operate above acritical can bow away from the rub causingthe phase angle to continually move againstrotation. Note that if a above criticalmachine has a light rub, it can be a bad ideato shut it down, because then it will have tocoast down through its critical speed.

Page 15: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

7: When the horizontal and verticalphase are the same or 180 degreesout, then look for rocking or a loosebase. Another thing to consider is thatif a machine is operating between avertical and horizontal naturalfrequency then his can also causeunusual phase relationships betweenthe vertical and horizontal directions.

Page 16: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

6 CASES OF LOOSENESS

Page 17: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Case History 1- The phase on a turbine bearingwas identical in the vertical and axial directionswith the axial vibration being very high. It wasdiscovered that one of the hold down bolts wasbroken off beneath the surface of the concreteallowing the bearing to rock.

Page 18: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Case 2- On a large fan, the horizontal and vertical vibration phaseangles were identical. The base bolts were loose allowing the bearing torock. The maintenance manager did not believe it so a cup of water waspoured on the base next to the bearing. When the water alternately shotout from between the bearing housing and the base plate, he agreed tohave the bolts tightened. The horizontal vibration dropped from 12 milsto less than 2 mils.

Page 19: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

CASE 3- A power plant had spent $30000 on a mill motor trying toget the vibration levels reduced. The rotor had been balancedseveral times, but the amplitude was still high.

Page 20: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

APPARENT COUPLE UNBALANCE IN AFAN THAT OPERATES BELOW 1st

NATURAL FREQUENCY

POSSIBLE CAUSES

DISSIMILAR PEDESTAL STIFFNESES

– WRONG PLACEMENT OF VIBRATION PICKUPS

– LOOSE BASE BOLTS

– PHASE REVERSAL WITHIN ONE PICKUP

• NOTE- IF THERE IS A LARGE COUPLE COMPONENT IN AFAN THAT OPERATES WELL BELOW ITS 1ST CRITICAL, THENBE VERY SUSPICIOUS AND AVOID INSTALLING A COUPLESHOT

Page 21: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Vectors showedwhat appearedto be a largeamount of

coupleunbalance

EXAMPLE OF A LARGE FAN WITHAPPARENT COUPLE UNBALANCE

Page 22: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

SOLUTION

• The large couple component raised the level ofsuspicion.

• The results of a previous balance person showedthe response to be highly non-linear

• The base bolt tightness was therefore checkedand all the bolts were all found to be significantlyloose.

• The bolts were tightened, the couple componentdisappeared and the levels dropped to 1/4th theiroriginal values.

• Following bolt tightening, the fan was then easilybalanced.

Page 23: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

PLUNGER BOLT HOLDS BEARING TIGHT WITHIN HOUSING.

IF PLUNGER BOLT IS NOT TIGHT, THENBEARING WILL MOVE RELATIVE TOHOUSING. THIS MOVEMENT RESULTSIN A NON-LINEAR SYSTEM. BALANCINGIS VERY DIFFICULT, IF NOT IMPOSSIBLEIN THIS SITUATION.

Page 24: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

LOOSE BEARING IN HOUSING COMPLICATESBALANCING

PLUNGER BOLT

BEARING HOUSING

BEARING

SHAFT

IF A BEARING IS LOOSE IN ITSHOUSING, A NONLINEAR SYSTEM ISCREATED AND BALANCING ISALMOST IMPOSSIBLE.

CASE HISTORYA LARGE ID FAN COULD NOT BEBALANCED. THE CASING LEVELSWERE SLIGHTLY OVER 2 MILS,HOWEVER, WHEN SHAFT STICKLEVELS WERE MEASURED, THEAMPLITUDE WAS GREATER THAN 17MILS. SINCE THE SHAFT TO INNERBEARING CLEARANCE WAS ONLY 8MILS, THIS MEANT THAT THEBEARING HAD TO BE MOVING IN THEHOUSING. WHEN THE PLUNGERBOLT WAS TIGHTENED, THE CASINGLEVEL ROSE TO 21.5 MILS. AFTERTHE TIGHTENING, THE FAN WASEASILY BALANCED.

17 MILS

2 MILS----

Page 25: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

8: When balancing a rotor and the phase suddenly shifts 180 degrees,then this is a sign that the rotor may be loose. Case History- Whilebalancing a large centrifuge, with a strobe light the vibration vectorchanged from 3 mils at a given phase angle to approximately that amount180 degrees out. The change was instantaneous. It was discoveredupon examination that the tapered fit of the shaft and bowl assembly wasloose.

Loose fitbetween bowland drive shaft

Page 26: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

LARGE POWERGENERATION GAS

TURBINES

• A different sort of an animal

• Balancing Cross effects are oftenmuch larger than direct influence.

Page 27: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 28: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

DIRECT AND CROSSEFFECT

WESTINGHOUSE 100MW 501 GT

Exhaust End Shot on Exhaust End 18.6 oz/mil 25 Degree lag

Exhaust End Shot on Compressor End 4.7 oz/mil 46 degree lag

Compressor end shot on Compressor end 18 oz/mil 353 degree lag

Compressor end shot on Exhaust end 8.6 oz/mil 30 degree lag

Page 29: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Weight addedhere has 4

times as mucheffect on

compressorend.

Page 30: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

ALIGNMENT

Page 31: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1: When aligning gear boxes with sleevebearings, beware of pop up pinions. Theircontribution to the shaft alignment does notshow up when you take hot alignment readings.Their effect also does not show up on laseralignment systems mounted on the cases or viaoptical means. Source: Charlie Jackson

Case History: A speed increaserGearbox at a refinery had an input ofapproximately 1200 RPM and an output of9600 RPM. The amount of upward movementof the pinion was greater than the tolerablemisalignment for the short high speed coupling.The amount of shaft movement vertical andhorizontal was included in the alignmentsettings. The unit operated for several yearswithout any problem or excessive couplingwear.

Page 32: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: When aligning turbines settingon condensers, beware of vacuumdraw down. It can be a muchgreater effect than thermal growth.

1- A large turbine was experiencing oil whip. As the unit wasbrought to speed, at almost exactly twice the critical speed, anapproximately ½ running speed component appeared as the speedcontinued to increase, the frequency of the instability remainedlocked at the critical speed frequency. A complex glycol proximityprobe alignment system was installed to measure the bearingmovement. When condenser vacuum was applied there was a.016” difference in elevation between the No. 2 and No. 3 bearings.

