46
Nuclear Innovation Analysis: Landscape Review September 2013 Produced for the Department of Energy & Climate Change Innovation Delivery Team by The Madano Partnership and Integrated Decision Management Ltd

Nuclear Innovation Analysis: Landscape Review September …...2005 • Nuclear Decommissioning Authority set-up taking strategic responsibility for UK’s nuclear legacy • British

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • Nuclear Innovation Analysis: Landscape Review

    September 2013

    Produced for the

    Department of Energy & Climate Change

    Innovation Delivery Team

    by The Madano Partnership and

    Integrated Decision Management Ltd

  • By The Madano Partnership

    and Integrated Decision Management Ltd

    Nuclear Innovation Analysis:

    Landscape Review

    Produced for the Department of Energy & Climate Change

    Innovation Delivery Team

    September 2013

  • Nuclear Innovation Analysis:

    Landscape Review

    Produced for the Department of Energy & Climate Change

    Innovation Delivery Team

    September 2013

  • Nuclear Innovation Analysis: Landscape Review

    Department of Energy and Climate Change

    Contents

    Chapter

    1. Introduction and Background to Study _____________ 1

    2. UK Nuclear Innovation Landscape _________________ 2

    3. Clarifying Assumptions and Project Development ___________________________ 7

    4. Stakeholder Research and Research Findings ____________________________________ 10

    5. Discussion of Findings _________________________ 12

    6. Cost Benefit Analysis __________________________ 21

    7. Conclusions and Recommendations ______________ 30

    Appendices:

    I. Bibliography _____________________________________________________ 32

    II. Study Participants ________________________________________________ 33

    III. Interview Guide __________________________________________________ 34

    IV. Challenges/Barriers derived and rated by workshop participants _____________________________________________ 36

    V. Acronyms _______________________________________________________ 37

    VI. UK Fuel Market Share from Oxford Economics Report _____________________ 38

  • Department of Energy and Climate Change 1

    Nuclear Innovation Analysis: Landscape Review

    The Madano Partnership (Madano) and Integrated Decision Management Ltd (IDM), were commissioned by the Department of Energy and Climate Change (DECC) to undertake a “Nuclear Energy Innovation – Investment Analysis”1.

    DECC’s Energy Innovation Delivery Team has a remit to

    invest in technologies that will provide significant benefits

    to the UK in terms of the secure supply of renewable and

    low carbon energy, and require that investment decisions

    are evidence-based to ensure that public money is used

    in the most cost effective manner. Previous analysis in the

    nuclear sector had indicated that investment across the

    nuclear life cycle could provide benefits worth between

    £5-40bn to 2050 and £5-90bn to 21002.

    DECC had prioritised a number of sub-areas where

    there was considered to be an early need for investment,

    identified as themes in this earlier analysis. Areas were

    prioritised based on the potential benefit resulting

    from investment in innovation that were within DECC’s

    Innovation programme remit. These themes included:

    i. Innovative Fuel Formsii. Capex – Components

    iii. Capex – Building Materialsiv. Capex – Construction, Installation and

    Commissioningv. Waste Management, Reprocessing and Storage (in

    relation to historic, existing and future systems)vi. Innovation in the Regulatory Process

    To ensure optimal benefit is derived from any future

    investment decisions, DECC wished to undertake further

    analyses within each of these sub-areas to define specific

    R&D programmes and/or capital investment that will

    unlock benefits for the UK. Early project meetings clarified

    that the area of study was to start with Technology

    Readiness Levels (TRLs)3 of around 4, with projects to take

    the TRL to around 8. The innovation should be deployable

    in 10-20 years, a much shorter time horizon than other

    studies which extended to 2050 and beyond.

    This shorter time horizon emphasised that reviewing

    the current organisation of the nuclear industry in the

    UK would enable innovation to be identified “starting

    from where we are now”, leading to an understanding

    of the opportunities, challenges and barriers faced

    by potential innovators operating in the real nuclear

    world of 2013. The Madano-IDM project therefore

    centered on engaging with a wide range of actual and

    would-be innovators, and with their actual and potential

    customers, to map both the innovation landscape and

    the marketplace in which they operate as well as the

    opportunities and possible barriers, including cost

    benefit analysis of investing in potential areas.

    Chapter 1.

    Introduction and Background to Study

    1 Tender No: TRN 500/10/2012

    2 See Technology Innovation Needs Assessment (TINA) Nuclear Fission, Summary Report, Carbon Trust, April 2013 at www.lowcarboninnovation.co.uk/document.php?o=16

    3 Technology Readiness Levels (TRLs) are a technology management tool that provides a measurement to assess the maturity of evolving technology. Typically, TRL 1 is where Basic Principles have been observed and reported; TRL 4 is where Technology basic validation has been made in a laboratory environment through to TRL 9 where Actual Technology has been qualified through successful mission operations. See for example “Technology Readiness Levels (TRLs) in the Project Lifecycle”, Ministry of Defence website, www.aof.mod.uk/aofcontent/tactical/techman/content/trl_applying.htm

  • 2 Department of Energy and Climate Change

    Nuclear Innovation Analysis: Landscape Review

    In order to explore the potential opportunities for the UK it is important to understand first the landscape in which UK nuclear innovation now operates. It is instructive to appreciate how the industry has evolved into its current state, and to be clear about the structural benefits and barriers presented by the 2013 nuclear industry in the UK.

    UK Nuclear Industry Evolution

    The UK nuclear power landscape evolved from the 1950s

    early dominance of the national imperatives to become

    a nuclear weapons state, to a structure reflecting the

    ‘flowsheet’ of nuclear energy generation, namely:-

    1. United Kingdom Atomic Energy Authority (UKAEA) – an R&D organisation which pursued scientific progress and undertook development of reactor designs and fuel cycle concepts

    2. British Nuclear Fuels plc. (BNFL) – a manufacturing and processing organisation, spun out of UKAEA in 1971, which carried out fuel cycle operations from uranium ore concentrate to nuclear fuel, and from spent fuel to wastes, reprocessed uranium and separated plutonium

    3. URENCO – a tri-national uranium enrichment organisation set up by the Treaty of Almelo in 1971, and pioneer of the centrifuge enrichment process. It and its technology are now world-leading. This was originally organised with three nationally-owned production plants.

    4. Reactor consortia: the UK contracted out the construction of both the Magnox and AGR stations to consortia of UK engineering companies

    5. Central Electricity Generating Board (CEGB) and South of Scotland Electricity Board (SSEB) – electricity utilities which placed orders for nuclear stations and sold their electricity output.

    The Figure below shows the arrangement circa 1975.

    Chapter 2.

    The UK Nuclear Innovation Landscape

    UOCReactor

    andProcess R&D

    UKAEA

    BNFL

    PurificationReactor Design

    Pu storage

    U storageU recycle

    fuel plant designFuel Element DesignSpringfields

    Harwell

    SellafieldCapenhurst

    Risley, Culcheth

    Uranium metalproduction

    Reprocessing U,Pu SeparationUranium

    Hexafluorideproduction

    Gaseous DiffusionCentrifuge

    Uranium Enrichment

    Uranium OxideFuel

    Uranium metalFuel CEGB

    MagnoxReactors

    CEGBAGR

    Reactors

    Figure 1. The UK Nuclear Industry circa 1975

  • Department of Energy and Climate Change 3

    Nuclear Innovation Analysis: Landscape Review

    40 020 1030

    1400

    0

    1200

    0

    1000

    0

    8000

    6000

    4000

    2000 0

    UK

    Nuc

    lear

    dev

    elo

    pm

    ent

    -19

    50 -

    201

    2 &

    onw

    ard

    s

    The

    Mad

    ano

    Par

    tner

    ship

    1950

    1960

    1970

    1980

    1990

    2000

    2010

    1957

    • N

    ucle

    ar p

    ower

    ac

    cide

    nt ta

    kes

    plac

    e at

    Win

    dsca

    le

    - a

    fire

    in th

    e re

    acto

    r re

    sults

    in a

    rele

    ase

    of r

    adio

    activ

    ity

    1986

    • C

    hern

    obyl

    acci

    dent

    2011

    • Fu

    kush

    ima

    acci

    dent

    1979

    • Th

    ree

    Mile

    Isla

    ndin

    cide

    nt

    1954

    • U

    KA

    EA

    cre

    ated

    und

    er

    the

    Ato

    mic

    Ene

    rgy

    Act

    1956

    • C

    alde

    r H

    all,

    Win

    dsca

    le is

    ope

    ned

    by th

    e Q

    ueen

    1962

    - 1

    971

    • N

    ine

    full

    scal

    e M

    agno

    x po

    wer

    st

    atio

    ns o

    pen.

