NTPC Limited CC-OS, EOC Noida
Subject: Qualifying requirement & other details for vendor enlistment – Vendors for supply of Valves and valve spares used in dry ash handling system. A) Details of MEG (Material Enlistment Group)
MEG No 18MEG-04 MEG Description Valves and valve spares used in dry ash handling system Responsibility Centre CC&M-CPC
B) Technical Criteria of QR: 1. The applicant should be a Micro Small Enterprise (MSE) manufacturer of Valves and should
have manufactured valves for dry ash handling system. 2. The applicant should have in house pneumatic & hydraulic test facilities. 3. The applicant should have supplied minimum 50 nos. dry ash pneumatic conveying valves
assembly (complete valve) to coal based thermal power plants / dry ash handling package contractor in any continuous 365 days period in the last 5 years from the date of application for enlistment.
C) Documents to be submitted as proof of meeting the stipulated Qualifying
Requirements: 1. QR-1: Copy of valid MSE Certificate for being manufacturer of Valves and proof of being
manufacturer of Valves for Dry Ash Handling system.
2. QR-2: Self declaration from the vendor along with details of the specified facilities.
3. QR-3: Copy of Purchase Orders from Thermal Power Plants / Dry Ash handling system package contractor for supply of Dry Ash Pneumatic Conveying Valves along with execution proofs.
NTPC can ask more documents if felt necessary. Also all documents/ facilities can be verified/ assessed if required. To be declared as qualified, an applicant has to meet all the requirements
D) Other documents to be submitted: In addition to the documents required in support of meeting technical requirements as stated above, following documents are required to be submitted by the applicant for enlistment:
1. Three POs of highest executed values of similar work during last five years from the date of application (PO date should not be more than five (5) years old as on the date of the application) along with copy of invoice / completion certificate from the concerned buyer/s in support of successful execution of supply against POs.
2. Audited balance sheet including profit and loss statement for the previous three completed financial years reckoned from the date of application.
In case the audited results for the preceding financial year is not available, certification of financial statements from a practicing chartered account may be submitted. In case, Applicant is not able to submit the certificate from practicing chartered Account
2
certifying its financial parameters, the audited results of three consecutive financial years preceding the last financial year shall be considered for evaluating the financial parameters. Further a Certificate would be required from the CEO/CFO as per the format enclosed in the application format documents stating that the financial results of the company are under audit as on the date of Application and the Certificate from the practicing Chartered Accountant certifying the financial parameters is not available
3. Any other documents in addition to the above which the applicant wants to submit.
E) Note-1 Definition of Similar work (Refer to Point 1 of Row D above):- Supply of Valves for Dry Ash Handling System to Coal Based Thermal power Plants / Ash Handling System Package Contractors.
Note-2 The executed value means Basic value of quantity of similar works / orders executed / supplied against the reference PO (also applicable to partly executed PO, as on the date of application). Where PO value is composite (i.e. including taxes etc.), the applicant should submit item wise break up of composite PO value mentioning basic PO Value, Tax details etc.
3
A) Details of MEG MEG No 18MEG-04 MEG Description Valves and valve spares used in dry ash handling system Responsibility Centre CC&M-CPC
B) Technical Specifications 1. As given in attachment
Specification of Dry Ash Handling Valves & Spares
Specifications of material of construction:-
1) Sliding Gate Material Handling Valve:-
Slide Gate Housing ACI, Hardness-250BHN min
Slide Gate SS 410, Hardness-300BHN min or 10 mm thick MS with 10-15
microns of hard chrome plating on both side of plate. The
chrome plating thickness shall be equivalent to 300-350 BHN
Valve seat ACI, Hardness-250BHN min or Replaceable SS hardened &
smooth finished ( 250 BHN min)
Air Inlet Check valve CI FG260
Gland Housing CI FG260
2) Ash Intake Valve below ESP hopper (Swing check type MHV)
Valve Body CI FG220
Gate Disc ACI, Hardness 300BHN
Gate seat ACI, Hardness 250BHN
Gate shaft EN 8
Pivot ball EN 24
Valve adaptor ACI, Hardness 250BHN
3) ALV Rotary Segregatingvalve
Lower Deck Plate MS IS:2062
Chamber MS IS:2062
Valve seat (Repl) ACI, 250 BHN. HARDNESS MIN.
