NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France 1 KICK-OFF MEETING May 10-11, 2010

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France 1 KICK-OFF MEETING May 10-11, 2010

Embed Size (px)

Citation preview

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

1

KICK-OFF MEETING

May 10-11, 2010

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

2

1.1. Work Breakdown into Work Packages Work Breakdown into Work Packages and partnersand partners

2.2. Study LogicStudy Logic

3.3. DeliverablesDeliverables

4.4. ScheduleSchedule

Introduction

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

3

Work Breakdown structure

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

4

Work Breakdown into WP and Partners

0

10

20

30

40

50

60

70

80

90

WP000 WP100 WP200 WP300 WP400 WP500 WP600 WP700

NOV

CEA-LSCE

CERC

MPI-BGC

AEA

TAS-F

ETH

DLO

USTUTT

PKU

UNIABDN

METO

EFI

CLIMMOD

Man M

onth

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

5

Study Logic

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

6

Study Logic

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

7

Deliverables

Formal deliverables to ECFormal deliverables to EC List will be maintained by CoordinatorList will be maintained by Coordinator Each deliverable under WP responsabilities, provided to deliverable under WP responsabilities, provided to

Coordinator for validation and delivery to ECCoordinator for validation and delivery to EC

→ The T0+6/12M deliverables list is recalled in the next slidesThe T0+6/12M deliverables list is recalled in the next slides

Internal deliveries followed by the Internal deliveries followed by the coordinator:coordinator: To ensure the smooth running of the projectTo ensure the smooth running of the project To have access of the correct level of monitoringhave access of the correct level of monitoring

→ Process of monitoring of the internal deliverables is illustrated Process of monitoring of the internal deliverables is illustrated with exampleswith examples

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

8

Formal Deliverables

Del. no.

Deliverable nameLead

beneficiary

Dissemination

levelDelivery date

D0.1 Project presentation (M 0) NOV PU Kick-Off Meeting

D300.2

Report on all data stream that CARBONES could

benefit + Assessment of the accessibility and of the necessary

mechanisms to grant the access.

MPI-BGC PU First version → Kick-Off Meeting

D120.1

CUAG meeting #1 minutes METO PU T0+5 → 1st September, 2010

D120.2

User requirements report V0 METO PU T0+5 → 1st September, 2010

D210.1

System Requirements synthesis and justification

TASF PU T0+6 → 1st October, 2010

D220.2

Document on the complementarities with other

EU/National projects and outside Europe if relevant.

TASF PU T0+6 → 1st October, 2010

D230.1

Scientific tools and architecture definition Document

including Data models, Engineering Point of View V0,V1

TASF PU Version 0 at T0+6 → 1st October, 2010

D220.1

Services/Product Definition V0, V1 TASF PU Version 0 at T0+6 → 1st October, 2010

D720.1

Market assessment reports 1, 2, 3 AEA CO Version 0 at T0+6 → 1st October, 2010

T0 → T0 + 6 months

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

9

Formal Deliverables

Del. no.

Deliverable nameLead

beneficiary

Dissemination

level

Delivery date(proj. month)

D410.1

Description document of the CCDAS, V1, V2

LSCE PU Version 1 at T0+8 → 1st December 2010

D230.1

Scientific tools and architecture definition Document

including Data models, Engineering Point of View V0,V1

TASF PU Version 1 at T0+12 → 1st April 2011

D300.1

CARBONES input and forcing data presentation

document, V1

MPI-BGC PU Version 1 at T0+12 → 1st April 2011

D430.1

CCDAS validation : Error estimations: Parameter errors on

base configuration

LSCE PU Version 1 at T0+12 → 1st April 2011

D430.2

CCDAS validation : Error estimations: Errors on output

fields

LSCE PU Version 1 at T0+12 → 1st April 2011

D510.1

CARBONES dataset V0 NOV PU Version 0 at T0+12 → 1st April 2011

D520.1

CARBONES portal description : simplified version V0

CERC PU Version 0 at T0+12 → 1st April 2011

D720.3

Business development plans, 1, 2, 3 AEA CO Version 1 at T0+12 → 1st April 2011

T0 + 6 months → T0 + 12 months

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

10

Internal Deliveries

For the good running of the project, internal deliveries will be followed by NOVELTIS. For that, each partner has to:→ sent their documents with NOVELTIS in copy.

→ sent an email to NOVELTIS informing the data delivery with the reference.

Examples of internal deliveries: For data:

Input data from the data providers to CCDAS responsible. Example of CCDAS output data for the CARBONES portal development.

For document: The specification document of the post-processing of the CCDAS

outputs for the CARBONES portal

NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France

11

Project Schedule

Meeting DateOrganised

byPlace

Kick-Off Meeting 10-11 May 2010 NOVELTIS Toulouse, France

CUAG Consultation Meeting September 2010 METO TBD

Progress Meeting # 1 October 2010

Progress Meeting # 2 April 2011 LSCE Paris, France

User Workshop #1 and CUAG meeting #2

September 2011 AEA

Mid Term Review Meeting October 2011

Progress Meeting # 3 April 2012

Progress Meeting # 4 October 2012 LSCE Paris, France

User Workshop #2 and CUAG meeting #3

December 2012 METO

Final Meeting April 2013 NOVELTIS Toulouse, France