    Of

    thes

    e W

    ylfa

    and

    O

    ldbu

    ry

    are

    still

    oper

    atin

    g to

    day

    1980

    • To

    rnes

    s, H

    eysh

    am,

    two

    AG

    Rs

    star

    t co

    nstr

    uctio

    n

    1965

    - 1

    970

    • A

    GR

    sta

    tions

    sta

    rt

    cons

    truc

    tion

    1971

    • U

    KA

    EA

    reor

    gani

    sed

    unde

    r th

    e A

    tom

    ic

    Ene

    rgy

    Aut

    horit

    y A

    ct•

    BN

    FL is

    form

    ed to

    ta

    ke c

    ontr

    ol o

    f the

    fuel

    cy

    cle

    oper

    atio

    ns

    prev

    ious

    ly u

    nder

    take

    n by

    UK

    AE

    A

    1976

    - 1

    988

    • S

    even

    adv

    ance

    d ga

    s co

    oled

    reac

    tors

    (AG

    Rs)

    ar

    e bu

    ilt to

    repl

    ace

    Mag

    nox

    as th

    e pr

    inci

    pal

    sour

    ce o

    f nuc

    lear

    en

    ergy

    . The

    se a

    re n

    ow

    owne

    d an

    d op

    erat

    ed b

    y E

    DF/

    Brit

    ish

    Ene

    rgy

    1988

    • C

    onst

    ruct

    ion

    begi

    ns

    at S

    izew

    ell B

    , Suf

    folk

    af

    ter

    a le

    ngth

    y pu

    blic

    en

    quiry

    . It r

    emai

    ns th

    e U

    K’s

    onl

    y P

    WR

    pow

    er

    stat

    ion.

    Fur

    ther

    pla

    ns

    for

    othe

    r po

    wer

    sta

    tions

    ar

    e dr

    oppe

    d

    1974

    • S

    GH

    WR

    ado

    pted

    - tw

    o st

    atio

    ns a

    t Tor

    ness

    and

    H

    eysh

    am a

    re a

    nnou

    nced

    1978

    • SG

    HW

    R ab

    ando

    ned

    - G

    over

    nmen

    t ann

    ounc

    es te

    n ne

    w p

    ress

    urise

    d w

    ater

    re

    acto

    rs (P

    WRs

    ) are

    to b

    e bu

    ilt

    1996

    • S

    izew

    ell B

    sta

    rts

    to

    gene

    rate

    ele

    ctric

    ity,

    Brit

    ish

    Ene

    rgy

    is

    priv

    atis

    ed

    1989

    • M

    agno

    x re

    acto

    rs

    are

    with

    draw

    n fro

    m

    gove

    rnm

    ents

    ele

    ctric

    ity

    priv

    atis

    atio

    n po

    licy

    plan

    s af

    ter

    inve

    stor

    s re

    fuse

    to b

    uy d

    ue to

    th

    e hi

    gh c

    osts

    of

    deco

    mm

    issi

    onin

    g

    1994

    • Fa

    st R

    eact

    or

    Pro

    gram

    me

    aban

    done

    d

    2003

    • E

    nerg

    y W

    hite

    Pap

    er

    rele

    ased

    sta

    ting

    that

    nu

    clea

    r po

    wer

    is a

    n un

    viab

    le o

    ptio

    n

    2006

    • G

    reen

    peac

    e ap

    peal

    ed a

    gain

    st

    the

    cons

    ulta

    tion

    proc

    ess

    • Th

    e ju

    dici

    al re

    view

    fo

    und

    in fa

    vour

    of

    Gre

    enpe

    ace

    2005

    • N

    ucle

    ar D

    ecom

    mis

    sion

    ing

    Aut

    horit

    y se

    t-up

    taki

    ng

    stra

    tegi

    c re

    spon

    sibi

    lity

    for

    UK

    ’s n

    ucle

    ar le

    gacy

    • B

    ritis

    h en

    ergy

    rest

    ruct

    ured

    2018

    • Fi

    rst n

    ew

    nucl

    ear

    pow

    er

    stat

    ion

    expe

    cted

    to

    be

    oper

    atio

    nal

    2006

    • G

    over

    nmen

    t rel

    ease

    s E

    nerg

    y R

    evie

    w R

    epor

    t. C

    onst

    ruct

    ion

    on th

    e po

    licy

    fram

    ewor

    k fo

    r ne

    w n

    ucle

    ar b

    uild

    2007

    • G

    over

    nmen

    t la

    unch

    ‘The

    Fut

    ure

    of N

    ucle

    ar P

    ower

    2008

    • ‘M

    eetin

    g th

    e En

    ergy

    Cha

    lleng

    e’: A

    W

    hite

    Pap

    er o

    n N

    ucle

    ar P

    ower

    set

    s ou

    t Gov

    ernm

    ent’s

    vie

    w th

    at n

    ucle

    ar

    shou

    ld b

    e pa

    rt of

    the

    ener

    gy m

    ix•

    Offi

    ce fo

    r Nuc

    lear

    Dev

    elop

    men

    t cr

    eate

    d En

    ergy

    Act

    200

    8 ga

    ins

    Roy

    al A

    ssen

    t

    2009

    • E

    DF

    com

    plet

    es £

    12.5

    billi

    on

    take

    over

    of B

    ritis

    h E

    nerg

    y•

    Dra

    ft N

    ucle

    ar N

    atio

    nal P

    olic

    y S

    tate

    men

    t (N

    PS

    ) pub

    lishe

    d al

    ongs

    ide

    five

    othe

    r N

    PS

    s

    2011

    • E

    lect

    ricity

    Mar

    ket

    Ref

    orm

    Pap

    er•

    Nat

    iona

    l Pol

    icy

    Sta

    tem

    ents

    Num

    ber

    ofR

    eact

    ors

    Cap

    acity

    MW

    e

    Num

    ber

    ofR

    eact

    ors

    onlin

    e

    +ve

    Pol

    icy

    chan

    ge

    -ve

    Pol

    icy

    chan

    ge

    Acc

    iden

    t

    Num

    ber

    ofR

    eact

    ors

    onlin

    e

    Rea

    ctor

    sun

    der

    cons

    truc

    tion

    Pea

    kca

    paci

    ty

    00

    1

    1012

    12 8

    18

    3434

    19

    11

    4112

    160

    MW

    e

    Rea

    ctor

    sun

    der

    cons

    truc

    tion

    UK

    Nuc

    lear

    dev

    elop

    men

    t –

    1950

    –201

    2 &

    onw

    ards

    Chapter 2

    Figure 2. UK Nuclear development – 1950-2012 onwards

  • 4 Department of Energy and Climate Change

    Nuclear Innovation Analysis: Landscape Review

    Chapter 2

    Notably, the French industry was organised on similar

    lines, with the Commissariat à l’énergie atomique (CEA)

    covering nuclear research; Comurhex (Conversion Métal

    URanium HEXafluorure) producing uranium hexafluoride;

    Eurodif (European Gaseous Diffusion Uranium Enrichment

    Consortium) undertaking enrichment operations;

    FBFC (Franco-Belge de Fabrication du Combustible)

    manufacturing nuclear fuel, Framatome designing reactors,

    Cogema (Compagnie générale des matières nucléaires)

    dealing with the spent fuel, and EDF (Électricité de France)

    owning the reactors and marketing the electricity.

    As set up, both the UK and French nuclear energy and fuel

    cycle systems were essentially state owned and operated.

    Though the French system has been consolidated under

    CEA (research), AREVA (reactors and fuel cycle) and EDF

    (reactor owner/operator and electricity supply), it remains

    within the orbit of the French state.

    The UK nuclear programme has been characterised by

    changes of policy direction, stops and starts over the

    decades since its inception, as illustrated in Figure 2.

    In 1990, the non-nuclear elements of the CEGB were

    privatised as part of the then Government policy to sell off

    nationalised industries. The CEGB’s nuclear responsibilities

    were split in 1996, with the Advanced Gas Reactor (AGR)

    stations and recently-completed Pressurised Water

    Reactor (PWR) at Sizewell B forming British Energy (BE),

    while the older Magnox reactor fleet became Magnox

    Electric, which was transferred to BNFL ownership in

    1998. In 1999, BNFL acquired the Westinghouse Electric

    Company, which covered fuel manufacture, reactor design

    and construction, and reactor services, making BNFL

    a complete nuclear company – from the processing of

    uranium, fuel manufacture via reactor operation to spent

    fuel management.

    The UK Government’s 2002 Energy Review4 concluded

    that “because nuclear is a mature technology within a

    well-established global industry, there is no current case

    for further Government support” and that “the decision

    whether to bring forward proposals for new nuclear build

    is a matter for the private sector”. This view was formalised

    in “Our Energy Future – creating a low carbon economy”5

    in 2003.

    Meanwhile, the liberalisation of the electricity supply

    structures under NETA (March 2001), meant that utilities

    which were not vertically integrated with retail suppliers

    were vulnerable to reductions in wholesale electricity price.

    British Energy, which was not so vertically integrated, had

    to be rescued by Government payments in 2002, and

    ultimately was sold, becoming part of EDF Energy in 2009.

    In parallel to the declaration of a ‘no new nuclear’ future,

    there was increasing recognition of the scale and costs of

    the historic waste management legacy, where liabilities had

    been accumulating since the 1950s. The early 2000s saw

    the restructuring of UK nuclear fuel cycle operations, with

    an emphasis on waste management and decommissioning

    rather than the commercial supply of fuel cycle services.

    The establishment of the Nuclear Decommissioning

    Authority (NDA) as a Non-Departmental Public Body under

    the Energy Act 2004 therefore resulted in the transfer of 19

    sites, previously under the control of UKAEA and BNFL, and

    their associated Civil Nuclear - Liabilities and Assets formally

    back into the public sector6. BNFL had been a plc (with the

    shares held by the Government) since 1984.

