24
SAP Project Cost Forecast, SAP Project Cost Forecasting, SAP Project Forecast, SAP Project Forecasting, SAP Project System, SAP PS, SAP Project Management, SAP Project Management solutions, SAP Project Planning, SAP Project Cost Planning, SAP Project Cost Plan, SAP Project Cost To Complete, SAP Project Remaining Cost To Complete, SAP Project CTC, SAP Project Estimate At Completion, SAP Project EAC, SAP Project Progress Analysis, SAP Project Earned Value, SAP Project Estimation, SAP Project Cost Estimation, SAP Project Cost Estimate, SAP Project Cost Estimating, SAP Project Estimate, SAP Project Estimating, SAP Project Margin Forecasting SAP Project System enhancements, SAP Project Portal, SAP Project Portfolio Report, SAP Project Portfolio Reporting, SAP Project Portfolio Planning, SAP Project Portfolio Management, SAP PPM, SAP Commercial Project Management, SAP CPM, SAP Easy Cost Planning, SAP ECP, SAP CJ9L, SAP Project Builder SAP Project Editor SAP Project Scheduling, SAP Project Schedule, SAP Project Gantt Chart, SAP Project Report, SAP Project Cash Flow, SAP Project Cashflow, SAP Project Cash Management, SAP Project Resource Forecasting, SAP Project Resource Planning, SAP Project Resource Management SAP Project KPI, SAP Project Key Performance Indicators, SAP Project S-curves reports, SAP Project Reporting, SAP Project Report, Noveco ePM 3.0 : Planning and Forecasting by Purchase Order

Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

  • Upload
    builien

  • View
    231

  • Download
    5

Embed Size (px)

Citation preview

Page 1: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

SAP Project Cost Forecast,

SAP Project Cost Forecasting,

SAP Project Forecast,

SAP Project Forecasting,

SAP Project System,

SAP PS,

SAP Project Management,

SAP Project Management solutions,

SAP Project Planning,

SAP Project Cost Planning,

SAP Project Cost Plan,

SAP Project Cost To Complete,

SAP Project Remaining Cost To Complete,

SAP Project CTC,

SAP Project Estimate At Completion,

SAP Project EAC,

SAP Project Progress Analysis,

SAP Project Earned Value,

SAP Project Estimation,

SAP Project Cost Estimation,

SAP Project Cost Estimate,

SAP Project Cost Estimating,

SAP Project Estimate,

SAP Project Estimating,

SAP Project Margin Forecasting

SAP Project Revenue Forecasting

SAP Solutions for Engineering and Construction,

SAP Solutions for Construction projects,

SAP Solutions for Construction industry,

SAP Solutions for Capital projects,

SAP Solutions for Capital and Maintenance projects,

SAP Solutions for Maintenance projects,

SAP Solutions for CAPEX projects,

SAP solutions for Manufacturing projects,

SAP solutions for Project Manufacturing,

SAP Solutions for Shipbuilding projects,

SAP Solutions for Engineering Projects

SAP Solutions for Professional Services,

SAP Solutions for EPCM

SAP Project Variation Management,

SAP Project Change Management,

SAP Project Change Control,

SAP Project Risk Management,

SAP Project Contingency,

SAP Project Risk Management,

SAP Project System enhancements,

SAP Project Portal,

SAP Project Portfolio Report,

SAP Project Portfolio Reporting,

SAP Project Portfolio Planning,

SAP Project Portfolio Management,

SAP PPM,

SAP Commercial Project Management,

SAP CPM,

SAP Easy Cost Planning,

SAP ECP,

SAP CJ9L,

SAP Project Builder

SAP Project Editor

SAP Project Scheduling,

SAP Project Schedule,

SAP Project Gantt Chart,

SAP Project Report,

SAP Project Cash Flow,

SAP Project Cashflow,

SAP Project Cash Management,

SAP Project Resource Forecasting,

SAP Project Resource Planning,

SAP Project Resource Management

SAP Project KPI,

SAP Project Key Performance Indicators,

SAP Project S-curves reports,

SAP Project Reporting,

SAP Project Report,

Noveco ePM 3.0 :

Planning and Forecasting by

Purchase Order

Page 2: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Process Flow

Planning and

Estimating Execution

Monitoring

and

Forecasting

• Create Project

• Plan Costs using

Easy Cost Planning

• Create Purchase

Orders

• Post Down Payments

• Post GR/IR for

Purchase Orders

• Perform Project

Forecasts

• Detail forecast by

Purchase Order

• Plan Purchase Order

remaining value by

period

Page 3: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Create Project

In this example we use project with WBS

only

Project with WBS and Network Activities

will work the same way

Page 4: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Plan Costs using Easy Cost Planning

We use cost type ‘V’ (variable), but we can

use ‘M’ material or ‘N’ service

If we use ‘M’ or ‘N’ we must enter material

or service number, we can also use Vendor

Name, Purchasing Info Record etc.

