    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    INDEX

    1.0 Project Background 2

    2.0 Third Party Quality Audit Consultant 3

    3.0 Major Activities and Review Meetings of the Month 3

    4.0 Status of TPQA Visits 4

    5.0 Progress of NCRMP works 5

    TPQA Status Report for NCRMP Works and NCRs Pending up to end of November 2012 6

    6.0 District wise status of tests conducted by TPQA 30

    7.0 Details of QC Audit Reports Submitted during this Month 31

  • 7/30/2019 November 2012 Mpr

    3/122

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    1.0 Project Background

    Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state,

    the nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-

    December, cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic

    events are increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years

    ranging from 1892 to 1989, there were as many as 67 cyclones within the State.

    It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster

    due to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based

    on experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the

    existing facilities available in the project area in Andhra Pradesh.

    The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development

    Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the

    proceeds to payments for goods, works, related services and consulting services under this Project.

    National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra Pradesh, headquartered at

    Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality

    Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna,

    Guntur, Prakasam and Nellore. The project Construction of Multipurpose Cyclone Shelters, Roads to Cyclone

    Shelters, and Roads to habitations and Roads & Bridges under NCRMP is funded by International Development

    Association and received through Government of India. This consultancy is envisaged to audit the quality of works being

    implemented by various line departments working under PIU. The number of works under progress / for which

    g t l d d i h di t i t i h i th t bl b l

  • 7/30/2019 November 2012 Mpr

    4/122

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    2.0 Third Party Quality Audit Consultant.

    To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to

    Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for

    Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV

    with Egis India Consulting Engineers (I) Pvt. Ltd. On 31 st May2011, the Contract for Consultancy Service was signed

    between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and

    the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd .

  • 7/30/2019 November 2012 Mpr

    5/122

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4.0 Status of TPQA Visits:

    The following table shows the details of TPQA visits to sites in respective districts.

    DistrictTotal Number of Visits

    Up to Oct.'2012 In Nov.'2012 Up toNovember.'2012

    Srikakulam 388 28 416

    Vizianagaram 66 05 71

    Vishakhapatnam 327 11 338

    East Godavari 558 32 590

    West Godavari 397 13 410

    Krishna 247 14 261

    Guntur 320 21 341Prakasam 367 17 384

    Nellore 294 13 307

    No. of Visits by TPQA

  • 7/30/2019 November 2012 Mpr

    6/122

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    5.0 Progress of NCRMP works:

    The district wise progress of works is shown below. The works in the West Godavari are not started and the works in

    Krishna District has just started. At many places the first milestone is completed but works are not started. The line

    departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the

    agreement conditions should be imposed.

    Third Party Quality Audit by Egis India consulting services

    Summary of Activities

    S.No. District

    Agreements for PackagesCommunicated Status of works

    PR R&B Progress Not Started

    1 Srikakulam 6 5 21 0

    2 Vizianagaram - 3 3 0

    3 Visakhapatnam 13 0 21 0

    4 East Godavari 7 0 12 1

    5 West Godavari 3 0 10 0

  • 7/30/2019 November 2012 Mpr

    7/122

    MONTHLY REPORT

    6 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    TPQA STATUS REPORT FOR NCRMP WORKS TO THE END OF NOVEMBER 2012

    S.No. District

    Packages / Worksentrusted Status of Works No. of

    Visitsof

    TPQA

    TotalNo. of

    QCtestsdone

    NCRs Audit

    ReportsIssued

    Environmental& SocialReportsIssued

    PR R&B Started NotStarted Issued closed Pending

    1 Srikakulam 06 - 16 5_5 21 0 416 1393 54 48 6 71 52

    2 Vizianagaram - 3_3 3 0 71 457 3 1 2 11 9

    3 Visakhapatnam 13 - 21 - 21 0 338 2131 25 25 0 69 41

    4 East Godavari 07 - 13 - 12 1 590 1076 28 28 0 49 30

    5 West Godavari 03 - 10 - 10 0 410 349 20 20 0 52 37

    6 Krishna 04 - 08 - 8 0 261 82 3 3 0 35 21

    7 Guntur 06 - 15 2_2 17 0 341 583 14 12 2 56 32

    8 Prakasam 12 - 23 1_1 24 0 384 1899 36 30 6 113 50

    9 Nellore 17 - 26 - 26 0 307 1093 31 26 5 106 48

    Total 68_132 11_11 142 1 3118 9063 209 185 21 562 320

  • 7/30/2019 November 2012 Mpr

    8/122

    MONTHLY REPORT

    7 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATUS OF WORKS IN SRIKAKULAM DISTRICT UP TO 30.11.2012

    Category

    Packagesallotted under

    Phase - 1Names of works under eachpackage AgreementNo. / Date

    Milestone Completion Dates Progress w.r.t.milestone up

    to 30.05.2012Remarks

    First Second Third

    RHB

    NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

    Road from DPN R&B road toUddandapalem

    /2010-11, Dt.30.04.2011 31.08.11 31.12.11 30.04.12

    complete Entirework

    BT layercompleted

    Road from K. Umilada Junction toKoduru (Link Road)

    /2010-11, Dt.30.04.2011 31.08.11 31.12.11 30.04.12

    complete Entirework

    BT layercompleted

    Road from Borubhadra, Malagam

    to Kollipadu via Seepuram,Gantapeta

    /2010-11, Dt.30.04.2011 31.08.11 31.12.11 30.04.12

    complete Entirework

    BT layercompleted

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

    Road from R&B road Mobagam toDuubakavanipeta via

    Gajapathinagaram

    /2010-11, Dt.30.04.2011 30.08.11 31.12.11 30.04.12

    First Milestonei.e Earthwork & Cd works &GSB

    300 mts CCroad

    completed,GSB laying is inprogress, road

    formationwidth vary

    from 6.00mtsto 7.50mts

    Road from Talasamudram to DolaRegulator

    /2010-11, Dt.30.04.2011 30.08.11 31.12.11 30.04.12

    First Milestonei.e Earthwork & Cd works &GSB

    WBM GR-IIIlaying is inprogress

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

    Road from R&B road Edulavalasa -Killam to Jonnam via

    Talasamudram

    /2011-12, Dt.30.04.2011 31.07.11 31.10.11 31.01.12

    First Milestonei.e Earthwork & Cd works &GSB

    WBM Gr-II & III metal

    collection is inprogress

  • 7/30/2019 November 2012 Mpr

    9/122

    MONTHLY REPORT

    8 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Bridges

    NCRMP/B-W/ AP/Br/R&B/01/Patnavanipeta/001

    Construction of bridge at Km 11/6-8 of NH-5 to PatnavanipetaConnecting Sundarapalem

    46/2011, Dt.17.12.2010 17.08.11 17.01.12 17.06.12

    Completion of entire work

    Sub structurefor bridgecompleted,

    Approach roade/w, GSB,WMM, SDBCcompleted. CD,R/W workscompleted.Slab concretework is inprogress.

    NCRMP/B-

    W/AP/Br/R&B/01/Surampeta/003

    Construction of Minor Bridge at Km

    12/2-4 of NH-5 to Surampeta Roadvia Naruva, Mentada

    45/2010-

    2011,Dt17.12.2010 17.05.11 17.10.11 17.03.12Completion of

    entire work

    Deck slabswearing coat &

    hand rails

    completed, Approach roadwork

    completed.

    NCRMP/B-W/AP/Br/R&B/01/Bendigedda/004

    Construction of High level bridgeacross Bendigedda at KM 4/10 of

    Pundi-Parlakimidi road inSrikakulam Dt, A.P.

    1/2010,Dt.11.11.2010 11.08.11 11.01.12 11.06.12

    Completion of entire work

    Slabscompleted and

    Approach roadWMM

    completed.

    RoadsNCRMP/B-W/AP/RD/R&B/01

    /Nowpada/006)

    Improvements Nowpada- Venkatapuram road from0/0to15/0km

    43/2010-11,17.12.201

    0 17.05.11 17.10.11 17.03.12Completion of

    entire work

    BT work completed, CC

    Roadcompleted

    RCS

    NCRMP/B-W/AP/RCS/PRED/01/V.KOTTURU/002

    Road from NP road to URK PuramG.o rt No 451

    dt06.04.2010

    29.01.12 29.05.12 29.09.12 WBM GR-II &IIIcomplete

    BT layercompleted &

    CC roadcompleted

    Road from Deppuru, Bahadapalliroad to Onkuluru & to cycloneshelter

    G.o rt No 451dt

    06.04.201129.01.12 29.05.12 29.09.12 WBM GR-II &IIIcomplete

    BT layercompleted &

    CC roadcompleted

  • 7/30/2019 November 2012 Mpr

    10/122

    MONTHLY REPORT

    9 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&B road toDevunthalada

    G.o rt No 451dt

    06.04.201229.01.12 29.05.12 29.09.12 WBM GR-II &IIIcomplete

    BT layercompleted &

    CC roadcompleted

    Road from Pollada toKomaralthada & to cyclonic shelter

    G.o rt No 451dt

    06.04.201329.01.12 29.05.12 29.09.12 WBM GR-II &IIIcomplete

    BT layercompleted &

    CC roadcompleted

    NCRMP/B-W/AP/RCS/PRED/

    01/ETCHERLA/005

    Road from Koyyam R&B Road toMoosavanipeta

    G.o rt No 451dt

    06.04.201007.11.11 07.02.12 07.06.12 Completion of entire work

    BT layercompleted

    Road from Mentada to DovupetaG.o rt No 451

    dt06.04.2010

    07.11.11 07.02.12 07.06.12 Completion of entire work BT layer

    completed

    Road from Kotcherela road toKollibhemavaram & cyclonicshelter

    G.o rt No 451dt

    06.04.201007.11.11 07.02.12 07.06.12 Completion of entire work

    BT layer

    completed & CC road

    completed

    Road from Kotcherla road toPathesundrapalem

    G.o rt No 451dt

    06.04.201007.11.11 07.02.12 07.06.12 Completion of entire work

    BT layer & CCroad

    completed

    MPCS

    NCRMP/B_W/AP/MPCS/PRED/01/S

    anthabommali/005

    Construction of Cyclone shelter atKollipadu

    G.o rt No 451dt

    06.04.201007.03.12 07.08.12 07.01.13

    Completion of stilt floor & first

    floor

    Silt floor levelslab

    completed.