    The commercial model adopted for the NDA was derived

    from the US system, and delivers its clean-up mission

    through Site Licensee Companies (SLCs) which are licensed

    to operate nuclear sites. Competitive contracts are let out to

    consortia of companies (Parent Body Organisations) who

    own the SLCs for the period of the contract.

    The Westinghouse business was sold to Toshiba in

    2006, thus removing reactor building and nuclear fuel

    manufacture from the UK’s nuclear portfolio. The decision

    to sell that business was once again due to the Government

    wanting to reduce the number of assets it actually owned,

    and also to remove any potential conflicts it could be seen

    to have with the advent of new nuclear build.

    The privatisation of the nuclear energy industry in the UK

    in the 1990s, the nuclear energy policy change between

    early 2000 and 2006, and the restructuring of the legacy

    clean-up sector has resulted in a much more fragmented

    and complex nuclear landscape, which is discussed in the

    following Section.

    UK Nuclear Landscape 2013

    The current UK nuclear marketplace can therefore be

    characterised under two main headings – activities

    associated with nuclear electricity generation and fuel

    cycle operations, and legacy clean-up.

    Legacy and current nuclear electricity generation and fuel cycle operations

    • Magnox reactors – run by Magnox Ltd, an SLC of NDA. All reactors except Wylfa 1 are shut down and have entered defueling/decommissioning. Wylfa 1 scheduled to stop generation in September 2014

    • AGRs – 7 twin-reactor stations owned and run by EDF Energy. Major work and incentive to increase planned lifetimes

  • Department of Energy and Climate Change 5

    Nuclear Innovation Analysis: Landscape Review

    Chapter 2

    • PWR – Sizewell B (single reactor) owned and run by EDF Energy. Currently scheduled to begin decommissioning in 2035, but life extension probable

    • Fuel Manufacture – Springfields Fuels Limited is owned by Westinghouse Electric Company UK on a long term site lease from the NDA. Undertakes conversion of uranium tetrafluoride to uranium hexafluoride for enrichment, and is the only manufacturer of AGR fuel. Also fabricates PWR fuel

    • Enrichment – URENCO has one of its three uranium enrichment plants at Capenhurst, and is installing a plant to convert uranium hexafluoride tails into oxide for storage and/or disposal. URENCO shares are currently held 1/3 by the UK Government, 1/3 by the Dutch Government and other parties and 1/3 by the German utilities RWE and E.On. The shareholders have all agreed to explore a possible sale of part or all of the organisation

    • Spent Fuel Reprocessing – Magnox reprocessing is undertaken by Sellafield Ltd, the Sellafield SLC. The activity is scheduled to come to an end around 2020. Oxide Fuel Reprocessing is undertaken in the Sellafield THORP facility for UK and foreign customers. The activity is scheduled to stop around 2018

    Nuclear New Build

    In January 2006, the Government launched another energy

    review consultation7, which revisited the potential role that

    new nuclear reactors could contribute to energy security

    and the decarbonisation of the UK economy. The “Meeting

    the Energy Challenge” White Paper of 2007 contained “a

    preliminary view is that it is in the public interest to give the

    private sector the option of investing in new nuclear power

    stations”.

    Over the next six years, the Government introduced

    a number of facilitative actions, including Regulatory

    Justification and Generic Design Assessment of ‘new

    build’ reactor designs, National Policy Statements with

    eight nominated sites, Funded Decommissioning Plans

    and Waste Transfer Prices, and Electricity Market Reform.

    This has led to three proposals for new build on five of the

    nominated sites. The three prospective ‘new build’ utilities

    are:

    • EDF Energy – Planning permission granted for the construction of two EPRs at Hinkley Point and a further 2 EPRs are proposed to be subsequently constructed at Sizewell. Originally the consortium anticipated the participation of Centrica, which withdrew from new build in February 2013. EPR™ (PWR – AREVA) achieved Regulatory Justification and, through the Generic Design Assessment (GDA) process, the issue of a Design Acceptance

    Confirmation by the Office of Nuclear Regulation (ONR) and a Statement of Design Acceptability from the Environment Agency (EA)

    • Horizon Nuclear – now owned by Hitachi-GE (Japan) - twin ABWR stations planned for the Wylfa and Oldbury sites. Hitachi-GE have applied to DECC for Regulatory Justification and the regulators have been asked to begin the GDA process

    • NuGen – owned by GDF-SUEZ (France) and Iberdrola (Spain), reactors planned to be constructed on the Moorside site adjacent to Sellafield but the technology choice has yet to be made.

    The Westinghouse AP1000® PWR has achieved Regulatory

    Justification, ONR Interim Design Acceptance Confirmation

    (IDAC) and EA Interim Statement of Design Acceptability

    (ISoDA), but has not yet been selected for deployment.

    Legacy Clean-up

    The NDA, through its SLCs, Dounreay Site Restoration

    Ltd (DSRL) and Research Sites Restoration Ltd (RSRL) are

    responsible for the remediation work at Dounreay, Harwell

    and Winfrith.

    • The Parent Body for DSRL is the Babcock Dounreay Partnership Ltd, a consortium of Babcock International Group (UK), CH2MHILL and URS (USA)

    • The RSRL Parent Body is the Babcock International Group (UK)

    The Magnox sites decommissioning SLC is Magnox Ltd,

    whose Parent Body is Energy Solutions (USA).

    The RSRL and Magnox Ltd contracts are currently the

    subject of an NDA competition process. The consortia

    wishing to proceed (as of January 2013) are:

    • Reactor Site Solutions (Bechtel, Energy Solutions)

    • Babcock Fluor Partnership

    • CAS Restoration Partnership (CH2MHill, AREVA, Serco)

    • UK Nuclear Restoration Ltd (AMEC, Atkins)

    Sellafield site’s parent body, Nuclear Management

    Partners, is a consortium of AREVA (France), URS (USA)

    and AMEC (UK).

    The NDA mission across its 19 sites is “to deliver safe,

    sustainable and publicly acceptable solutions to the

    challenge of nuclear clean-up and waste management”

    and involves decommissioning and cleaning up the

    range of civil nuclear facilities, ensuring that all the waste

    products, both radioactive and non-radioactive, are

    safely managed, and implementing Government policy

    on the long-term management of nuclear waste. This

    also involves managing the UK’s stocks of civil nuclear

  • 6 Department of Energy and Climate Change

    Nuclear Innovation Analysis: Landscape Review

    Chapter 2

    materials including the development of technology

    options for the storage, and either re-use or disposal of

    uranium and plutonium inventories.

    From the outline above, the structure of UK’s nuclear

    sector is seen to be complex and complicated to map, as

    seen in Figure 3 below.

    With the advent of new international entrants into the

    UK, it is still evolving both in market area of new nuclear

    build projects and in legacy clean-up. This presents

    challenges in aligning the range of structural, contractual

    and commercial drivers of this diverse

    marketplace to promote innovation.

    UK Nuclear Market Size

    The UK civil nuclear market size is also

    split between ‘new build’ and clean-up;

    the potentially major, developer-funded

    ‘new build’ market being added to the

    publically funded legacy management

    initiative set up in the early 2000s.

    The financial split between these two

    elements will depend on the size of

    the ‘new build’ programme, this has

    been initially envisaged as 16GWe8, but

    DECC has been studying a number of

    scenarios of up to 75GWe. The overall

    size of the two markets is illustrated semi-

    quantitatively, for programmes of 16GWe

    and 40GWe, in Figure 4 below.

    Figure 4 illustrates:

    1. A clean-up market which, at least in this decade, is comparable in size to the ‘new build’ market, and is characterised by many one-off projects which would benefit from innovative approaches in the short term if legacy management costs are to be contained and progress facilitated.

    2. A 16GWe ‘new build’ programme whose undiscounted costs are comparable with those of legacy clean-up in the early years. For this tranche, the reactor designs are

    essentially fixed, and this would be expected to limit the possible potential for innovation in the 15-20 year timeframe envisaged in this study.

    3. The large increase in amount and rate of spend attendant on changing to a 40GWe new build programme.

    4 The Energy Review, Performance and Innovation Unit Energy, February 2002

    5 Our Energy Future: Creating a low carbon economy, February 2003 CM 5761) http://webarchive.nationalarchives.gov.uk/+/http://www.berr.gov.uk/files/file10719.pdf

    6 Noting that BNFL had been a plc (with the shares held by the Government) since 1984

    7 Our Energy Challenge, securing clean affordable energy for the long term, January 2006 (cm6887) http://www.official-documents.gov.uk/document/cm68/6887/6887.pdf

    8 See Nuclear Industrial Vision Statement, HMG, 2013

    Figure 4. UK Nuclear Spend, Schematic

    Figure 3. Nuclear Industry in the UK, 2013

    0.0

    2.0

    4.0

    6.0

    8.0

    10.0

    12.0

    14.0

    2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029

    16GWe 40GWe

    Clean-up - Discounted programme spend £ 53 B

    £3.0B Current NDA SpendGross Annual

    Und

    isco

    unte

    d A

    nnua

    l Spe

    nd

    Control by licence/ownership Control by contract *Currently subject to competition

    AGRs

    SXB

    ChapX

    NB3Winfrith

    MagnoxRepro

    AGRRepro

    AGR SFStorage

    EDF (F) Reactors EPR Areva (F) Fuel Areva (?)

