NORTH WEST PROVINCE DEPARTMENT OF DEVELOPMENTAL LOCAL GOVERNMENT AND HOUSING NCOP SELECT COMMITTEE ON FINANCE 13 February 2008 HOUSING PERFORMANCE REPORT 07/08 (3 rd Quarter). PRESENTATION INDEX HOUSING DELIVERY PERFORMANCE REPORT Introduction 07/08 Housing Delivery overview - PowerPoint PPT Presentation
Citation preview
NORTH WEST PROVINCEDEPARTMENT OF DEVELOPMENTAL LOCAL
GOVERNMENT AND HOUSING
NCOP SELECT COMMITTEE ON FINANCE13 February 2008
HOUSING PERFORMANCE REPORT 07/08 (3rd Quarter)
1
PRESENTATION INDEX
HOUSING DELIVERY PERFORMANCE REPORT
• Introduction
• 07/08 Housing Delivery overview
• 07/08 conditional Grant Allocation
• Conditional Grant Expenditure
• Summary of Blocked Projects
• Challenges • 08/09 Plans • Khutsong Re-settlement Plan (KRP)
2
Introduction 07/08-08/09 allocation of 39 000
Focus on: Project Linked Rural Housing Informal Settlement Upgrading. Social Housing FLISP
3
Introduction. cont Municipal accreditation(Municipal Capacity
Assessments) Blocked projects Closing off old business New implementation approach Khutsong Re-settlement Plan
4
07/08 Budget AllocationDescription
Financial Interventions (Ind. Subs, Relocation, DDIS, extended benefit scheme, social amenities)
223 912 001
Incremental Housing programmes
(Project Linked subsidies, consolidation subsidies, PHP)
Rural Housing 17 253 850
Social and Rental Housing 40 361 593
Additional funding ( Khutsong Development project)
105 000 000
766 800 644
+105 000 000
= 871 800 644
485 273 200
TOTAL BUDGET
5
2007 / 2008 Financial Year
3rd Quarter – Oct 2007 to Dec 2007
REGIONS BOJANALA BOPHIRIMA CENTRAL SOUTHERN TSHWANEGRAND TOTAL
MONTH SITES SERVICED
Oct 2007 0 0 0 0 0 0
Nov 2007 0 0 0 0 0 0
Dec 2007 0 0 0 0 0 0
TOTAL 0 0 0 0 0 0
Beneficiaries Approved for Financial Year
MONTH TOTAL
Oct 2007 1743
Nov 2007 377
Dec 2007
GRAND TOTAL 2120
REGIONS BOJANALA BOPHIRIMA CENTRAL SOUTHERN TSHWANEGRAND TOTAL
MONTH HOUSES BUILT
Oct 2007 1080 329 222 34 21 1686
Nov 2007 582 60 323 34 0 999
Dec 2007 1126 1 700
226 1423
TOTAL 2788 390 615 68 247 4108
TOTALS UP TO END OF 3RD QUARTER
TOTAL BENEFICIARIES APPROVED = 6 331
TOTAL SITES SERVICED =3 119
TOTAL HOUSES BUILT =12 913
6
2007 / 2008 Financial Year
Financial information
Expenditure for 2007 / 2008 Financial Year
Month HSS Expenditure
April 2007 R49,032,920.05
May 2007 R32,701,866.52
June 2007 R94,033,023.16
July 2007 R73,298,845.29
August 2007 R72,608,073.78
September 2007 R14,668,644.64
October 2007 R115,238,490.89
November 2007 R30,286,280.22
December 2007
January 2008
February 2008
March 2008
•TOTAL R 481,868,144.54
Month Walker Expenditure
Apr-07 R 49,032,920.00
May-07 R 31,950,212.00
Jun-07 R 94,033,024.00
Jul-07 R 74,018,570.77
Aug-07 R 72,640,002.79
Sep-07 R 14,668,644.33
Oct-07 R 115,733,194.26
Nov-07 R 57,289,096.39
Dec-07 R 38,591,924.41
Jan-08 R -
Feb-08 R -
Mar-08 R -
GRAND TOTAL R 547,957,588.95
7
Comparative Exp AnalysisMonth 2007/08 2006/07 2005/06
April R 49,032,920 R 53,877,445 R 46,001,040
May R 32,701,867 R 58,979,075 R 48,502,921
J une R 94,031,024 R 51,361,153 R 43,284,647
J uly R 74,018,570.77 R 51,206,590.00 R 36,162,220.00
AugustR 72,640,002.79 R 67,173,879.00 R 65,517,255.00
September R 14,668,644.33 R 28,387,061.00 R 5,857,311.00
October R 115,733,194.26 R 77,254,636.00 R 80,459,892.00
November R 57,289,096.39 R 64,127,722.00 R 48,212,075.00
December R 38,591,924.41 R 44,275,492.00 R 125,391,459.008
Blocked projects Number of projects 24 Total Number of planned units 28625 Number of completed housing units 16953 Units still to be built 11672 Budget amount of projects R 580,974,852.00 Total amount paid R 319,711,366.38 Balance amount available R 261,263,485.62 Additional funding needed R 223,319,348.00
9
Challenges Matlosana Pilot Project NHBRC Enrollments Funding for Internal Services
10
Challenges: Matlosana Pilot Project Project stalled since November ’06 Pending Litigation processes between
Municipality and appointed contractor and project manager.
Various intervention strategies at varying levels already applied yielding little/no success
Cancellation of development agreement with Municipality
11
Challenges, NHBRC Enrollments Major delays in registration of projects for
enrollment Bureaucratic enrollment processes.
12
Housing Delivery Plans 08/09 Implementation of 07/08-08/09 allocation Integrated Housing Pilot Project-Mafikeng Municipal Accreditation-Shishaka Municipal
Capacity Assessment ISUP-CSIR Survey Unblocking of Blocked Projects Rectification Programme (post-1994)
13
Khutsong Resettlement Plan(KRP) WHAT IS THE KRP?
The relocation of approximately 21 485 families residing in geologically unsuitable informal areas , 3 600 formal houses,public and private infrastructure in Khutsong to geologically suitable land needs to be undertaken as a matter of urgency.
14
15
16
Khutsong Resettlement Plan…… A project of 4 700 units was initially approved with the intention to
increase it to 18 000 units by Gauteng Department of Housing during 2004
Land identification,EIA’s and geotech investigations were undertaken during 2004/5 – only 14 852 stands were found to be suitable for township establishment in the identified area
Discussions with ABSA North West Province allocated a project of 5 500 subsidies on the
R38,984 for the 2007/2008 and 2008/2009 financial years as the first two phases of the original 18 000 project.
The project is at tender phase for the installation of services.
17
Khutsong Resettlement Plan……(LAND FOR DEVELOPMENT)
18
Khutsong Resettlement Plan……The following issues need to be address:
Land Housing Internal Services Bulk and Connector Services Rehabilitation of Khutsong after resettlement Security
19
Khutsong Resettlement Plan…..
SUMMARY-FINANCIAL IMPLICATIONS Secured R319m Unsecured R2,7 b
20
NORTH WEST PROVINCEDEPARTMENT OF DEVELOPMENTAL LOCAL
GOVERNMENT AND HOUSING
THANK YOU????????