    Construction of Cyclone Shelter atRunku

    G.o rt No 451dt

    06.04.201007.03.12 07.08.12 07.01.13

    Completion of stilt floor & first

    floor

    plinth beamcompleted

    sand filling isin progress,and columnsabove plinthbeam is inprogress

  • 7/30/2019 November 2012 Mpr

    11/122

    MONTHLY REPORT

    10 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATUS OF WORKS IN VIZIANAGARAM DISTRICT UP TO 30.11.2012

    CategoryPackages

    allotted underPhase - 1

    Names of works under eachpackage

    AgreementNo./ Date

    Milestone Completion Dates Progress w.r.t.milestone up

    to 31.08.2012Remarks

    First Second Third

    Bridges

    NCRMP/B-W/ AP/Br/ R&B/

    02/Puligadda/ 007

    Construction of Minor Bridge atKm. 7/2 near Puligedda of Konada Ramatheertham R&B Road toKonathalapalem via Yerukonda,

    Pasupam, Kollayavalsa (Z.P. Road)

    31/2010-2011Dt. 01.12.2010 30.06.11 31.01.12 31.05.12

    100% of work completed

    As against of 100 % in the

    3rdMilestone

    NCRMP/B-W/ AP/Br/ R&B/ 02/

    Chakaligadda /008

    Construction of Minor Bridge atKm 15/2 near Chakaligadda of

    Konada Ramatheertham R&B roadto Konathalapalem (via)

    Yerukonda, Pasupam, Kollayavalsa(ZP Road)

    34/2010-2011Dt. 08.12.2010 07.07.11 07.02.12 07.06.12

    90% of work completed

    As against of 100 % in the

    3rdMilestone

    RoadNCRMP/B-

    W/AP/RD/R&B/02/ Konada/009

    Improvements to Road from

    Konada Ramatheertham (R&B)Road to Konathalapalem (Via)Pasupam, Yerukonda,

    Kollayavalsa from Km 12/0 to 16/5(Km 0/0 to 4/0 i.e. up to NH-5

    crossing)

    33/2010-2011Dt. 08.12.2010 07.06.11 07.12.11 07.03.12

    100% of work completed -

  • 7/30/2019 November 2012 Mpr

    12/122

    MONTHLY REPORT

    11 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATUS OF TOTAL WORKS IN VISAKHAPATNAM DISTRICT UP TO NOVEMBER-30.11.2012

    Categor y

    Packagesallotted underPhase - 1

    Names of worksunder each package

    AgreementNo. / Date

    Milestone Completion DatesProgress w.r.t.milestone up to

    30.11.2012Remarks

    First Second Third

    MPCS

    NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/

    003

    Construction of cycloneshelter at

    Gajapathinagaram

    /2011-12, Dt.03.10.2011 05.06.12 05.10.12 05.02.13

    Plinth beam & Staircase,Stilt floor slab, First floorslab, ramp slabs arecompleted. EOAT submittedon 24.08.12

    RevisedMilestonesubmitted

    & Work progress is

    withinmilestone.

    Construction of cycloneshelter at Ratnayampeta

    /2011-12, Dt.03.10.2011 02.02.12 02.06.12 02.10.12

    All Slabs are completed.Inside and outside wallplastering work completed.White cement applications,wood joinery and Electricalworks are to be progress.

    Within theMilestone

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cycloneshelter at Patimeeda

    /2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13

    Plinth beam & Staircase,Stilt floor slab, First floorslab, ramp slabs arecompleted. EOATsubmitted on 24.08.12

    Work progress is

    slow.

    Construction of cycloneshelter at Mullaparra

    /2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13

    Stilt Slab & stilt floor, Firstfloor and head room slabsare completed. Ceilingplastering work and firstfloor brick work are inprogress.

    Work progress is

    slow.

  • 7/30/2019 November 2012 Mpr

    13/122

    MONTHLY REPORT

    12 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Construction of cycloneshelter at Bangarampeta

    /2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13

    Stilt floor, First floor,second floor, Head roomslabs are completed. Istfloor and second floor brick masonry work is inprogress.

    Work progress is

    slow.

    NCRMP/B-W/AP/MPCS/PRED/

    03/Rambilli/004

    Construction of cycloneshelter at

    Venkayyapalem

    /2011-12, Dt.03.10.2011 02.01.12 02.04.12 02.07.12

    Plinth beam completed andfilling under floor is inprogress. EOAT proposalssubmitted on 29.06.12.

    Progressis Slow

    NCRMP/B-W/AP/MPCS/PRED/03/Parawada/001

    Construction of cycloneshelter at

    Thikkavanipalem

    /2011-12, Dt.07.10.2011 06.01.12 06.04.12 06.07.12

    Work not started due tosite problem

    Progressis Slow

    NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/00

    1

    Road from NH-5 toRamarayadupalem

    /2011-12, Dt.15.09.2011 14.12.11 14.03.12 14.06.12

    Road Furniture & B.T iscompleted.

    Within theMilestone

    NCRMP/B-W/AP/RCS/PRED/0

    3/Rambilli/002

    Road from R & B road toRajakoduru

    /2011-12, Dt.15.09.2011 14.01.12 14.05.12 14.09.12

    CD works are completed & B.T work is Completed

    Within theMilestone

    Road from R & B road toKattubolu to Marripalem

    /2011-12, Dt.15.09.2011 14.01.12 14.05.12 14.09.12

    CD works are completed & B.T work is Completed

    Within theMilestone

    Road from R & B road toKrishnampalem

    /2011-12, Dt.15.09.2011 14.01.12 14.05.12 14.09.12

    CD Work is completed & B.T work is completed

    Within theMilestone

    NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

    Road from R&B road toPedatheernala toChinatheernala

    /2011-12, Dt.15.09.2011 14.12.11 14.03.12 14.06.12

    B.T & C.C road works areCompleted.

    Within theMilestone

  • 7/30/2019 November 2012 Mpr

    14/122

    MONTHLY REPORT

    13 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from UpmakaRajayyapeta R&B road

    to Janakayyapeta

    /2011-12, Dt.15.09.2011 14.12.11 14.03.12 14.06.12

    CD works are Completed & B.T work is completed

    Within theMilestone

    NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001

    Road from Vempudi toPatimeeda

    /2010-11, Dt.11.01.2011 10.05.11 10.09.11 10.01.12 Work is completed -

    Road from R&B road toMullaparra up to Beach

    end

    /2010-11, Dt.27.01.2011 26.04.11 26.07.11 26.10.11 Work is completed -

    NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/00

    3

    Road from R&B B.PKallalu to

    Matchvanipalem

    /2010-11, Dt.10.03.2011 09.06.11 09.09.11 09.12.11 Work is completed -

    NCRMP/B-W/AP/RHB/PRED/0

    3/Paravada/004

    Road from R & B road to

    Pothurajanapalem

    /2010-11, Dt.

    28.03.201127.06.11 27.09.11 27.12.11 Work is completed -

    Road from R & B road toJalaripeta

    /2010-11, Dt.28.03.2011 27.06.11 27.09.11 27.12.11 Work is completed -

    NCRMP/B-W/AP/RHB/PRED/0

    3/Rambilli/006

    Road from R & B road to Venkayyapalem

    /2010-11, Dt.11.01.2011 10.04.11 10.07.11 10.10.11 Work is completed -

    NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/0

    07

    Road from R&B road to Ava- Somavaram

    /2011-12, Dt.27.04.2011 26.07.11 26.10.11 26.01.12 Work is completed -

    Road from R&B Road to Avarajam

    /2011-12, Dt.27.04.2011 26.07.11 26.10.11 26.01.12 Work is completed -

  • 7/30/2019 November 2012 Mpr

    15/122

    MONTHLY REPORT

    14 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATUS OF WORKS IN DISTRICTS UP TO 30.11.2012 IN EAST GODAVARI DISTRICT.

    Categor y Packages allotted underPhase - 1 Names of worksunder each package Agreement No./ DateMilestone Completion Dates

    Progressw.r.t.

    milestoneup to

    31.07.2012

    Remarks

    First Second Third

    RCS

    NCRMP/B-W /RCS/PRED/04/Karapa/001

    Approach Road tocyclone Shelter at

    Adivipudi32/2011-12Dt:20.05.2011

    30-11-2011 31-10-2011 31-01-2012 100% Completed.

    NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto P.Chodipallipeta CS 73/2011-12Dt:07.09.2011

    3 months06.12.2011

    3 months06.03.2012

    3 months06.06.2012 100% Completed.

    NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto K.Chodipallipeta CS 73/2011-12Dt:07.09.2011

    3 months06.12.2011

    3 months06.03.2012

    3 months06.06.2012 100% Completed

    NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Hukumpeta CS 73/2011-12Dt:07.09.2011

    3 months06.12.2011

    3 months06.03.2012

    3 months06.06.2012 100% Completed

    NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003

    Road from R&B Roadto ChinaraghavulapetaCyclone Shelter

    74/2011-12Dt: 23.09.2011

    3 months22.11.2011

    3 months22.06.2011 ----------- 100% Completed

    NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Gaddipeta CS 73 /2011-12Dt:07.09.2011

    3 months06.12.2011

    3 months06.03.2012

    3 months06.06.2012 100% Completed

    NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Danavaipeta CS 73 /2011-12Dt:07.09.2011

    3 months06.12.2011

    3 months06.03.2012

    3 months06.06.2012 100% Completed

  • 7/30/2019 November 2012 Mpr

    16/122

    MONTHLY REPORT

    15 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto G.MusalayyapetaCS

    73/2011-12Dt:07.09.2011

    3 months06.12.2011

    3 months06.03.2012

    3 months06.06.2012 Nil

    Not yetStarted

    RHB

    NCRMP/B-W /AP/RHB/PRED/04/Karapa /001

    Road from Gurjanapallito Bandulavaripalem 24/2011-12Dt:27.04.2011

    30-09-2011 31-10-2011 31-01-2012 100% Completed

    NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

    Road from PR roads toDasarivanipeta and toCyclone Shelter

    18/2011-12Dt:27.04.2011

    30-11-2011 30-11-2011 20-01-2012 100% Completed.