    Magnox SF Storage

    NuGen (F, Sp) Reactors ? Fuel ?

    UF4, previously UOC

    UF6 LEUF6

    SpringfieldsFuel, UF6

    CapenhurstEnrichment

    MagnoxOps +

    Cleanup

    Ops, Fuel CycleCleanup

    Magnox

    Calder

    Reactor AP1000Westinghouse –Toshiba (US/J) UK Build???

    *

    *

    NDA

    Dounreay

    Harwell

    NB1

    Horizon (J) Reactors ABWR Hitachi (J) Fuel Hitachi (?)

    NB2

    EDF (F)

    NDA

    Last fuel supply 2008Tos

    hiba

    (J)

    Wes

    tingh

    ouse

    (US)

    Sella

    field

    Ltd

    (SLC

    )

    Ure

    nco

    (D, N

    L, U

    K??

    ?)

    Bab

    cock

    Inte

    rnat

    iona

    lG

    roup

    (UK

    ), C

    H2M

    HIL

    L, U

    RS

    (US

    )

    DSR

    L(S

    LC)

    RSR

    L(S

    LC)

    Babc

    ock

    Inte

    rnat

    iona

    l G

    roup

    (UK)

    NM

    PA

    reva

    (F)

    AM

    EC

    (UK

    ) )

    UR

    S (U

    S

    Mag

    nox

    Ltd

    (SLC

    )

    Ene

    rgy

    Sol

    utio

    ns

    (US

    )

  • Department of Energy and Climate Change 7

    Nuclear Innovation Analysis: Landscape Review

    As discussed in Chapter 1, the Madano-IDM project was asked to consider six sub-areas prioritised by DECC from the Carbon Trust report “Technology Innovation Needs Assessment: Nuclear Fission”, and other areas of potential interest to identify possible projects looking to advance from around TRL 4 to around TRL 8. The sub-areas were:

    i. Innovative Fuel Formsii. Capex – Components

    iii. Capex – Building Materialsiv. Capex – Construction, Installation and

    Commissioningv. Waste Management, Reprocessing and Storage (in

    relation to historic, existing and future systems)vi. Innovation in the Regulatory Process

    The first four sub-areas can be viewed from the point of

    view of innovation in either (a) existing (GEN III)9 or (b)

    future reactor and fuel cycle technologies (GEN IV). The

    Carbon Trust assessment included examination of GEN IV

    systems, but the analysis does not differentiate between

    the very different reactor systems within the GEN IV

    categorisation, and there is currently no Government

    policy on which, if any, of the systems are of interest to the

    UK. These considerations, and the 10-20 year time horizon

    of the Madano-IDM project, led to the exclusion of GEN

    IV reactor systems from further study. The exclusion of

    GEN IV essentially rules out the theme of Innovative Fuel

    Forms, and even GEN III systems would be unlikely to be

    able to introduce any truly innovative fuel in the 20 year

    timeframe10.

    For GEN III reactor systems, the assertion11 has been that as

    more reactors are built, the cheaper the individual reactors

    become, and this has been used to scope the effects of

    innovation in any defined programme. The “First of a Kind”

    (FOAK) to “Nth of a Kind” (NOAK) improvement is largely

    predicated on economic modelling work for low-value

    high-number manufactured items such as computers and

    compact fluorescent light bulbs12. There are problems in

    transferring this model to nuclear reactors, as published

    figures for reactor cost are extremely variable13, and

    modelling studies of nuclear systems14 15 16 generally rely

    on an assumed improvement figure.

    NOAK improvement has been tested by examining one

    of the few sources of hard data on nuclear projects. The

    IAEA’s Power Reactor Information System (PRIS)17, gives

    building start dates and on-line dates for all reactors

    in IAEA-participating countries. If there are FOAK to

    NOAK improvements, these should be mirrored in a

    reduction in construction time as programmes progress.

    However, extensive examination has revealed only one

    programme, PWRs constructed in South Korea, where

    such a reduction is observed. A more typical example is

    that of reactor construction in France, which is illustrated

    in Figure 5 below, and where build time increases from

    FOAK to NOAK. Similar effects are observed in the UK’s

    Magnox and AGR programmes.9

    Chapter 3.

    Clarifying Assumptions and Project Development

  • 8 Department of Energy and Climate Change

    Nuclear Innovation Analysis: Landscape Review

    Chapter 3

    The UK is seeking to embark upon a 16GWe initial

    programme of ‘new build’ Light Water Reactors, which

    relies on the candidate reactors satisfying the rigorous

    demands of the GDA, which has involved reactor vendors

    providing extensive and detailed information on their

    designs to the UK Regulators. The GDA, therefore in

    effect ‘freezes’ many details of the candidate reactor

    design and, by extension, many of the components of

    those designs and their manufacture, together with the

    methods of construction of the reactor buildings.

    In relation to the innovation marketplace, this means

    that ‘new build’ innovation cannot be scaled by an

    “NOAK Driver”, and must look to innovation at levels of

    the supply chain which will not adversely impact on the

    ability of reactors to meet GDA requirements and build

    programmes.

    It is also notable that themes ii – iv cover the supply

    of components, the building and commissioning of

    reactors, but do not focus on their subsequent operation,

    maintenance, or assuring their operational life. In fact

    there are many areas where developments in sensors,

    data acquisition, storage and handling, and condition

    monitoring could be assumed to be brought to bear on

    the post-commissioning life of a nuclear power station.

    These innovations were sought and examined as part of

    the project.

    In sub-area v, (Waste management, reprocessing and

    storage in relation to historic, existing and future systems),

    considerations of timescale have already eliminated

    innovation for future (GEN IV) systems. Reprocessing

    activities in the UK are scheduled to be completed by

    around 202018. The current new build programme is

    predicated on ‘one-through’ LWRs, where the spent fuel

    is consigned to geological disposal, so current policy

    would seem to offer little market driver for innovation in

    this area. In the longer term, some of the Generation 4

    systems being studied do require reprocessing, but others

    do not. A driver for innovation would therefore only occur

    when there was some level of strategic intent to deploy

    systems requiring reprocessing.

    In the area of waste management, decommissioning and

    storage, there is great scope for innovation in the legacy

    clean-up of NDA’s facilities, and the techniques developed

    could assist in future decommissioning projects such as

    the AGR stations, Sizewell B and, in due course, ‘new

    build’ reactors in the UK, and a multitude of potential

    facilities overseas.

    A 2012 paper to the NDA Research Board19 reported the

    R&D needs generated by the NDA, Radioactive Waste

    Management Directorate (RWMD), ONR, EDF, EA, the

    Atomic Weapons Establishment (AWE) and the European

    Commission. Many UK responses were co-ordinated by

    the Nuclear Waste Research Forum, which is seeking to

    share experience and maximise learning across the whole

    UK Waste Management and Decommissioning sector.

    The broad research topics derived are shown below.

    18

    Figure 5. Build times of French reactors versus start number

    Bui

    ld T

    ime

    for a

    ll Fr

    ench

    Rea

    ctor

    s (y

    ears

    )

    Reactors in order of construction start date

  • Department of Energy and Climate Change 9

    Nuclear Innovation Analysis: Landscape Review

    Chapter 3

    In sub-area vi (Innovation in the Regulatory Process),

    innovation would involve improvements in cost and

    timescale of projects by seeking ways of optimising the

    regulatory approach while maintaining the stringent

    application of safety, security and environmental

    standards. For ‘new build’ reactors, there has already been

    very significant innovation in the setting up and running

    of the Generic Design Assessment (GDA) process,

    which brought all the regulators together under a co-

    ordinated joint programme. This innovation is now being

    further tested by the requirement to perform GDA on a

    very different reactor type, Hitachi’s ABWR. Anecdotal

    evidence suggested that the GDA process evolved during

    the consideration of the EPR and AP1000 reactor systems,

    and is likely to further evolve during ABWR and any other

    systems seeking deployment in the UK.

    In the legacy clean-up area, the research topics already

    quoted will involve site operators working with the

    regulators to extend innovation from technology into the

    effective regulation of the changing practices.

    This review of the six sub-areas has shown that:

    i. Innovative fuel forms: the timescale and TRLs examined by this project make it unlikely that any candidates for innovation will be found under this theme.

    ii. Capex - Components iii. Capex - Building Materials iv. Capex - Construction, Installation and

    Commissioning: innovation by the currently planned candidate reactors would appear to be somewhat constrained as a result of the reactor designs being fixed in order to pass through the GDA process. A UK commitment to a larger programme and/or the deployment of advanced reactor systems could open up further innovation opportunities.

    v. Waste Management, Reprocessing and Storage (in relation to historic, existing and future systems): a fertile area for innovation in a marketplace currently worth £3bn per annum.

    vi. Innovation in the Regulatory Process: possibilities for innovation in systems and processes, already achieved in new reactor build and with significant possibilities in waste management and decommissioning.