Page 33: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

500 MW TURBINE OILWHIRL-WHIP

• When turbine would be shut down, ifit was not started up within 2-3hours, it could not be started up fortwo days because of excessivevibration.

• SOUNDS LIKE XENON POISONINGON A NUCLEAR REACTOR

Page 34: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

MACHINE LAY OUT

HP TURBINE LP-1 TURBINE LP-2 TURBINE GENERATOR

HIGH VIBRATION ON THISBEARING WOULD TRIP

TURBINE ON HOT RESTART

CONDENSER

Page 35: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

VIBRATION SPECTRUM

Page 36: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

MAP PLOT

NOTE AS SPEED CHANGES WHIRLFREQUENCY DOES NOT. IT IS LOCKED

ONTO ROTOR’S NATURAL FREQUENCY.THIS IS CALLED OIL WHIP

Page 37: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

ALIGNMENT TEST SYSTEM

SUPPLIES DC OFFSET AND ACMOVEMENT

DIAL INDICATOR MEASURESDC MOVEMENT

READOUT SHOWS MOVEMENTOF FLOAT WHICH IS COMPAREDTO DIAL INDICATOR READING.

Page 38: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

HEART OF SYSTEM

FLOAT WITH METAL TARGET MOVESWITH CHANGE IN FLUID ELEVATION.

PROXIMITY PROBE MEASURES CHANGEIN GAP DISTANCE.

Page 39: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

SETUP ON TURBINE

Page 40: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

REFERENCE PICKUP TO ACCOUNTFOR FLUID EXPANSION OR LOSS

Page 41: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

TEST RESULTSMILS MOVEMENT VERSUS VACUUM

16 MILDIFFERENTIAL

Page 42: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

DISCUSSION

VACUUM DRAW DOWN COMBINED WITH THERMALDIFFERENTIAL GROWTH UNLOADED BEARING CAUSINGIT TO GO UNSTABLE. WHEN BOTH WERE COLD,IT WOULD BE STABLE. WHEN BOTH WERE HOT,IT WOULD BE STABLE. THE PROBLEM OCCURREDAFTER A TRIP, WHEN THE THINNER LP SECTIONWOULD COOL DOWN QUICKER THAN THE THICKHP SECTION. THIS DIFFERENTIAL ADDED TO THEVACUUM DRAW DOWN WAS TOO MUCH.BEARING METAL TEMPERATURECONFIRMED THIS FINDING.

Page 43: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

SOLUTION

TILT PADBEARING

Page 44: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

FINAL RESULTS

Page 45: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

. Case 2- Two boiler feed pumps were having vibration problems andwearing out their gear couplings. When dynamic alignment wasperformed between the turbines and pumps, it was discovered thatwhen vacuum was pulled on the turbines that they dropped .020”relative to the pumps.

Page 46: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

COUPLINGS BEING DESTROYED ON STEAMGENERATOR FEED PUMP AT NUCLEAR

STATION

Page 47: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

VIBRATION SPECTRUM

5.8 Mils of 2XVIBRATION

Page 48: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

ORBIT DISPLAY

Page 49: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

PROBLEM-ALIGNMENTSPEC. WAS WRONG

• Vacuum draw down was 20 mils

• Even though pump was centermounted, it was growing.

• Turbine was growing unevenly

PUMP NEEDED TO BE SET LOW RATHER THAN HIGH

Page 50: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

CHILLER TURBINE WASDESTROYING BEARINGS

UPPER HALF OFBEARINGS WERE

FAILING BY FATIGUE

Page 51: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

MACHINE SETUP

TURBINE

CHILLER

Page 52: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

MONITORING OFALIGNMENT

Page 53: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

MACHINE LAYOUT

TURBINE

EXPANSION JOINT

COMPRESSOR

Page 54: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

TEST RESULTS

TURBINE

EXPANSION JOINTDIAL INDICATORS SHOWED THAT

THERE WAS NO MOVEMENTACROSS JOINT

COMPRESSOR

Page 55: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

ACTUAL PROBLEM

TURBINE

When compressor started up,this pipe cooled down causingcompressor to rock back. Thismade turbine appear to dropdown relative to compressor.

LASERMOUNTED ON

BEAM

LASERMOUNTED ONCOMPRESSOR

Page 56: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: If a machine operates well for a few weeks following an overhaul,then 2X running speed shows up in the proximity probe spectrum,suspect a locked coupling. The amount of misalignment may not havechanged. The problem is that either the coupling grease has brokendown or escaped from the coupling.

Page 57: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

PUMPS

Page 58: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

LOMAKIN EFFECT

A LARGE PUMP WOULD OPERATE FOR AYEAR OR SO, THEN THE VIBRATION WOULDGET HIGH. THIS HAPPENED REPEATABLY.AFTER THE OVERHAULS, THE PUMP WOULD OPERATEOK FOR A FEW MONTHS. THE ROTOR WAS NEVERFOUND TO BE OUT OF BALANCE.

Page 59: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

PUMPS1: Pump seals can act like bearings and stiffen the shaft to the

point that the critical speed will be pushed out beyond theoperating speed. When the seals wear, the critical speed may

move back into the operating range. This seal stiffeningphenomenon is often referred to as the Lomakin effect.

Page 60: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Case History- A large feed pump had a history of operating well after itwas overhauled with new seals, but after time the running speed vibrationwould increase. A system was set up to monitor the amplitude and phaseas the pump was brought to speed. It was discovered that after the sealsexperienced wear that the pump was operating just below a rotor criticalspeed.

Page 61: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

TEST RESULTS

PEAK HOLD PLOTSHOWS THAT

VIBRATION DROPSOFF RAPIDLY WITH

SPEED.

Page 62: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

LOMAKIN EFFECT

WHEN SEALS WEAR,ROTOR STIFFNESS DROPSCAUSING NATURALFREQUENCY TO DROP INTOOPERATING SPEED RANGE.

Page 63: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: Pump seals can unload the bearings making them unstableor reduce their damping. Running speed levels will be muchhigher than normal and will be unstable. Due to the lowloading, even though the vibration response is high, themachine can often operated indefinitely.

Case History- A steam generator feed pump at a nuclearpower plant had above normal levels of vibration present on itsproximity probes, but there was never any damage to thebearings. An analysis of the pump was performed and it wasdetermined that the seals were supporting the shaft to thepoint that the bearings were only carrying a small fraction ofthe rotor’s weight. Collaborated on this case with MalcolmLeader who did the rotor analysis.