    MPCS

    NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

    Construction of Cyclone Shelter atPedaraghavulapeta of Uppalaguptam Mandal

    E.G.Dt.

    78/2011-12Dt:17.10.2011

    3 months16.01.2012

    3 months16.04.2012

    3 months16.07.2012 30%

    Stilt FloorBeams andSlabreinforcement

    is in progress.

    NCRMP/B-W /AP/MPCS/PRED/04/Thondangi/001

    Construction of Cyclone Shelter atLakshmanudipeta inThondangi

    77/2011-12Dt:07.09.2011

    4 months16.02.2012

    4 months16.06.2012

    4 months16.10.2012 75%

    Stilt floorceiling,columnsplastering,Brick work infirst floor andCompoundwall is inprogress.

    NCRMP/B-W /AP/MPCS/PRED/04/Thondangi/001

    Construction of Cyclone Shelter at

    Avulamanda77/2011-12Dt:07.09.2011

    4 months16.02.2012

    4 months16.06.2012

    4 months16.10.2012 75%

    Stilt floorceiling,columnsplastering,Brick work infirst floor andCompoundwall is inprogress.

  • 7/30/2019 November 2012 Mpr

    17/122

    MONTHLY REPORT

    16 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATUS OF WORKS IN WEST GODAVARI DISTRICT UP TO 30.11.2012

    Category

    Packagesallotted under

    Phase 1

    Names of works under eachpackage

    AgreementNo. / Date

    Milestone Completion Dates Progress w.r.t.milestone up

    to 30.11.2012

    RemarksFirst Second Third

    RHB

    NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001

    Road from NH 214 A at Ranga Statuecenter to Harijanawada of Kalipatnam

    (E) (Mogalthuru Mandal

    16 /2011-12Dt.27.04.2011

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/2012

    100% Work Completed.

    R&B road at Panchayat Office toPulaparthivarithota via Badava(Mogalthuru Mandal W.G.Dist.)

    100% Work Completed.

    Mogalthuru Vempa R&B Road atUchintha Kalava Bridge to Gogulamma

    Harijanapeta (Mogalthuru Mandal)100% Work Completed.

    From Narsapur Mogalthuru R&B road toDayadaldaspeta via VenkateshwaraSwamy temple (Mogalthuru Mandal )

    100% Work Completed.

    Road from NH 214 A road toHarijanapeta of Kothota

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/2012100% Work Completed.

    NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002

    R&B road to Indira Nagar (via)Pochamma temple (Narsapur Mandal)

    21 /2011-12Dt.09.05.2011

    09/05/2011to

    04/09/2011

    05/09/2011to

    06/01/2012

    07/01/2011to

    08/5/2012

    100% Work Completed.Road from R&B road to Pedalanka

    (Narsapur Mandal W.G.Dist.) 100%Work

    Completed.Road from LB Cheria CC road to

    Chillapalem of LB Cheria.100% Work

    Completed.

    NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

    From A-U R&B Road toSatyanarayanapuram (Kalla Mandal)

    25 /2011-12Dt.26.05.2011

    26/5/2011To

    20/8/2011

    20/8/2011to

    21/11/2011

    22/11/2011To

    23/2/2012

    100% Work Completed.

    From A-U R&B Road to Mekaladibba(Kalla Mandal W.G.Dist.) 100%

    Work Completed

  • 7/30/2019 November 2012 Mpr

    18/122

    MONTHLY REPORT

    17 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATUS OF WORKS IN KRISHNA DISTRICT UP TO 30.11.2012

    Category

    Packages allottedunder Phase - 1

    Names of works undereach package

    Agreement No. /Date

    Milestone Completion DatesRemarks

    First Second Third

    RHB

    NCRMP/B-W/AP/RHB/PRED/06/Ma

    chilipatnam/001

    Road connecting R&B roadthrough Gantlammapalem

    8/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012

    CD works, GSB, Gr-II,Gr-III, BT completed

    NCRMP/B-W/AP/RHB/PRED/06/Ma

    chilipatnam/002

    Road from R & B Road toB.V Thota

    7/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012

    CD works, GSB, Gr-II,Gr-III, BT completed

    Road from Potalapalem Z.Proad to Chikativanipalem

    7/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012

    CD works, GSB, Gr-II,Gr-III, BT completed

    NCRMP/B-W/AP/RHB/PRED/06/Kr

    uthivennu/003

    Road from Intheru R&BRoad to Rangaraopet

    9/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012

    CD works, GSB, Gr-II,Gr-III, BT completed

    Road from R&B road toCyclone Shelter atChandala

    9/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012

    CD works, GSB, Gr-II,Gr-III, BT completed

    RCS

    NCRMP/B-W

    /AP/RCS/PRED/06/Machilipatnam/001

    Road from BhogireddypalliR&B Road toRamakhandam

    32/2011-12/Dt.02.09.2011 01.12.2011 01.03.2012 01.06.2012

    CD works, GSB, Gr-II,Gr-III, BT, CC

    completed

    Road from R&B Road

    Chinnapuram toGundupalem

    32/2011-12/27.04.2011 01.12.2011 01.03.2012 01.06.2012

    CD works, GSB, Gr-II,Gr-III, BT completed

    Road from Potlapalem Z.Proad to Pothepalli.

    32/2011-12/Dt.02.09.2011 01.12.2011 01.03.2012 01.06.2012

    GSB, Gr-II, Gr-III, CC,BT completed

  • 7/30/2019 November 2012 Mpr

    19/122

    MONTHLY REPORT

    18 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATUS OF WORKS IN GUNTUR DISTRICT UP TO 30.11.2012

    Category

    Packages allottedunder Phase - 1

    Names of works undereach package

    Agreement No./Date

    Milestone completion dates Progress

    w.r.t.milestoneup to

    31.11.2012

    RemarksFirst Second Third

    RHB

    NCRMP/B-W/AP/RHB/PRED/07/KA

    RLAPALEM/001

    R/f Ganapavaram R&BRoad to Kesavapuri ST colony

    7/2011-2012

    27.04.2011

    26.7.2011 26.10.2011 26.01.2012 - Completed.

    NCRMP/B-W/AP/PRED/07/Nagara

    m/002

    R/f R&B Road to Mohammad Alipalem

    8/2011-2012

    27.04.2011

    26.8.2011 26.12.2011 26.4.2012 - Completed.

    R/f R&B Road toKaturivaripalem.

    - Completed.

    Bridges

    NCRMP/B-W/AP/Br/R&B/07/Bapatl

    a/010

    Reconstruction of High-levelBridge @Km5/2 of Bapatla-Suryalanka Road across peralidrain in Guntur Dt.

    79/2010-20111.12.2010

    31.5.2011 30.11.2011 31.5.201290% WMMcompleted.

    NCRMP/B-W/AP/Br/R&B/07/Bapatl

    a/011

    Reconstruction of High-levelBridge @Km2/4 of Bapatla-Pandurangapuram Road acrossperali drain in Guntur Dt.

    78/2010-2011

    1.12.2010

    31.5.2011 30.11.2011 31.5.2012

    90% Approaches

    is inprogress

    RCS

    NCRMP/B-W/AP/RCS/PRED/07/PV

    Palem/001

    Road from R&B road toMandevaripalem

    2011-20121.11.2011

    31.01.2012 30.04.2012 31.07.2012- Completed.

    Road from R&B Road Alluru to

    Yadavapalem

    31.01.2012 30.04.2012 31.07.2012

    45%

    From Km

    0.574 to km0.964 CCcompleted.

    NCRMP/B-W/AP/RCS/PRED/07/Karl

    apalem/002

    Road from Ganapavaram R&BRoad to Pedamarpuvaripalem

    2011-20121.11.2011

    29.02.2012 30.06.2012 31.10.201220%

    WBM Gr-IIis in

    ProgressRoad from R&B Road toChinapuluguvaripalem

    29.02.2012 30.06.2012 31.10.201225% GSB, CC isin Progress

  • 7/30/2019 November 2012 Mpr

    20/122

    MONTHLY REPORT

    19 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    From R&B roadtoYaramvaripalem

    29.02.2012 30.06.2012 31.10.201295% Completed.

    Road from R&B Road toPedagollapalem CycloneShelter

    29.02.2012 30.06.2012 31.10.201298% Completed.

    Pedagollapalem P.R road toBonthagoralapalem

    29.02.2012 30.06.2012 31.10.201295%

    Shouldersare in

    progress.

    NCRMP/B-W/AP/RCS/PRED/07/Niz

    ampatnam/003

    Road from R&B Road toGurunadhanagar

    2011-201217.10.2011

    16.01.2012 16.04.2012 16.07.201299% Completed.

    Road from R & B Road to Adavala H/O Bavaji palem

    16.01.2012 16.04.2012 16.07.201299% Completed.

    Road from R & B Road to Atlavaripalem

    16.01.2012 16.04.2012 16.07.201299% Completed.

    NCRMP/B-W/AP/RCS/PRED/07/Bap

    atla/004

    Road from R & B Road toHanumathanagar 2011-201227.10.2011 26.01.2012 26.04.2012 26.07.2012 99% Completed.

    Road from R & B Road to Adarsh nagar

    26.01.2012 26.04.2012 26.07.201299% Completed.

  • 7/30/2019 November 2012 Mpr

    21/122

    MONTHLY REPORT

    20 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATUS OF WORKS IN PRAKASAM DISTRICT -NOVEMBER-2012

    Category

    PackagesallottedunderPhase - 1

    Names of works undereach package

    Agreement No. /Date

    Milestone completion dates Progress of work for the

    month -November

    Remarks

    %Work

    CompletedFirst Second Third

    BRIDGES

    NCRMP/B-W/AP/Br/R& B/08/Kanaparthy/012

    Construction of High level Bridgeat Km 16/10 of Naguluppapadu

    Kanaparthyroad

    76/2010-11 Dated1/12/2010

    5/31/2011Completionup to silllevel

    12/31/2011Completionup to belowdeck slab

    5/31/2012Completionof entirework includingapproaches

    Bridge work iscompleted.