    1. Characterisation:

    • Improved techniques to support the development of decommissioning and site remediation plans

    • Improved techniques to support the application of the waste hierarchy as a framework for waste management decision making, from prevention of waste generation through to minimisation of impact of disposal

    2. Decommissioning:

    • Improved decontamination techniques – to minimise waste or allow man entry

    • Improved remote decommissioning technologies – to avoid man entry

    3. Waste Treatment:

    • Treatment techniques for wastes with no confirmed disposal route

    • Alternative techniques to encapsulation

    4. Waste Packaging & Storage:

    • Optimised packaging solutions

    • Understanding of waste package evolution from production to disposal

    5. Land Quality:

    • Improved technologies or approaches for the management of contaminated land to avoid ex-situ disposal

    6. Management of Plutonium:

    • Technically underpinned route for re-use in modern reactors

    Box 1. Common R&D Themes from NDA Research Board Paper

    9 ‘GEN III’ refers to reactors that are commercially available for deployment at the present time. The term ‘GEN IV’ is a generic catch-all for systems being developed for future use under the Generation 4 International Forum. The technologies covered by this term may be seen at http://www.gen-4.org/Technology/systems/index.htm

    10 For an example of the issues involved, see feature on the development of slicon carbide fuel cladding at http://www.neimagazine.com/features/featurestudying-silicon-carbide-for-nuclear-fuel-cladding/

    11 See, for example, Electricity Generation Cost Model - 2011 Update, Revision 1, Parsons Brinkerhoff for DECC, August 2011, page 2412 For example, Using the Experience Curve Approach for Appliance Price Forecasting, USDOE Energy Efficiency and Renewable energy, February 201113 Costs of Generating Electricity, IEA-NEA, 201014 Mott McDonald UK Electricity Generation Costs Update, Mott McDonald, 201015 Parsons Brinkerhoff Electricity Generation Cost Model - 2011 Update16 Electricity generation cost model 2012 update of non-renewable technologies, Parsons Brinkerhoff, 201217 At www.iaea.org/programmes/a2/ 18 NDA-Business Plan 2013-2016, March 201319 Summary and Analysis of Board Member Responses to UK Decommissioning R&D Needs, Paper for NDA Research Board, April 2012

  • 10 Department of Energy and Climate Change

    Nuclear Innovation Analysis: Landscape Review

    Stakeholder Engagement

    The examination in Chapter 3 of the industry and market structure, together with the analysis of the likely areas for innovation, prescribed a direct approach to a broad cross-section of the industry and its supply chain. This involved the Project Team undertaking desktop studies, using personal contacts and subsequent referrals to approach lead organisations such as NDA, NDAs SLCs, AREVA, Horizon and Westinghouse, together with Tier 2 contractors, universities, and research consortia. These contacts led to the identification of relevant SMEs.

    An interview framework was created and is included in

    Appendix IV, which was used to guide a variety of contacts

    through interview discussions and in-depth meetings. The

    purpose of the interview guide was intended to:

    1. Guide the respondent as to the areas, TRLs and timescales that we were hoping to cover.

    2. Identify innovation candidate technologies or opportunities.

    3. Define the TRLs involved before/after innovation development.

    4. Ask whether barriers exist to the maturing of these projects and what magnitude of investment would be involved?

    5. If so, to identify the barriers.

    6. Identify whether new funding or potential collaboration would assist the development of the innovation.

    7. Determine if any current projects were feeding into any co-ordinating/networking schemes of workshops.

    8. Ask whether the respondent ever engaged with DECC, TSB or EPSRC on any other funding body on the particular project(s) or technology(s)?

    9. Find out whether the respondent consider bidding for such funding and;

    10. If not why not?

    11. Enquire whether the respondent any estimates of the cost/benefit of the market opportunity and;

    12. If so could an estimate be given?

    13. Had the respondent any other suggestions for DECC on the piece of work being undertaken by Madano-IDM.

    By no means were all of those contacted willing to respond.

    Their stated reasons ranged from time constraints, to

    slight apathy with the current state of nuclear in the UK,

    to some parties even denying involvement in the industry

    even though they are clearly involved. However, some

    56 responses were obtained and a complete list of the

    organisations represented is seen in Table 1 below.

    Information Sensitivity

    The responses to the interviews and to the more

    extensive meetings yielded a range of information at

    varying levels of detail and commercial sensitivity. It

    was impossible, when having in-depth discussions with

    innovative organisations, to avoid conversations which at

    least touched on levels of detail which impinged on the

    Intellectual Property Rights of the companies concerned.

    Also, in seeking to discuss opportunities and challenges

    some fairly direct and forceful observations were made

    which might be misconstrued outside the context of the

    meeting/interview.

    The decision has therefore been taken not to attribute

    quotations to individual companies in this report, but

    still to use the anonymised quotations where they add a

    particular flavour and emphasis to the points respondents

    made and the clear themes that developed over the

    course of the interviews. Similarly, it was not felt prudent

    to include all the meeting notes and completed interview

    forms into a public domain report. Instead, a Commercial

    Annex to this report is being prepared which will go only

    to DECC as the commissioning organisation for the work.

    Market Uncertainty

    UK organisations seeking to develop innovative products

    and services into the overall UK nuclear market, face the

    fundamental problem of predicting the market size. As

    detailed in Chapter 3, the size of the legacy market (waste

    management, decommissioning and storage) is relatively

    Chapter 4.

    Stakeholder Research and Research Findings

  • Department of Energy and Climate Change 11

    Nuclear Innovation Analysis: Landscape Review

    Chapter 4

    well understood, in comparison to the uncertainty

    associated with the size of the new build market. With

    the reactor designs for at least the first phase of new

    build essentially fixed, and as UK manufacture will

    feed into, rather than lead, the supply chain, it would

    appear unrealistic to expect UK innovation to have any

    significant effect on the size of the market. UK innovation

    in new build will therefore rely on generating market

    share in the market that materializes. This is currently

    uncertain, given the continued hiatus in the EDF Energy

    commitment to Hinkley Point C, and the introduction of

    new, ABWR, technology for Horizon’s two potential sites

    in October 2012.

    Because of this uncertainty, there was no valid basis on

    which innovators could have been expected to produce

    detailed business cases for their innovations, and there

    was therefore limited evidence available from would-be

    innovators which could present the basis of a “bottom-

    up” Cost Benefit Analysis approach. Such uncertainty will

    affect all and any CBA techniques, and for this reason the

    analyses in Chapter 6 of this report are based on defined

    new build scenarios20.

    Consolidation of information

    The information obtained was found to contain many

    themes and topics which were common to many

    organisations, sometimes viewing the same topic from

    very different viewpoints. Overall, the project team

    considered that the ‘general overview’ defined itself after

    the first few contacts, and further interviews/meetings

    added more detail, but did not change what became a very

    well-defined picture of the industry and the opportunities

    and challenges of innovation within it.

    Workshop

    This picture was further tested in a workshop held on

    1st May 2013 and attended by some 20 people representing

    a cross section of the industry, together with DECC, TSB

    and the Carbon Trust. The workshop aimed to:

    • Understand the current innovation context, landscape and concepts;

    • Appreciate the challenges which innovation could address;

    • Explore possible futures, developments and innovation directions.

    This gave rise to a 20-page photo report full of useful and

    astute observations, which was distributed to attendees

    for comment. Once this material had been consolidated,

    it was evident that, while it raised very few matters or

    concepts which had not arisen in the interviews/meetings,

    it did add greatly to the richness of views expressed and

    underlined the wide agreement on a variety of topics.

    In the light of this preliminary finding, it was decided not

    to produce a separate report on the workshop, but to use

    the workshop as an additional data source for the overall

    evaluation of the industry’s views on the opportunities of,

    and barriers to, innovation as defined by the DECC project

    specification. This is discussed in Chapter 5.

    •Alstom•AREVA•ONR •Arup•Atkins•Babcock•Bellrock Technology Ltd•Beran Instruments•Bradtec•Cambridge Ultrasonics•The Carbon Trust•CEMEX•Ceram•Costain•Cranfield University•Cybula Ltd•Dalton Cumbria Facility•Dalton Institute•Darchem Engineering

    •DBD•Department for Business,

    Innovation and Skills (BIS)•EDF Energy•EPSRC•Fluor•GE Hitachi•Halcrow•Horizon•Hosakawa Micron•Imperial College•Jacobs•Lloyds Register•Mott MacDonald•National Nuclear Laboratory (NNL)•Nuclear AMRC•Nuclear Decommissioning

    Authority (NDA)•Nuclear Engineering Services (NES)

    •NIA•Nuvia•OC Robotics•ONR•PCubed•Pinsent Masons•REACT•Redhall•Rolls Royce•Sellafield Sites Ltd•Sheffield Forgemasters•Sir Robert McAlpine•Sulzer•Technology Strategy Board•Tetronics•TISICS Ltd•University of Birmingham•University of Manchester•URENCO

    Table 1. Organisations involved in interviews and/or meetings

    20 For example, see range of scenarios in DECC 2050 Pathways at https://www.gov.uk/2050-pathways-analysis

  • 12 Department of Energy and Climate Change

    Nuclear Innovation Analysis: Landscape Review

    This chapter summarises the findings of the interviews, meetings and workshop facilitated by Madano-IDM, under a variety of headings which arose from the assembled data and views, namely:

    • What is Innovation?