Gate Arm C.S. ASTM A-148, GR. 90-60
Gate ACI WITH 300-350 BHN. HARDNESS
Crank Arm DUCTILE IRON
Spool Piece MS IS:2062
4) Transporter Inlet/Outlet valve
Valve Body ACI, Hardness 250 BHN
Gate Disc ACI, Hardness 400 BHN
Gate seat(Repl) ACI, Hardness 400 BHN
Gate shaft EN8
Pivot ball EN24
Valve adaptor ACI, Hardness 250 BHN
5) Transporter Inlet Cup Valve
Valve Body ACI, Hardness 250BHN
CUP Cast Steel, IS 1030, Gr280-520W, Chrome plated
Lever IS 2068, Gr E250A
Seal Ring Viton Rubber
Shaft EN8
Valve Face, Covers IS 2062, Gr.E250A
Connecting Rod IS 2062, Gr.E250A
6) Segregating Slide Gate Valve
Valve Body ACI, Hardness-250BHN min
Slide Gate SS410, Hardness-300BHN min
Valve seat ACI, Hardness-250BHN min
End Cap CI FG260, IS210
Spacer Adaptor CI FG260, IS210
7) Rotary Slide Gate Branch Isolating Valve
BODY GRAY IRON, ASTM A159-70, CL-G4000, 250 BHN
SLIDE GRAY IRON, ASTM A159-70, CL-G4000, 250 BHN
SHAFT C40, IS1570
BUSHING BRONGE, SAE 841/ASTM B-438-73/ EQUAL
GASKET SILICON RUBBER
SEAT (Repl) GRAY IRON, ASTM A159-70, G4000, 250 BHN
8) Double Disk Valve
Middle Ring ACI, 250 BHN
End Ring ACI, 250 BHN
Disk Tool Steel D3, ASTM A681, Hardness 550 BHN
Seat Ring Tool Steel D3, ASTM A681, Hardness 550 BHN
Rod Seal PTFE
Gland Spring Spring Steel, EN45
Disk Drive EN 8
Disk Pin EN 36, Hardness 500-550 BHN
Disk Spring Spring Steel, EN45
9) Three way Equalizing valve
Spacer CI FG 260, IS:210
Valve Seat EN-31, Hardness 500 BHN
Adaptor CI FG 260, IS:210
Top Port Adaptor CI FG 260, IS:210
Valve Disk Sub Ass. EN31, Hardness 500 BHN
Side Port Adaptor CI FG 260, IS:210
Gland Follower CI FG 260, IS:210
Bottom Adaptor MS, IS:2062 GR. B
Sleeve SS 304
Quality Plan:
As per annexed Sheet
ITEM : MATERIAL
HANDLING VALVE
INDICATIVE QUALITY PLAN SHEET –1 OF 2 REV : 00 DATE :30.10.19
S.No COMPONENT/OPER
ATION CHARACTERISTIC CLASS TYPE OF
CHECK QUANTUM OF CHECK
REFERENCE DOCUMENT
ACCEPTANCE NORMS
FORMAT OF RECORD
AGENCY** REMARKS
D* M C N
1 2 3 4 5 6 7 8 9 10 11 1.0 RAW MATERIAL/ IN-PROCESS INSPECTION 1.1 Slide Gtae Chemical
Composition Major Chemical One sample per Heat
As per appd. Drg./DS As per Col.7 QC
Report P V
Mech. Properties Major Mech. 1/Heat As per appd. Drg./DS As per col.7 QC
Reprot P V
Hardness Major Measure-ment
One sample per Heat
As per appd. Drg./DS As per Col.7 QC
Report P V
1.2 Valve Body ,Valve outlet, Valve Seat & Slide gate housing
Chemical Composition Major Chemical One sample
per Heat Apprd
Drg/DS/Mfg std As per Col.7 QC Report P V
Hardness Major Measure-ment
One sample per Heat
As per appd. Drg./DS As per Col.7 QC
Report P V
1.3 End cover Chem & Mech Major Tensile & hardness
1 per Lot As per appd. Drg./DS
As per appd. Drg./DS
QC Report P V
1.4 Air inlet check valve Material check
function Major
Tensile, hardness &
Manual operation
1 per Lot As per appd. Drg./DS
As per appd. Drg./DS
QC Report P V