Page 64: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: When analyzing pumps, measure the suctionpressure, the discharge pressure, calculate the totaldeveloped head then look at the pump head curvebefore doing anything else. Case History 1- Threeidentical pumps were operating side by side. One of thepumps was failing bearings every few weeks. A studyof the suction and discharge pressure showed that thepump was operating at near shut off head conditions.The problem was that during recirculation conditions,the flow was way too small due to the presence of aone inch orifice plate instead of the required three inchorifice plate. Replacement of the orifice plate solved thebearing failure problem.

Page 65: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

FLOW IS BALANCED SO THERE SHOULD BE NO THRUST

Page 66: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 67: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2- Several large circulating water pumps had highlevels of broad band vibration followed by failure of

the cases and impellers. It was found that thedischarge pressure was one third of the design point,meaning that the pumps were operating in a run outcondition. The problem was that at times only one

pump was in operation instead of the two pumps thatwere considered in the initial design.

Page 68: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

4: If multiple pumps arein the same header,then if one pump isdominate, then it willforce the weaker pumpback on its flow headcurve.

Page 69: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

5: Vertical pumps have a high incidence ofresonance problems. Always test forresonance in the direction in line with thedischarge line and in a direction 90 degreesout from that orientation. Discharge lines canstiffen the pump and the cutout that allowsthe coupling to be removed can weaken thestructure. The combined effect of thedischarge line and access hole cutoutresults in vastly different natural frequenciesin the two orthogonal directions. The resultcan be 20 mils vibration in one direction and2 mils in the other direction.

Page 70: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 71: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 72: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

NATURAL FREQUENCY OF LARGE VERTICAL PUMPIN LINE WITH DISCHARGE

Page 73: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

90 DEGREES OUT FROM DISCHARGE

Page 74: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

MODE SHAPE OF 480 CPM MODE

Page 75: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

AMPLIFICATION FACTOR CALCULATION USING LOGDEC APPROACH

Page 76: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

6: One of the most important settings on avertical pump is the lift. The lift is thedistance between the impeller and thestationary components. It is determined by

measuring the gap in the coupling before the bolts aretightened and the impeller is lifted off the bottom of thepump. If the lift is too much, then the pump will be inefficientand will not produce the desired head or flow. If the lift is tosmall, then the impeller can contact stationary components.

Page 77: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

VERTICAL PUMP

Page 78: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

7: At the Best Efficiency Point, theangle of the fluid coming off theimpeller matches the angle of thediffusers. Operating off of thispoint will result in lower efficiencyand higher levels of vibration.

Page 79: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 80: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 81: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 82: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 83: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 84: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 85: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

8: If the discharge valve of a large pump is not completelyclosed, then this can cause the startup time to increase,resulting in an over current trip.

Case history- A water company could not get a largevertical pump to start. They brought in electrical experts,but everything checked out properly. It was suggested bythe vibration analyst that the valve might be leaking.When it was examined, it was discovered that the sealwas damaged. When the valve was repaired, the motorstarted with no problem.

Page 86: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Sleeve BearingsImportant Points

1: Improper bonding of the babbitt to thebase metal will cause sleeve bearings to run

hot because of poor heat transfer in theareas where the bonding was not complete.

In many cases, you will see fans and airmovers blowing air across the bearing tocool it, when the actual cause of the high

reading at the thermocouple is poor bonding.An ultrasonic exam of the bearing will

quickly identify the problem.

Page 87: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: A good rule of thumb is that a machine thatoperates with shaft motion levels of less than25% of clearance is running with acceptableamplitudes. Above 30% is a low level alarmand above 40% is a high level alarm. Levelsgreater than 50% will cause rapid fatigue ofthe babbitt. Source: Jim McHugh

Page 88: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: When an axial resonance is suspected on a machinewith sleeve bearings, it is necessary to rotate the shaftduring the impact test. This gets the shaft up on the oilfilm and decouples the end bell from the shaft, so that arealistic natural frequency can be determined. CaseHistory- A large feed pump motor had .6 in/second ofaxial vibration. Resonance was suspected. When astatic impact test was performed, there did not appearto be a problem. However, when a strap wrench wasused to rotate the shaft and get the shaft up on the oilfilm, a natural frequency appeared at almost exactlyrunning speed. This is a very common occurrence andthe number of times this has occurred are almost toonumerous to list.

Page 89: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

RESPONSE TO IMPACTS IN AXIAL DIRECTION ONLARGE MOTOR WITH SLEEVE BEARINGS

Page 90: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

RESPONSE ON END BELL IN AXIAL DIREXCTIONWHILE TURNING SLOWLY AS COMPARED TO

SITTING STILL

6 TIMES AS MUCH RESPONSE WITHSHAFT TURNING ON OIL FILM

Page 91: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

RESPONSE TO IMPACTS IN AXIAL DIRECTION ONMOTOR WITH SLEEVE BEARINGS WHILE SHAFT

IS STATIC AND TURNING

Page 92: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

4: If excessive clearancesare suspected in a machinewith sleeve bearings, thenput a dial indicator on theshaft and do a lift check.

Page 93: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

SIGNAL PROCESSING

Page 94: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1: When performing resonancetests, do not use the Hanning orany similar windows, unless theimpact and response signals aredelayed to move them to thecenter of the time block. Sincethe response is maximum afterthe impact, this data must bemoved away from the edge ofthe time block where it would bedestroyed or severely attenuatedby the Weighting factor. Use of aUniform Window does notrequire a delay, because it doesnot attenuate the signal at thebeginning or end of the timeblock.

Page 95: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

372 HZ IS CLOSE TO360 HZ SCR FIRING

FREQUENCY

A customer had tested thismotor and did not find aresonance near 360 HZ.

They had used a Hanningwindow that destroyed thedata at the beginning of the

time block.

Page 96: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: The FFT is a batch process. Impacts or

other transient processes which occur in time frameswhich are short compared to the period of the analysistime block result in significant amplitude errorsregarding peak values. Therefore a user shouldalways take a look at the time domain whentransients are present. THIS IS WHY IT ISEXTREMELY IMPORTANT TO LOOK ATACCELERATION TIME WAVES WHEN IMPACTSARE PRESENT

Page 97: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: A simple way to determine a mode shape isthe take a transfer function at equally spacedpoints along the structure, then plot thenormalized amplitudes of the imaginarycomponents above the location of the testpoints on a scaled plot. Note that this works foracceleration and displacement data. If velocitydata is used, plot the normalized values of thereal part of the transfer function.

