NPDES Reporting

Indiana NPDES DMR Data:maintained for compliance tracking

purposes for Indiana and EPA

Indiana Society of Mining and ReclamationTechnology Transfer Seminar

December 7, 2009

Page 2: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

IDEM Contact Information:IDEM Toll Free Number: 800-451-6027

Office of Water Quality, IDEMRamona Malone, Receptionist: 317-232-8670Office Fax Number: 317-232-8406

Spill Hotline: 888-233-7745

Page 3: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

IDEM Contact Information (cont):Data and Information Services Section:

(for DMRs and MMRs)Jeff Ewick, Section Chief: 317-233-0676

[email protected] Rose McDaniel: 317-233-2653

[email protected] Demmings: 317-232-8815

[email protected]

Page 4: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

DMR Definition• DMR: Discharge Monitoring Report Form: a federal

pre-printed Form (3320-1) • Source: IDEM prints DMRs using data from a federal

database and mails them out annually.• The DMR is specific for that NPDES permitted facility.• There is one DMR per outfall: summary data from

MMR will be used to complete the DMR.• The DMR must be submitted/postmarked by 28 days

following its Monitoring Period end date.

Page 5: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

MMR Definition• MMR: Monthly Monitoring Report: a state form

required by Indiana• Source: http://www.in.gov/idem/5104.htm • For Coal Mines choose the “Industrial Type” MMR.• Can be used as an Excel Spreadsheet or printed as a

copy that can be filled out by hand.• One MMR per outfall: data results for each day of

sampling will be used to complete it.• MMR must be submitted w/corresponding DMR.

Page 6: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Goal: Report NPDES data Accurately, Completely, and on Time

• To fulfill reporting requirements of NPDES permit.• To receive Compliant status (for DMR data) in EPA

database.– To prevent false Missing violations from

accruing.– To facilitate accurate data entry of NPDES

sampling results.• To demonstrate good stewardship of the use of the

waters of the State of Indiana.

Page 7: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

DMR violations in the EPA database• There are 3 types of DMR data violations in

the EPA database:Missing Exceedence Late

• Missing DMR data is currently the most common violation for Indiana coal mine NPDES permittees, in the EPA database.

Page 8: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

12/05/08: 1,915 Missing Coal Mine DMRs for Indiana from 01/07 to 09/08

Start of List End of List

Page 9: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

12/04/09: 601 Missing Coal Mine DMRs for Indiana from 01/07 to 09/08

Start of List End of List

Page 10: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

12/04/09: 629 Missing Coal Mine DMRs for Indiana from 01/08 to 09/09

Start of List End of List

Page 11: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

DMR and MMR Forms are Provided by IDEM

IDEM prints and mails one years’ worth of DMRs per NPDES facility every July (using EPA database info).

DMR forms have exact codes, parameters, monitoring period dates, and IDs on them so that their data can be entered into the EPA database to receive compliant status each monitoring period.

MMRs can also be printed and mailed out, as requested, but are downloadable as Excel spreadsheets from the IDEM website.

Page 12: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Provide Correct Contact Address: To Receive DMR Forms

• In order to receive annual paper DMRs, each facility must give IDEM has their correct mailing address. Please notify IDEM whenever there is a change.

• Alternatively, facilities may receive their DMRs by email. Notify one of the Data Section Contacts with the email address of the appropriate contact person.

• Another way a facility can receive their DMRs is to use electronic submittal via the new eDMR system.

Page 13: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Part I: How to complete the DMRand MMR forms correctly:

In order to have compliant DMR data in the EPA database.

Page 14: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Check the DMR and MMR for completeness prior to submittal

• For No Discharge monitoring periods - be sure the “No Discharge” box is marked.

• For monitoring periods with discharge - be sure that each DMR blank is filled in with the required measurement and use correct abbreviations if parameters have no measured data results.

• For all submitted DMRs: sign, date, and list the correct applicable telephone number.

Page 15: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Send the completed DMR/MMR to the correct IDEM address, on time

• DMR/MMR submittal should be postmarked by the 28th of the month following the DMR Monitoring Period End Date to:

• Indiana Dept. of Environmental Management• Office of Water Quality Mail code: 65-42 DISS• Data & Information Services Section• 100 N Senate Ave• Indianapolis, IN 46204

Page 16: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Supply both Average and Maximum Data, when required

• Report both average and maximum data, even for once-per-month or quarterly sampling frequencies.