Page 5: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Open Project in Noveco Project Manager Workbench

• Original Estimate

derived from Easy Cost

Planning

• Cost To Complete initially

generated from Original

Estimate

Page 6: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Noveco Project Manager Workbench

NOTE:

- In “Forecast” tab cost plan is summarized by Cost Element, Resource Name and Value Category

Estimated at Completion = Actual Costs + Commitments +

Costs To Complete

Page 7: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Noveco Project Manager Workbench

Select Costing item and choose “Detail Forecasting”

Page 8: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Noveco Project Manager Workbench

When run for the first time, costing line items are copied from

Easy Cost Planning

Page 9: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Process Flow

Planning and

Estimating Execution

Monitoring

and

Forecasting

• Create Project

• Plan Costs using Easy

Cost Planning

• Create Purchase

Orders

• Post Down

Payments

• Post GR/IR for

Purchase Orders

• Perform Project

Forecasts

• Detail forecast by

Purchase Order

• Plan Purchase Order

remaining value by

period

Page 10: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Post Time Sheets

Noveco demo: Plan By PO

Engineering

Design

Noveco demo: Plan By PO

4500009115 / 10

“Engineering:

Electrical”

4500009116 / 10

“Engineering:

Mechanical”

Goods receipt

Down Payment

Goods receipt

4500009117 / 10

“Engineering:

Structural”

Down Payment

Goods receipt

Page 11: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Process Flow

Planning and

Estimating Execution

Monitoring

and

Forecasting

• Create Project

• Plan Costs using Easy

Cost Planning

• Create Purchase

Orders

• Post Down Payments

• Post GR/IR for

Purchase Orders

• Perform Project

Forecasts

• Detail forecast by

Purchase Order

• Plan Purchase Order

remaining value by

period

Page 12: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Project Manager Workbench

Actual Costs and PO Commitments are

displayed

Exclamation mark indicates that forecast

cost to complete must be recalculated

PO List is displayed

for selected WBS

hierarchy

Page 13: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Project Manager WorkbenchClick “Refresh” to automatically

recalculate Cost To Complete and adjust

Estimated at Completion (if necessary)

Cost and Work To Complete reduced from

actual costs and purchase commitments

Page 14: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Switch to Change mode

Select Costing item and choose “Detail Forecasting”

Page 15: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Detailed Forecasting by Purchase Order

When run for the first time, the system copies plan cost

items from ECP.

Delete them if they are no longer required

Page 16: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Detailed Planning by Purchase Order

PO Progress calculated

as %: PO Actual Cost /

PO Plan ValuePO Down

Payment amount

Current total

PO Plan Value PO Actual Costs

and Remaining

Committed value

PO Value of Work Done = Value of Work

Done as % * ( PO Plan Value + PO Cost To

Complete)

Page 17: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Detailed Planning by Purchase Order

System recalculates PO Estimated at Completion =

PO Plan Value + PO Cost To CompleteEnter PO Cost To Complete amount

Page 18: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Detailed Planning by Purchase Order

System recalculates PO Value Of Work Done =

% of Value of Work Done * PO Estimated at CompletionEnter % of Value of Work Done by PO item

Page 19: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Detailed Planning by Purchase Order

System recalculates PO Accrued Value = Value of

Work Done – Actual Costs – Down Payment

Page 20: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Detailed Planning by Purchase Order

System recalculates PO Remaining Value = Value of

Work Done – Actual Costs – Down Payment

Page 21: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Plan by Period PO Remaining value

Select Purchase Order item (or multiple items) and click

on “Plan By Period”

Page 22: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Plan by Period PO Remaining value

When Completed click “Confirm” to copy new Cost To

Complete to “Forecast” tab

Page 23: Noveco ePM 3.0 : Planning and Forecasting by - SAP Project Cost Forecast, ... Planning and Forecasting by Purchase Order. Process Flow Planning and ... • Post GR/IR for Purchase

Update Project Forecast from Detailed Forecasting

Cost To Complete are updated

from the Detailed Forecasting

screen

Estimated at Completion is updated

and it is now over Budget by

$30000.0 or by 10.0%

Exception indicator turns red because

project Estimated Cost at Completion