2.0 IN-PROCESS INSPECTION 2.1 Valve Body (Flange
Valve Body and Slide Gate Housing)
Casting Defects & Dimension Major Visual & Measuement 100% Mfr Std. As per Col.7 QC
Report P
2.2 Valve Outlet, Valve Seat Dimensional Conformity Minor Measure-ment 10% Mfr DRG As per Col.7 QC
Report P
2.3 Slide gate Dimension including thickness Minor Measurement 10% Apprd/Mfg Drg As per Col.7 QC
Report P V
LEGEND D* : RECORDS INDENTIFIED WITH “TICK” SHALL BE
ESSENTIALLY PROVIDED BY CONTRACTOR IN QA DOCUMENTATION
** M : MANUFACTURER / SUB-CONTRACTOR C : MAIN CONTRACTOR, N-NTPC
INDICATE “P” PERFORM “W” WITNESS & “V” VERFICATION AS APPROPRIATE “CHP” NTPC SHALL BE IDENTIFIED IN COLUMN “N”, MTC : MATERIAL TEST CERTIFICATE, IR : INSPECTION REPORT
FOR NTPC USE
ITEM : MATERIAL HANDLING VALVE
INDICATIVE QUALITY PLAN SHEET –1 OF 2 REV : 01 DATE :30.10.19
S.No COMPONENT/OPERATION
CHARACTERISTIC CLASS TYPE OF CHECK
QUANTUM OF
CHECK
REFERENCE DOCUMENT
ACCEPTANCE NORMS
FORMAT OF RECORD
AGENCY** REMARKS
D* M C N 1 2 3 4 5 6 7 8 9 10 11 Valve seat & slide
gate Grinding & Lapping Major Kerosene fill test
100% Apprd Drg/Mfr Drg As per Col.7 QC
Report P W 10% witness by NTPC. Refer Note 3.
3.0 FINAL INSPECTION 3.1 Assembly Dimension and
Completeness Major Visual/ /measurement 100% Appd.Drg. As per Col.7 QC
Report. P W 10% witness by NTPC
3.2 Check for Operation Completeness &appearance
Operation Check (10 cycles) along with pneumatic cylinder
Major Visual & operation with air
100% As per app. Drg./DS
Smooth Operation
QC Report P W
10% witness by NTPC
3.3 Check for painting Paint shade,DFT Minor Visual 100%
Apprd Painting schedule/Apprd Drg/Mfg std
As per Col.7 QC Report P
Note : 1. All material shall be as per NTPC approved drawing/data sheet 2. No weld repair is allowed on Alloy CI/CI. 3. No visible flow of kerosene from the matching joint for a duration of 2 Min. However the appearance of film at the matching joint will not be a cause of rejection.
LEGEND D* : RECORDS INDENTIFIED WITH “TICK” SHALL BE
ESSENTIALLY PROVIDED BY CONTRACTOR IN QA DOCUMENTATION
** M : MANUFACTURER / SUB-CONTRACTOR C : MAIN CONTRACTOR, N-NTPC
INDICATE “P” PERFORM “W” WITNESS & “V” VERFICATION AS APPROPRIATE “CHP” NTPC SHALL BE IDENTIFIED IN COLUMN “N”, MTC : MATERIAL TEST CERTIFICATE, IR : INSPECTION REPORT
FOR NTPC USE
Rev.00
DT:30.10.2019
SH 1 0f 2
S NO COMPONENT/ CHARACTERISTIC CLASS TYPE OF QUANTUM REFERENCE ACCEPTANCE FORMAT OF REMARKSOPERATION CHECK OF CHECK DOCUMENT NORMS RECORD M C N
1 2 3 4 5 6 7 8 9 D* 10 111 RAW MATERIAL/IN-PROCESS INSPECTION1.1 Slide Gate Chemical Composition Major Chemical One sample/Heat Apprd DRG/DS As per Col.7 Mfr.TC's/QCR √ P V Corelation shall be
Maintained by IndureHardness Major Measurement One Sample per As per Appd.Drg/. As per Co;.7 QC Report √ P V
Heat Data SheetMech. Properties Major Mechanical 1/heat Apprd DRG/DS As per col.7 QC Report √ P V
