Upload
doanh
View
216
Download
1
Embed Size (px)
Citation preview
A L A S K A C A L I F O R NI A F L O R I D A M I D - P A C I F I C N O R TH EA S T NO R TH ER N R O C K I E S
NO R TH W ES T R O C K Y M O U N TA I N W A S H I NG T O N , D . C . I N T ER NA TI O NA L
N O R T H W E S T O F F I C E 7 0 5 S E C O N D A V E N U E , S U I T E 2 0 3 S E A T T L E , W A 9 8 1 0 4
T : 2 0 6 . 3 4 3 . 7 3 4 0 F : 2 0 6 . 3 4 3 . 1 5 2 6 N W O F F I C E @ E A R T H J U S T I C E . O R G W W W . E A R T H J U S T I C E . O R G
November 18, 2013
The Honorable Jo-Ellen Darcy
Assistant Secretary of the Army (Civil Works)
108 Army Pentagon
Washington, D.C. 20310-0108
The Honorable Nancy Sutley, Chair
White House Council on Environmental Quality
730 Jackson Place, N.W.
Washington, D.C. 20503
Re: U.S. Army Corps of Engineers Decisions for Determining Scope of
Environmental Review Under NEPA for Coal Export Facilities in Washington
and Oregon
Dear Ms. Darcy and Ms. Sutley:
We are writing on behalf of Climate Solutions, Sierra Club, National Wildlife Federation,
Columbia Riverkeeper, RE Sources, Washington Environmental Council, Greenpeace, Western
Organization of Resource Councils, and Friends of the Columbia Gorge with regard to a critical
question of public interest: the appropriate scope of the environmental review for three coal
export terminals currently going through the Army Corps permitting process: the Gateway
Pacific Terminal (“GPT”) facility near Bellingham, Washington, the Millennium Bulk
Terminals-Longview (“MBL”) facility near Longview, Washington, and the Coyote Island Dock
at the Port of Morrow in Oregon (“Morrow”). Specifically, the Corps has misapplied the
National Environmental Policy Act (“NEPA”) and its governing regulations by determining that
most of the environmental impacts of vital interest to the public are outside the scope of the
Corps’ environmental impact statement (“EIS”) for the GPT facility. Given its previous
statements, we anticipate that the Corps will make a similar erroneous decision with respect to
the scope of the environmental reviews for the MBL and Morrow facilities.
The Corps’ decision with respect to the scope of the GPT environmental review is wrong
and will not withstand federal court review. We ask you to revoke and revise the GPT scoping
memorandum. It serves neither the applicant nor the public to have the Corps spend the next few
The Honorable Jo-Ellen Darcy
The Honorable Nancy Sutley
November 18, 2013
Page 2
years studying the wrong things, only to have the EIS set aside by a federal court and be directed
to start over. Similarly, the Corps should make a lawful decision with respect to the appropriate
scope of NEPA review for the MBL and Morrow terminals.
As a threshold matter, we continue to believe that the best approach for dealing with
these three terminals is for the Corps to conduct an area-wide environmental impact statement
that covers the cumulative and joint impacts of all three terminals, which collectively would
move 100 million tons of Powder River Basin coal through a single rail line into the Pacific
Northwest, increase mining in the basin, and trigger dramatic increases in global greenhouse gas
emissions. An area-wide approach would allow the individual terminal-specific EIS processes to
continue, albeit with a focus on individual and site-specific concerns, while addressing many of
the cumulative impact concerns within a single process.
In the absence of an area-wide EIS, it is particularly crucial that the Corps analyze the
indirect and cumulative impacts of greatest concern to the public in the three terminal NEPA
processes. Unfortunately, already the Corps is making the wrong decisions in this regard, stating
that these concerns are too far removed from the Corps’ permitting responsibility to warrant
inclusion in the review. As explained in the accompanying legal memorandum, the Corps’
approach violates governing law, which requires consideration of all indirect effects that are
“proximately caused” by the decision under review. Determining proximate causation requires a
fact-specific inquiry into whether a given impact is a “reasonably foreseeable” result of an
action. Because significant increases in train and vessel traffic, mining, and GHG emissions are
all reasonably foreseeable results of the three pending coal terminals, the Corps is required by
law to include them in the EIS.
In deciding otherwise, the Corps has misapplied its own NEPA regulations, which define
the scope of Corps actions based on the amount of responsibility and control. But the Corps has
incorrectly applied regulations governing the scope of the action under review to determine the
scope of the effects of such action. There is no regulation or precedent that allows the Corps to
ignore indirect effects that are proximately caused by a permitting decision in a NEPA review
based on the amount of “responsibility and control” the Corps retains. Indeed, such an approach
could eviscerate the entire purpose of including indirect effects in a NEPA document, as they are
by definition later in time and space and not a direct result of the action being permitted.