Page 98: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

MODE SHAPE OF 480 CPM MODE

Page 99: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

4: Beware of fat peaks- A fat peakcan be the result of a beat,modulation, speed changes or aresonance being excited.

Note that the amplitude of the peakin the spectrum can be significantlyin error as compared to the actualpeak value. This is because theenergy is spread out over severalcells. Supplied by Jack Frarey.

Page 100: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

5: When attempting to measurethe loc decrement to determine thedamping, if the desired frequencyis low, then if possible, use analogintegration so the time plot will bein displacement. This techniquelowers the influence on the timeplot of the higher frequencieswhich might dominate if anaccelerometer is being used.

Page 101: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

NATURALFREQUENCY

1770 CPM

N0=.0914, N10=.027

PSI=1/10*1/(2*PI)*ln(.0914/.027)=.0194

Q=1/(2*.0194)= 25.7

Time decay in g’s. Notethe presence of higherfrequency in time plot.

Page 102: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

AMPLIFICATION FACTOR CALCULATION USING LOGDEC APPROACH WITH ANALOG INTEGRATION

Time plot is indisplacement. Note thatno high frequencies are

present.

Page 103: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

6: Long time samples are useful when lowfrequency beats are present.

7: Long time samples are also useful whenrapid transients occur on a random basis.

8: Long time samples are bad when thefrequency is shifting.

Page 104: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Vibratory conveyors that were shaking houses ½mile from foundry. Calculated Peak-Peak 4.1 mils.Actual P-P over 7 mils. People feel much higherlevels than spectrum indicates.

DALT - DINING ROOM TABLE AT RHODES

DINING TBL-E-W EAST WEST

ROUTE SPECTRUM23-JUN-99 13:11:40

OVRALL= 4.15 D-DGP-P = 4.13LOAD = 100.0RPM = 360.RPS = 6.00

2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5

0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

Frequency in Hz

P-P

Dis

pla

cem

en

tin

Mils

4.4

0 4.5

54.7

1

4.9

45.0

7

ROUTE WAVEFORM23-JUN-99 13:11:40P-P = 4.31PK(+) = 3.93PK(-) = 3.96CRESTF= 2.60

0 2 4 6 8 10 12 14 16 18 20

-6

-4

-2

0

2

4

6

Time in Seconds

Dis

pla

cem

en

tin

Mils

Time:Ampl:

8.8483.931

Long time block, in thiscase 20 seconds,allows time for all

components to phasetogether so worsecase can be seen.

Page 105: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

9: If a signal is clipped, then this effectively introduces a DC shiftinto the data. This can prove disastrous if the data is then

integrated. Example:A high output accelerometer was used to measure vibration on apump. The signal was integrated into velocity. Unfortunately, thepump cavitated. The cavitation overloaded the accelerometer’s

electronics introducing a DC shift. The overall output of the pumpthen fictitiously read several inches per second and all the alarms

went off. Source: Jack Frarey

Page 106: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

10: When trying to separate two closely spacedsignals, remember that the frequency resolution is notthe number of lines divided by Fmax. It is not eventhe number of lines divided by Fmax X the weightingwindow factor. It is actually the number of linesdivided by Fmax X the widow factor X 2. If the factorof 2 is not included, then the modulating effect of thewindow function can create false sidebands that aremistaken for actual frequencies. Source: Jack Frarey

Page 107: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

A BEAT THAT COMPLETES ONE CYCLE DURING TIME BLOCK-CENTERED IN BUFFER

Amplitude 1.46 units

Peak motion 1.69 Units from timeplot

Page 108: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

A beat with one cycle in time buffer-Peak Amplitude atbeginning and end of buffer-minimum at center

Amplitude .6 units.Note false resolutioncaused by HanningWindow.

Actual peak motion 1.69 units

Page 109: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

11: When viewing a spectrum and time plot, thereare often times when things do not seem to add up.For instance, the spectrum may show low levelsand generate no concern. On the other hand, thetime plot might show very high amplitudes. Onereason for this is the fact that the time based datawas sampled at a frequency that is equivalent to2.56 Fmax. According to the Nyquist sampling law,this is sufficient to pick up frequencies at 1.28Fmax. This means that the time data can seehigher frequencies than are displayed in thespectral plot. Example: When viewing data from amotor, the spectrum showed nothing over .03in/sec. In the acceleration time plot levels as highas 8 g’s were observed. The maximum frequencywas set at 1000 HZ. The actual problem was thatthe 1750 RPM motor had rotor bars generating asignal just above 1000 HZ . The vibration wasvisible in the time plot, but was beyond the 1000 HzFmax, so it was not seen in the spectrum.Solution: When this type of situation isencountered, then increase the Fmax.

Page 110: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

12: A similar discrepancy can occur when analogoverall levels are compared to spectral data or overallvalues computed from the spectral data. The analogoverall value includes energy all the way out to say20000 Hz. The digital overall value only includes thosecomponents that are in the calculated spectrum. If thereis a discrepancy, then as stated in the previous topic,increase the Fmax to determine what is causing thedifference.

Page 111: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

RESONANCE1: When performing a resonance test,if a peak shows up at the frequency ofinterest, but the phase shift is small,then this is an indication that there isa resonant component that may be

located some distance from where thetest is being performed. For instance

if a section of pipe is tested for aresonance and there is a peak, but asmall phase shift, then there might befor example a nearby control valvethat is resonant. If the control valveitself is tested, then the normal 180

degree phase shift would be presentwhen its natural frequency is excited.

Page 112: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

RESONANCE TEST ON VERTICAL PUMP WHEREPUMP IS RESONANT AT RUNNING SPEED AND

RESPONSE WAS MEASURED ON MOTOR

Note the presenceof a small peak at3600 and small

phase shift

Page 113: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

RESPONSE IS MEASURED ON PUMP

3600 CPMRESONANCE

Page 114: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: When anchor bolts or rebar break under thesurface of concrete, this reduction in stiffnesscan alter the natural frequency and result inresonance problems. Case History- Threeidentical pumps were installed. On one pump,the 120HZ vibration on the motor was severaltimes higher than on the other two. When themotor positions were swapped, the problemalways occurred in the same location, indicatingthat problem was location related instead ofmotor related. A resonance test showed thatthere was a resonance near 120 Hz at thelocation with the high levels, but not at the othertwo locations. When the foundation was brokenup, it was discovered that the re-bar was brokenin the foundation that had the problem.