1.2 Valve Body Chemical Composition Major Chemical One Sample per Apprd DRG/DS As per Col.7 QC Report √ P VHeat
Hardness Major Measurement One Sample per As per Appd.Drg./ As per Co;.7 QC Report √ P VHeat Data Sheet
1.3 End Cap Chemical Composition Major Chemical One sample Apprd DRG/DS As per col.7 QC Report P Vspacer,adaptor per heat
1.4 Valve Seat Chemical Composition Major Chemical One sample Apprd DRG/DS As per col.7 QC Report √ P V(Replaceble Alloy per heat
Hardness Major Measurement One Sample per As per Appd.Drg./ As per Co;.7 QC Report √ P VHeat Data Sheet
V V2 IN-PROCESS INSPECTION2.1 Valve Seat Casting Defects Major Visual 100% Appd.Plant Std. As per Col.7 QC Report P
Dimensional Conformity Minor Measurement Only critical Dim. Mfr Drg. As per Col.7 QC Report P
Grinding and Lapping MajorKerosine Fill test with master plate 100% Apprd DRG/DS/Mfr StdApprd DRG/DS/Mfr Std QC Report √ P W
CHP(10% witness by NTPC).Refer Note 3
LEGENDS FOR NTPC USE*RECORDS IDNETIFIED WITH "TICK"SHALL BE ESSENTIALLY
PROVIDED BY CONTRACTOR IN QA DOCUMENTATION
** M:MANUFACTURER/SUB-CONTRACTOR
C : CONTRACTOR/NOMINATED INSPECTION AGENCY N : NTPC
INDICATE "P"PERFORM "W"WITNESS & "V"VERIFICATION AS
APPROPRIATE "CHP" NTPC SHALL IDENTIFIED IN COLUMN "N" REVIEWED BY NAME &SIGN OF APPROVING AUTHIRITY &SEAL
AGENCY**
ITEM : SEGREGATING SLIDE VALVE INDICATIVE QUALITY PLAN
Rev.00
DT:30.10.2019
SH 2 0f 2
S NO COMPONENT/ CHARACTERISTIC CLASS TYPE OF QUANTUM REFERENCE ACCEPTANCE FORMAT OF REMARKSOPERATION CHECK OF CHECK DOCUMENT NORMS RECORD M C N
1 2 3 4 5 6 7 8 9 D* 10 112.2 Valve Body Dimensional Conformity Major Measurement Only critical Mfr Drg. As Per Col.7 QC Report P
DimensionsCasting Defects Major Visual 100% Mfr Std As Per Col.7 QC Report P
2.3 End cap, End Dimensional Conformity Minor Measurement Random 5% Mfr Drg. As Per Col.7 QC Report PCover
Casting Defects Minor Visual 100% Mfr Std As Per Col.7 QC Report P
2.4 Slide Gate Dimensional Conformity & Thickness
Minor Measurement 100%
Mfr Drg.
As Per Col.7 QC Report P
Grinding Major Visual 100% Mfr Drg. Ground Finish QC Report √ P V3 FINAL ASSEMBLY & INSPECTION
3.1 Assembly Dimension&Completenes Major Visual 100% As per appd.drg As Per Col.7 QC Report √ P WCHP (10% witness by NTPC)
3.2 Check for operationOperational Check Major Visual& 100% As per appd.drg Smooth operation QC Report √ P WCHP (10% witness by NTPC)
completeness& (10 Cycles) along operationAppearance with cylinder Check
3.3 Check for painting Paint shade,DFT Minor Visual 100% As Per Col.7 QC Report P
NOTE : 1. All materials shall be as per appd. Drg./data sheet. 2. No welding permitted on castings. 3. No visible flow of kerosene from the matching joint for a duration of 2 Min. however the appearance of film at the matching joint will not be a cause of rejection.