As you are aware, recent hearings in the region on the proper scope of the EIS for the
GPT and MBL projects resulted in a total attendance of over 10,000 citizens, the overwhelming
majority of whom oppose the issuance of permits for coal export terminals. Over 280,000
citizens have submitted written scoping comments on the MBL and GPT proposals, and that
number continues to grow. Tens of thousands more have asked the Corps for a close evaluation
of all impacts from the Morrow project. The Corps cannot narrowly define the scope of the
A L A S K A C A L I F O R NI A F L O R I D A M I D - P A C I F I C N O R TH EA S T NO R TH ER N R O C K I E S
NO R TH W ES T R O C K Y M O U N TA I N W A S H I NG T O N , D . C . I N T ER NA TI O NA L
N O R T H W E S T O F F I C E 7 0 5 S E C O N D A V E N U E , S U I T E 2 0 3 S E A T T L E , W A 9 8 1 0 4
T : 2 0 6 . 3 4 3 . 7 3 4 0 F : 2 0 6 . 3 4 3 . 1 5 2 6 N W O F F I C E @ E A R T H J U S T I C E . O R G W W W . E A R T H J U S T I C E . O R G
MEMORANDUM
TO: Interested Parties
FROM: Jan Hasselman & Kristen L. Boyles
DATE: November 18, 2013
RE: Appropriate Scope of NEPA Analysis for Washington and Oregon Coal Export
Terminals
This memorandum explains how the National Environmental Policy Act (“NEPA”)
applies to the indirect and cumulative effects of proposed coal export terminals in the Pacific
Northwest that are of great interest to the public. It concludes that most if not all of the impacts
of critical concern in the process to date, including expanded rail and vessel traffic, coal mining,
and downstream combustion of exported coal, would be proximately caused by the U.S. Army
Corps of Engineers’ authorization to build the terminals, and must be included in the scope of the
environmental impact statement of the three terminal projects under review.
A. Overview of NEPA
NEPA, 42 U.S.C. §§ 4321–4370f, is our “basic national charter for protection of the
environment.” 40 C.F.R. § 1500.1(a). It makes environmental protection a part of the mandate
of every federal agency. 42 U.S.C. § 4332(1); Calvert Cliffs Coordinating Comm. v. U.S. Atomic
Energy Comm’n, 449 F.2d 1109, 1112 (D.C. Cir. 1971). It requires federal agencies to take
environmental considerations into account in their decisionmaking “to the fullest extent
possible.” 42 U.S.C. § 4332; 40 C.F.R. § 1500.2. It also supplements the existing authority of
agencies to allow them to act based on environmental considerations. 42 U.S.C. § 4335.
NEPA seeks to ensure that federal agencies take a “hard look” at environmental concerns.
Young v. Gen. Servs. Admin., 99 F. Supp. 2d 59, 67 (D.D.C. 2000). One of NEPA’s primary
purposes is to ensure that an agency, ‘“in reaching its decision, will have available, and will
carefully consider, detailed information concerning significant environmental impacts.’”
Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 349 (1989). NEPA also
‘“guarantees that the relevant information [concerning environmental impacts] will be made
available to the larger audience,” including the public, “that may also play a role in the
decisionmaking process and the implementation of the decision.’” Id.
2
The cornerstone of NEPA’s protections is the environmental impact statement (“EIS”).
NEPA requires federal agencies to prepare an EIS before undertaking any “major federal action
significantly affecting the quality of the human environment.” 42 U.S.C. § 4332(2)(C). The EIS
requires a detailed, “hard look” at the environmental impact of—and alternatives to—the
proposed action. Id. The EIS serves to ensure informed decisionmaking to the end that “the
agency will not act on incomplete information, only to regret its decision after it is too late to
correct.” Marsh v. Or. Natural Res. Council, 490 U.S. 360, 371 (1979). By considering the
environmental consequences of agency decisions, compliance with NEPA’s procedure is “almost
certain to affect the agency’s substantive decision.” Robertson, 490 U.S. at 350.