    As permilestonecompleted

    100%

    RHB

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

    Road fromPakala ZP Roadto AulavaripalemCyclone shelter

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Dated25.04.2011

    8/24/2011Earth work,

    CD work,GSB

    12/24/2011WBM, Grade

    II & III

    4/24/2012BT,

    Shoulders& road

    furniture

    CC Road & Shoulders work isCompleted.

    Mile stone-IIIcompleted

    100%

    Road from R&BRoad toSomarajupalli

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Dated25.04.2011

    BT, CC road & culverts arecompleted fromKM 0/0 to 2/146.

    Mile stone-IIIcompleted

    100%

    Road from R&Broad toNarravaripalem

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Dated25.04.2011

    BT, & culverts areCompleted from

    KM 0/0 to 0/900.work iscompleted

    Mile stone-

    IIIcompleted 100%

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    Road from NH5toMulaguntapadu

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 dated10/02/2011

    6/9/2011Earth work,

    CD work,GSB

    10/9/2011WBM, Grade

    II & III

    2/9/2012BT,

    Shoulders& road

    furniture

    WBM-Grade-IIILayer Completed.OGPC + SealCoat To be takenup

    NotReached asper Milestone-III

    80%

  • 7/30/2019 November 2012 Mpr

    22/122

    MONTHLY REPORT

    21 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&Broad toChalivendradibba

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 dated -10/02/2011

    WBM-Grade-IIILayer Completed.OGPC + SealCoat To be taken

    up

    NotReached asper Milestone-III

    80%

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    Road fromPakala R&B roadtoMosanaladinne

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 dated10/02/2011 6/9/2011

    Earth work,CD work,

    GSB

    10/9/2011WBM, Grade

    II & III

    2/9/2012BT,

    Shoulders& road

    furniture

    WBM-Grade-IIImaterial layingwork is inprogress

    NotReached asper Milestone-III

    75%

    Road from R&Broad toBinginapalliHarijanawadaCyclone Shelter

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 dated10/02/2011

    CC road work iscompleted fromKM 0/0 to KM0/220. Shoulderswork is to be

    taken up.

    Mile stone-III(Awaitingfor 2 nd EOTProposal)

    98%

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

    Road from R&BRoad Allur to MT Raju colony

    NCRMP/B-W/AP/RHB/PRED/08/K othapatnam/003Dated 27/04/2011

    8/26/2011Earth work,CD work,GSB

    12/26/2011WBM, GradeII & III

    4/26/2012BT,Shoulders& roadfurniture

    BT, CC road,shoulders & culverts arecompleted fromkm 0/0 to km3/8.work iscompleted

    As permilestonecompleted

    100%

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

    Road from KEMR&B Road toSankuvarigunta

    NCRMP/B-W/AP/RHB/PRED/08/K othapatnam/004Dated 27/04/2011

    9/26/2011Earth work,

    CD work,GSB

    2/26/2012WBM, GradeII & III

    7/26/2012

    BT,Shoulders& road

    furniture

    BT completed.CDwork completed.CC

    road work completed fromkm 0/0 to km1/430 and CC dipwork iscompleted

    ReachedMile stone-III

    100%

  • 7/30/2019 November 2012 Mpr

    23/122

    MONTHLY REPORT

    22 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from KEMR & B Road toPullareddypalem

    NCRMP/B-W/AP/RHB/PRED/08/K

    othapatnam/004Dated 27/04/2011

    BT completed.CDwork completed.CCroad and

    shoulders work completed fromkm 0/0 to km3/900.

    As permilestonecompleted

    100%

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07

    Road from MCRoad toSubbarayuduSatram

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07 dated27/04/2011

    8/26/2011Earth work,CD work,GSB

    12/26/2011WBM, GradeII & III

    4/26/2012BT,Shoulders& roadfurniture

    BT completed.CDwork completedand shoulderswork completedfrom km 0/0 tokm 3/4. work iscompleted

    As permilestonecompleted

    100%

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08

    Road from R&Broad Tettu toRamayapatnam

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08 dated27/04/2011

    8/26/2011Earth work,CD work,GSB

    12/26/2011WBM, GradeII & III

    4/26/2012BT,Shoulders& roadfurniture

    BT completed.CDwork completed.CCroad andshoulders work completed fromkm 0/0 to km5/086. work iscompleted

    As permilestonecompleted

    100%

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09

    Road from R&Broad Pellur to

    Vasepallipadu

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09 dated16/03/2011

    7/15/2011Earth work,CD work,GSB

    11/15/2011WBM, GradeII & III

    3/15/2012BT,Shoulders& roadfurniture

    BT completed.CD work completed.CCroad andshoulders work completed fromkm 0/0 to km4/5. work iscompleted

    As permilestonecompleted

    100%

  • 7/30/2019 November 2012 Mpr

    24/122

    MONTHLY REPORT

    23 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10

    Road from R&B

    road toKesupalem

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10 dated19/04/2011

    7/18/2011Earth work,CD work,GSB

    10/18/2011

    WBM, GradeII & II

    1/18/2012BT,

    Shoulders& roadfurniture

    BT completed.CD work completed.CCroad and

    shoulders work completed fromkm 0/0 to km2/103. work iscompleted

    As per

    milestonecompleted

    100%

    RCS

    NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001

    Road from R&Broad to

    Vijayanagarcolony cycloneshelter

    NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001 dated2011/12 dated30.09.2011

    1/29/2012Earth work,GSB

    5/29/2012shoulders,Gr-III

    9/29/2012BT, CCpavementand roadfurniture

    cc roadcompleted, BTroad completed& shoulderscompleted. Roadfrom km 0/0 to

    km 0/525. work is completed

    As permilestonecompleted

    100%

    Road from NHroad toChallareddypalem

    cc roadcompleted, BTroad completed& shoulderscompleted. Roadfrom km 0/0 tokm 1/735. work is completed

    As permilestonecompleted

    100%

    Road from R&Broad to

    jeevarakshnagar colonycyclone shelter

    C.C.road andShoulders arecompleted Roadfrom km 0/0 tokm 0/500.

    As permilestonecompleted

    100%

    Road from R&Broad toRamnagarcolony cycloneshelter

    C.C.completedRoad from km0/0 to km0/475.Shouldersto be taken up.

    ReachedMile stone-III

    98%

  • 7/30/2019 November 2012 Mpr

    25/122

    MONTHLY REPORT

    24 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&Broad to cycloneshelter atMankenavaripale

    m

    CC roadcompleted.Shoulders work isto be taken up.

    ReachedMile stone-III

    95%

    NCRMP/B-W/AP/RCS/PRED/08/Chirala/002

    Road from R&BRoad toKeerthivaripalemcyclone shelter NCRMP/B-

    W/AP/RCS/PRED/08/Chirala/002 dated27.08.2011

    C.C road andShoulders arecompleted fromkm 0/0 to km0/265. work iscompleted

    As permilestonecompleted

    100%

    Road from R&BRoad toDevinuthulacyclone shelterof ChiralaMandal

    C.C road andShoulders arecompleted fromkm 0/0 to km0/800. work iscompleted

    As permilestonecompleted

    100%

    MPC

    S

    NCRMP/B-W/APMPCS/P

    RED/08/Ulavapadu/001

    Chakicharlacyclone shelter

    in UlavapaduMandal

    NCRMP/B-W/AP/MPCS/PRED/08/

    Ulavapadu/001

    24.11.2011 All items upto stilt floorslabincludingramp, stair

    casefoundations,columns,beams, pccflooring etc.,

    24.02.2012 All items upto secondfloor slabincludingfirst floor,

    and in 2ndfloorincludingstair case,columnsetc.,

    24.05.2012Head room,plastering,flooring,watersupplyarrangements,sanitaryfitting,

    electricalitems,compoundwall, ccpavement.Earthenmounds(raisedportion),

    Stilt floor, G.F , & Terrace floor-roof slabcompleted. Brick work completed,Plastering work completed, Cattleplatformcompletedrevetment work

    completed,flooring work iscompleted,compound wall120 meterslengthcompleted,Electrical work iscompleted.

    As permilestone

    completed

    100%

  • 7/30/2019 November 2012 Mpr

    26/122

    MONTHLY REPORT

    25 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    waterharvesting,septic tank,slump and

    soak pit.etc.,

    work iscompleted

    NCRMP/B-W/APMPCS/PRED/08/NGPadu/003

    Kanaparthycyclone shelterinNaguluppapaduMandalprakasamdistrict

    NCRMP/B-W/AP/MPCS/PRED/08/NG Padu/003

    23.11.2011 All items up

    to stilt floorslabincludingramp, staircasefoundations,columns,beams, pccflooring etc.,

    23.02.2012 All items up

    to first floorslab andhead roomslb in 2 ndfloorincludingstair case,columnsetc.,

    23.05.2012plastering,flooring,watersupplyarrangements,sanitaryfitting,electricalitems,compoundwall, ccpavement.Earthenmounds(raisedportion),waterharvesting,

    septic tank,slump andsoak pit.etc.,

    Internal & ExternalPlasteringcompleted.Flooring Work Completed.Compound WallPaintingCompleted. CCRoad Completed.Shoulder work inCompleted.Painting work inCompleted.Electrical Fittingsin progress. Tilesin bathroomswork inCompleted.

    Water harvest & Soak pit work incompleted.