LEGENDS FOR NTPC USE*RECORDS IDNETIFIED WITH "TICK"SHALL BE ESSENTIALLY
PROVIDED BY CONTRACTOR IN QA DOCUMENTATION
** M:MANUFACTURER/SUB-CONTRACTOR
C : CONTRACTOR/NOMINATED INSPECTION AGENCY N : NTPC
INDICATE "P"PERFORM "W"WITNESS & "V"VERIFICATION AS
APPROPRIATE "CHP" NTPC SHALL IDENTIFIED IN COLUMN "N" REVIEWED BY NAME &SIGN OF APPROVING AUTHIRITY &SEAL
AGENCY**
Apprd Painting schedule/Mfg std
ITEM : SEGREGATING SLIDE VALVE INDICATIVE QUALITY PLAN
FORMAT NO.: QS-01-QAI-P-10/F3-R1 1/1 ENGG. DIV./QA&I
ITEM(Material, Class, Grade, Rating, Range, Size, etc.) Ash Transporter Vessel inlet outlet valve
INDICATIVE QUALITY PLAN REV. NO: 00
DATE :01.11.2019
PAGE 01 OF 01
Reviewed by:-
Approved by:-
CONFORMING TO CODE: SL. No. COMPON
ENT & OPERATION
CHARACTERISTICS
CLASS TYPE OF CHECKS
QUANTUM OF CHECK
REFERENCE DOCUMENTS
ACCEPTANCE NORMS
FORMAT OF RECORDS
AGENCY REMARK
M C/N M C N
1 2 3 4 5 6 7 8 9 D* 10** 11 1. Raw Material 1.1
Body, Gate Disk & Gate Seat
Surface condition Hardness Chemical composition
Major Major Major
Visual Lab test Chemical
100% 1/heat 1/heat
1/heat 1/heat
…. Approved Drawing Approved Drawing
No cast defects Approved Drawing Approved Drawing
IR TC TC
P P P
V V V
V V
1.2 Shaft Chemical composition Physical properties UT(for dia. >50mms)
Major Major
Lab test Ultrasonic
1/lot 100%
1/lot 100%
Approved drawing
ASTM A388
Approved drawing Note 1
TC TC
P P
V V
V V
Note 1: When back wall echo (BWE) set to 100%. Full screen height (FSH), a defect echo>20% FSH is not acceptable. Also loss of BWE>20% is not acceptable.
2 In Process Inspection
2.1 Machining of components
DPT Major NDT 100% 100 % ASTM E 165 No Relevant Indication
IR P V V
2.2 Pressure test of body
Leakage test Major Hydraulic 100% 10% Approved drawing
No leakage
IR P W W
2.3 B/O: Diffuser Fluidizing pad
Std. Mfr. TC Major Measurement Review
100% 100 % Approved drawing/ Mfg. Standard/ Data sheet
Approved drawing/ Mfg. Standard/ Data sheet
Mfr. TC
P V V
3 Final inspection
3.1 Assembly Completeness & Dimensions
Major Visual & measurement
100% 10% Approved drawing
Approved drawing IR P W W .
Final check Major Operation 100% 10% Approved drawing
Smooth operation IR P W W
4. Painting Color Shade & DFT Major Visual & measurement
100% Random
Approved drawing
Approved drawing IR P V
legeNd: * Records, identified with “Tick” ( ) SHALL be essentially included by SUPPLIER in QA documentation. ** M: Manufacturer / Sub-SUPPLIER C: MAIN SUPPLIER, N: NTPC p: perform W: witness and V: verification. as appropriate, CHP: Ntpc shall identifY in colum “N” AS ‘W’.
FORMAT NO.: QS-01-QAI-P-10/F3-R1 1/1 ENGG. DIV./QA&I
ITEM (Material, Class, Grade, Rating, Range, Size, etc.) Ash Intake Valve
INDICATIVE QUALITY PLAN REV. NO: 00
DATE : 01.11.2019
PAGE 01 OF 01
Reviewed by:-
Approved by:-
CONFORMING TO CODE:
SL. No.
COMPONENT & OPERATION CHARACTERISTICS CLASS TYPE OF CHECKS
QUANTUM OF CHECK
REFERENCE DOCUMENTS
ACCEPTANCE NORMS
FORMAT OF RECORDS
AGENCY REMARK
M C/N M C N
1 2 3 4 5 6 7 8 9 D*
10** 11
1. Raw Material 1.1
Body, Gate Disk, Gate Seat & adopter
Surface condition Hardness Chemical composition
Major Major Major
Visual Lab test Chemical
100% 1/heat 1/heat
1/heat 1/heat
…. Approved Drawing Approved Drawing
No cast defects Approved Drawing Approved Drawing
IR TC TC
P P P
V V V
V V
1.2 Shaft Chemical composition Physical properties UT(for dia. >50mms)
Major Major
Lab test Ultrasonic
1/lot 100%
1/lot 100%
Approved drawing
ASTM A388
Approved drawing Note 1
TC TC
P P
V V
V V
Note 1: When back wall echo (BWE) set to 100%. Full screen height (FSH), a defect echo>20% FSH is not acceptable. Also loss of BWE>20% is not acceptable.