Of course, the development of an EIS is not an end in itself—its purpose is to inform the
substantive decision that an agency will ultimately make. Id. at 350. With respect to the
Gateway Pacific Terminal in Bellingham, Washington (“GPT”), the Millennium Bulk Logistics
Terminal in Longview, Washington (“MBL”), and the Morrow Pacific Terminal on the Oregon
side of the Columbia River, the Corps must make a decision to grant, condition, or deny Clean
Water Act and Rivers and Harbor Act permits. Importantly, the Corps’ discretion with respect to
what to consider in its permit decisions is sweeping. See 33 C.F.R. § 320.1-.4 (general
regulatory policies); id. § 230.1-.97 (guidelines for fill permits). Notably, permits cannot be
granted if they are “contrary to the public interest.” Standards for such review are exceedingly
broad, balancing “the benefits which reasonably may be expected to accrue from the proposal”
with “its reasonably foreseeable detriments.” 33 C.F.R. § 320.4(a)(1). The Corps is required to
consider “all factors which may be relevant to the proposal” as well as cumulative effects. The
list of relevant considerations is expansive, and includes not just a range of environmental
concerns, but also economics, flood hazards, navigation, energy needs, safety, and “in general,
the needs and welfare of the people.” Id. Additional criteria spelled out in the Corps’ public
interest regulation include: “the relative extent of the public and private need” for the project; the
practicability of alternatives that accomplish the objective of the project; and “the extent and
permanence of the beneficial and/or detrimental effects” of the project. Id. § 320.4(a)(2).
Finally, the Corps is directed to consider “overriding national factors of the public interest.” 33
C.F.R. § 320.4(j)(4). One such “national objective” that is called out is “energy conservation and
development.” Id. § 320.4(n); James City Cnty. v. EPA, 12 F.3d 1330, 1335 (4th Cir. 1993)
(“Congress obviously intended the Corps of Engineers in the initial permitting process to
consider the total range of factors bearing on the necessity or desirability of building” a project).
Obviously, the Corps cannot make this evaluation appropriately unless it has before it all the
factors that weigh on these questions.
B. Federal Agencies Must Consider All Direct, Indirect, and Cumulative Effects of a
Proposed Project in Their EIS.
NEPA’s governing regulations define what “range of actions, alternatives, and impacts
[must] be considered in an environmental impact statement.” 40 C.F.R. § 1508.25. This is in
part what is known as the “scope” of the EIS. First, the EIS must consider direct and indirect
effects. The direct effects of an action are those effects “which are caused by the action and
occur at the same time and place.” 40 C.F.R. § 1508.8(a). The indirect effects of an action are
those effects “which are caused by the action and are later in time or farther removed in distance,
but are still reasonably foreseeable.” 40 C.F.R. § 1508.8(b). For example, “[i]ndirect effects
may include growth inducing effects and other effects related to induced changes in the pattern
3
of land use, population density or growth rate, and related effects on air and water and other
natural systems, including ecosystems.” Id. In fact, “[f]or many projects, these secondary or
induced effects may be more significant than the project’s primary effects.... While the analysis
of secondary effects is often more difficult than defining the first-order physical effects, it is also
indispensable.” Fifth Annual Report of the Council on Environmental Quality (CEQ), 410-11
(Dec. 1974).1
An environmental impact statement must also analyze and address the cumulative
impacts of a proposed project. 40 C.F.R. § 1508.25(c)(3). Cumulative impacts are the result of
any past, present, or future actions that are reasonably certain to occur. Such effects “can result
from individually minor but collectively significant actions taking place over a period of time.”
40 C.F.R. § 1508.7. By way of comparison, indirect effects are effects caused by a project, albeit
potentially later in space or time. Cumulative effects are separate actions that are not caused by
the action under review, but that increase the level of concern when added to the effects of the
project.
The “scope” of the EIS (or the decision not to prepare one) includes a determination of
which direct, indirect, and cumulative effects are to be included and which are to be excluded.
40 C.F.R. § 1508.8. In the case of the GPT, MBL, and Morrow facilities, the scope of the EIS is
a critical threshold question to an adequate environmental review, since many of the critical
environmental impacts associated with these projects fall into the category of indirect and
cumulative effects that are removed in space or time from the terminal site.
C. Indirect Effects Must Be Considered Where It Is “Reasonably Foreseeable” That
They Will Result from the Action Under Review.
Courts frequently are called upon to determine whether indirect effects that are related to
an action subject to NEPA should be included in the EIS. 2
The standard for including such
indirect effects in an EIS is whether they are “proximately caused” by the action under review.
See Dep’t of Transp. v. Public Citizen, 541 U.S. 752, 767 (2004) (effect must have a “reasonably
close causal relationship” to the proposed action). One way of evaluating whether proximate
cause exists is if an environmental impact is “reasonably foreseeable.” Robertson, 490 U.S. at
355. “Reasonably foreseeable” effects are those that are “sufficiently likely to occur that a
person of ordinary prudence would take it into account in reaching a decision,” meaning that an
agency does not have to consider potential effects that are highly speculative or indefinite.
Sierra Club v. Marsh, 976 F.2d 763, 767-68 (1st Cir. 1992). In general, “the determination of
whether a future action is foreseeable turns on the specific facts of the case.” City of Oxford v.