Page 115: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3. When doing impact tests, beware oftrying to get too much resolution. Forinstance, if you have a vertical pump thathas a suspected resonance at 10 HZ andyou choose a 100 HZ Fmax with 800 lines ofresolution, then the sample time is 8seconds. If the response decays away in 1second, then there will be 7 seconds ofnoise present versus 1 second of good data.The phase shift will look rough and thecoherence will be low. If on the other hand a500 Hz Fmax and 400 lines of resolution arechosen, then the sample time will be .8seconds. In this instance, the data will bemuch cleaner.

Page 116: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

4: The opposite situation could also betrue. If a lightly damped component is

excited then it may continue to ring clear tothe end of the time block. This can cause

problems when the FFT is performedbecause a discontinuity is introduced. Inthis case an exponential weighting factormay need to be introduced to drive the

response to zero and eliminate thediscontinuity. It has to be noted that if a

log decrement calculation is made on datathat has been modified by an exponentialweighting factor that the answers will be

wrong.Solution- Use exponential weighting factor

when viewing spectrum, but shut it offwhen viewing the time domain.

Page 117: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

5: A convenient way to locate support beams in a floor is to perform animpact test and look for a reversal in the direction of the imaginarycomponents.

Page 118: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

INDUCTION MOTOR CURRENTTESTING

Page 119: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1: When taking spectrum of the current, measure theratio of the lower number of poles times slip frequencyside band in dB to the level of the line frequency currentin dB . If there are no other recommendations, then usethe 54-45dB rule. If the side band is more than 54 dBbelow the line frequency signal, then the rotor isprobably OK. If the side band is less than 45 dB belowthe line frequency, then the rotor is probably bad.

Page 120: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

NOTE DATE IS1982

Page 121: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 122: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 123: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 124: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 125: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 126: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 127: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 128: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: Beware of cast aluminumrotors. Cast aluminum rotorswill sometimes have voidsthat will cause false positivesof the above described sideband test. When in doubt,test the motor over severalstarting cycles to determine ifthe level is stable or gettingworse.

Page 129: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: Pole modulation- If the number of spiders inthe rotor equals the number of poles, the currentwill modulate and look just like a broken rotor baris present. The way to tell if this is the case is to vary the load

on the motor. If it is pole modulation, then the side band ratio willbe higher at low load. If there is an actual broken bar problem, theopposite will be true. When a broken bar is present the degree ofmodulation will increase at higher loads. Case History- A powerplant had 8 pole motors on its FD fans. Every year a currentspectrum test was performed to identify broken rotor bars. It wasnoted both FD fan motors had indications of what appeared to bebroken rotor bars. The interesting thing was that the modulationwas less at high loads than at low loads. The cause of themodulation turned out to be pole modulation. The motors ran formany years and never had any problems, even though an expertsystem program kept calling them out as having broken rotorbars.

Page 130: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

4: Mechanical Modulation- Beware of motor current testing, ifthere is a speed reduction gearbox coupled to the motor. Lowspeed mechanical modulation will sometimes cause the currentto modulate thereby mimicking a rotor problem. Alwaysdetermine the motor speed to within 1 RPM, then calculate thenumber of poles times slip frequency side band frequency. Ifthere is any variation in the calculated versus the actualfrequency, then suspect mechanical modulation. Examples:

Case 1: Coal barge unloader. The rate at which the buckets duginto the barge of coal was exactly the number of motor polestimes the slip frequency making it impossible to perform anaccurate rotor bar analysis.

Page 131: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Case 2- In large coal mills, therate at which the rolls pass overthe rotating table is very close tothe number of poles times theslip frequency. This has resultedin several mill motors beingfalsely called out as having badrotor bars.

Page 132: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Case 3- A coal conveyor motor wascalled out as having rotor problems. Itwas discovered that the speed of theoutput gear was close to the number ofpoles times the slip frequency. Theproblem was with the gear instead of withthe motor rotor. Very accuratelydetermining the speed of the motorallowed a calculation to be made thatdetermined that the modulatingfrequency was a match with the gearinstead of the number of poles times theslip frequency.

Page 133: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

5: Two pole and four pole motors with brokenrotor bars will often cause number of poles timesslip frequency side bands in both the current andvibration spectra. Higher pole lower speedmotors, particularly those driving high inertialoads will create number of poles times slip sidebands in the current spectra, but will in manycases not cause them to appear at all in thevibration spectra.

Page 134: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

INDUCTION MOTORSVIBRATION TESTING

Page 135: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1: Rotor eccentricity- An eccentric rotor will of course result inunbalance. If the rotor is balanced, there can still be a problem of arotating deviation in the air gap. This causes unequal pull on therotor as the magnetic poles pass the rotating gap deviation. Thisoccurs at the number of poles times the slip frequency, which is thesame frequency that is generated by a broken rotor bar. Note thatin neither case will this low (usually less than 1.5 HZ) frequencyshow up in the spectrum, but they can both appear as side bands ofrunning speed in the vibration spectrum. The way to tell thedifference between an eccentric rotor and broken rotor bars is toobtain a current spectrum. A broken rotor bar will generate no.poles times slip frequency around the line frequency in the currentspectrum where as the eccentric rotor will not.

Page 136: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Distinct No.Poles X slipsidebands in

vibrationspectrum

Currentsidebands are

over 60dBdown

ECCENTRIC ROTOR

Page 137: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 138: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: New highefficiencymotors aremuch moresusceptible tosoft foot thanolder heavyframe motors.

Page 139: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: Large 2 pole motors that have shorted laminations can have very highlevels of thermal vectors that cause the amount of unbalance to vary withload. Case History- A 4000 Hp motor in a power plant was overhauled.After the overhaul, the motor vibration would increase and the bearingswould be destroyed. The plant sent the motor back to the motor shop for

balancing, but upon return, it again wiped out the bearings.The motor was then sent to the manufacturer to be balanced in a high

speed balance pit. Upon return, it again wiped out the bearings. Solution-Proximity probes were installed on the motor and the amplitude and

phase were monitored as the motor was loaded. The motor had an 8 milthermal vector. The motor was compromise balanced and ran for severalyears. It was discovered that the original motor shop that overhauled themotor had dropped the rotor and damaged some of the laminations. Theeddy current heating in the shorted laminations had caused the rotor to

bow thereby causing the large thermal vector. If this condition issuspected, induction heating the rotor then looking at it with an infrared

camera will allow the hot spots to be seen.