• It is okay if the reported Average measurement is identical to the Maximum measurement.

• If more sampling occurred than required, all data for that parameter must be on MMR.– And it should be reflected in the Average

measurement on the DMR.

Page 17: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Example of DMR w/incomplete data

Page 18: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Example of DMR w/complete data

Page 19: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Report Flow in MGD• Report flow as million gallons per day (MGD), not

gallons. For example: 10,000 gallons should be reported as 0.01 million

gallons.• Do not report “0” flow on the DMR: either it is a “No

Discharge” DMR or there was a flow measurement.• If the dry weather flow was “0”: “0” should be listed

on the MMR for that day of discharge checking.

Page 20: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Calculate Average Flow CorrectlyTo average flow for dry and wet discharges: Use two flow samples representative for the month.

Example 1: “0.000 MG” (dry) and 0.010 MG (wet) Monthly Average Daily Maximum 0.005 MGD 0.010 MGD Example 2: “0.010 MG” (dry) and 0.050 MG (wet) Monthly Average Daily Maximum 0.030 MGD 0.050 MGD

Page 21: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Calculate Averages correctly forOther Parameters on dry/wet months

• Calculate averages (except pH) using measured data: Example 1: “No Discharge” (dry) and 40 mg/l (wet) TSS: Monthly Average Daily Maximum 40 mg/l 40 mg/l Example 2: 3 mg/l (dry, but discharge) and 1 mg/l(wet) Iron: Monthly Average Daily Maximum 2 mg/l 3 mg/l

Page 22: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Alkaline DMR (wet/dry samples)

Page 23: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Alkaline MMR (wet/dry samples)

Page 24: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Report Non-detect Data correctly

• Report less than the Limit of Detection (i.e.,“<0.005”) when reporting non-detect DMR measurements.

• The lab work (or testing equipment instructions) should indicate what the Detection Limit is.

• Do not report “0” or “ND” or “BD” or “BDL”.• Be sure to use “<” symbol if “less than” is meant.• Less than (<) can only be used on the DMR in

combination with the actual Detection limit.

Page 25: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Report Conditional Data Correctly• Use “Exempt” or “N/A” (“not applicable”) to report

excused missing data, per parameter.• This should only be used for the exempt condition

parameters when reporting alternative sampling.• Note: Exempt data that is truly exempt (as per the

Rule) does not create missing data violations in the EPA database. Exempt data will be processed as compliant, as long as the reason for the missing data is clearly explained on the DMR.

Page 26: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Complete No. of Exceedences, Frequency, and Sample Type Correctly

• Complete the remaining three columns on the DMR form.

• When the reported measurement on the DMR exceeds the permit limit, report the number of times the limit was exceeded that reporting period in the “No. Ex.” column.

Page 27: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Report Other Missing Data Correctly • Use “*” (asterisk) on the DMR blank if sampling did

not occur (but it should have) for a parameter.• Explain what the “*” (asterisk) means at the bottom

of the DMR page.• Based on the explanation, IDEM Data Stewards can

give the missing data a process code that will at least make the data appear more complete in the EPA database, although it may still generate some kind of missing data violation.

Page 28: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Report No Discharge correctly• Mark the No Discharge Box when submitting DMRs

for outfalls that did not have a discharge for that monitoring period.

• Do not ask IDEM (Permit Writers or Data Stewards) to temporarily “delete”, “inactivate”, or otherwise terminate an outfall as an alternative to reporting no discharge. Outfall inactivation should be permanent.

• “Re-activating” an inactive outfall in the federal database can cause false violations to occur.

Page 29: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

No Discharge DMR

Page 30: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

No Discharge MMR

Page 31: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Report Alternative Parameters -1

• Under specific precipitation conditions, the permittee may adjust reporting as follows:

• If precipitation <= 10 year, 24 hr storm event flow:– Report Flow, Settleable Solids, pH, Precipitation

(inches/month) and Duration (days/month).– For all other parameters, report “N/A” or

“Exempt”.

Page 32: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Report Alternative Parameters - 2• If precipitation > 10 year, 24 hr storm event flow:

– Report Flow and pH, Precipitation (inches per month) and Duration (days per month).

– For all other parameters, report “N/A” or “Exempt”.

• Precipitation and Duration shall be reported on both the DMR and MMR.