    Not as perMilestone 98%

  • 7/30/2019 November 2012 Mpr

    27/122

    MONTHLY REPORT

    26 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATUS OF WORKS IN SPSR NELLORE DISTRICT -NOVEMBER-2012

    Name of package Name of work date of

    agreement mile stone -I mile stone -IImile stone -

    IIIPresent

    Statues of work

    %work

    completed

    RHB

    NCRMP/B-W/AP/RHB/PRED/09/BOGOLO/RHB/

    001

    1. Road from NH5 toSambasiva Puram

    1/19/20115Months: Earth

    Work, PipeCulverts, GSB

    10 Months:WBM GrII,GrII and

    Shoulders

    15 Months:BT and Road

    Furniture

    OGPC+ SCcompleted 100%

    Road from 9/6 of JuvvaladinneR&B Road to 11/0 of

    Juvvaladinne R&B Road Via Venkateshpalem

    OGPC+ SCcompleted 99%

    NCRMP/B-W/AP/RHB/PRED/09/BOGOLU/002

    Road from 1/6 of ZuvvaladinneR&B Road to Tellagunta KM to

    2/72007.02.2011

    6.5,2011 3Months:Earth Work, Pipe

    Culverts, GSB

    6.8.2011 6Months: WBMGrII, GrII and

    Shoulders

    6.11.20119Months: BTand Road

    Furniture

    OGPC+ SCcompleted 95%

    NCRMP/B-W/AP/RHB/PRED/09/CHITTAMURU/

    003

    Road from R&B Road toMuttambeka Via Pittuvanipalla

    18.01.2011

    17.6.20115Months: Earth

    Work, PipeCulverts, GSB

    17.11.2011 10Months: WBMGrII, GrII and

    Shoulders

    17.4.2012 15Months: BTand RoadFurniture

    OGPC+ SCcompleted 96%

    Road from R&B Chittamur toSoma Samudram

    OGPC+ SCcompleted 98%

    NCRMP/B-W/AP/RHB/PRED/09/RHB/KAVALI/0

    04

    Road from5/8 of Chennayapalem Road to

    Gummadi bandla

    17.01.2011

    16.6.20115Months: Earthwork, CD

    Works, ccpavement and

    GSB

    16.11.2011 10Months: WBM

    GrII, GrIi Iand Shoulders

    16.4.201215 Months:

    BT and RoadFurniture

    OGPC+ SCcompleted 98%

    Road from pedattapupalemR&B road to Chennayapalem

    H.wada

    OGPC+ SCcompleted 98%

    Road from K.T R&B Road to Alliguntapalem

    OGPC+ SCcompleted 97%

    NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/

    005

    1)Road from KT R&B road to Alaganipadu to Vavilla

    27.04.2011

    26.9.20115Months: Earth

    Work, PipeCulverts, GSB

    26.2.201210Months: WBMGrII, GrII and

    Shoulders

    26.7.2012 15Months: BTand RoadFurniture

    OGPC+SCcompleted 99%

    Road from R&B roadKancharapalem HW to

    Alaganipadu.

    WBM Gr-II isin progress &

    CD Workscompleted.

    61%

  • 7/30/2019 November 2012 Mpr

    28/122

    MONTHLY REPORT

    27 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/PRED/09/MUTHUKUR/RHB/0

    06

    Road from R&B road toPatuvari Kandriga 25.4.11

    24.7.20113Months: Earth

    Work, PipeCulverts, GSB

    24.10.2011 6Months: WBMGrII, GrII, CCPavement and

    Shoulders

    24.1.2012 9Months: BTand RoadFurniture

    OGPC+ SCcompleted 96%

    NCRMP/B-W/AP/RHB/PRED/09V.CHALEM/RHB

    /007

    Road from Survepalli-Pudiparthiroad to Srikanth Colony

    27.04.2011

    26.8.20114Months: Earth

    Work, PipeCulverts, GSB

    26.12.2011 8Months: WBMGrII, GrII and

    Shoulders

    26.4.2012 12Months: BTand RoadFurniture

    OGPC+ SCcompleted 99%

    providing BT Surface to theroad from R&B road to Edagali

    Kandriga

    OGPC+ SCcompleted 97%

    NCRMP/B-W/AP/RHB/PRED/

    09/Allur/009

    Road from R&B road Alluru toGalidibbalu (via) Chukavani

    dibba24.01.2011

    23.6.20115Months: Earth

    Work, PipeCulverts, GSB

    23.11.2011 10Months: WBMGrII, GrII and

    Shoulders

    23.4.2012 15Months: BTand RoadFurniture

    OGPC+ SCcompleted 99%

    NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/0

    12

    Ring Road to TP Gudur-

    Salipeta R & B Road via CSPuram and Mandapam Village 19.05.2011

    18.8.20113Months: Earth

    Work, PipeCulverts, GSB

    18.11.2011 6

    Months: WBMGrII,GrII, CCPavement and

    Shoulders

    18.2.2012 9Months: BTand RoadFurniture

    OGPC+ SCcompleted 96%

    Road from R & B Road C SPuram to Sivaramapuram

    OGPC+ SCcompleted 98%

    RCS

    NCRMP/B-W/AP/PRED/09/k ota/RCS /001

    Road from R&B road to A.SPURAM

    10.05.20119.8.2011 3Months:Earth Work, Pipe

    Culverts, GSB

    9.11.11 6Months: WBMGrII,GrII and

    Shoulders

    9.2.2012 9Months: BT,

    CC Pavementand RoadFurniture

    OGPC+ SCcompleted 97%

    NCRMP/B-W/AP/PRED/09/k ota/RCS /001

    Road from GD Road to VavillaPalem

    OGPC+ SCcompleted 100%

    NCRMP/B-W/AP/PRED/09/MUTHUKUR/RCS/00

    2

    Road from R&B Roadkappaladoruvu to bandla PalemH.wada

    21.04.2011

    20.7.20113Months: Earth

    Work, PipeCulverts, GSB

    20.10.2011 6

    Months: WBMGrII,GrII,CCPavement and

    Shoulders

    20.1.2012 9

    Months: BTCC road andRoad

    Furniture

    OGPC+ SCcompleted 98%

    NCRMP/B-W/AP/PRED/09/Chillakur/RCS/004

    Road from Kakuvaripalem R&Broad to Vellapalem 23.05.2011

    22.8.20113Months: Earth

    Work, CD Works,GSB

    22.11.2011 6Months: WBMGrII,GrII and

    Shoulders

    22.2.2012 9Months: BT,

    CC Pavementand RoadFurniture

    OGPC+ SCcompleted 98%

  • 7/30/2019 November 2012 Mpr

    29/122

    MONTHLY REPORT

    28 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RCS/PRED/09/T.P.GUDUR/00

    5

    Road from7/2 M.C Road to Venkannapalem Pattuapalem 17.05.2011

    16.8.20113Months: EarthWork, PipeCulverts, GSB

    16.11.2011 6Months: WBMGrII,GrIIShoulders and

    CC Pavement

    16.2.2012 9Months: BT,CC Pavementand Road

    Furniture

    OGPC+ SCcompleted 99%

    NCRMP/B-W/AP/RCS/PRED/

    09/KAVALI/006

    Road Connecting R&B Roadthrough Voturu Village in SPSR

    Nellore District.21.09.2011

    20.1.2012 4Months: Earth

    Work, PipeCulverts,

    GSB

    20.5.2012 4Months: WBM

    GrII,GrII ,Shoulders andCC Pavement

    20.9.2012 4Months: BT,

    CC Pavementand RoadFurniture

    GSB. From0.00 to

    5.320(Bits),WBM Gr-II

    ,Gr-III from0.00 to 5.320and OGPC+SC0/6 to 5/1 iscompleted

    85%

    NCRMP/B-W/AP/RCS/PRED/

    09/KAVALI/007

    Road from Kotha satram R&Bto Indrsanagar (via)

    Thumalapenta palam,Patharavadu palam, Ramudupalam, Karaduvari palam &

    Sreeramapuram

    29.08.2011

    28.12.20114Months: Earth

    Work, PipeCulverts, GSB

    28.4.2012 4

    Months: WBMGrII,GrII ,

    Shoulders andCC Pavement

    28.8.2012 4

    Months: BT,CC Pavement

    and RoadFurniture

    OGPC+ SCcompleted 99%

    NCRMP/B-W/AP/PRED/09/D. V.SATRAM/RCS/0

    08

    Road from R&B road toSullurpeta Mallam to

    Berijengalapalli cyclone shelter09.05.2011

    8.8.2011 3Months:Earth Work, PipeCulverts, GSB

    8.11.2011 6Months: WBMGrII, GrIIShoulders andCC Pavement

    8.2.2012 9Months: BT,CC Pavementand RoadFurniture

    OGPC+ SCcompleted 98%

    NCRMP/B-W/AP/RCS/PRED/

    09/TADA/009

    Providing BT road to

    Pedapannamgadu in TadaMandal

    14.09.2012

    14.02.2013(5Months) Earth

    Work, PipeCulverts, GSB & CC road

    13.06.2013 (4Months): WBMGrII, GrIIShoulders

    13.09.2013Months) BTand RoadFurniture

    GSB work is inprogress

    Road from @ 56/8 to C.K roadto Periyavettu kuppam cycloneshelter

    14.02.2013(5Months) EarthWork, PipeCulverts, GSB & CC road

    13.06.2013 (4Months): WBMGrII, GrIIShoulders

    13.09.2012Months) BTand RoadFurniture

    work is notstarted

  • 7/30/2019 November 2012 Mpr

    30/122

    MONTHLY REPORT

    29 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    LIST OF NCR'S PENDING FOR NCRMP WORKS TO THE END OF NOVEMBER 2012

    Sl.

    No

    Dist

    rict

    sl.

    no

    Date of Inspecti

    onName of Work/Package No. Observation Remarks Status

    1

    S R I K A K U L A M

    1 23.08.12 Road from Talasamudram to Dolaregulator.NCRMP/B-W/AP/RCS/PRED/01/Polaki/006.

    WBM GR-III compaction istested by Volumetric analysismethod and degree of compaction is not satisfactory.

    NCR-37 Issued and thecontractor/LineDepartment isrequested to takesuitable remedialaction.

    NCR No-37pending.

    2 2 05.10.12 Construction of Cyclone Shelter atRunku,NCRMP/B-W/AP/MPCS/PRED/01/

    Santhabommalli/005

    Columns number A3, J6, H1,J1 are not as per drawing andplinth beam between PB1a is

    not constructed as perdrawing.

    NCR-46 Issued and thecontractor/LineDepartment are

    requested to takesuitable remedialaction.

    NCR No-46pending

    3 3 09.10.12 Construction of Cyclone Shelter atKoliipadu,NCRMP/B-W/AP/MPCS/PRED/01/Santhabommalli/005

    Bulging or sagging is observedunder 3 beams. NCR 44 and47 and Stop work ordersissued until structural stabilityis ensured. Ceiling plasteringwas done and NCR 48 and 53issued.