Page 140: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 141: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

DC MOTORS

Page 142: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1: D.C. MOTORS- The spectrum of the current toa D.C. Motor can be used to find problems withSCRs or firing circuits. The rectifier input supplyfrequency (50 or 60 HZ) times 6 for 3 phase fullwave rectifiers will normally be present in thecurrent spectrum. When 1/3 or 2/3 of the firingfrequency is present, it indicates failed SCRs orfiring circuits. It is much simpler to look at thecurrent spectrum or current waveform than to try tosee the problem with vibration. Vibration is asecondary effect reflecting the problem which isactually of electrical origin.

Page 143: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

½ HALF WAVE RECTIFIER

Page 144: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 145: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

WHAT DOES THECURRENT PATTERN OF ANORMAL DRIVER LOOK

LIKE

Page 146: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

6 PULSES IN 1/60th OF A SECOND

Page 147: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

WHAT DOES THEWAVEFORM OF A BADDRIVE LOOK LIKE ?

Page 148: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

BAD

SCR’S

GOOD

SCR’S

120 HZ

GOOD

BAD

Page 149: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

F E B R U A R Y 1 8 , 1 9 9 8V IS Y F A N P U M P D R IV E2 5 0 A M P L O A D

W H E N S C R ’S W E R E R E P L A C E D , T H E W A V E F O R M A N D S P E C T R U M R E T U R N E D T ON O R M A L .

N O T EV A R IA T IO N INH E IG H T O FP E A K S .

1 2 0 H Z isP R E S E N TA L O N G W IT HS O M E 6 0 H ZC O M P O N E N T

3 6 0 H Z S C RF IR IN GF R E Q U E N C Y

Page 150: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: D.C. MOTORS- The current spectrum from a D.C.Motor can also be used to find tuning problems with

D.C. Drives. Improperly tuned drives will producefrequencies at the oscillation rate of the instability.These frequencies can also appear in the vibration

spectra and are very difficult to analyze since they donot have a mechanical origin. These oscillation

frequencies are unpredictable. They are a result of theinteraction between the rotating inertias of themechanical components, the torsional stiffness

of the shafts and the tuning of the electrical controlsystem. If a completely unexplainable frequencyappears on a drive, then it may well be due to this

complex interaction.

Page 151: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

BAD TUNING, WHERESPEED IS CONSTANTLYMOVING UP AND DOWN.

Page 152: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 153: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

NORMALSPECTRUM

ONLY 360 HZ

BADLY ADJUSTED

DRIVE

OVERHEATING 180DEG.

F

Page 154: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

DRIVE INSTABILITY

AFTER TUNING

Page 155: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

SOMETIMES THEPROCESS CAN CAUSE THE

DRIVE TO APPEARUNSTABLE

Page 156: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: DC MOTORS- Unknown frequenciesin the spectrum of the current going to aDC drive can originate from othermechanical equipment in the drive train.Case History- The current on a couchroll of a paper machine had an unknowncomponent in its spectrum. It turned outto be the vane pass frequency of the fanpump located several yards away in thebasement. The fan pump was causingpressure pulsations in the head boxthat caused the paper to be deposited invarying thicknesses. As the thickermaterial passed over the vacuum rolls,this caused the tension to increasewhich changed the tangential force onthe couch roll which in turn caused thecurrent draw to the couch roll tomodulate at that rate.

Page 157: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

COUCH ROLL DRIVE

12.5 HZ VIBRATION DID NOTMATCH ANYTHING

Page 158: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

12.58 HZ SIGNAL MATCHES VANEPASS OF FAN PUMP

Page 159: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

HEAD BOX

1:FAN PUMP GENERATES PRESSURE PULSATIONSAT RPM TIMES NO. OF VANES.

2: MATERIAL IS UNEVEN FROM PULSES

3: VACUUM ROLL PULLS DOWN ONFELT.

4: TENSION VARIES IN FELT

5: DRIVE ROLL VIBRATES AT VANE PASSDUE TO CHANGES IN TENSION AND MOTORCURRENT VARIES AT SAME RATE.

Page 160: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

VARIABLE FREQUENCY DRIVESCAN CAUSE PREMATURE

BEARING FAILURES

Page 161: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1: Line length is a factor in voltage spikes. Rapid switching of inverters causesvoltage spikes that can be amplified by longer line lengths

2: Solutions to minimize bearing failures that result from VFD problems.A: Lower the firing frequency of the inverter The switching speed is a critical

factor in regards to VFD drive problems. “When VFD drives were firstintroduced in the eighties, there were few field problems. The carrier

frequencies were generally below 2.5 kHz. As the switching frequenciesincreased, the number of problems also went up

B: Keep the line length between the inverter and the motor as short aspossible.

C: Insulate bearings- Both bearings need to be insulated. In addition, thecoupling must also be insulated or the current can travel through the coupling

to the driven unit’s bearings and then to ground.

Page 162: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

D: Shaft Grounding- Grounding the shaft with carbon brushesallows the potential to travel to ground. The problem with this

approach is that brushes need to be maintained. If thebrushes wear out, then the current will again start flowing

through the bearings.E: Conductive grease- Conductive grease allows the currentto drain off rather than building up to a destructive potential.

The downside to conductive grease is that it has beenreported that bearing life is not as long as with standard

grease.F: Ceramic Bearings- Since ceramic bearings are

nonconductive, they are another method of achievingelectrical isolation between the rotor and the frame. Do not

forget to insulate the coupling.G: Output filters- These devices filter out the unwanted high

order harmonics.H: Isolation Transformers- “An isolation transformer with a

delta primary and a wye secondary will greatly reducecommon mode voltages within a drive and motor system.

Page 163: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

GEARBOXES

Page 164: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1: Gear boxes which have common prime factorsbetween the teeth of intermeshing gears canproduce sub harmonics of the tooth meshfrequency.

Case History- A large drag line gear box had 1in/sec of exact ½ tooth mesh vibration. It wasdiscovered that there was a common prime factorof two on the pinion and bull gear. The pinionwas worn badly . When the pinion was replaced,the ½ tooth mesh vibration disappeared.