F.A.A., 428 F.3d 1346, 1355 n. 22 (11th Cir. 2005).
1 Available at http://www.slideshare.net/whitehouse/august-1974-the-fifth-annual-report-of-
thecouncil-on-environmental-quality.
2 These questions can arise in two ways: first, where an agency decides that an action’s effects
are minor and no EIS is needed—reaching that conclusion by ignoring some indirect effect; and
second, where an EIS is prepared but challenged as failing to consider a particular effect. There
does not appear to be any meaningful distinction between these kinds of cases for purposes of
determining the scope of the EISs for the coal export terminals.
4
Notably, agencies cannot avoid their responsibility to consider such future effects by
claiming that they are uncertain, as NEPA requires some element of predictive behavior. City of
Davis v. Coleman, 521 F.2d 661, 676 (9th Cir. 1975) (“Reasonable forecasting and speculation is
thus implicit in NEPA, and we must reject any attempt by agencies to shirk their responsibilities
under NEPA by labeling and all discussion of future environmental effects as ‘crystal ball
inquiry’.”); 46 Fed. Reg. 18026 (Mar. 23, 1981) (“The EIS must identify all the indirect effects
that are known, and make a good faith effort to explain the effects that are not known but are
‘reasonably foreseeable.’ Section 1508.8(b). …[I]f there is total uncertainty about the identity
of future land owners or the nature of future land uses [for example], then of course, the agency
is not required to engage in speculation or contemplation about their future plans. But, in the
ordinary course of business, people do make judgments based upon reasonably foreseeable
occurrences.”).
The most common scenario in which indirect effects arise is when a project induces
growth or development, for example, a highway project that causes increased suburban sprawl.
The law is clear that these types of growth-inducing impacts must be analyzed at the time of the
initial highway project. City of Davis, 521 F.2d at 676; see also Sierra Club v. Marsh, 769 F.2d
868, 877-82 (1st Cir. 1985) (Corps NEPA document assessing impact of decision to approve
cargo terminal must disclose impacts of induced private land development).
D. An EIS Must Include Rail and Ship Vessel Impacts That are Proximately Caused
by the Coal Terminals.
At this point, it is well settled—particularly in the Ninth Circuit Court of Appeals—that
an agency must evaluate the environmental and public health impacts of additional transportation
that is proximately caused by the decision under review.
For example, in Ocean Advocates v. U.S. Army Corps of Eng’rs, 402 F.3d 846 (9th Cir.
2005), the Ninth Circuit held that the Corps violated NEPA in approving an oil dock expansion
because the Corps did not consider the increased vessel traffic (and consequent increased risk of
oil spills) resulting from the dock’s expansion. Notably, the dock in question was in Cherry
Point, Washington—a few hundred yards away from the proposed coal terminal dock for the
GPT project. Similarly, in Barnes v. Dep’t of Transp., 655 F.3d 1124, 1138-39 (9th Cir. 2011),
the court held that NEPA requires an agency to consider the effects of increased air traffic likely
to follow from construction of new runway. Finally, in S. Fork Band Council of W. Shoshone of
Nev. v. U.S. Dep’t of the Interior, 588 F.3d 718, 725 (9th Cir. 2009), the court found unlawful an
agency’s decision to grant a mining permit because it failed to evaluate the environmental
impacts of transporting and processing the ore at a facility 70 miles away. The court noted that
“[t]he air quality impacts associated with transport and off-site processing of the five million tons
of refractory ore are prime examples of indirect effects that NEPA requires be considered.” Id.
(emphasis added).
The impacts of additional rail traffic associated with these two projects are a matter of
critical public concern—communities all along the rail line between the Powder River Basin and
the terminal sites would see dramatic increases in train traffic associated with these projects,
estimated at over 30 additional trains per day. Commenters have raised significant concerns
5
regarding the public health impacts of coal dust, diesel emissions, noise, and delay of emergency
response capability. Others have raised concerns about impacts to road traffic and other rail
system users, such as passenger rail and other important but potentially displaced commodities
such as agricultural products. Finally, several commenters expressed concern about the GHG
impacts of transporting 100 million tons of coal via rail across a third of the country, which itself
is a significant source of GHGs that undercuts the commitment of both the state and federal
governments to reduce GHG emissions. The Corps’ decision to limit its evaluation of rail-
related impacts to only the Custer Spur will mean virtually all of these concerns would go
unaddressed in the Corps’ GPT EIS and likely the MBL and Morrow terminals’ environmental
review as well. This decision is inconsistent with well-settled law in this Circuit and should be
reversed.