2 In Process Inspection 2.1 Machining of components DPT Major NDT 100% 100 % ASTM E 165 No Relevant
Indication IR P V V
2.2 B/O: Diffuser Fluidizing pad
Std. Mfr. TC Major Measurement Review
100% 100 % Approved drawing/ Mfg. Standard/ Data sheet
Approved drawing/ Mfg. Standard/ Data sheet
Mfr. TC
P V V
3.1 Final Inspection Completeness & Dimensions
Major Visual & measurement
100% 10% Approved drawing Approved drawing IR P W W
Functional test Major Operation 100% 10% Approved drawing Smooth operation IR P W W Leakage test Major Vacuum 100% 10% Approved drawing No leakage/
Approved Drawing IR P W W
4. Painting Color Shade & DFT Major Visual & measurement
100% Random Approved drawing Approved drawing IR P V
Legends: * Records, identified with “Tick” ( ) SHALL be essentially included by SUPPLIER in QA documentation. ** M: Manufacturer / Sub-SUPPLIER C: MAIN SUPPLIER, N: NTPC p: perform W: witness and V: verification. as appropriate, CHP: Ntpc shall identify in column “N” AS ‘W’.
FORMAT NO.: QS-01-QAI-P-10/F3-R1 1/1 ENGG. DIV./QA&I
ITEM (Material, Class, Grade, Rating, Range, Size, etc.) EQUALIZING AND VENT VALVE
INDICATIVE QUALITY PLAN
REV. NO: 00
DATE :01.11.2019
PAGE 1 OF 1
Reviewed by:-
Approved by:-
CONFORMING TO CODE: VALID UPTO : SL. No.
COMPONENT & OPERATION
CHARACTERISTICS CLASS TYPE OF CHECKS
QUANTUM OF CHECK
REFERENCE DOCUMENTS
ACCEPTANCE NORMS
FORMAT OF RECORDS
AGENCY REMARK
M C/N M C N
1 2 3 4 5 6 7 8 9 D*
10** 11
1. Raw Material 1.1 End cover, middle ring Surface condition
Hardness Chemical
Major Major Major
Visual Lab test Chemical
100% 1/heat 1/heat
1/heat
…. Approved Drawing Approved/Mfg Drawing
No cast defects Approved drg. Approved/Mfg Drawing
IR TC TC
P P P
V V V
V V
1.2 Disk & seat ring Chemical & Hardness Major Lab test
One sample/lot
One sample/lot
Approved drawing / Data sheet
Approved drawing/ Data sheet
TC P V V
1.3 Shaft Chemical composition Physical properties UT(for dia. >50mms)
Major Major
Lab test NDT
1/lot 100%
1/lot 100%
Approved drawing / Data sheet ASTM A388
Approved drawing Note 1
TC UT report
P P
V V
V V
Note 1: When back wall echo(BWE) set to 100%. Full screen high (FSH), a defect echo>20% FSH is not acceptable. Also loss of BWE>20% is not acceptable.
2 In Process Inspection 2.1 Hydro test of end covers Pressure test Major Hydraulic 100% 100% Approved drawing No leakage IR P V V 2.2 Machining of components DPT Major NDT 100% 100 % ASTM E 165 No Relevant
Indication IR P V V
3. Final Inspection 3.1 Assembly Completeness &
Dimensions Major Visual &
measurement 100% 10% Approved drawing Approved
drawing IR P W W
3.2 Final check Major Operation 100% 10% Approved drawing Approved drawing
IR P W W
4. painting Color Shade & DFT Major Visual & measurement
100% Random
Approved drawing Approved drawing
IR P V
legeNd: * Records, identified with “Tick” ( ) SHALL be essentially included by SUPPLIER in QA documentation. ** M: Manufacturer / Sub-SUPPLIER C: MAIN SUPPLIER, N: NTPC p: perform W: witness and V: verification. as appropriate, CHP: NTPC shall identify in column “N” AS ‘W’.