Page 165: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: Side bands are often the result ofmodulation by a defective componentin a gear box. However, beware ofmaking hasty conclusions whenanalyzing a planetary gear box, wheremodulation naturally occurs due to acontinually varying transmission pathcaused by rotation of the planetarygears. Jack Frarey

Page 166: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: Non-linearmodulation resultingfrom looseness cangenerate families ofside bands. Theworse the looseness,the greater thenumber of sidebands.

Page 167: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then
Page 168: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

TORSIONAL VIBRATION1: When making torsional measurements, pulse trains need to be placed on

anti-nodes and strain gauges installed on nodes.2: As a synchronous motor comes up to speed, the torsional stimulation willstart out at 120 HZ and then drop off in frequency as the motor comes up to

speed.3: It a torsional natural frequency needs to be altered, then the most likelyplace to make a modification whether it be stiffness or damping is in the

coupling.

Page 169: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

FANS

Page 170: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1: Always take an axial reading on the bearing that absorbs the thrust.

Page 171: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: If a fan is mountedon isolation springs,then lock up theisolators prior tobalancing.

Page 172: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: On large sleeve bearing fans, excessive motion of the shaft can bethe result of the plunger hold down bolts being loose. This conditioncan be picked up by either a shaft stick reading or a proximity probe.The casing level may be moderate, but the shaft motion can besevere. For instance, there may be three mils of vibration on a largefan’s bearing housing and maybe 15 mils on the shaft. If the bearingclearance is only .008” then it is a good bet that the bearing is movingwithin the housing. Tightening up the plunger bolt will raise the casingmotion and reduce the absolute shaft motion. Once this is done, itwill be possible to balance the fan. In the case where the bearing canmove within the housing, the system is highly nonlinear and balancingis almost impossible.

Page 173: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

4: Large airfoil blade fanshave hollow blades. Theseblades can fill with dust oreven worse with waterwhen they are pressurewashed.

Page 174: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

OIL WHIRL

Page 175: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Oil Whirl

1: If oil whirl occurs, check bearingclearances, oil temperature and

alignment. Any of these can causea marginal system to whirl. If these

simple field fixes do not work, then call a bearingexpert.

There are too many things involved in bearing designto try to do it yourself.

Page 176: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: Oil whirl will remain oil whirl until themachine reaches a speed of twice therotor’s natural frequency at that point itcan turn into oil whip. Even if the speed isincreased, the whip frequency will remainlocked in at the shaft critical speed. ( notethe critical speed will change slightly asthe speed increases due to oil filmstiffness and gyroscopics that changewith speed).

Page 177: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

LOW STIFFNESS PROBLEMS

Page 178: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

TROUBLE BREWINGEXPANSION JOINTS PRESSURE PULSATIONS

Page 179: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1: Beware of expansion joints when dynamic pulses arepresent. Also beware of long bolts holding expansion boltstogether. Expansion joints have very low stiffness, so smallpressure pulsations can result in large axial movements. Longbolts can have low stiffness values. K=EA/L If L is big, thenK is small. The combination of a large expansion jointrestrained by long bolts can result in very high levels ofvibration if pressure pulsations are present. Case History - Apipe in a refinery had over 2.3 inches per second of vibration at4500 CPM on its end cap which was mounted past anexpansion joint. Pressure pulsation from throttling by a valvecaused high amounts of motion due to the large area (1075square inches) on which the pulses acted combined with 20 ft.long restraining bolts that had low K values.

Page 180: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

WHY AM I IN THISBUSINESS?

Page 181: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

SOLUTION

• A 37” pipe has an area of 1075square inches.

• Stiffness of bolts is EA/L

• Partially closed butterfly valve wasgenerating broad band noise thatcaused pipe to resonate.

• Missing baffle allowed pressurepulsations to move end cap.

Page 182: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

MISSING COMPONENT

BAFFLE HAD BEENREMOVED FROMTHIS LOCATION

DURING OUTAGE

Page 183: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

IMPORTANT POINTS

• 1: Large areas can generate largeforces

• 2: Expansion joints allow those largeforces to generate high levels ofvibration

• 3: Long bolts are not very stiff

• 4: Do not remove components youdo not understand. Just because it isfull of holes does not mean that it isnot needed.

Page 184: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2: Beware of large thin surfaces that are subject topressure pulsations. Case History- A 6’ by 8’window was vibrating excessively in a largebuilding. The thinness of the window meant that itsstiffness was very low. This in combination with itslarge area combined to produce large amounts ofmovement as a result of pressure pulsations from aloose heat exchanger coil that was vibrating in aduct feeding the atrium of the building.

Page 185: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

PUFFS OF AIR

AT AN OFFICE BUILDING WITH AN ATRIUMWINDOWS IN THE LOWER OFFICES WERE VIBRATING

7 MILS OF VIBRATIONAT 240

CYCLES/MINUTE

Page 186: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

BUILDING LAYOUT

OPEN ATRIUM

FAN ROOM FAN ROOM

VIBRATINGWINDOW

Page 187: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

LOOSE COIL

FAN

COIL WAS SUPPORTED BY ONLY SUPPLY ANDRETURN PIPE. NATURAL FREQUENCY 240 CPM.

DISCHARGE TO ATRIUM

VIBRATING COIL ACTED LIKE6X6 FOOT SPEAKER ELEMENTFIVING OFF LOW FREQUENCY

PRESSURE PULSES

Page 188: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: Even worse- Beware of large thin surfaces that have a naturalfrequency that equals that of a pressure pulsation. Case history-A large circular window had a natural frequency of 33 Hz whichwas the firing frequency of newly installed high efficiency boilers.The exhaust stack from the boilers was located only a few feetfrom the window. The window had extremely high levels ofmovement which in turn generated a very high level of 33Hzsound in the building which annoyed the people who wereoccupants of this large sub-woofer of a building. To makematters even worse, the stair well leading up to the window wasexactly one wave length of the 33 Hz signal. Solution- Exhauststacks were lengthened to a point well above window.

Page 189: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

SOUND PROBLEM FROMFURNACE

At a university, the new alumni office was experiencing highlevels of both sound and vibration. The problem was traced tonew pulse furnaces that had been installed.

Stacks from pulse furnaces

VIBRATION AND SOUND LEVELS IN ROOMSNEXT TO WATCHTOWER WERE HIGH.