    NCR-44, 47, 48 and 53issued and thecontractor/LineDepartment isrequested to takesuitable remedial actionbefore proceeding with

    further work.

    NCRs pending. AndhraUniversityprofessor thatno structuralproblem isthere. However,

    contractor hasarranged forbeam loadtesting.

    4 4 10.10.12 Road From K.Umilada to Koduru(Link road)NCRMP/B-W/Ap/RHB/PRED/001/

    Santhabommalli/003

    Rain gullies observed at someplaces on shoulders portionand OGPC + Seal coat patchwork is observed in Km 1/000

    NCR-50 Issued and thecontractor/LineDepartment isrequested to take

    NCR-50pending. FieldOfficersinformed that

  • 7/30/2019 November 2012 Mpr

    31/122

    MONTHLY REPORT

    30 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    suitable remedialaction.

    rectification willbe done afterrains arestopped.

    5 5 10.10.12 Road From DPN R&B roadUddandapalemNCRMP/B-W/Ap/RHB/PRED/001/Santhabommalli/003

    Shoulders are uneven surfaceobserved and OGPC+ Sealcoat patches are observed inKm 1/000 and 1/200

    NCR-51 Issued and thecontractor/LineDepartment arerequested to takesuitable remedial actionbefore proceeding withfurther work.

    NCR-51pending. FieldOfficersinformed thatrectification willbe done afterrains arestopped.

    6 6 19.10.12 Construction of Minor bridge at KM12/2-4 of NH-5 to Surampeta viaTamada, Naruva

    Revetment thickness forQuadrants is verified at somelocations. Thickness is notsatisfying. As per MORT&Hclause 2504, Requiredminimum weight is 40 kgs andminimum size is 300mm. Andat some locations grouting isnot done properly.

    NCR-54 Issued and thecontractor/LineDepartment isrequested to takesuitable remedial actionbefore proceeding withfurther work.

    NCR-54pending.Departmentalofficers justinformed thatrectification wasdone. It needsto be verified.

    7

    V I Z I N A G A R A M

    1

    06.04.12

    Construction of Minor Bridge at Km15/2 near Chakaligadda of KonadaRamatheertham R&B road to

    Konatalapalem (via) Yerukonda,Pasupam, Kollayavalasa (ZP Road)NCRMP/ B-W/ AP/ Br/ R&B/ 02/Chakaligadda / 008

    Revetment, Apron stonesamples are collected andverified for size and weight.

    Some samples are notsatisfying the requirements of MORT & H Clause2504.Required minimumweight is 40 kgs and minimumsize is 300 MM minimum.

    NCR-2 Issued to takesuitable remedial actionbefore proceeding with

    further layers.

    The Contractortold that theunder size

    stones will beremoved andrepacked withsuitable stonesas peragreement. NCR Pending.

  • 7/30/2019 November 2012 Mpr

    32/122

    MONTHLY REPORT

    31 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    8 2

    25.07.12

    Construction of Minor Bridge atKm. 7/2 near Puligadda of Konada

    Ramatheertham R&B Road toKonathalapalem via Yerukonda,Pasupam, Kollayavalasa (Z.P.Road)NCRMP/B-W/ AP/ Br/ R&B/02/Puligadda/ 007

    Rain cuts and gullies areformed in shoulder portion.Shoulders are disturbed atsome places. The same shallbe rectified.

    NCR-3 Issued to takesuitable remedial actionbefore proceeding withfurther work.

    The Contractorintimated thatthe gullies willbe rectified byfilling,compacting andsectioning theslopes after thecompletion of Rainey season.NCR Pending.

    9

    G U N T U R

    1 30.10.12 Reconstruction of HLB @ km5/2 of Bapatla - Suryalanka road acrossperali drain in Guntur Dt

    Package No.: NCRMP/B-W/AP/Br/R&B/07/Bapatla/010.

    Revetment thickness is varyingfrom 220 mm to 275 mm asagainst the specified thickness

    300 mm. rectify the samebefore tacking up thegrouting.

    NCR-13 Issued, R&BDepartment officers isrequest to take suitable

    remedial action beforepreceding the furtherwork.

    Pending Ncr

    10 2 29.11.12 Road from R & B road toChinapuluguvaripalem.Package No.: NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002

    The Fine aggregate material iscollected and sieve analysistest Conducted and test resultis found beyond the specifiedlimits as per IS: 383.

    NCR-14 Issued,Department officers isrequest to take suitableremedial action beforepreceding the furtherwork.

    Pending NCR

    11

    P R A K A S A M

    1

    01.09.12

    Road from R&B road Pellur to Vasepallipadu.NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09

    The sign boards which areprovided in site are not semireflective. Semi reflective signboards are to be provided asper agreement.

    NCR-27 Issued, PR Department officersinform that suitableremedial action will betaken beforeproceeding with furtherwork.

    NCR Pending

  • 7/30/2019 November 2012 Mpr

    33/122

    MONTHLY REPORT

    32 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    12 2

    11.10.12

    Construction Thoupula Kanaparthycyclone shelter in Nagulappapadumandal prakasam districtNCRMP/B-W/APMPCS/PRED/08/NGPadu/003

    1. Street light fittings are notof approved brand specified inthe agreement.2. Exhaust fans (2no's) of 225mm size are providedwhereas the agreementspecifies 300mm size.3. For ceiling fans & tube lightsceiling roses are not provided.

    NCR-32 Issued, PR Department officersinform that suitableremedial action will betaken beforeproceeding with furtherwork.

    NCR Pending

    13 3

    19.10.12

    Construction of High level Bridge atKm 16/10 of Naguluppalapadu Kanaparthi road in PrakasamDistrict NCRMP/B-W/AP/Br/R&B/08/ Kanaparthi/012

    Rain cuts & dip gullies areformed in the bridgeapproaches. Shoulders aredisturbed at many places. Thesame shall be rectified

    immediately.

    NCR-33 Issued, R & BDepartment officersinform that suitableremedial action will betaken before

    proceeding with furtherwork.

    NCR Pending

    14 4

    21.11.12

    Construction of High level Bridge atKm 16/10 of Naguluppalapadu Kanaparthi road in PrakasamDistrict NCRMP/B-W/AP/Br/R&B/08/ Kanaparthi/012

    Grouted rough stonerevetment work for quadrantsis damaged, deep gullies areformed in the bridgeapproaches and shoulders aredisturbed at many places (NCR no- 33). These damages shallbe rectified immediately andcompliance report furnished.

    NCR-34 Issued R & BDepartment officers isinform to take suitableremedial action beforeproceeding with furtherwork.

    NCR Pending

    15 5

    28.11.12

    Road from Pakala R&B road toMosanaladinneNCRMP/BW/AP/RHB/PRED/08/S.Konda/002

    WBM Grade-III layer is badlydisturbed in the stretch km0/000 to km 0/450 which is tobe rectified immediately andcompliance furnished.

    NCR-35 Issued, P R Department officers isinforming to takesuitable remedial actionbefore proceeding withfurther work.

    NCR Pending

  • 7/30/2019 November 2012 Mpr

    34/122

    MONTHLY REPORT

    33 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    16 6

    28.11.12

    Road from NH5 to MulaguntapaduNCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    WBM Grade-III layer is badlydisturbed in the stretches fromkm 0/000 to km 0/310 andfrom km 0/400 to km 0/600.The disturbed stretches are tobe rectified immediately andcompliance furnished.

    NCR-36 Issued, P R Department officers isrequested to takesuitable remedial actionbefore proceeding withfurther work.

    NCR Pending

    17

    N E L L O R E

    1 18.07.12 Road from 1/6 of ZuvvaladinneR&B Road to Tellagunta NCRMP/B-W/AP/RHB/PRED/09/BOGOLU/001

    1. Non Reflective type signboards are provided. As peragreement specifications allthe sign boards shall be semireflective in nature. Suitableremedial action is to be takenup

    2. in KM 1/6, big hole is left inbetween road and sluice headwall. it is very dangerous tothe public. Immediateprotective action she be takento prevent accidents.

    NCR-14 Issued, PR Department officersinform that suitableremedial action will betaken beforeproceeding with furtherwork.

    NCR Pending

    18 2 17.07.12 Road fromR&bB road topatuvarikandrigaNCRMP/B-W/AP/RHB/PRED/09/MUTHUKUR/006

    Sump is constructed in theformation width of the roadnear slab culvert location in km0/200. Proper safety measuresshall be taken to avoidaccidents

    NCR-28 Issued, PR Department officersinform that suitableremedial action will betaken beforeproceeding with furtherwork.

    NCR Pending

  • 7/30/2019 November 2012 Mpr

    35/122

    MONTHLY REPORT

    34 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    19 3

    17.08.12

    Road from R&B Chittamur to SomaSamudramNCRMP/B-W/AP/RHB/PRED/09/CHITTAMURU

    /003

    l)At Km 1.380(RHs),collectionchamber has to be coveredwith suitable measures toavoid accident.2.At Km 1.250(LHS)a deepditch exist at the BT edgewhere a water Bump islocated. It is hazardous tothe road user and it shall beprotected by suitablearrangements

    NCR-28 Issued, PR Department officersinform that suitableremedial action will betaken beforeproceeding with furtherwork.

    NCR Pending

    20 4

    17.08.12

    Providing BT Surface to the Roadto the Road from R&B Road toEdagali Kandriga

    Package No.:NCRMP/B-W/AP/RHB/PRED/09/Chalam/007

    At Km 0,010(RHs), uncoveredwater pump chamber islocated on the shoulder of the

    road. It has to be coveredirnmediately

    NCR-29 Issued, PR Department officersinform that suitable

    remedial action will betaken beforeproceeding with furtherwork.

    NCR Pending

    21 5

    08.10.12

    Road Connecting R&B Roadthrough Voturu Village in SPSR Nellore District. NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006

    Road is badly damaged insome stretches from km 1/8 tokm 2/6 .Thorough rectificationis to be done

    NCR-30 Issued, PR Department officersinform that suitableremedial action will betaken beforeproceeding with furtherwork.

