Regional Connector Transit Project Construction Update Flower St/Financial District CLC Meeting November 8, 2016
1
CONSTRUCTION UPDATE Flower St/Financial District
2
Flower St/Financial District Ongoing/Look Ahead Schedule
Activity NOV DEC JAN FEB MAR APR
24” waterline relocation 5th–6th St. (nights)
Deck installation 4th–5th St. (weekends only)
Pre-trenching (weekdays) and piling 5th–6th St (east side)
Tieback removal at 3rd St. 3
Deck Installation Closure Details
> Flower St (3rd to 5th St) and 4th St (Figueroa to Flower St)
> Traffic lane reduction, followed by full street closure, start at 7 p.m., Friday. Street reopens at 5 a.m., Monday
> 14 weekends
> Activities include: – Roadway removal
– Excavation
– Hanging of utilities
– Cap beam installation
Flower St/Financial District 4
− Deck beam installation − Deck panel installation − Grade deck transition
Local Access Map – Through 12/5/16
> Local access maintained – Bank of America Plaza & World Trade Center enter from 3rd St
– Citigroup Center, J2 Garage and The Bonaventure Hotel enter from 5th St. Drivers must turn right onto Flower St from 5th St
5 Flower St/Financial District
Local Access Map – Starting 12/9/16
> Local access maintained – Bank of America Plaza & World Trade Center enter from 3rd St – Citigroup Center, J2 Garage and The Bonaventure Hotel enter
from 4th & 5th St. Drivers must turn right onto Flower St from 5th St
6 Flower St/Financial District
Detour Map
> Alternate routes: – Grand Ave to 5th St – 3rd St to Beaudry to 6th St
7 Flower St/Financial District
Deck Installation Closure Dates
> Initial weekend closure dates: > 7pm on 10/14/16 - 5am on 10/17/16 - Completed > 7pm on 10/21/16 - 5am on 10/24/16 - Completed > 7pm on 10/28/16 - 5am on 10/31/16 - Completed > 7pm on 11/4/16 - 5am on 11/7/16 - Completed > 7pm on 11/18/16 - 5am on 11/21/16 > 7pm on 12/2/16 - 5am on 12/5/16 > 7pm on 12/9/16 - 5am on 12/12/16 > 7pm on 12/16/16 - 5am on 12/19/16 > 7pm on 1/6/17 - 5am on 1/9/17 > Four additional weekends are scheduled in January/February
Flower St/Financial District 8
Deck Installation Progress Photos
9 Flower St/Financial District
Deck Installation Progress Photos
10 Flower St/Financial District
Decking on Flower St, 4th to 5th St
> Mitigations – Activities such as saw cutting, grinding and
roadway removal will be performed before 9 pm
– Sound barriers will be in place
– Lights will be directed toward the work zone
– Use of back-up alarms will be minimized
– Flaggers will assist motorists
– In-language 24/7 hour hotline—213.922.7277
11 Flower St/Financial District
Ongoing Activities
> Tieback removal at 3rd Street, over 40’ deep (on photo)
> 24” water line relocation on Flower St, at the 5th and 6th St intersections
Flower St/Financial District 12
Contact Us
metro.net/RegionalConnector twitter.com/MetroConnector facebook.com/MetroRegionalConnector 213.922.7277 [email protected]
13