ITEM : EQUALISING VALVE
INDICATIVE QUALITY PLAN SHEET –1 OF 2 REV : 0 DATE :30.10.19
S.No COMPONENT/OPERATION
CHARACTERISTIC CLASS TYPE OF CHECK
QUANTUM OF CHECK
REFERENCE DOCUMENT
ACCEPTANCE NORMS
FORMAT OF RECORD
AGENCY** REMARKS
D* M C N 1 2 3 4 5 6 7 8 9 10 11
1.0 RAW MATERIAL/ IN-PROCESS INSPECTION 1.1 Valve Disc & Seat Chemical
Composition Major Chemical One sample per Heat Apprd Drg/DS As per Col.7 Mfr.T.C
/QCR. P V
Hardness Major Measure-ment
One sample per Heat As per appd. Drg. As per Col.7 QC
Report P V
1.2 Adaptor & spacer (C.I FG 260)
Chemical Composition Major Chemical One sample per
Heat Apprd Drg/DS As per Col.7 QC Report P
Tensile Test Major Mech. One sample per Heat Apprd Drg/DS IS-210 QC
Report P V
2.0 IN-PROCESS INSPECTION 2.1 Adaptor & spacer Casting Defects Major Visual 100% Mfr Std As per Col.7 QC
Report P V
Dimensional Conformity Minor Measure-
ment Only critical dimensions Mfr Drg. As per Col.7 QC
Report P V
2.2 Valve Disc and Seat
Dimensional Conformity Minor Measure-
ment 10% Mfr Drg As per Col.7 QC
Report P V
LEGEND D* : RECORDS INDENTIFIED WITH “TICK” SHALL BE
ESSENTIALLY PROVIDED BY CONTRACTOR IN QA DOCUMENTATION
** M : MANUFACTURER / SUB-CONTRACTOR C : INDURE, N-NTPC
INDICATE “P” PERFORM “W” WITNESS & “V” VERFICATION AS APPROPRIATE “CHP” NTPC SHALL BE IDENTIFIED IN COLUMN “N”, MTC : MATERIAL TEST CERTIFICATE, IR : INSPECTION REPORT
FOR NTPC USE DOC. NO.
MANUFACTURER / SUB CONTRACTOR SIGNATURE
REVIEWED BY NAME & SIGN OF APPROVING AUTHORITY & SEAL
ITEM : EQUALISING VALVE
INDICATIVE QUALITY PLAN SHEET –2 OF 2 REV : 0 DATE :30.10.19
S.No COMPONENT/OPERATION
CHARACTERISTIC CLASS TYPE OF CHECK
QUANTUM OF CHECK
REFERENCE DOCUMENT
ACCEPTANCE NORMS
FORMAT OF RECORD
AGENCY** REMARKS
D* M C N 1 2 3 4 5 6 7 8 9 10 11
Grinding & Lapping Major Kerosene fill test
100% Apprd Drg/Mfr Drg As per Col.7 QC
Report P
Refer Note 3. 10% shall be witnessed by NTPC.
3.0 FINAL INSPECTION 3.1 Assembly
Dimension and Completeness Major Visual
Checking 100% Appd.Drg. As per Col.7 QC Report. P W
10% shall be witnessed by NTPC.
3.2 Check for Operation Completeness &appearance
Operation Check (10 cycles) along with pneumatic cylinder
Major Visual & operation with air
100% As per app. Drg. Smooth Operation QC Report P W
10% shall be witnessed by NTPC.
Check for painting Paint shade, DFT Minor Visual 100%
One coat of primer/Apprd Painting procedure
As per Col.7 QC Report P
Note : 1. All material shall be as per approved drawing/data sheet 2. No weld repair is allowed on Alloy CI/CI. 3. No visible flow of kerosene from the matching joint for a duration of 2 Min. However the appearance of film at the matching joint will not be a cause of rejection.
LEGEND D* : RECORDS INDENTIFIED WITH “TICK” SHALL BE
ESSENTIALLY PROVIDED BY CONTRACTOR IN QA DOCUMENTATION
** M : MANUFACTURER / SUB-CONTRACTOR C : INDURE, N-NTPC
INDICATE “P” PERFORM “W” WITNESS & “V” VERFICATION AS APPROPRIATE “CHP” NTPC SHALL BE IDENTIFIED IN COLUMN “N”, MTC : MATERIAL TEST CERTIFICATE, IR : INSPECTION REPORT
FOR NTPC USE DOC. NO.