    • Roles and Organisation

    • Public and Political Acceptance

    • Innovation and Access

    • IPR and Commercial Arrangements – sharing risk and reward

    • New Build

    • Waste Management and Decommissioning Legacy

    • The Market is International

    • Innovation Examples

    • Recognising and Measuring Success

    • Innovation Opportunities

    What is Innovation?

    The question “What is innovation?” came up in many of the

    interviews and was extensively covered in the workshop,

    as it became apparent that many meanings of the word

    ‘innovation’ were in use, some of them contradictory:

    “I just improve the way we do things, I don’t

    innovate.”

    Madano-IDM had started from the Oxford English

    Dictionary definition – “the introduction of novelties,

    the alteration of what is established” – which covers

    all ‘change in the way things are done’. In the current

    context, we must add the rider that the “introduction

    of novelties” should improve the outcome, arriving at a

    definition like “the introduction of novelties, the alteration

    of what is established so as to improve the outcome of the

    endeavour.”

    Clearly this beneficial change can take many forms, from

    developing a totally new technology (e.g. flash drives),

    developing completely novel materials (e.g. graphene),

    via applying different technologies to old problems, to

    simple incremental improvement of existing systems. All

    these ‘introduce novelties that makes things better’, so we

    have considered ‘innovation’ to cover everything from a

    Nobel Prize to a successful item in a suggestions box.

    Debate in the workshop centred round the Madano-IDM

    view of innovation as shown in Figure six below. This had

    been predicated on the DECC requirement for innovations

    from TRLs 3-4 to TRLs 8-9, and for deployment over 10-20

    years. It was pointed out that ‘manufacturing’ had been

    omitted as a category, and this has been added to Figure 6.

    Figure 6. Types of Innovation

    Chapter 5.

    Discussion of Findings

    Types of innovation

    • Science

    • Technologies

    ◊ New Technologies

    ◊ Improvements

    ◊ New Applications

    • Materials

    • Engineering

    • Manufacturing

    • Regulation

    • Organisational Structures

    • Contractual Structures

    • Commercial Systems/Applications

    Too long timescale?

    Too long timescale?

    Drivers/barriers

    Drivers/barriers

    New materials too long timescale (?) – but new applications?

    Immediate – but codes, regs?

    Immediate – drivers/barriers

    Balance timescale improvements with regulatory dilemmas

    Attributes

    Motivations

    Barriers}

  • Department of Energy and Climate Change 13

    Nuclear Innovation Analysis: Landscape Review

    Chapter 5

    While the general impression given by Figure 6 was

    agreed, it was felt, in many areas, to be too broad

    brush, and probably too much influenced by the pace of

    innovation in mainstream reactor designs and fuel cycle

    processes. In particular, some SMEs pointed out that, in

    areas such as data gathering/manipulation and robotics,

    the pace of change can be such that projects will advance

    from TRL3 to full deployment in less than a decade. The

    Figure was thus deemed useful, but as a guide rather than

    a ‘straitjacket’.

    While the research found a significant number of areas

    of activity around innovation based on new materials

    or technologies, it was evident that process innovation

    also offers significant savings and should be an area of

    attention.

    “My work is more around improving

    processes in nuclear rather than new

    technologies, it is just as important.”

    Overall there was strong agreement that the key process

    was to identify innovation, of whatever sort, then to make

    and sell a compelling case for its introduction.

    Roles and Organisation

    There were many views expressed on the value of the

    UK defining, and sticking to, a long term strategy for the

    role of nuclear power in meeting energy security and

    carbon reduction targets. This was contrasted with the

    stop-go-stop experience over the last 60 years which has

    been illustrated in Figure 2 in Chapter 2, and has led to an

    industry structure put together for the 2003 ‘No Nuclear’

    energy policy being still in place in the current “‘New

    Build’, New Opportunities” climate.

    The UK has a current policy of reducing its carbon

    emissions by 80% (from the 1990 baseline) by 2050, which

    will require the decarbonisation, not only of the electricity

    supply industry, but of large segments of the economy. It

    is clear to most informed opinion that nuclear must have a

    significant role to play in this decarbonisation. Presently a

    very large range of scenarios is in play (zero to 75GWe),

    so there is no real clarity of what nuclear role is desired or

    required. During the consultations most opinion was firm

    that such decarbonisation could not be achieved without

    a long term energy strategy with a clearly defined role for

    nuclear.

    This perceived lack of a long term strategy is combined

    with a lack of clarity on who does what, both at policy

    level between DECC and BIS, and in the roles of, and

    coordination between, associated organisations such as

    the DECC Innovation team, the BIS Low Carbon Economy

    team, Go-Science, and the TSB. One continuing theme

    was that there is real difficulty in “mapping the system”,

    leading to uncertainty in matters such as who to talk

    to, who funds what, and who to consult about making

    alliances.

    Amongst those we spoke to, DECC is widely seen as

    lacking the general industry, and specific nuclear industry

    background necessary to be able to look forward and

    solve issues in the nuclear world ‘as it is’. In particular

    the acquisition of such industry knowledge could aid

    innovation projects by being able to understand the

    challenges and how to help overcome them. There is

    also a perception that there is very little knowledge flow

    across departments and organisations, and still less cross-

    department or cross-organisation working.

    Moving away from central government, the current

    structures of both the NDA and National Nuclear

    Laboratory (NNL) are seen as sub-optimal, which seems

    mainly to derive from an uncertainty in their roles. For NDA

    this includes its role in setting strategy and its relationship

    to DECC, and the level of its control/influence on SLCs.

    NDA’s role in R&D comes in for comment, and for some its

    role is not understood:

    “Need a body to lead on R&D….. and leave

    the NDA to start/keep shutting things down.”

    “NDA does not accept responsibility for

    technical strategy and expects its contractors

    to lead engineering innovation and

    development.”

    NNL is widely seen as a potential competitor by many to

    whom a proper “National Laboratory” would be a strong

    ally (see also IPR). It should be noted that this study

    was conducted before, during and after the Beddington

    Review21 and Nuclear Industrial vision statement22. Various

    Beddington-derived proposals include moves to develop

    NNLs status as a National Laboratory, which would seem

    to be universally welcomed.

    Both NDA and NNL are perceived as lacking in commercial

    expertise and acumen. There are, however some good

    exceptions to this rule, with the Nuclear Waste Research

    Forum (driven by Sellafield Technical Strategy area and the

    NDA), which is itself driven by the NDA Research Board

    already mentioned in Chapter 3. This is taking a ‘pan-UK

    view’ and is appearing to open minds and to be making

    progress in co-ordinating, and sponsoring best practice

    and innovation in the area of waste management and

    decommissioning. However such ‘areas of excellence’

    often rely on personalities rather than system drivers,

    which are notably absent – and this is acknowledged by

    the participants.

  • 14 Department of Energy and Climate Change

    Nuclear Innovation Analysis: Landscape Review

    Chapter 5

    The potential sponsors of innovation complain of a lack of

    appreciation of the problems that need to be tackled, and

    the timescales involved.

    “Don’t propose immediate treatment of

    groundwater when I won’t be tackling that

    until 2040.”

    – but from the supply chain this is read as a lack of

    imagination:

    “2040 is only a point on a Gantt chart, moving

    points like that are what innovation is about.”

    All of the above feed into a lack of energy and drive

    from within the industry to find new projects and ways

    to overcome the barriers. There are many reports of

    nuclear-relevant innovations being used in oil and gas

    sectors, because access is easier and innovation drivers

    are stronger.

    The Beddington Review has, however, raised expectations

    that there is more interest in nuclear R&D and in nuclear

    strategy in general. However, there are doubts of the

    realism of the achievability of the stated objectives when

    starting from the current fragmented industry structure

    and R&D landscape. It is widely mentioned that France has

    CEA as a ‘one-stop-shop’, whereas UK, by contrast, has a

    dozen overlapping organisations to talk to. A coordinating

    body is desperately needed and long overdue.

    The overall requirement is for the UK to develop an

    innovation-friendly culture, with a ‘chain of benefit’ across

    the supply chain, so that innovation can come from any

    level but retain a fair reward.

    This ‘chain of benefit’ was explored in the workshop, and

    was agreed to be the central requirement for a culture of

    successful innovation. The need for linked drivers and

    enablers is represented in Figure 7 below.

    Figure 7. Need for linked drivers and enablers

    This sort of coherence was deemed essential for success,

    and the workshop also outlined a ‘path to the future’,

    which, though currently only in outline, would surely

    repay study and development. It is shown below.

    Figure 8. Coherent route to a successful UK nuclear future

    JointSharedVision

    Fast startthat

    fades out

    ‘Bottom of the Inbox’

    Anxiety

    Frustration

    Falsestart

    Success

    Must have all 4 of these in place...

    If any one is missing...

    FAILURE

    PressureFor

    Change

    CapacityFor

    Change

    ActionableFirstSteps

    JointSharedVision

    Fast startthat

    fades out

    ‘Bottom of the Inbox’

    Anxiety

    Frustration

    Falsestart

    Success

    PublicPositive

    • Government Investment• Private Investment• Universities attract new talent• Skill culture• Programmes growing• Investment in facilities

    • Customers buy• Learning curves / cost reduction• Supply pipeline• Plants building• World Gold Standard

    GovernmentPositive

    Must have all 4 of these in place...