Page 190: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

LAYOUT OF BUILDING

Page 191: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

BAD LUCK

TEST - I.U. FOUNDATION BUILDINGI.U. BLDG -P01 POINT 1

Route Spectrum11-JAN-00 09:29:40

OVRALL= .9600 V-DGPK = .9550LOAD = 100.0RPM = 3600.RPS = 60.00

0 60 120 180 240 300

0

0.2

0.4

0.6

0.8

1.0

Frequency in Hz

PK

Velo

cit

yin

In/S

ec

37.9

4

Freq:Ordr:Spec:

37.81.630.751TEST - I.U. FOUNDATION BUILDING

I.U. BLDG -P01 POINT 1

Analyze Spectrum11-JAN-00 14:00:30

PK = .4147LOAD = 100.0RPM = 3600.RPS = 60.00

0 100 200 300 400 500 600

0

0.05

0.10

0.15

0.20

0.25

0.30

0.35

0.40

Frequency in Hz

PK

Ve

loc

ity

inIn

/Se

c

Freq:Ordr:Spec:

32.50.542.273

FIRINGFREQUENCY OFFURNACE IS 33

HZ

Response of 3 footdiameter window in

watch towerto impact 33 hz.

Page 192: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

More Bad Luck

Natural frequency of large windowequals pulse frequency creating a

gigantic subwoofer 3 feet indiameter.

Height of tower closelymatched wavelengthof problem frequency

Page 193: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

SOLUTIONRaised height of stacks to well

above window

INSTALLEDBETTER

MUFFLERS

Page 194: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

TEST TECHNIQUES

Page 195: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

1: Don’t forget to use a strobe light- In the past Strobe lights wereused frequently due to fact that they were utilized to obtain the phasereadings. Their use will almost certainly remain relevant as long asthere is rotating equipment. Strobe lights are still the best way tolooks at belts or to see if the elements in a coupling have cracked.They can also be used to determine the size of a key or locate akeway or look at balance weights. Strobes that are triggered by thevibration signal are useful to freeze the rotating element that is

causing the vibration. Case History- A paper mill was going toremove a roll to get it balanced. The frequency of the vibrationmatched the frequency that the group of wire rolls wasvibrating at. This was determined by a calculation of the RPMof the roll base upon the roll diameter and the product’s speed.A strobe fired by the vibration was used to verify that the rollwas the source. To everyone’s surprise, the strobe froze adifferent roll. It turned out that the drawings had incorrectdiameters. The strobe didn’t lie or care about drawings, it just frozethe correct component.

Page 196: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

2. Phase locked loop strobes with a phase delayare very useful for providing a once perrevolution output that can be used for balancing.The use of a phase lock strobe can make itunnecessary to stop a machine so that photo-reflective tape can be installed. This can savehours of time on a balance job, particularly whena machine is limited to the number of starts thatis can go through.

Page 197: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

3: Don’t forget shaft sticks- While itwould be great to have proximity probeson every machine to measure shaftmotion, in the real world this is just notthe case. A shaft stick can measure theabsolute motion of a shaft. Note, beforeusing a shaft stick, use the strobementioned in point 1 to make sure thereis not a keyway where the shaft stick isto be placed against the shaft.

Page 198: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

4: It is handy to have an analog integration box for certain tests thatallow the time waveform from an accelerometer to be viewed indisplacement. Case 1- Two large vertical pumps had resonant

frequencies near their operating speed. One of the calculations thatwere needed was to determine the damping so the amplificationfactor could be obtained. By using an analog integrator, the time

waveform of the low frequency response could be directly measuredand used for the log decrement calculation. Case 2- Foundries havelow frequency vibratory conveyors that move the castings throughout

the plant. These often cause vibration problems beyond the plantboundaries that result in complaints by neighbors. These conveyors

which operate around 5 HZ move in and out of phase with oneanother causing the vibration levels to vary significantly with time. If aspectrum is taken of one snapshot in time, the overall value is hard toobtain. It is much easier to look at the motion in the time domain over

a period of several seconds. The maximum peak to peak motionsthat people offsite are feeling can them be easily determined.

If analog integration is available, then a long term time plot of themotion in displacement is very useful in determining the maximum

levels of motion that are being experienced.

Page 199: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Vibratory conveyors that were shaking houses ½mile from foundry. Calculated Peak-Peak 4.1 mils.Actual P-P over 7 mils. People feel much higherlevels than spectrum indicates.

DALT - DINING ROOM TABLE AT RHODES

DINING TBL-E-W EAST WEST

ROUTE SPECTRUM23-JUN-99 13:11:40

OVRALL= 4.15 D-DGP-P = 4.13LOAD = 100.0RPM = 360.RPS = 6.00

2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5

0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

Frequency in Hz

P-P

Dis

pla

cem

en

tin

Mils

4.4

0 4.5

54.7

1

4.9

45.0

7

ROUTE WAVEFORM23-JUN-99 13:11:40P-P = 4.31PK(+) = 3.93PK(-) = 3.96CRESTF= 2.60

0 2 4 6 8 10 12 14 16 18 20

-6

-4

-2

0

2

4

6

Time in Seconds

Dis

pla

cem

en

tin

Mils

Time:Ampl:

8.8483.931

Page 200: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

5: A microphone with an analog output that can be used tosupply a signal to a spectrum analyzer can be very usefulin the analysis of vibrations that are transmitted by the airrather than through solid material. Note that mostmicrophones have a pretty severe roll of below 20Hz, sothe true pressure pulsation amplitude may not be presentat a lower frequency. The spectral data can still howeverbe used to identify the problem.

Page 201: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

6: If a temporary shaft rider is needed, then Ebelon rodworks well. Ebelon is graphite impregnated Teflon and itwill last a significant amount of time in contact with areasonably smooth shaft.

Page 202: Nuggets of Gold - Vibration 2010.pdf · Nuggets of Gold • Troubleshooting ... Case History 1- The phase on a turbine bearing ... • Following bolt tightening, the fan was then

Some Final ThoughtsA vibration analyst must understand the

basic laws of physics (F=ma and F=kx andthat dynamic stiffness is different than

static stiffness). They must alsounderstand signal processing so they do

not get bad data. They must have anappreciation for human nature so they can

get the truth out of mechanics andoperations personnel. They need to

understand how fans motors, gear boxes,compressors, pumps and turbines work.

But most of all they must be able to put allthese things together under adverse

conditions and then be able to think clearlyand arrive at a logical conclusion.