The Corps’ decision with respect to vessel traffic represents an improvement over its rail
decision because it will at least evaluate impacts within Puget Sound and the Strait of Juan de
Fuca, but it nonetheless imposes an arbitrary line that ignores some of the critical impacts of
concern to the public. Specifically, the Corps’ scoping decision states that vessel traffic impacts
will be considered up until a point eight miles from a buoy off Cape Flattery. This arbitrary
cutoff ignores at least two critical indirect impacts, if not more. First, it ignores the GHG
emissions of the vessel traffic for the entire ocean journey. There is no justification in policy or
law for cutting off ship traffic GHG emissions at an arbitrary boundary offshore, since all of the
GHG vessel emissions are proximately caused by the decision under review. Vessel GHG
emissions are both easy to calculate and important to consider. Second, commenters have
expressed concerns about vessel impacts through other territorial waters of the United States and
Canada, including Umiak Pass in Alaska, where increased vessel traffic would increase the risk
of spills, collisions, accidents, and other environmental harms. Again, there is no rational
explanation as to why vessel impacts and spill risk should be evaluated in one part of the country
but not another. The law requires consideration of vessel impacts that are proximately caused by
the Corps’ permitting decision, not solely in Puget Sound, but for the entire predictable vessel
journey.
Rail and vessel traffic, like the impacts discussed below, are required because they are
proximately caused by the Corps’ action. In Public Citizen, the Supreme Court reasoned that an
agency did not need to include impacts in its NEPA review where it had lacked the power to act
on whatever information resulted. Here, in contrast, the Corps’ broad responsibility under the
CWA to consider the public interest and environment generally when it makes its permit
decisions gives it abundant authority to act on the information related to rail and vessel impacts.
The Corps may decide that the benefits of the project are worth such impacts; it may decide that
they need to be mitigated; or it may decide that the risks outweigh the project’s benefits.
However, the Corps cannot carry out its substantive duties if it ignores these issues in the coal
terminal EISs.
E. Additional Mining Is an Indirect Effect of the Terminals That Must Be Included
in the EIS.
Permitting export terminals that would ship 100 million tons of Powder River Basin coal
to Asian markets will “proximately cause” the mining of an additional 100 million tons of coal
beyond what would otherwise be mined for U.S. consumption—no other conclusion is possible.
6
U.S. mining companies have told their investors that because of declining U.S. consumption, the
only hope for getting new mines active is by opening up West Coast coal terminals.3 The only
new mine in Wyoming recently halted construction because, its chief executive told newspapers,
there is no export capacity to serve.4 Nor is the location and extent of such additional mining
speculative. Cloud Peak Coal, for example, has explicitly told investors that a series of mines it
hopes to develop in Montana will not go forward until Washington export terminals are
permitted.5 Ambre Energy owns or has an interest in two operating mines in the Basin and two
existing deposits, and it has explicitly told its investors that it hopes to integrate its two proposed
coal export terminals with its mines. “Our target is low-ash, low-moisture coal deposits that are
close to rail infrastructure so they can supply our thermal coal export business.” 6
Simply put,
without the terminals, the vast volumes of coal that proponents would like to ship will remain in
the ground. Accordingly, the impacts from additional mining that will be caused by the MBL
project, and other coal terminals, should be included in the EIS.
In Sierra Club v. Dep’t of Energy, 255 F. Supp. 2d 1177 (D. Colo. 2002), a court found
that a lease and easement for road had to consider environmental effects of the mine that would
be made accessible by the road. Even though the mine was on private property and there was no
certain date at which mining would begin, it was still a “reasonably foreseeable” result of the
agency decision to permit the road. For the same reasons, it is a “reasonably foreseeable” result
of the Corps’ decision to authorize the export terminals that additional mining will occur. In
part—for example, the MBL facility—we know precisely where that mining would take place.
These indirect impacts of the Corps’ decision should be included within the EIS.
Project proponents have argued that mining need not be considered in this EIS because
they have already been discussed in other EIS documents, for example, mining leases authorized
by the Bureau of Land Management.7 This argument reflects a misunderstanding of NEPA. The
goal of including mining in these EISs is not simply the value of another chapter in a document.
It is to inform the Corps’ substantive decision as to whether this permit should be granted. The
extent to which these permit decisions will proximately cause additional environmentally
destructive mining is part of the Corps’ public interest balancing as it exercises its CWA
discretion. NEPA authorizes agencies to tier to other NEPA document—for example, suitable
BLM EISs—where appropriate. What is not permissible is to pretend that the issue simply
doesn’t exist.
3 http://climatesolutions.org/cs-journal/cloud-peak-energy-201call-in201d-for-coal-exports-from-
the-west-coast.
4 http://climatesolutions.org/cs-journal/memo-to-the-very-serious-people-resistance-isn2019t-
futile-and-irony-can-be-delicious.