    If any one is missing...

    FAILURE

    NOW

    FUTURE

    PressureFor

    Change

    CapacityFor

    Change

    ActionableFirstSteps

  • Department of Energy and Climate Change 15

    Nuclear Innovation Analysis: Landscape Review

    Chapter 5

    One missing element in Figure eight, but which was

    reflected in many of the interviews and much of the

    workshop discussion, was the need for the UK to identify

    and pursue a niche or niches where it could feasibly

    become the ‘World Gold Standard’. This reflects a need

    to “identify business opportunities” rather than “pursue

    innovation per se” – identifying the niches, then using

    “the supply chain from academia through to industrial

    development and manufacture” as the best way of

    maximising market development.

    The contrast between Figure eight and the situation

    reported in the bulk of the research findings, points to

    a clear opportunity for DECC to lead in facilitating the

    development of innovations across the TRL 3-4 to 7-9

    TRL “Valley of Death”. However, from the evidence,

    many of the key barriers to innovation appear cultural

    and structural rather than stemming merely from lack

    of funding. Creating a “Nuclear UK Innovation Culture”

    will probably depend more on coherent leadership than

    additional funding, however welcome this might be.

    The workshop looked, in four groups, at four ‘case

    studies’ of different types of innovation, and reported

    on the challenges and barriers to innovation that

    were anticipated. These were then ‘marked’ by all the

    workshop attendees. The results of this exercise are

    given in Appendix V, and while not, of course, statistically

    robust, do give a very useful insight into the difficulties

    anticipated by those actually operating within the industry.

    In particular, the four highest ranked challenges/barriers

    chime very well with the rest of the research findings, and

    are reproduced below.

    Challenge/Barrier Marks Rank

    Lack of institutional innovation climate

    13 1

    Need for national leadership (public and private), direction and vision

    11 2

    No incentive for business given long return on investment/access to (private sector) funding

    9 3

    Making and selling a compelling case for changes (team/individual credibility)

    8 4

    Table 2. Ranked Challenges/Barriers from Workshop Exercise

    During the workshop there was much discussion around

    the development of “innovation portals” similar to the

    Centre for Defence Enterprise (CDE). Many thought

    such a scheme aligned to civil nuclear power could have

    enormous benefit for the UK and help unblock a number

    of the current issues.

    The CDE is aligned with the Government’s Small Business

    Research Initiative (SBRI) managed by the Technology

    Strategy Board (TSB).

    CDE is the first point of contact for anyone with a disruptive

    technology, new process or innovation that has a potential

    defence application. CDE funds research into novel high-

    risk, high-potential-benefit innovations sourced from

    the broadest possible range of science and technology

    providers, including academia and small companies, to

    enable development of cost-effective capability advantage

    for UK Armed Forces.

    CDE is the entry point for new science and technology

    providers to defence, bringing together innovation and

    investment for the defence and security markets.

    All CDE research proposals must be submitted online via

    the portal. The CDE team at Harwell is available to talk to

    you about your innovative idea or you can book a one-to-

    one surgery appointment via the events page. Once your

    proposal is submitted you can track its progress online.

    CDE welcomes research proposals via two different routes:

    • Open call – an enduring call for any innovative research ideas that have a potential defence and security application;

    • Themed call – a specific call for innovative research ideas to meet particular challenges.

    Public and Political Acceptance

    This area, which would not initially come to mind under

    the heading of ‘innovation’, was mentioned in several

    interviews and was discussed in the workshop, appearing

    in Figure eight. It is plausible that the cyclical nature of

    political support for nuclear power revealed in Figure two,

    Chapter two, may be put down to a relationship between

    the perceived need for nuclear power by politicians and

    the acceptance of it by the public. It has been argued that

    a long term strategy is necessary if innovation is to flourish

    in the nuclear industry in the UK. This would involve a long

    term political commitment, which would be made easier if

    there was demonstrable long-term public support, which

    in turn would require public appreciation of the role of

    nuclear in an energy-secure low carbon economy.

    The fragmented nature of the industry, already reviewed,

    has meant there is no ‘owner’ of the industry’s stakeholder

    relations, a role which was, in the past, largely undertaken

    by BNFL as part of its ‘license to operate’. The need for

    some overall stakeholder role was emphasised in the

    workshop:

    “Scope for innovation in political/public

    acceptability arenas, particularly with respect

    to the Geological Disposal Facility.”

  • 16 Department of Energy and Climate Change

    Nuclear Innovation Analysis: Landscape Review

    Chapter 5

    This in turn chimes well with the work being done by

    DECC to define/refine the Managing Waste Safely

    (MRWS) process in the aftermath of the rejection by the

    Cumbrian stakeholders of continued participation in the

    search for a Geological Disposal Facility for radioactive

    waste, The broader context of public acceptance should

    be borne in mind during any future developments in the

    industry, and will be a factor in the on-going support for

    secure low carbon energy.

    Innovation and Access

    Reflecting the fragmented nature of the industry, its

    confusing organisation and the inadequately-defined

    roles, the innovation landscape lacks co-ordination and

    collaboration – there is no one-stop shop to find out what

    is happening, and there are major issues of accessibility

    and complexity. This makes both ‘knowing what’s going

    on” and “affecting what’s going on” difficult.

    There is perceived to be lack of innovation right across the

    landscape, partly due to past and on-going uncertainties

    around nuclear policy – the same legacy of the past 60

    years of chopping and changing. This feeds into difficulties

    in R&D funding and access to innovation – with diverse

    funders mirroring the complex industry structure. Access

    is adequate for practised companies, but even the good

    ones admit that entry is a struggle, and many holders of

    good innovations are not big enough/good enough/

    determined enough to succeed. SMEs particularly find it

    difficult to be able to put together bids: it is always difficult

    to break into new markets, and SMEs are at a natural

    disadvantage as they are small and any extra effort in

    processes is disproportionately difficult for them.

    “It would be easier if the funding was better

    aligned.. at least in one central place.”

    The TSB approach was actively criticised by some SMEs

    and Institutions, and it is considered onerous, particularly

    as it appears to require a large commercial partner

    (though, in some situations, this is actually not the case).

    Such partners can be difficult to find, and when they are

    found it is often difficult to partner while at the same time

    protecting the SME’s IPR. However, and understandably,

    the process has been praised by some of the larger

    players. Alternative approaches are suggested, with the

    MOD’s Centre for Defence Enterprise23 much quoted

    as an exemplar of good practice. This offers open calls

    on managed themes, and once an outline proposal is

    received CDE representatives contact the proposer to

    refine an application with the intent that its assessment

    chances will be improved. There is also no requirement

    for partnering or matching funding, making it easier for

    SMEs with worthwhile innovations to make progress.

    “TSB calls are quite difficult actually. We can

    end up doing projects we don’t necessarily

    want to do as the guidelines push you into

    collaborations you wouldn’t otherwise do.”

    “We have a lot of experience and have been

    successful in TSB calls, but can understand

    how new entrants find the task daunting.”

    The paragraphs above indicate a real problem: that

    SMEs, particularly ‘out of industry’ SMEs, may have the

    innovations that the nuclear industry needs, but the

    barriers to entry are high: how to find out what’s needed,

    how to fit solutions within the nuclear regulatory and

    safety case framework, how to find industry players

    motivated to innovate, how to get partners without being

    ‘eaten’. Individually, such remarks could be passed off a

    “the whingeing of the unsuccessful”. Collectively, they

    paint a clear picture of an industry with widespread and

    high barriers to innovation, particularly from SMEs.

    “The key thing for companies like us, is

    that we need to bring the market in to us…

    we need big companies to engage with us

    otherwise we’re almost shooting in the dark.”

    With these barriers, the 3-4 to 7-9 TRL “Valley of Death”,

    which innovations fail to cross, seems to be a reality. A

    DECC call for projects in this area would be well aimed,

    but might end up ameliorating a few of the symptoms,

    while leaving the structural ‘illness’ untreated. There is

    a need to generate market “pull” as well as innovation

    “push”: perhaps targeted contractual change which would

    allow/promote cultural and motivational change to “do a

    good job for UK plc”. The key question is how to generate

    motivation within a system with multiple organisational,

    contractual, commercial and procurement barriers to

    innovation. This is reported at various layers – from those

    who look above them and find barriers to innovation, and

    to those that look at them from below and find the same

    problem.

    “We spend 1bn euros a year on R&D and

    while we have an interest to do that, the UK’s

    set up is almost anti-innovation.”

    Innovation requires access to information – “what is the

    problem” – access to data (which frequently cannot, or

    will not, be shared) and physical access to environments in

    which solutions can be tested. There was speculation on

    whether it might be possible to derive metrics for inertia/

    resistance to innovation: while clearly a non-trivial task,

    this might allow improvement to be measured.

  • Department of Energy and Climate Change 17

    Nuclear Innovation Analysis: Landscape Review

    Chapter 5

    IPR and Commercial Arrangements – sharing risk and reward

    There were many problems reported on the difficulty of

    protecting IPR, and difficulties in negotiating confidentiality

    agreements. Some of the larger organisations are said to

    refuse confidentiality agreements outright, and often take

    over the IPR as a condition of support. Innovative SMEs

    can end up either with little return for their idea, or they

    can be bought up and shut down.

