Upload
sailormoon72
View
222
Download
0
Embed Size (px)
Citation preview
8/8/2019 Note Planning.
1/25
1
PROJECT PLANNING USING NETWORKTECHNIQUE
INTRODUCTION
Network planning technique is a very usefultool in project management.
Two different types of networks are the Arrowdiagram and the Precedence diagram.
In principle, both techniques use the critical
path method to analyze the project time.
8/8/2019 Note Planning.
2/25
2
Historical Background
During world war 1, Henry L.Gantt develop agraphical technique of displaying bar type line uponspecific time.
The technique was known as Bar Chart. In 1956 E.I. du Pont de Nemours & Company
developed network concept known as Critical PathMethod
Booz Allen & Hamilton develop Project Evaluation
Review Technique (PERT) Scheduling software application are Primavera,
Microsoft Project, Artemis, Timeline etc
8/8/2019 Note Planning.
3/25
3
Choice of Scheduling Method
Factors that governed the choice of the
technique are:
Familiarity on the technique to be used Type and size of project
Purpose of scheduling
8/8/2019 Note Planning.
4/25
4
Familiarity on the technique to be used
A planner should not engaged any techniquewhich he has a limited knowledge on itsapplication
Main objective of the schedule as acommunication tool
Important to have a schedule technique
which is acceptable by all parties.
8/8/2019 Note Planning.
5/25
5
Type and Size of the Project
Project with few but repetitive tasks Line ofBalance
Medium to Large Project (Critical PathMethod) like Precedence Method or ArrowDiagram
Small Project Gantt Chart or Bar Chart
8/8/2019 Note Planning.
6/25
6
Purpose & Important of Schedule
Claim Project time and cost control Allocate project resources more efficiently As a monitoring tool Material delivery at site Storage all material cannot put in the site (confined space)
Avoid delay of the work and activity. Minimize the cash flow as min as possible such as order material
stage by stage depend on the work needed. To guide fabricate (roofing, steel etc) Control human resources and machinery To give confidence to the client especially when bidding process. To improve the efficiency of the operation through the efficient use of
resources and cost control. Basic schedule for endorsement.
8/8/2019 Note Planning.
7/25
7
Basic Scheduling Technique
Gantts Chart or Bar Chart
Networking
Arrow diagram method Precedence Diagram Method
Project Evaluation Review Technique (PERT)
Line of Balance
8/8/2019 Note Planning.
8/25
8
Bar Chart
Bar Chart is one of the oldest scheduling technique
Wide acceptance because it is readily understoodby almost every one
It is very easy to develop and used Useful technique for a small project
Task schedule can be graphically presented on thetime-scale.
The main weakness is that relationship that existbetween the task cannot be shown.
8/8/2019 Note Planning.
9/25
9
Bar Chart
8/8/2019 Note Planning.
10/25
10
Network Method
Arrow Diagram
In arrow diagram project task or activities are represented bythe arrow and connected by the node to express their logicalrelationship
Arrow diagram for pad footing
Arrow ActivityNode Junction to the event
- Activity started or end
8/8/2019 Note Planning.
11/25
11
Precedence Diagram Method
PDM activity is place on the node
The arrow used to connect between project task to show their
logical relationship
PDM diagram for pad footing
Arrow - LogicalNode - ActivityLogical Show the relationship two activity
- Sequences of interrelated activity
8/8/2019 Note Planning.
12/25
12
Line of Balance
Used to plan for construction of a number ofrepetitive activities.
Concept of keeping all of resources in
balance, each following the other productivity Main objective to optimum use of all
resources
Example for road construction, bridge, pipelaying, housing and etc
8/8/2019 Note Planning.
13/25
13
Line of Balance Chart
8/8/2019 Note Planning.
14/25
14
week
Number ofproduct
Line of Balance for Housing Project
8/8/2019 Note Planning.
15/25
8/8/2019 Note Planning.
16/25
16
Basic Resources In Planning
Special long lead item may required several monthsbefore actual delivery can be made to site.
The machine and technology to be used in the
project has strong influence on the productivity rateat site also number of workers planned to beemployed.
Understanding of labor requirement for thedetermination of performance time of the variousactivities during the construction process.
8/8/2019 Note Planning.
17/25
17
Project task or Activity
Definition an Activity or task-
single work step that has a recognizable beginningand end and requires time and resources for its
accomplishment . Dummy Activity
- Have zero duration
- Do not require any resources
- Happen in both arrow diagram & precedence diagram
- Needed to have proper logic, maintain numbering, system or
milestone event.
8/8/2019 Note Planning.
18/25
18
Project Breakdown
Process of dividing it into smaller segments
Several criteria can be used to divide the projectsuch follows:
1. By area of responsibility
2. By structural elements
3. By category of works
4. By location of project
Planner must be able to identify all project activitiesor task to executed.
8/8/2019 Note Planning.
19/25
19
Logical Relationship of ProjectActivities
Understand the order of how the job to beaccomplished in the field.
The planner must understand how variousactivities of the project related to each otherin term of their logical sequence.
Example preparing formwork before
reinforcement could be place & than pouringconcrete.
8/8/2019 Note Planning.
20/25
20
Strip top soil Cut and Fill
Form work Pour Concrete
Fixed rebar
Figure-1 the logical relationship between the two activities showsthat the start of cut & fill activity can only accomplished upon thecompletion of the activity strip top soil.
Figure-2 indicate that activities formwork and rebar must beaccomplish before the start of activity pour concrete
8/8/2019 Note Planning.
21/25
21
ACTIVITY ON ARROW (AOA)
ES = Earliest Start (Masa Mula Awal)
LS = Latest Start ( Masa Mula Akhir)
EF = Earliest Finish ( Masa Tamat Awal)
LF = Latest Finish ( Masa Tamat Akhir)
TF = Total Float (Jumlah Apungan)
FF = Free Float (Apungan Bebas)
Duration = Time to complete an activity (D)
ES & LF From arrrow diagram
EF = ES + Duration
LS = LF Duration
TF = LF EF FF = Early start of succeeding - EF of activity
8/8/2019 Note Planning.
22/25
22
AOA
Forward pass - a process to find the earliest start time
for all activities
Backward - a process to find latest finish time for allactivities
Critical Path - the longest paths of the planning from start
to finish
Total Float (TF) - the maximum time available for anactivity that can be delay withoutdelaying the completion date(TF = LF ES)
Free float (FF) - the maximum time for an activity that can bedelayed without delayed the start of any
succeeding activity.(FF = Early start of succeeding - EF of activity )
8/8/2019 Note Planning.
23/25
23
AOAEXAMPLE ARROW DIAGRAM
Activity Duration Predecessor A 5 - B 2 - C 1 - D 4 A E 3 B
F 6 C G 2 C H 5 D I 1 E,F J 6 G
8/8/2019 Note Planning.
24/25
24
\10
8/8/2019 Note Planning.
25/25
25
Result
Activity Duration ES EF LS LF TF FF
A 5 0 5 0 5 0 0
B 2 0 2 8 10 8 0
C 1 0 1 5 6 5 0
D 4 5 9 5 9 0 0
E 3 2 5 10 13 8 2
F 6 1 7 7 13 6 0
G 2 1 3 6 8 5 0
H 5 9 14 11 14 0 0
I 1 7 8 13 14 6 6
J 6 3 9 8 14 5 5