5 http://seekingalpha.com/article/1182631-cloud-peak-energys-ceo-discusses-q4-2012-results-
earnings-call-transcript.
6 http://www.ambreenergy.com/us-thermal.
7 As a threshold matter, the argument is simply incorrect because the BLM has not performed
full EISs on all lease sales and lease expansions in the Powder River Basin. Moreover, some
BLM EISs are currently under court review regarding claims of inadequate disclosure or
consideration of mining-related impacts.
7
F. Downstream Consumption of Fossil Fuels Is an Indirect Effect that Must be
Included in the EIS.
Finally, a critical concern to decision-makers and the public is whether the decision to
authorize these terminals—which would be the only coal export infrastructure on the West Coast
of the United States—would result in GHG emissions that should be evaluated in the EIS. The
GHG emissions from burning 100 million tons of coal are staggering, equivalent to about three
times the entire gross emissions of Washington State.8
As a threshold matter, there no longer is any meaningful dispute that GHG emissions
must be included within an EIS pursuant to NEPA. The Ninth Circuit has rejected the argument
that individual actions represent too minor of a contribution to the global problem to merit
consideration under NEPA. “The impact of greenhouse gas emissions on climate change is
precisely the kind of cumulative impacts analysis that NEPA requires agencies to conduct. Any
given rule setting a [vehicle fuel-efficiency] standard might have an ‘individually minor’ effect
on the environment, but these rules are ‘collectively significant actions taking place over a period
of time.’” Ctr. for Biological Diversity v. Nat’l Highway Traffic Safety Admin., 538 F.3d 1172,
1217 (9th Cir. 2008) (internal citations omitted). Draft CEQ guidance published in 2010 directs
agencies to consider indirect GHG-related impacts. “Analysis of emissions sources should take
account of all phases and elements of the proposed action over its expected life, subject to
reasonable limits based on feasibility and practicality.” CEQ, Draft NEPA Guidance on
Consideration of the Effects of Climate Change and Greenhouse Gas Emissions (Feb. 18, 2010),
at 5. Although the draft guidance has yet to be finalized, CEQ did emphasize that consideration
of GHG emissions was not a new component of the NEPA process, but an important factor to be
considered under the existing framework. Id. at 11.9
Downstream consumption of fuels is subject to the same analysis as any other indirect
effect: is the impact proximately caused by the decision under review? On one level, the
decision is simple: the EIS should consider the GHG impacts of burning 100 million tons of coal
that would be shipped from the terminals because it is not just “reasonably foreseeable” that it
will be burned—it is inevitable. There is no other thing that could conceivably happen to that
coal except be burned, and hence its substantial GHG emissions should be considered in the EIS
and weighed by the Corps as part of its substantive CWA decisions.
8 Washington Greenhouse Gas Inventory for 2010, available at https://fortress.wa.gov/ecy/
publications/publications/1202034.pdf. One ton of PRB coal generates 2.86 tons of CO2. See
http://www.eia.gov/coal/production/quarterly/co2_article/co2.html.
9 Moreover, there is no rule that says consideration of indirect or direct effects stops at the U.S.
borders—indeed, quite the opposite. Gov’t of the Province of Manitoba v. Salazar, 691 F. Supp.
2d 37, 51 (D.D.C. 2010); Executive Order No. 12114 (1979) (EIS required for “Major federal
actions significantly affecting the environment of the global commons”); CEQ Guidance on
NEPA Analyses for Transboundary Impacts (July 1, 1997) (case law has “reinforced the need to
analyze impacts regardless of geographic boundaries of United States”).
8
Caselaw suggests an alternative approach to calculating GHG emissions in the context of
permitting export terminals. In Mid States Coal. for Progress v. Surface Transp. Bd., 345 F.3d
520, 550 (8th Cir. 2003), the Eighth Circuit invalidated an authorization to build a new rail line
(that would make available 100 million tons of low-cost coal) because the EIS failed to consider
the increased power plant emissions that would be caused by this increased availability of coal.
The Court rejected the argument that “demand for coal will be unaffected by an increase in
availability and a decrease in price,” observing that the availability of cheap coal will make coal
a more attractive option for future power generation compared to other options. “Even if this
project will not affect the short-term demand for coal, which is possible since most existing
utilities are single-source dependent, it will most assuredly affect the nation’s long-term demand
for coal….” Id. at 549. The Court also rejected the argument that the effects could be ignored
because the impacts were “speculative”—even if the extent of the effects were unknown, the
“nature” of the effect was not. Id.
In Border Plant Working Grp. v. Dep’t of Energy, 260 F. Supp. 2d 997, 1028 (S.D. Cal.
