Note Planning

Embed Size (px)

Citation preview

  • 8/8/2019 Note Planning.

    1/25

    1

    PROJECT PLANNING USING NETWORKTECHNIQUE

    INTRODUCTION

    Network planning technique is a very usefultool in project management.

    Two different types of networks are the Arrowdiagram and the Precedence diagram.

    In principle, both techniques use the critical

    path method to analyze the project time.

  • 8/8/2019 Note Planning.

    2/25

    2

    Historical Background

    During world war 1, Henry L.Gantt develop agraphical technique of displaying bar type line uponspecific time.

    The technique was known as Bar Chart. In 1956 E.I. du Pont de Nemours & Company

    developed network concept known as Critical PathMethod

    Booz Allen & Hamilton develop Project Evaluation

    Review Technique (PERT) Scheduling software application are Primavera,

    Microsoft Project, Artemis, Timeline etc

  • 8/8/2019 Note Planning.

    3/25

    3

    Choice of Scheduling Method

    Factors that governed the choice of the

    technique are:

    Familiarity on the technique to be used Type and size of project

    Purpose of scheduling

  • 8/8/2019 Note Planning.

    4/25

    4

    Familiarity on the technique to be used

    A planner should not engaged any techniquewhich he has a limited knowledge on itsapplication

    Main objective of the schedule as acommunication tool

    Important to have a schedule technique

    which is acceptable by all parties.

  • 8/8/2019 Note Planning.

    5/25

    5

    Type and Size of the Project

    Project with few but repetitive tasks Line ofBalance

    Medium to Large Project (Critical PathMethod) like Precedence Method or ArrowDiagram

    Small Project Gantt Chart or Bar Chart

  • 8/8/2019 Note Planning.

    6/25

    6

    Purpose & Important of Schedule

    Claim Project time and cost control Allocate project resources more efficiently As a monitoring tool Material delivery at site Storage all material cannot put in the site (confined space)

    Avoid delay of the work and activity. Minimize the cash flow as min as possible such as order material

    stage by stage depend on the work needed. To guide fabricate (roofing, steel etc) Control human resources and machinery To give confidence to the client especially when bidding process. To improve the efficiency of the operation through the efficient use of

    resources and cost control. Basic schedule for endorsement.

  • 8/8/2019 Note Planning.

    7/25

    7

    Basic Scheduling Technique

    Gantts Chart or Bar Chart

    Networking

    Arrow diagram method Precedence Diagram Method

    Project Evaluation Review Technique (PERT)

    Line of Balance

  • 8/8/2019 Note Planning.

    8/25

    8

    Bar Chart

    Bar Chart is one of the oldest scheduling technique

    Wide acceptance because it is readily understoodby almost every one

    It is very easy to develop and used Useful technique for a small project

    Task schedule can be graphically presented on thetime-scale.

    The main weakness is that relationship that existbetween the task cannot be shown.

  • 8/8/2019 Note Planning.

    9/25

    9

    Bar Chart

  • 8/8/2019 Note Planning.

    10/25

    10

    Network Method

    Arrow Diagram

    In arrow diagram project task or activities are represented bythe arrow and connected by the node to express their logicalrelationship

    Arrow diagram for pad footing

    Arrow ActivityNode Junction to the event

    - Activity started or end

  • 8/8/2019 Note Planning.

    11/25

    11

    Precedence Diagram Method

    PDM activity is place on the node

    The arrow used to connect between project task to show their

    logical relationship

    PDM diagram for pad footing

    Arrow - LogicalNode - ActivityLogical Show the relationship two activity

    - Sequences of interrelated activity

  • 8/8/2019 Note Planning.

    12/25

    12

    Line of Balance

    Used to plan for construction of a number ofrepetitive activities.

    Concept of keeping all of resources in

    balance, each following the other productivity Main objective to optimum use of all

    resources

    Example for road construction, bridge, pipelaying, housing and etc

  • 8/8/2019 Note Planning.

    13/25

    13

    Line of Balance Chart

  • 8/8/2019 Note Planning.