    “How can you encourage innovation when

    the client will take the IP off you in return for

    a relatively small contract.”

    This perception is widespread, and emphasises the need

    for a ‘chain of benefit’ across the supply chain – with

    a fair distribution of risk and benefit for all stages of the

    innovation chain. ‘Small’ must be able to present to ‘large’

    without getting ‘eaten’. There seems little to encourage

    joint engagement between an equipment manufacturer

    and an end user, and the ‘Tiering’ of contractors, formalised

    in the legacy waste management and decommissioning

    market, promotes barriers between tiers.

    New Build

    There is a growing lack of conviction that ‘new nuclear’

    will actually happen, and no real understanding of the role

    nuclear could/would play in the UK low carbon energy

    future. The 2050 aspiration (i.e. 80% less CO2 by 2050)

    does not appear to reflect the UK’s need for integrated

    energy systems to deliver a low carbon economy, and

    a meaningful longer term energy policy joining “now”

    and “then” with a real strategy would help to signal

    Government commitment.

    If ‘new build’ does not happen, there will be major

    knock-on effects for people, skills, graduate recruitment/

    retention, all of which are essential resources if any UK

    nuclear success is to be had. On the other hand, positive

    commitments on ‘new build’ can unlock investment in the

    UK ‘new build’ supply chain.

    “Financing R&D on civil nuclear remains challenging...

    particularly with the delays on ‘new build’, a move on ‘new

    build’ would unlock a lot of stalled activity.”

    The current position is that on ‘new build’ “UK is playing

    catch-up and the start is being delayed”, although EDF is

    progressing AGR life extension.

    UK is seen as highly regulated across the whole nuclear

    industry, and this is essential to the level of public

    acceptance it can achieve. However, it should be noted

    that the Generic Design Assessment process was an

    example of innovation, with all the regulators working

    as a team with a common goal and an incentive to

    work thoroughly but without delay. This ‘balance of

    forces’ was conspicuously lacking during the licensing

    of Sizewell B, as there were strong timescale drivers

    to get the station constructed, licensed and operating,

    which overrode any motivation of the Sizewell B team to

    challenge the regulator requirements to modify/augment

    safety systems, therefore increasing costs. There was

    widespread support in the workshop for the proposition

    that “there would never have been another reactor as long

    as the Sizewell B licensing process remained in place,”

    Waste Management and Decommissioning Legacy

    The UK legacy nuclear cleanup is, at £3bn or so per annum,

    a major market which should give a real opportunity for

    the UK to be a world leader in nuclear decommissioning.

    The current structure is widely seen as a barrier rather

    than a driver of such developments, with perceptions

    from the outside virtually unanimous that the system

    does little to incentivise innovation or, indeed, progress

    a decommissioning and waste management, a drive by

    Government which could “help UK firms to the top table.”

    “Decommissioning is an obvious area for the

    UK to develop a leadership role both in terms

    of expertise and technology innovation…

    It’s a large industry for the UK and I don’t

    understand why we don’t exploit the

    opportunities it presents more.”

    There are exceptions, for example the Nuclear Waste

    Research Forum, but as already discussed this is

    ‘people and personality’ based rather than driven by the

    contractual/commercial structure. It would only take a few

    people to move on and the progress could cease.

    Perceptions of the legacy clean-up market include:

    “There is currently no incentive to

    decommission and deal with waste …

    [decommissioning] policy is about care and

    maintenance.”

    “The current system is based upon care and

    maintenance rather than actually wanting to

    do anything.”

    “The current system at Sellafield does not

    make contractors think how best to get the

    most innovative processes or technologies

    on to the site… it is very much focused on an

    operations and maintenance model.”

    One area where innovation is reported is in a more

    phased approach by regulators to high-hazard-potential

    plants at Sellafield. Formerly, no project could be initiated

    until all the downstream processes and projects were in

  • 18 Department of Energy and Climate Change

    Nuclear Innovation Analysis: Landscape Review

    Chapter 5

    place to take waste into a final disposable form. Now, the

    realisation that the priority is progress in Hazard Potential

    reduction in the short term, short term progress is being

    facilitated by phased approvals, while ensuring that routes

    to final disposal are not compromised.

    To maximise the chances of the UK becoming a world

    leader in nuclear clean-up, the clean-up market would

    need to maximise the opportunities for UK firms to win

    jobs, gain experience and strengthen the UK supply chain.

    However, the perception is that procurement procedures

    and recourse to OJEU24, are widely used/interpreted to

    the detriment of setting up UK capabilities and supply

    chains, with the UK apparently playing to a set of rules

    very different to those of its international competitors.

    One subject which was not much mentioned in the

    interviews/meetings, but was dealt with in the workshop,

    was the disposal of radioactive waste and the progress

    towards a Geological Disposal Facility. Progress on

    disposal, along with ‘new build’, would be a signal that the

    UK nuclear industry is ‘on the move from cradle to grave’.

    The current hiatus may, in the long term, be as damaging

    as a short term hiatus for ‘new build’.

    “They need to sort out the GDF issue. It was

    a massive blow to the UK and the nuclear

    industry that GDF process has stalled. It

    could have really delivered a lot of innovation

    around nuclear waste management.”

    The Market is International

    The international dimension of innovation is growing, and

    this was discussed, and found broad agreement, in the

    workshop. Even a nuclear industry the size of France’s is

    turning to its international peers for ideas. This was not to

    say that the UK could not find international markets for

    its innovative ideas, merely that it must find, and pursue,

    suitable niches. For example by setting the benchmark for

    regulation, standards and codes, the UK could develop

    an international niche, attracting good people into the

    industry and the UK.

    This observation emphasises the need for any analysis of

    nuclear industry futures for the UK to ‘start from where we

    are’ (i.e. the industry structure as seen in Figure three), not

    ‘where we’d like to be’.

    Innovation Examples

    Though the observations of the industry representatives

    that have been contacted, as reported in the sections

    above, has concentrated on barriers to innovations and

    on the changes needed for improvement, the interviews

    and meetings did reveal a range of innovative ideas which

    could make a significant difference to the effectiveness of

    nuclear activities in the UK if they were implemented.

    The detailed findings have been included in the

    Commercial Appendices to this report, with distribution

    restricted to DECC, but it is relevant here to give a broad

    representation of the innovations proposed and the field

    in which they could operate. It should be noted that Table

    3 below is not intended to be comprehensive, but gives

    a “snapshot” of the innovation topics discussed during

    the stakeholder engagement exercise. The innovations

    are assigned to the six themes identified by DECC, which

    were examined in Chapter three, and are repeated for

    convenience below.

    i. Innovative Fuel Formsii. Capex – Components

    iii. Capex – Building Materialsiv. Capex – Construction, Installation and

    Commissioningv. Waste Management, Reprocessing and Storage (in

    relation to historic, existing and future systems)vi. Innovation in the Regulatory Process

  • Department of Energy and Climate Change 19

    Nuclear Innovation Analysis: Landscape Review

    Chapter 5

    Table 3. Example Innovations proposed during stakeholder contacts

    Technology Description TRL Level Opportunities Theme

    Data management and consolidation

    Integrates sensors and monitoring technologies without the need for a central concentrator

    5 Automatically determine how data can be interpreted in a system

    a25

    Condition monitoring system

    Monitors integrity of machinery Not stated Identifies early on issues with machinery and parts and allows early warning for maintenance / improves safety

    a

    Corrosion studies and testing

    Only one rig in the UK 4-5 As a nuclear capability the ability to understand corrosion in reactors is very important

    a

    Virtual environments Developing gaming engines to deal with specific issues around nuclear sites

    7-8 Develops knowledge on decommissioning and testing. Good training tool

    v

    Robotics Development of hand sensors for robotics

    5-6 Would reduce time and improve efficiency

    v

    Graphite management Convert graphite to CO2

    7 Speed up decommissioning and save money

    v

    Concrete integrity measurement

    CMS – Inspects and monitors the integrity of concrete structures from installation and construction

    5-6 Identifies early on issues with structures and allows early warning for maintenance

    iv

    Waste encapsulation Encapsulation of solid intermediate Level Waste (ILW)

    4 More cost effective than other forms of encapsulation

    v

    Depth of contamination in concrete

    Measuring the depth of contamination in concrete

    5 Reduction in the cost of decommissioning and waste management

    v

    Plasma Arc Technology

    Using plasma arc technology will significantly reduce amount of nuclear waste for disposal

    7 Technology would significantly reduce the amount of cost spent on nuclear waste disposal

    v

    Data Signals monitoring system

    Monitors signals – heat, vibrations, movements. Seeks to analyse data and produce abnormality detection systems

    4 Requires large data sets. Difficult to get access to large players and existing plants

    a

    Fire protection technology

    The thermal insulation technology is endothermic and absorbs heat

    7-8 Would reduce major fire risks ii

    Metal-fuelled fast reactor

    Various components and fuel forms Not Applied

      -

    Powder technology applications

    Applying powder processing and sorting techniques in place of chemical processes

    9 in other industries