2003), a district court held that the federal agency, when considering proposed electrical
transmission lines that crossed the U.S.-Mexico border, was required to consider the effects of
the operation of the coal plant at the end of the transmission line. Because there was nothing in
the record to suggest that the Mexican power plant could sell its power in the absence of the
transmission line, the court found the line to be a “cause” of the plant’s emissions, and hence the
plant’s emissions needed to be included in the EIS.
These cases indicate that NEPA requires that the Corps disclose and consider how the
availability of so much low-cost PRB coal will influence short-term consumption patterns and
long-term investment decisions in Asia. Recent scholarly analysis agrees that this would be the
appropriate approach for coal export terminals. See NEPA & Downstream Greenhouse Gas
Emissions of U.S. Coal Exports (Columbia Law School, 2013), at 12 (“If an increase in exports
is a reasonably foreseeable result of allowing the construction of new ports, then the emissions
associated with that export may be indirect effects that are subject to NEPA review.”). Indeed,
evidence submitted by commenters shows that this is precisely what will happen. In The
Greenhouse Gas Impact of Exporting Coal from the West Coast: An Economic Analysis,
Dr. Thomas M. Power of the University of Montana concluded:
The proposed coal export facilities in the Northwest will result in more coal
consumption in Asia and undermine China’s progress towards more efficient
power generation and usage. Decisions the Northwest makes now will impact
Chinese energy habits for the next half-century; the lower coal prices afforded by
Northwest coal exports encourage burning coal and discourage the investments in
energy efficiency that China has already undertaken.
We acknowledge that others take different views of the impacts of exporting coal, and
NEPA does not require agencies to foresee the unforeseeable. It does, however, require the
agencies to take a “hard look” at these questions. While forecasting price and specific
consumption rates with any precision can be challenging, it is relatively easy to calculate the
GHG emissions associated with any given volume of coal—and the companies have already
estimated the amounts of coal they wish to ship. The public, and NEPA’s policies, are well
9
served by providing a forum to disclose and consider the competing views as the impacts of
opening up large volumes of low-cost PRB coal to the Asian market.
To summarize, the law is quite clear that agencies must consider all effects that are
proximately caused by the action under review, regardless of their location and without regard to
the extent of the agency’s ability to regulate those effects. An effect is proximately caused if it is
reasonably foreseeable. Increased train and vessel traffic, additional surface mining of coal, and
increased coal combustion in Asia are all reasonably foreseeable effects of the Corps’ decision to
authorize terminals capable of exporting 100 million tons of coal, and should be included within
the scope of the EIS.
G. The Corps Has Misapplied Its NEPA Regulations Governing Scope.
The Corps has its own set of regulations governing implementation of NEPA for projects
within its jurisdiction. 33 C.F.R. Pt. 325, App. B. These regulations direct the district engineer
to determine the “scope” of the NEPA analysis with reference to the extent of the Corps’
“control and responsibility” over components of a project that are outside the Corps’ jurisdiction.
Id. ¶ 7(b). In these regulations, Corps addresses a concern that frequently arises where a major
private project (for example, a 1,000 acre subdivision development) needs a Corps permit for a
small or even tiny component of that project (say, 2 acres of wetlands fill as part of that
development for one of the holes on the golf course). Where the Corps does not have “control
and responsibility” of the project as a whole, its regulations direct it to look just at the effects of
its permit—i.e., the two acres of wetlands fill—and not the project as a whole. Id.
The Ninth Circuit has developed a test to determine when the Corps can properly limit
the scope of its review to just the area effected by its permit or must look more broadly at the
entire project facilitated by its permit. See White Tanks Concerned Citizens v. Strock, 563 F.3d
1033 (9th Cir. 2009). On one end of the spectrum, where jurisdictional waters are concentrated
in a way that would be easy to avoid—meaning the project could proceed without needing a
Corps permit without significant change—the NEPA analysis can be limited to just the effect of
the permit (e.g., the 2 acre wetland) rather than the project as a whole (the 1,000 acre
development). See, e.g., Wetlands Action Network v. U.S. Army Corps of Eng’rs, 222 F.3d 1105
(9th Cir. 2000) (upholding decision not to complete EIS for wetland fill associated with
development project). On the other end of the spectrum, where jurisdictional waters are
disbursed throughout the site such that the project would effectively be impossible without Corps
permits, issuance of the permit is essentially the “cause” of all of the project’s environmental
effects, and the environmental review must include them. See, e.g., Save Our Sonoran v.