    14/25

    14

    week

    Number ofproduct

    Line of Balance for Housing Project

  • 8/8/2019 Note Planning.

    15/25

  • 8/8/2019 Note Planning.

    16/25

    16

    Basic Resources In Planning

    Special long lead item may required several monthsbefore actual delivery can be made to site.

    The machine and technology to be used in the

    project has strong influence on the productivity rateat site also number of workers planned to beemployed.

    Understanding of labor requirement for thedetermination of performance time of the variousactivities during the construction process.

  • 8/8/2019 Note Planning.

    17/25

    17

    Project task or Activity

    Definition an Activity or task-

    single work step that has a recognizable beginningand end and requires time and resources for its

    accomplishment . Dummy Activity

    - Have zero duration

    - Do not require any resources

    - Happen in both arrow diagram & precedence diagram

    - Needed to have proper logic, maintain numbering, system or

    milestone event.

  • 8/8/2019 Note Planning.

    18/25

    18

    Project Breakdown

    Process of dividing it into smaller segments

    Several criteria can be used to divide the projectsuch follows:

    1. By area of responsibility

    2. By structural elements

    3. By category of works

    4. By location of project

    Planner must be able to identify all project activitiesor task to executed.

  • 8/8/2019 Note Planning.

    19/25

    19

    Logical Relationship of ProjectActivities

    Understand the order of how the job to beaccomplished in the field.

    The planner must understand how variousactivities of the project related to each otherin term of their logical sequence.

    Example preparing formwork before

    reinforcement could be place & than pouringconcrete.

  • 8/8/2019 Note Planning.

    20/25

    20

    Strip top soil Cut and Fill

    Form work Pour Concrete

    Fixed rebar

    Figure-1 the logical relationship between the two activities showsthat the start of cut & fill activity can only accomplished upon thecompletion of the activity strip top soil.

    Figure-2 indicate that activities formwork and rebar must beaccomplish before the start of activity pour concrete

  • 8/8/2019 Note Planning.

    21/25

    21

    ACTIVITY ON ARROW (AOA)

    ES = Earliest Start (Masa Mula Awal)

    LS = Latest Start ( Masa Mula Akhir)

    EF = Earliest Finish ( Masa Tamat Awal)

    LF = Latest Finish ( Masa Tamat Akhir)

    TF = Total Float (Jumlah Apungan)

    FF = Free Float (Apungan Bebas)

    Duration = Time to complete an activity (D)

    ES & LF From arrrow diagram

    EF = ES + Duration

    LS = LF Duration

    TF = LF EF FF = Early start of succeeding - EF of activity

  • 8/8/2019 Note Planning.

    22/25

    22

    AOA

    Forward pass - a process to find the earliest start time

    for all activities

    Backward - a process to find latest finish time for allactivities

    Critical Path - the longest paths of the planning from start

    to finish

    Total Float (TF) - the maximum time available for anactivity that can be delay withoutdelaying the completion date(TF = LF ES)

    Free float (FF) - the maximum time for an activity that can bedelayed without delayed the start of any

    succeeding activity.(FF = Early start of succeeding - EF of activity )

  • 8/8/2019 Note Planning.

    23/25

    23

    AOAEXAMPLE ARROW DIAGRAM

    Activity Duration Predecessor A 5 - B 2 - C 1 - D 4 A E 3 B

    F 6 C G 2 C H 5 D I 1 E,F J 6 G

  • 8/8/2019 Note Planning.

    24/25

    24

    \10

  • 8/8/2019 Note Planning.

    25/25

    25

    Result

    Activity Duration ES EF LS LF TF FF

    A 5 0 5 0 5 0 0

    B 2 0 2 8 10 8 0

    C 1 0 1 5 6 5 0

    D 4 5 9 5 9 0 0

    E 3 2 5 10 13 8 2

    F 6 1 7 7 13 6 0

    G 2 1 3 6 8 5 0

    H 5 9 14 11 14 0 0

    I 1 7 8 13 14 6 6

    J 6 3 9 8 14 5 5