    NCR Pending

  • 7/30/2019 November 2012 Mpr

    36/122

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    6.0 District wise status of tests conducted by TPQA:

    Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various

    stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are

    carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of

    tests conducted in the field till end of November 2011 are presented.

    Summary of QC Tests - Up to 30.11.2012

    S.No. District

    No. TestsConductedduring the

    Month

    Total no. of TestsCumulativeTests Done

    Total no. of Tests

    Passed Failed Passed Failed

    1 Srikakulam 29 29 0 1393 1387 6

    2 Vizianagaram 57 57 0 457 457 0

    3 Visakhapatnam 88 88 0 2131 2085 46

  • 7/30/2019 November 2012 Mpr

    37/122

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    7.0 Details of Quality Control Audit Reports Submitted During this Month:

    Package Number Name of Work District

  • 7/30/2019 November 2012 Mpr

    38/122

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/010/2010

    RECONSTRUCTION OF HLB @ Km5/2 OF BAPATLA-SURYALANKA ROAD

    ACROSS PERALI DRAIN

    Guntur

    NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005.

    Road from R&B road Alaganipadu to Vavilla of Vidavalur SPSR Nellore

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    Road from Pakala R&B road toMosanaladinne Prakasam

    NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

    Road from NH 214 A at Ranga statue

    center to Harijanawada of Kalipatnam(E) of Mogalthuru Mandal West Godavari

    NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

    R&B Road at Panchayat office toPulaparthivarithota via Badava of

    Mogalthuru MandalWest Godavari

    NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

    Mogaltur Vempa R&B Road atUchintha kalava Bridge to

    Gogulamma Harijanapeta of

    Mogalthuru Mandal

    West Godavari

    NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

    Road from NH 214 A road toHarijanawada of kothota of

    Mogalthuru MandalWest Godavari

    NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

    From Narsapur Mogaltur R&B road toDayadalspeta via Venkateshwara

    Swamy Temple of Mogalthuru MandalWest Godavari

    NCRMP/B- Road from R&B Road to

  • 7/30/2019 November 2012 Mpr

    39/122

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cyclone shelter atMullaparra in Nakkapalli Mandal Vishakhapatnam

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cyclone shelter atPatimeeda in Nakkapalli Mandal Visakhapatnam

    8.0 Details of Environmental and Social Reports Submitted During this Month:

    Package Number Name of Work District

    NCRMP/B-W/AP/Br/R&B/PRED/O7/Bapatla/010

    Reconstruction of HLB @ Km.5/2 of Bapatla-Suryalanka road across Perali Drain

    Guntur

    NCRMP/B-W/AP/Br/R&B/PRED/O7/Bapatla/011

    Reconstruction of HLB @ Km.2/4 of Bapatla-Pandurangapuram road across Perali Drain

    Guntur

    NCRMP/B-W/AP/RCS/PRED/O7/Karlapalem/002

    Road from R&B Road to Pedagollapalem Guntur

    NCRMP/B-W/AP/RCS/PRED/O7/Karlapalem/002

    Road from Pedagollapalem P.R. Road toBonthagoralapalem

    Guntur

    NCRMP/B-W/AP/RCS/PRED/O7/Nizampatnam/003

    Road from R&B Road to Gurunadhanagar Guntur

    NCRMP/B- Road from Ganapavaram R&B Road to Guntur

  • 7/30/2019 November 2012 Mpr

    40/122

    MONTHLY REPORT

    39 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Consolidated E&S Report for Prakasam District in the Month of October 2012:

    Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details of Guntur inOctober,2012)

    S.No Activity Measures to be implemented by the contractor COMPLICED NOTCOMPLICEDNOT

    APPLICABLE TOTAL

    1Work Plan forEMPimplementation

    The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP

    12 12

    2RegulatoryPermissions andConsents

    The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes: Consent for establishment and operation of plant (for concretework) from SPCB. 12 12

    PUC certification for all vehicles/equipment used for/duringconstruction. 12 12

    Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations

    for materials like sand and earth.

    12 12

    Permission for water extraction, if applicable in the local areacontext. 12 12

    The Contractor shall abide by all conditions laid out in the saidclearances. 12 12

    3Consultation andCommunityConsent

    The Contractor shall consult and obtain written consents of landowners(individual/panchayat/govt. agency) for temporary use of land for all construction related activities including:

  • 7/30/2019 November 2012 Mpr

    41/122

    MONTHLY REPORT

    40 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    a) Setting-up and operation of construction camp including labourcamps, stock yards etc. 12 12

    b) borrow areas and 12 12c) Disposal of debris and other waste material. 12 12

    4 Construction/Labour Camp

    a) Location: The camp and plant site/s location and establishmentshall be done in a manner that does not interfere or disturb theactivities of local inhabitants, particularly those of schools and healthfacilities. Written permission (no objection certificate) shall be takenfrom the Gramsabha and the land owner prior to location selection anda copy shall be submitted to the Engineer approval.

    12 12

    b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 12 12

    c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

    12 12

    b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisionsof Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional spacefor cooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

    12 12

    c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 12 12

    d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided. 12 12

    e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

    12 12

    5 Site Clearance

    a) NO tree cutting is to carried out without the written instructionfrom the Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) areobtained prior to cutting of such trees.

    12 12

  • 7/30/2019 November 2012 Mpr

    42/122

    MONTHLY REPORT

    41 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department. 12 12

    c) The Contractor shall strip, store and preserve top soil from the siteof construction work and in the stock yards prior to stacking of materials. The top soil shall be reinstated in the cyclone sheltercompound after the construction is over.

    12 12

    6Protection of Properties andResources

    The Contractor shall take due care to protect and prevent damages tothe following resources during preparatory and construction work:a) Water supply lines 12 12b) Irrigation canals 1 11 12c) Cart, cattle and/or foot trail/tracks 12 12d) Cultural properties and sites/structures of religious importance 12 12e) Houses, Farmlands, Orchids and/or Trees. 11 1 12f) School and other existing buildings adjacent to the site of construction. 12 12

    In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost. 12 12

    7 QuarryOperations

    The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

    12

    8 Borrow Areas

    a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verificationto cross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractor

    shall enter into a formal agreement with landowner.

    12 12

    b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protectedareas.

    12 12

    c) Identification and Selection:

  • 7/30/2019 November 2012 Mpr

    43/122

    MONTHLY REPORT

    42 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    1. The borrow area should not be located in agriculture fields/unless unavoidable i.e. barren land is not available. In case borrowingneeds to be done on an agricultural land, top-soil stripping, stackingand preservation is must.

    12 12

    2. Borrow pits shall not be located within a distance of 100mts.

    From any NH, SH or other roads.12 12

    3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 12 12

    4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres. 12 12

    5. No borrow area shall be opened with in 500mts. from a reservedor protected forest area, protected sites, wildlife movement zone andcultural heritage site.

    12 12

    6. No tree cutting shall be undertaken. 1 127. Borrow area near any surface water body will be at least 100mts.away. 1 12

    d) Operation 121. Area up to which material will be extracted shall be cleareddemarcated on ground. 12 12

    2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 12 123. Borrowing of earth should be preferably limited to a depth of 1.5mtr from the existing ground level. 12 12

    4. Slope at the edges will be maintained not steeper than 2:3(Vertical : Horizontal) 12

    e) Rehabilitation of Borrow Areas:1. Rehabilitation shall be satisfactory undertaken immediately after

    the use has ceased and at least three weeks prior to monsoon 12 122. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

    12 12

  • 7/30/2019 November 2012 Mpr

    44/122

    MONTHLY REPORT

    43 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    9 Water Extraction /Use

    Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) theindividual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

    12 12

    10Safety of RoadUsers and LocalResidents

    a) Traffic safety arrangements (including provision of warningsignage, speed breakers etc.) shall be made by the contractor toensure safety of road users and local people, particularly in the internalvillage roads which will be used for transporting materials.

    12 12

    b) Material shall be covered during transportation to preventspillage, accidents and pollution. 12 12

    c) All required measures to ensure safety of local residentsincluding children and other near-by residents shall be taken up by theContractor. This shall include provisions to prevent un authorised entryinto the construction.

    12 12

    11 Workers Safety

    a) All measures required for ensuring safety and health of theworkers shall be taken up by the Contractor. This includes provisionand enforcement of appropriate personal protective equipment; firstaid facility; emergency response arrangement; proper storage of hazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

    12 12

    b) All methods steps and measures are required for ensuring safetyof workers, particularly those needed while undertaking work in oraround excavations; workings at height; and; while handlinginflammable, toxic and/or hazardous materials shall be ensured by thecontractor.

    12 12

    c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 12 12

    12 Air pollution a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and finematerial storage stock yards

    12 12

    b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

    12 12

  • 7/30/2019 November 2012 Mpr

    45/122

    MONTHLY REPORT

    44 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    c) All plants and equipment shall comply with pollution controlnorms.

    12 12

    d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)

    12 12

    13 Water Pollution

    a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts towater bodies (such as ponds, streams, canals and rivers), watersources (such as hand pumps and wells) and adjacent farmland shallbe undertaken by the Contractor.

    12 12

    b) Storage of materials like fuel, chemicals, and cement shall bedone in a manner (with impervious layer on bottom and a coveredshed on top) that does not contaminate land and ground/surfacewater.

    12 12

    14 Noise Pollution

    a) All noise causing activities shall be stopped during night time(9.00 PM to 6.00 AM). The Contractor shall schedule constructionworks in consultation with local Panchayat Authority and SchoolPrincipal to ensure least disturbance to school children and otheradjacent residents.

    12 12

    b) Ear plugs shall be provided to the labour facing risk from highnoise pollution such as plant site and those working near generators,heavy equipment /machinery.

    12 12

    c) Appropriate noise controlling devices including acousticgenerators shall be used to minimise noise during construction work and operation of camp.

    12 12

    15 Disposal Debris/wastes

    a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

    12 12

    b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. of ecologically sensitive areas, including forests, wetlands and protectednatural habitats.