Flowers, 408 F.3d 1113 (9th Cir. 2005). It is not the percentage of the project that are “waters of
the U.S.” subject to Corps’ jurisdiction that matters, but “whether the waters must be affected to
10
fulfill the project’s goals.” White Tanks, 563 F.3d at 1041 (noting that full review was warranted
in case where 5% of project was subject to federal jurisdiction).10
The Corps’ July 3, 2013 scoping memorandum for the GPT facility focused on the
“control and responsibility” regulation, applying the various factors to find that it actually has
“control and responsibility” over all of the GPT project. The memo noted that 50% of the upland
facilities occur in regulatory wetlands subject to Corps jurisdiction and, of course, the project
requires a dock subject to Corps permitting. In other words, applying the Ninth Circuit’s White
Tanks test results in a clear answer—the entire project must be included in the Corps’
environmental analysis, because without the Corps’ permit, the project could not go forward.
Accordingly, under governing precedent, the entire GPT project is subject to Corps’ control and
responsibility, and all direct, indirect, and cumulative effects should be included within the scope
of the EIS.
However, having concluded that the entire GPT project is under the Corps’ control and
responsibility, the memo next asserts that “many of the activities of concern to the public, such
as rail traffic, coal mining, shipping coal outside U.S. waters and burning of coal overseas, are
outside the Corps’ control and responsibility.” Memo at 6. The Corps claims that these
activities are “too attenuated and distant from the proposed activities being evaluated by the
Corps to be considered effects of the Corps’ permit actions.” Id.
This analysis has confused the action that is subject to NEPA in the first place with the
effects that must be considered in the EIS. Rail and ship traffic, mining, and coal combustion are
not components of the GPT, in the same sense that filling of the wetlands or construction of the
dock are components of the project. Rather, they are effects of the action: as a result of the
Corps’ authorization to build the GPT, it is reasonably foreseeable that there will be an increase
in rail and vessel traffic, additional mining, and additional coal consumption. Under controlling
Ninth Circuit law, those indirect effects must be included in the EIS and the amount of “control
and responsibility” the Corps has over them simply has nothing to do with it.
In Save Our Sonoran, the Ninth Circuit found that the Corps had incorrectly conflated the
extent of its jurisdiction with the extent of the effects it must consider:
Although the Corps’ permitting authority is limited to those aspects of a
development that directly affect jurisdictional waters, it has responsibility under
NEPA to analyze all of the environmental consequences of a project. Put another
way, while it is the development’s impact on jurisdictional waters that determines
the scope of the Corps’ permitting authority, it is the impact of the permit on the
environment at large that determines the Corps’ NEPA responsibility. The Corps’
10
The Ninth Circuit has also emphasized that the views of other agencies, especially the EPA,
are relevant in determining whether to uphold a Corps determination regarding scope. Id. at
1042. Where, as here, EPA and/or other agencies object on the record to the Corps’
jurisdictional decisions, it is more likely to be found arbitrary and capricious. Id. In its comment
letters on coal export terminals, EPA has asked for a far broader scope than the one the Corps
adopted for the GPT facility.
11
responsibility under NEPA to consider the environmental consequences of a
permit extends even to environmental effects with no impact on jurisdictional
waters at all.
Save Our Sonoran, 408 F.3d at 1122 (emphasis added); see also Border Plants Working Grp.,
260 F. Supp. 2d at 1014 (discussing difference between scope of “action” and scope of “review,”
which includes effects of the action); Sierra Club v. Mainella, 459 F. Supp. 2d 76 (D.D.C. 2006)
(invalidating environmental assessment for a permit to drill underneath a National Park unit
because agency did not inadequately consider the environmental impacts of the surface drilling
operations that were outside the Park, even though agency could not directly regulate them). As
one recent scholarly paper correctly noted, “If all effects of upstream or downstream activities
were excluded from NEPA analysis because the relevant agency did not have direct control over
those actions, then the specific inclusion of ‘indirect’ effects in the CEQ regulations would be
largely meaningless.” NEPA & Downstream Greenhouse Gas Emissions of U.S. Coal Exports
(Columbia Law School, 2013), at 12. In almost every case discussed above, the indirect impacts
that a court directed the agency to include in its environmental review was not within the
“control and responsibility” of the agency making the decision—that is indeed a hallmark of
indirect effects in most cases.
The reasoning in these cases is equally applicable here: the scope of the EIS should be
determined by the environmental effects that are proximately caused by the Corps’ decision, not
the extent to which such effects are under the Corps’ “control.” The Corps’ misapplication of its
regulations is leading not just to a violation of governing law, but it undermines public
confidence in the process that is crucial to informed decisionmaking. Most importantly, an
inadequately scoped EIS will leave the Corps unable to fulfill its statutorily mandated
responsibility to consider the public interest, the environment, and other factors when deciding
whether or not to grant a permit for any of these three coal export terminals.