Scoping, Estimating and Negotiations
Laura Sutton, PE, CPM
November 6, 2018 Project Manager Workshop
Notice to Proceed in 30-Days
Scoping, Estimating and Negotiations
Identify Project Needs
Develop Project Fact
Sheet
Select Firm from LSC
DOH / Unit Approves Firm
Notify Firm & Provide Fact
Sheet
NCDOTPre-Scopes
Tasks
FirmPre-Scopes
Tasks
Scope Tasks with Firm(May involve meeting / teleconference /
email exchange / questions / minutes)
NCDOT completes independentManday Cost Estimate
Firm completes independentManday Cost Estimate
Complete Cost Comparison
Verify rates
Check Sub-consultants
DAY –XNotify Firm and
Supporting Units
DAY 0Scope Contact
DAY 6Scope Response from Firm, Subs and Supporting Units
DAY 10Scope
Concurrence
DAY 17Unit Estimates
Due to PMSub Estimates Due to Prime
DAY 20Initial Estimate
Submitted
DAY 21 DAY 24Negotiations
Complete
Negotiate Mandays and Classifications
Submit Final NCDOT and PEF Manday
Cost Estimates
Complete AIR Form
Complete and Sign
Cost Comparison
Sheet
Firm begins Work
Gather Executed NTP Letter and
Signed RS-2 Forms
DAY 30Process
Complete
Attach forms to PO in SAP and email PSMU
DAY 28Forms
Returned
PO Approval in SAP Workflow
(PSMU, OIG, Fiscal)
Create PO in SAP
under LSC
DAY 25Notice to Proceed
Issue NTP Letter
• What information is available?
– STIP Description
– Feasibility Study or Project Scoping
Reports
– SPOT safety project
• Major Milestone Schedule
– Environmental Document
– Right-of-Way Plans
– Let Date
• What should be scoped?
– Scope to entire project or limit task
order to a specific phase
– Cost plus or lump sum
Identify Project Needs:
Scoping, Estimating and Negotiations
• Is specialized expertise needed?
– Innovative interchange or intersection
design
– Significant hydraulic or structure
design
– Railroad track design or detour
alignment
• Are there special considerations?
– Rail involvement
– Land management agency
involvement
– FERC conveyance or application
– Local municipality requests
– Maintenance of traffic concerns
Develop Project Fact Sheet:
• Include basic project
information such as
programmed R/W and
Let dates, funding
source and contract
type
• Identify services /
disciplines to be
included in contract
• List important
milestonesReference:
https://connect.ncdot.gov/business/cons
ultants/Pages/Guidelines-Forms.aspx
Scoping, Estimating and Negotiations
Select Firm:
• Use available on-call
contracts or project
specific advertisements
• On-call (LSC and GESC)
contracts typically allow
for quicker on-boarding
• Utilization reports are
updated monthly and
show details such as
remaining contract
authorityReference:
https://connect.ncdot.gov/business/consult
ants/Pages/Guidelines-Forms.aspx
Contract Expiration
Date
Extension Option
Revised Expiration
Date
Estimated Advertisement
ScheduleNew Contract
2015 Eastern Divisions’ LSCs (1-4 & 6)
February 2019
ExtendAugust 2019
February 2019Will cover Divisions 1-7 and overlap current Central Divisions’ LSCs.
2016 Central Divisions’ LSCs (5 & 7-9)
October 2018
ExtendOctober
2019NO
READVERTISEMENT
Merged into Westernand Eastern Divisions’ LSCs
2016 Statewide Planning & Design LSCs
February 2020
ExtendAugust 2020
February 2020Centrally managed Planning & Design contracts
2017 On-call GESC for Division Managed Projects LSCs
March2019
ExtendMarch2020
NO READVERTISEMENT
Merged into Westernand Eastern Divisions’ LSCs
2018 Western Divisions’ Planning &Design and GESC LSCs
August 2020
Covers Divisions 8-14 and overlaps current Central Divisions’ LSCs.
Scoping, Estimating and Negotiations
NCDOT Pre-Scope Tasks:
• Check WBS funding (SAP transaction ZPSR01).
• If needed, request additional PE funds (EBS Portal – TIP Funding Request
tile).
• Develop preliminary scope of work including preliminary task list using the
NCDOT SCOPE AND MANDAY ESTIMATE FORM spreadsheet.
In an effort to minimize back and forth that often occurs, everyone should
come prepared to discuss their tasks with the goal of clarifying and/or
modifying tasks based during the scoping
meeting discussions.
• Establish NTP timetable, including initial
scope contact date (Day 0), and update
the project fact sheet.
Scoping, Estimating and Negotiations
Firm Pre-Scope Tasks:
• Based on data provided to
date, the firm pre-scopes
tasks and develops a
“blank” scope and manday
estimate form with
anticipated tasks for each
discipline.