MANUFACTURER / SUB CONTRACTOR SIGNATURE
REVIEWED BY NAME & SIGN OF APPROVING AUTHORITY & SEAL
Rev.00
DT:30.10.2019
SH 1 0f 2
S NO COMPONENT/ CHARACTERISTIC CLASS TYPE OF QUANTUM REFERENCE ACCEPTANCE FORMAT OF REMARKSOPERATION CHECK OF CHECK DOCUMENT NORMS RECORD M C N
1 2 3 4 5 6 7 8 9 D* 10 111 RAW MATERIAL/IN-PROCESS INSPECTION
1.1 Gate&Gate Seat Chemical Composition Major ChemicalOne Sample per heat As per Appd.Drg. As per Col.7 Mfr.TC's/QCR √ P V
Hardness Major MeasurementOne Sample per heat As per Appd.Drg. As per Co;.7 QC Report √ P V
1.2 Yoke,coverChem & mech Composition Major Chemical 01/Heat Apprd Drg As per Col.7 QC Report P
Louver Chamber &Louver Deck
1.3Gate arm & crank arm Chem composition Major Chemical 01/Heat Apprd Drg As per Col.7 QC Report √ P V
2 IN-PROCESS INSPECTION2.1 Yoke,cover Dimensional- Major Measurement 100% Mfr Drg. As per Col.7 QC Report P V
Louver Chamber & ConformityLouver Deck
2.2 Gate&Gate Seat Dimensional Confmity Major Measurement 100% Mfr Drg. As per col.7 QC Report P V
Grinding and Lapping Major Leakage(Kero 100% See note 4 As per col.7 QC Report √ P W10% witness by NTPC. Ref. Note 3
sine fill test)LEGEND FOR NTPC USE*RECORDS IDNETIFIED WITH "TICK"SHALL BE ESSENTIALLY
PROVIDED BY CONTRACTOR IN QA DOCUMENTATION
** M:MANUFACTURER/SUB-CONTRACTOR
C : CONTRACTOR/NOMINATED INSPECTION AGENCY N : NTPC
INDICATE "P"PERFORM "W"WITNESS & "V"VERIFICATION AS
APPROPRIATE "CHP" NTPC SHALL IDENTIFIED IN COLUMN "N" REVIEWED BY NAME &SIGN OF APPROVING AUTHIRITY &SEAL
AGENCY**
ITEM : ROTARY SEGREGATING VALVE INDICATIVE QUALITY PLAN
Rev.00
DT:30.10.2019
SH 2 0f 2
S NO COMPONENT/ CHARACTERISTIC CLASS TYPE OF QUANTUM REFERENCE ACCEPTANCE FORMAT OF REMARKSOPERATION CHECK OF CHECK DOCUMENT NORMS RECORD M C N
1 2 3 4 5 6 7 8 9 D* 10 112.3 Gate Arm&Mach- Dimensional Conformity Major Measurement Only critical Mfr Drg. As Per Col.7 QC Report P V
iend parts Dimensions3 FINAL INSPECTION
3.1 Assembly Dimension& Major Measurement 100% As per appd. Drg. As Per Col.7 QC Report √ P W 10% witness by NTPCCompleteness
3.2 Check for opera- Operation Check(10 Major Operational 100% As per appd. Drg. Smooth operation QC Report √ P W 10% witness by NTPCtion complete- cycles)along with ness and appea- CylinderrenceCheck for painting Physical Appearance Minor Visual 100% One coat of pri- As Per Col.7 QC Report P
mer/NTPC Spec.NOTE : 1. All materials shall be as per appd. Drg./data sheet. 2. No welding permitted on castings. 3.No visible flow of kerosene from the matching joint for a duration of 2 Min.however the appearance of film at the matching joint will not be a cause of rejection
LEGEND FOR NTPC USE*RECORDS IDNETIFIED WITH "TICK"SHALL BE ESSENTIALLY
PROVIDED BY CONTRACTOR IN QA DOCUMENTATION
** M:MANUFACTURER/SUB-CONTRACTOR
C : CONTRACTOR/NOMINATED INSPECTION AGENCY N : NTPC
INDICATE "P"PERFORM "W"WITNESS & "V"VERIFICATION AS
APPROPRIATE "CHP" NTPC SHALL IDENTIFIED IN COLUMN "N" REVIEWED BY NAME &SIGN OF APPROVING AUTHIRITY &SEAL
ITEM : ROTARY SEGREGATING VALVE INDICATIVE QUALITY PLAN
AGENCY**