12
Health and Safety Executive Notification of Conventional Tower Cranes Regulations 2010 Gavin Bye, Construction Sector A presentation to CONIAC, March 2010

Notification of Conventional Tower Cranes Regulations 2010

Embed Size (px)

DESCRIPTION

Notification of Conventional Tower Cranes Regulations 2010. Gavin Bye, Construction Sector A presentation to CONIAC, March 2010. New Regulations. laid Monday 22 February 2010 coming into force 06 April 2010. Scope - ‘conventional’ tower cranes on construction sites. Requirements. - PowerPoint PPT Presentation

Citation preview

Page 1: Notification of Conventional Tower Cranes Regulations 2010

Health and Safety Executive

Notification of Conventional Tower Cranes Regulations

2010

Gavin Bye, Construction SectorA presentation to CONIAC, March 2010

Page 2: Notification of Conventional Tower Cranes Regulations 2010

New Regulations

laid Monday 22 February 2010

coming into force 06 April 2010

Scope - ‘conventional’ tower cranes on construction sites

Page 3: Notification of Conventional Tower Cranes Regulations 2010

Requirements Notify to HSE certain information:

crane owner/lessor details;address of construction site;crane identification details;date of thorough examination (t/e);t/e carried out for whom? Details;did t/e reveal defects ‘reportable’ defects?

Trigger for notification – the t/e.

Page 4: Notification of Conventional Tower Cranes Regulations 2010

INDG437

http://www.hse.gov.uk/pubns/books/indg437.htm

Web-friendly version available at:

Guidance

Page 5: Notification of Conventional Tower Cranes Regulations 2010

The Register

Available at: http://www.cranesregister.org.uk.

Cost - £20 per notification, payment via the website.

Input - uploaded directly by duty-holder.

Enquiry - enquiry form available on website.

Output - interrogation by HSE only.

Holding the notified information

HSE will be able to handle hard copy Input, payment, Enquiries

Page 6: Notification of Conventional Tower Cranes Regulations 2010

The Register http://www.craneregister.org.uk/

Page 7: Notification of Conventional Tower Cranes Regulations 2010

The Register – crane details

Page 8: Notification of Conventional Tower Cranes Regulations 2010

The Register - enquiry

Page 9: Notification of Conventional Tower Cranes Regulations 2010

Communications

Duty-holdersHSE website; trade press;mail shots; press releases…

and…

Around 6 April, with…

Page 10: Notification of Conventional Tower Cranes Regulations 2010

Communications

Members of the public:

site posters;

HSE website…

Around 6 April, with…

Page 11: Notification of Conventional Tower Cranes Regulations 2010

Evaluation

• Report to HSE Board, Ministers after a year on:

– the numbers of registrations by duty-holders;

– number of enquiries from the public;

– enforcement and other activity taken by HSE inspectors in relation to Regulations

Page 12: Notification of Conventional Tower Cranes Regulations 2010

Operational Work

• Head office visits done - report prepared and results shared with tower crane industry body

• Industry committed to full competence 31.12.2010

• 2010 – 11 plan shifts emphasis to on site visits with contractors

• Follow up work on design underway on early HSL results (wind)