• For costs to be calculated,
the consultant employees,
classifications, and rates
should be entered on the
PEF Classification Tab.
Scoping, Estimating and Negotiations
Firm Pre-Scope Tasks:
• If the firm would like NCDOT to
consider increasing the standard 9%
fee (profit margin) for a specific
project/task order based on schedule,
size/value, duration or complexity, the
firm is required to justify the higher fee
and submit the Fee Negotiation Form
for approval by PSMU, the Division
Engineer or the business unit head
prior to submitting their initial
estimate.
Reference:
January 24, 2018 Technical Services Memo
Scoping, Estimating and Negotiations
Scope Tasks with Firm:
Day 0 Scope Contact
Hold scoping meeting with all involved
NCDOT staff, the firm and their
sub-consultants.
Day 6
Firm submits scoping meeting minutes for review and acceptance to the
project manager, project team and meeting invitees.
Firm submits proposed schedule in Microsoft Project Gantt Chart format.
Day 10 Scope Concurrence
Scopes and schedules are agreed upon. Project manager submits a
“blank” spreadsheet to team members in each discipline and requests
an initial manday cost estimate with a 1 week deadline.
Scope Tasks with Firm(May involve meeting / teleconference / email
exchange / questions / minutes)
DAY 0Scope Contact
DAY 6Scope Response from Firm, Subs
and Supporting Units
DAY 10Scope
Concurrence
Scoping, Estimating and Negotiations
Initial Estimate Review:
Day 21
Complete cost comparison spreadsheet, verify rates (salary,
classifications, overhead, fee, and cost of capital) on the
PEF Classification Sheet tab. In addition, check for appropriate
usage of sub-consultants for consistency with the original LSC outline
agreement documentation. Responsibility for this task generally falls to a
PSMU liaison but may vary across your division or business unit.
When the cost comparison indicates that the initial manday
cost estimates differ by more than 5% by discipline, then
negotiations are required. The project manager will submit
both the cost comparison and the firm’s initial estimate to
the required team member(s) to negotiate with the firm.
Complete Cost Comparison
Verify rates
Check Sub-consultants
DAY 21
Scoping, Estimating and Negotiations
Negotiations:
Day 24
Negotiations for each discipline should be completed within
three days and the final estimate for each discipline returned to
the project manager.
Since NCDOT now uses the firm’s salary rates (with a few exceptions),
it is important to negotiate not only the mandays but also the
classifications and direct costs, if necessary.
Project Manager compiles/merges the final (i.e., negotiated) in-house
manday cost estimate for all disciplines.
Firm compiles/merges the estimates for each sub-consultant and
submits their final negotiated PEF manday cost estimate.
DAY 24Negotiations
Complete
Negotiate Mandays and Classifications
Submit Final NCDOT and PEF
Manday Cost Estimates
Scoping, Estimating and Negotiations
Final Estimate/AIR Form:
Day 25
Project manager completes the Account Initiation Request
(AIR) form. This includes populating all selected disciplines
and assigning the WBS, Cost Centers and Function Codes.
Please note that some disciplines (i.e., Roadway and Hydraulics) may
have more than one line item due to multiple function codes (3PEF or
4PEF).
Project manager submits the final in-house manday cost estimate.
Re-negotiations will be required if mandays differ by more than 5% after
the final cost comparison is completed.
Complete AIR Form
Complete and Sign Cost
Comparison Sheet
Scoping, Estimating and Negotiations
Notice to Proceed in 30-Days
Scoping, Estimating and Negotiations
Identify Project Needs
Develop Project Fact
Sheet
Select Firm from LSC
DOH / Unit Approves Firm
Notify Firm & Provide Fact
Sheet
NCDOTPre-Scopes
Tasks
FirmPre-Scopes
Tasks
Scope Tasks with Firm(May involve meeting / teleconference /
email exchange / questions / minutes)
NCDOT completes independentManday Cost Estimate
Firm completes independentManday Cost Estimate
Complete Cost Comparison
Verify rates
Check Sub-consultants
DAY –XNotify Firm and
Supporting Units
DAY 0Scope Contact
DAY 6Scope Response from Firm, Subs and Supporting Units
DAY 10Scope
Concurrence
DAY 17Unit Estimates
Due to PMSub Estimates Due to Prime
DAY 20Initial Estimate
Submitted
DAY 21 DAY 24Negotiations
Complete
Negotiate Mandays and Classifications
Submit Final NCDOT and PEF Manday
Cost Estimates
Complete AIR Form
Complete and Sign
Cost Comparison
Sheet
Firm begins Work
Gather Executed NTP Letter and
Signed RS-2 Forms
DAY 30Process
Complete
Attach forms to PO in SAP and email PSMU
DAY 28Forms
Returned
PO Approval in SAP Workflow
(PSMU, OIG, Fiscal)
Create PO in SAP
under LSC
DAY 25Notice to Proceed
Issue NTP Letter