NPDES REQUIREMENTS. NPDES REQUIREMENTS. Pollution Control is Contractor’s responsibility PennDOT is responsible for enforcement Its our Public Duty Environmental compliance is a major initiative of the Department. P.O.M. SECTION B 4 10-1. E & S Plan . Pollution Prevention Plan includes - PowerPoint PPT Presentation

Citation preview

Page 1: NPDES REQUIREMENTS

NPDES REQUIREMENTS

Page 2: NPDES REQUIREMENTS

NPDES REQUIREMENTSPollution Control is Contractor’s

responsibilityPennDOT is responsible for enforcementIts our Public DutyEnvironmental compliance is a major

initiative of the Department

Page 3: NPDES REQUIREMENTS

P.O.M. SECTION B 4 10-1

Page 4: NPDES REQUIREMENTS

E & S Plan Pollution Prevention Plan includesMaps and DrawingsNarrativeSequencing

Page 5: NPDES REQUIREMENTS

TerminologyNPDESBMPCCDRain Event

Page 6: NPDES REQUIREMENTS

Monitoring and ReportingAll NPDES Permits requireWeekly Inspection of SiteSite Inspection after every measureable rain

event within 24 hours Written reports for every inspectionInspections performed by Department and

Contractor

Page 7: NPDES REQUIREMENTS

VISUAL INSPECTION CHECKLIST

Page 8: NPDES REQUIREMENTS

So WhatNon-Functioning BMP repaired in 48 HrIf not fixed – PennDOT to report to CCDWhat makes more sense?

You Have contractor fix ORCall CCD to have contractor fix it

Details are in Permit

Page 9: NPDES REQUIREMENTS

So What if Contractor is FinedIt is his problemHe will have to pay the fineIt is not PennDOT’s faultWRONG

Page 10: NPDES REQUIREMENTS

IIC ResponsibilityAttain Transfer/ Co-Permittee Application Coordinate required Inspection process with

ContractorDetails how inspection reports are provided

to CCDRain gage on Project

Page 11: NPDES REQUIREMENTS

Violations - NOVWhat are they:Non-Functioning BMP from InspectionBMP not repaired after 48 hrsCCD comments that a BMP needs repairedNone of the above

Page 12: NPDES REQUIREMENTS

Violations - NOVOfficial NOV issued by DEP or CCDResult of Serious violation Has DEP Case Number on itDistrict must submit copy to

BOCMOffice of Chief CounselWithin 48 hours

Page 13: NPDES REQUIREMENTS

N.O.V. TRACKING

The NOV Tracking spreadsheet has been placed at the following location:

P:\Penndot Shared\NOV District Tracking\Notice of Violation Capture With Threat of NOV.xlsm

Page 14: NPDES REQUIREMENTS

N.O.V. TRACKING INFORMATION COUNTYDEP REGIONSR/SECCONTRACT #ISSUING AGENCYCONTRACTORCONTRACTOR INFO

DATE OF VIOLATIONNATURE OF VIOLATIONDESCRIPTION OF VIOLATIONACTIVITY CAUSING N.O.V.RESOLUTIONSTATUS OF NOVCITATION AMOUNT

Page 15: NPDES REQUIREMENTS

APPROVAL FROM D.E.P. OR C.C.D.Individual Permits

(PAI)General Permits

(PAG)

Page 16: NPDES REQUIREMENTS

PERMIT RETURNED FROM D.E.P.

Page 17: NPDES REQUIREMENTS

PERMIT RETURNED FROM C.C.D.

Page 18: NPDES REQUIREMENTS

PERMIT DETAILS

Page 19: NPDES REQUIREMENTS

Permit ApprovalApproval with ConditionsE & S Plan, Post Construction Stormwater Management

(PCSM) Preparedness, Prevention and Contingency

(PPC) Plans

Page 20: NPDES REQUIREMENTS

E & S POLLUTION CONTROL PLAN

Page 21: NPDES REQUIREMENTS

E & S POLLUTION CONTROL PLAN

Page 22: NPDES REQUIREMENTS

P C S M PLAN EXAMPLE

Page 23: NPDES REQUIREMENTS

P C S M PLAN EXAMPLE

Page 24: NPDES REQUIREMENTS

P P C PLAN

Preparedness,Prevention

AndContingency

Plan

Page 25: NPDES REQUIREMENTS

P P C PLAN EXAMPLE

Page 26: NPDES REQUIREMENTS

P P C PLAN EXAMPLE

Page 27: NPDES REQUIREMENTS

TRANSFEREE/CO-PERMITTEE APPLICATION

Page 28: NPDES REQUIREMENTS

TRANSFEREE/CO-PERMITTEE APPLICATION

Page 29: NPDES REQUIREMENTS

TRANSFEREE/CO-PERMITTEE APPLICATIONMAKE SURE THAT ALL APPLICABLE PAGES

ARE SIGNED BY ALL PARTIESMAKE SURE DOCUMENT IS NOTARIZEDTHIS DOCUMENT IS VITAL IF CONTRACTOR

BEGINS WORK AND A VIOLATION OCCURS !

Page 30: NPDES REQUIREMENTS

BORROW EXCAVATION AND WASTE AREAS

E & S PLAN for all Borrow and waste AreasSUBMITTED TO THE DEPARTMENT and

AUTHORIZED C.C.D.FORM 4345 COMPLETEDENVIRONMENTAL DUE DILIGENCE FORM

COMPLETED

Page 31: NPDES REQUIREMENTS

OTHER ENTITIES (IF APPLICABLE)US ARMY CORPS OF ENG. WATER OBSTRUCTION

– ENCROACHMENT PERMITUS FISH & WILDLIFE SERVICEUS COAST GUARDPA DEPT OF ENVIRONMENTAL PROTECTIONPA FISH & BOAT COMMISSIONPA GAME COMMISSIONPA DEPT OF CONSERVATION & NATURAL

RESOURCES US ENVIRONMENTAL PROTECTION AGENCY

Page 32: NPDES REQUIREMENTS

EXPIRATION OF PERMIT

Revisions to the Permit may be necessary upon renewal!

Page 33: NPDES REQUIREMENTS

NOTICE OF TERMINATION MANAGEMENT REQUIREMENTS permittee or co-permittee must submit a

Notice of Termination (NOT) form signed with Signatory Requirements of this

permit. All NOTs certifying discharge termination are

to be sent to the Department, or the authorized County Conservation District.

Page 34: NPDES REQUIREMENTS

NOTICE OF TERMINATION

CCD indicated this is a MUSTC.C.D. will confirm that the stormwater

Management activities are complete.This relieves PennDot and the contractor

from any further responsibilities