    News/Updates

    Despite a very wet August, the roof of the new facility is now sealed against the weather

    with all the glass installed in the roof lights. The facades are beginning to take shape

    with brickwork showing over the hoarding and glass being installed on the gable ends.

    The M&E specialists are now very much involved and have to date installed 65.5km of

    cabling.

    The squash court walls are also starting to be installed.

    As we head into the final stages of the build, we will update you of further progress.