Page 33: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Alkaline Mine drainage status

Page 34: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Alkaline MMR

Page 35: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

NPDES Permits w/no point discharge• NPDES permittees that have no designated outfall

point but still have the possibility of discharging will receive a “000 A” outfall in the EPA database.

• They will need to submit DMRs for this outfall, which should usually be “No Discharge”.

• The parameters on the DMR will be the same as the Reclamation Outfall parameters (quarterly).

Page 36: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Reclamation Mine drainage status

Page 37: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Reclamation MMR

Page 38: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Part II. Permit Changes that require written notification to the Permit

Section

In order to have changes/corrections officially made to the permit and

reflected in the EPA database.

Page 39: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Changes to Ownership, Facility Name, or Signatory Authority

• Submit these changes to the Permit Section as soon as possible, using the correct notification form.

• An ownership change requires a formal modification.• Be sure the notification form is filled out completely.• It may take 2-4 weeks for changes to be completed in

EPA database.• New DMRs can be sent to the facility after that time.

Page 40: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Updating the Facility Location Address

• Federal and State databases now require more complete locational information for facilities.

• When applying for permit renewals (or even new permits) each facility needs to supply both:– a specific street address or the nearest crossroads

to the NPDES permitted facility, and – latitude/longitude (“lat-long”) coordinates.

Page 41: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Changes to the Permit Coverage Area: Permitted area should be contiguous

• The facility location lat-long should generally indicate the center of the facility.

• Thus, each NPDES facility needs to be one contiguous site, not multiple noncontiguous mines.

• During NPDES permit renewals, permits with noncontiguous pits/mines may be split such that each noncontiguous pit/mine will have its own NPDES permit (and improved locational information).

Page 42: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Changes to Outfall status

• Activity status types: Active, Inactive, Proposed.• Drainage status types: Undetermined, Alkaline,

Acid, Reclamation.• Changes to either status type should be sent to the

Permit Writer on the notification form, in order to have the change made in the EPA database and on the corresponding DMR.

Page 43: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Report Influent for Undetermined Outfalls

• Report the required pH and iron influent monitoring for Undetermined outfalls for at least 6 months.

• After 6 months of data, permittee can apply to permit writer to remove the influent monitoring.

• Permit writer will notify permittee and Data Steward if influent monitoring can be removed.

• Permittee must continue to report influent monitoring until notified by permit writer, in order to prevent missing data violations in EPA database.

Page 44: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Undetermined Mine DMR

Page 45: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Undetermined Mine MMR

Page 46: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Report metals for Acid Outfalls• Report the required metal monitoring for Acid

outfalls for at least 12 months.• After 12 months of metals data, permittee can apply

to permit writer to remove the parameters.• Permit writer will notify permittee and Data Steward

if metal monitoring can be removed.• Permittee must continue to report metal monitoring

until permit writer notifies permittee otherwise, in order to prevent false missing data violations.

Page 47: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Acid Mine DMR (page 1)

Page 48: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Acid Mine DMR (page 2)

Page 49: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Acid Mine MMR

Page 50: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Adding an Outfall to Existing Permit• Notify the permit writer whenever a new discharge

point is added to an NPDES permitted area.• Each new outfall, per permit, must have a new

outfall ID that has never been used with that permit.• Each new outfall must also have a unique and

permanent lat-long assigned, and a start date.• Do not re-use an outfall ID in a new location, per

permit – it will compromise historical data.

Page 51: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Adding Proposed Outfalls• If a new permit only has proposed outfalls, the first

outfall listed (or designated) will be activated in the EPA database such that DMRs for that outfall must be submitted as per effective date of the permit.

• Notify the Permit writer as soon as each proposed outfall is built, with a “start date” for that outfall.

• DMRs for each active outfall must be submitted from then on, even if there is no discharge.

Page 52: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Inactivating an Outfall: Permanent

• Notify DNR inspector so that he can confirm closure. • Notify IDEM Permit Writer, clearly indicating which

outfall is permanently closed and the date of closure.• The Permit Writer will notify Data Stewards so that

DMR reporting requirements can be removed from EPA database for that outfall, to prevent false noncompliance (due to DMR non-submittals).

Page 53: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

Questions?

Page 54: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

DMR with Violation

Page 55: NPDES Reporting Indiana NPDES DMR Data: maintained for compliance tracking purposes for Indiana and EPA Indiana Society of Mining and Reclamation Technology

MMR w/Exemption Violation