    12 12

  • 7/30/2019 November 2012 Mpr

    46/122

    MONTHLY REPORT

    45 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    16

    Restoration and

    Rehabilitation of Sites

    All work sites and areas under temporary use (including constructionand labour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

    12 12

    Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposalof debris/construction wastes at pre-approved locations and;restoration of borrow areas and other sites/ locations used for materialsourcing.

    12 12

    17 Liabilities

    Any liability arising out of Contractors agreement with landowners/local people/gram anchayat ( including those related to temporary useof land, water extraction and disposal of debris) shall be settled by theContarctor.

    12 12

    MONTHLY REPORT

  • 7/30/2019 November 2012 Mpr

    47/122

    MONTHLY REPORT

    46 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    9.0 Statement Showing the Inspections and Site Visits of Districts during the Month of November -2012

    STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THE MONTHOF OCTOBER 2012

    SNO.

    PACKAGE NO NAME OF WORK

    TPQA INSPECTIONSDURING THIS MONTH

    DATES OFVISIT

    NO. OFVISITS

    1 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005 Construction of Cyclone shelter at Runku in SanthabommaliMandal.

    07.11.12,14.11.12,17.11.12

    3

    2 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Deppuru, Bahadapalli road to Onkuluru & cycloneshelter. 16.11.12 1

    3 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram 06.11.12,16.11.12 2

    4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komrlatjhada&Cyclonic shelter 16.11.12 1

    5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B ROAD TO Devunalthada 16.11.12 1

    6 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005 Construction of Cyclone shelter at Kollipadu in Santhabommali

    Mandal.17.11.12 1

    7 NCRMP/B_W/AP/Br/R&B/01/Bendigedda/004 Construction of High level Bridge across Bendigedda at km 4/10 of Pundi-Parlkimidi road in Srikakulam Dist. 15.11.12 1

    8 NCRMP/B_W/AP/Br/R&B/01/Surampeta/003 Construction of Minor Bridge at km 12/2-4 of NH-5 to Surampetaroad via Naruva & Mentada05.11.12,21.11.12 2

    MONTHLY REPORT

  • 7/30/2019 November 2012 Mpr

    48/122

    MONTHLY REPORT

    47 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    9 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Talasamudram to Dola regulator 29.11.12 1

    10 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Mabagam R&B road to Dubbakavanipeta via

    gajapathinagaram.29.11.12 1

    11 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/005 Road from R&B road Edullavalasa-Killam to jonnam viatalasamudram 29.11.12 1

    12 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from DPN road Uddandapalem 20.11.12 1

    13 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from K.Umilada to Koduru (Link road) 20.11.12 1

    14 NCRMP/B_W/BR/R&B/01/uppigedda/002 Construction of HLB across uppugedda at Km 7/6 of Srikakulammunicipal limits to Pukkalapeta 20.11.12 1

    15 NCRMP/B_W/AP/RCS/PRED/01/ETCHERLA/005 Road from kotcherla road to Kollibhemavaram & cyclone shelter 05.11.12,21.11.12 2

    16 NCRMP/B_W/AP/RCS/PRED/01/ETCHERLA/005 Road from kotcherla road to Pathasundarapalem 05.11.12,21.11.12 2

    17 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001Construction of Bridge at km 11/6-8 of NH-5 to Patnavanipetaconnecting Sundarapalem.

    05.11.12,18.11.12,21.11.12,28.11.12,29.11.12,30.11.12

    6

    TOTAL 28

    MONTHLY REPORT

  • 7/30/2019 November 2012 Mpr

    49/122

    MONTHLY REPORT

    48 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THEMONTH OF OCTOBER 2012

    SNO

    .PACKAGE NO NAME OF WORK

    TPQA INSPECTIONS DURINGTHIS MONTH

    DATES OF VISIT NO. OF VISITS

    1 NCRMP/B-W/ AP/ Br/ R&B/ 02/Chakaligadda /008

    Construction of Minor Bridge at Km 15/2 near Chakaligadda of Konada Ramatheertham R&B road to Konatalapalem (via) Yerukonda,Pasupam, Kollayavalasa (ZP Road) in Vizianagaram District.

    08.11.1219.11.1223.11.1224.11.1229.11.12

    5

    Total 5

    MONTHLY REPORT

  • 7/30/2019 November 2012 Mpr

    50/122

    MONTHLY REPORT

    49 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISHAKAPATNAM DISTRICT DURING THEMONTH OF NOVEMBER 2012

    SNO

    .PACKAGE NO NAME OF WORK

    TPQA INSPECTIONSDURING THIS MONTH

    DATES OF VISIT

    NO. OF VISITS

    1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004 Construction of cyclone shelter at Venkayyapalem in RambilliMandal10.11.1220.11.12 2

    2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Mullaparra in Nakkapalli Mandal 11.11.1226.11.12 2

    3 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003Construction of cyclone shelter at Gajapathinagaram inPayakaraopeta Mandal 28.11.12 1

    4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Bangarrampeta in NakkapalliMandal 27.11.12 1

    5 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003Construction of cyclone shelter at Ratnayampeta in PayakaraopetaMandal 20.11.12 1

    6 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda in Nakkapalli Mandal

    10.11.12

    11.11.1220.11.1226.11.12

    4

    TOTAL 11

    MONTHLY REPORT

  • 7/30/2019 November 2012 Mpr

    51/122

    MONTHLY REPORT

    50 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DISTRICT DURING THEMONTH OF NOVEMBER 2012

    S NO. PACKAGE NO NAME OF WORK TPQA INSPECTIONS DURING THISMONTH

    DATES OF VISIT NO. OF VISITS

    1 NCRMP/B-W/ AP/RCS/ PRED/04/KARAPA/001ROAD FROM APPROACH ROAD TO CYCLONE SHELTER

    AT ADAVIPUDI IN E.G.Dt. Nil Nil

    2 NCRMP/B-W/ AP/RHB/ PRED/04/KARAPA/001 ROAD FROM GURAJANAPALLI TO BANDULAVARIPALEM Nil Nil

    3 NCRMP/B-W/AP/RHB/ PRED/04/Katrenikona/003Road from PR road to Dasarivanipeta and to Cyclone

    Shelter Nil Nil

    4

    NCRMP/B-W /AP/RCS/PRED/04/

    Thondangi/004

    Road from R&B Road to G.Musalayyapeta CS Nil Nil

    5 Road from R&B Road to P.Chodipallipeta CS 05.11.2012, 14.11.2012,19.11.2012 & 29.11.2012 4

    6 Road from R&B Road to K. Chodipallipeta CS 05.11.2012, 14.11.2012,19.11.2012 & 29.11.2012 4

    7 Road from R&B Road to Hukumpeta CS 05.11.2012, 14.11.2012,19.11.2012, 22.112012 & 29.11.2012

    5

    8 Road from R&B Road to Gaddipeta CS 05.11.2012, 14.11.2012,19.11.2012& 29.11.2012 4

    MONTHLY REPORT

  • 7/30/2019 November 2012 Mpr

    52/122

    MONTHLY REPORT

    51 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    9 Road from R&B Road to Danavaipeta CS 05.11.2012, 14.11.2012,19.11.2012 & 29.11.2012 4

    10NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001

    Cyclone Shelter at Avulamanda and of Thondangi Mandal,E.G.Dt. 14.11.2012, 19.11.2012,22.11.2012, & 29.11.2012 4

    11 Cyclone Shelter at Lakshmanudipeta of ThondangiMandal, E.G.Dt.

    05.11.2012, 07.11.2012,14.11.2012, 19.11.2012,

    22.11.2012, & 29.11.20126

    12 NCRMP/B-W/ AP/RCS/PRED/04/Uppalaguptam/003Road from R&B Road to Chinarghavulapeta Cyclone

    Shelter Nil Nil

    13 NCRMP/B-W/ AP/MPCS/PRED/04/Uppalaguptam/002Cyclone Shelter at Pedaraghavulapeta of UppalaguptamMandal, E.G.Dt. 26.11.2012 1

    TOTAL 32

    MONTHLY REPORT

  • 7/30/2019 November 2012 Mpr

    53/122

    MONTHLY REPORT

    52 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN WEST GODAVARI DISTRICT DURING THEMONTH OF NOVEMBER 2012

    S

    NO.PACKAGE NO NAME OF WORK

    TPQA INSPECTIONS DURINGTHIS MONTH

    DATES OF VISITS NO. OF VISITS

    1.

    NCRMP/B-W/AP/RHB/PRED/05/Mogalthuru/001

    Road from NH 214 A at Ranga Statue center to Harijanawada of Kalipatnam (E)(Mogalthuru Mandal W.G.Dist.) 05.11.2012 1

    2. R&B road at Panchayat Office to Pulaparthivarithota via Badava (MogalthuruMandal W.G.Dist.) 05.11.2012 1

    3. Mogalthuru Vempa R&B Road at Uchintha Kalava Bridge to GogulammaHarijanapeta (Mogalthuru Mandal W.G.Dist.)05.11.2012,22.11.2012 2

    4.From Narsapur Mogalthur R&B road to Dayadaldaspeta via Venkateswara Swamytemple (Mogalthuru Mandal W.G.Dist.) 05.11.2012 1

    5. Road from NH 214 A road to Harijanapeta of Kothota (Mogalthuru MandalW.G.Dist.) 05.11.2012 1

    6.

    NCRMP/B-W/AP/RHB/PRED/05/Nasapur/002

    R&B Road to indira nagar (via) Pochamma temple (Nasapur Mandal W.G.Dist.) 22.11.2012 1

    7. Road from R&B road to Pedalanka (Nasapur Mandal W.G.Dist.) 15.11.2012,26.11.2012 2

    8. Road from LB Cheria CC road to Chillapalem of LB Cheria (Nasapur MandalW.G.Dist.)15.11.2012,26.11.2012 2

    9.NCRMP/B-W/AP/RHB/

    PRED/05/Kalla/003

    From A-U R&B Road to Satyanarayanapuram, (Kalla Mandal W.G.Dist.) 15.11.2012,26.11.2012 2

    10. From A-U R&B Road to Mekaladibba (Kalla Mandal W.G.Dist.) 0

    Total 13

    MONTHLY REPORT

  • 7/30/2019 November 2012 Mpr

    54/122

    MONTHLY REPORT

    53