Page 2: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

The RTD FasTracks Plan• 122 miles of new light rail and

commuter rail

• 18 miles of Bus Rapid Transit (BRT) service

• 31 new Park-n-Rides; more than 21,000 new parking spaces

• Enhanced Bus Network & Transit Hubs (FastConnects)

• Redevelopment of Denver Union Station

• 57 new rail and/or BRT stations

• Opportunities for Transit Oriented Communities

2

Page 3: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

FasTracks Status• West Line first FasTracks line to open

– April 26, 2013

• Denver Union Station – 89% complete

• East Line/Gold Line/NW Rail Segment One – 50% complete

• US 36 BRT – under construction, bus service begins 2016

• I-225 Line – under construction, opens 2016

• Free MetroRide (formerly the Circulator) to open this summer

Page 4: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

FasTracks Snapshot• One line opened, construction underway on four rail lines, BRT,

Union Station

• Continue to implement $5 billion across the region

• Economic driver for the region

– $2.6 billion spent and injected into the local economy since 2005

– 600 construction jobs during West Rail Line construction

– 2,500 direct and indirect jobs during Eagle P3 construction

• Pursue any possible funding alternatives to complete FasTracks sooner rather than later

• RTD is committed to completing the whole FasTracks program

Page 5: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

North Metro Rail Line

18.5 Miles

Electrified Commuter Rail

8 Stations

Parking spaces4,020 – opening year8,500 – 2035

Single track with multiple passing tracks

Serves Denver, Commerce City, Thornton, Northglenn, Adams County

Page 6: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

• Complete all work in a safe manner to protect the construction workers and the public.

• Complete all or a portion of North Metro Rail Line beyond the previously announced terminus at 72nd Ave.

• Integrate within the Commuter Rail Network currently underway on Eagle Project.

• Comply fully with the Record of Decision.

Goals for North Metro

Page 7: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

• Meet  Disadvantaged Business Enterprise (DBE) goals established by the RTD Civil Rights Dept. and demonstrate commitment to utilize Small Business Enterprises and WIN Program

• Offer added-value solutions to deliver the FasTracks program.

Goals for North Metro

Page 8: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

• Design/build with three phases:– Union Station to 72nd Ave– 72nd Ave to End of Line (Hwy 7)– SE, SW & Central Extensions

• Willing to include related stakeholder projects (non-federal) to lock in price. Stakeholders to pay for these projects

• Award based on best value with emphasis on creativity and innovation within financial capacity

RFP Scope

Page 9: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

• Civil Works (grading, drainage, utilities, roadway, traffic)

• Bridges and Structures

• Stations

• Right-of-way– RTD Responsibility from DUS

to 72nd Avenue– Contractor assistance on

72nd to SH7 (End of line)

Civil Elements

Page 10: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

• Train Control System

• Communications and Control System

• Traction Electrification System

• System-wide Electrical

• Systems Integration

Systems Elements

Page 11: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

Civil RightsDBE Goal

• 23% Design

• 21% Construction

WIN Program Goals

• 4% Professional Services

• 8% Skilled Craft

SBE Utilization

• Contractor to prepare plan to maximize

Page 12: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

RFP Schedule • Advertised RFP – June 28, 2013

• Pre-proposal briefing – July 8, 2013 – 250 attendees

• Proposers/Stakeholders Questions and Comments due – August 12

• Issue Final Addendum with Response to Questions and Comments – August 26

• Proposals Due – Sept 23

Page 13: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

RFP Schedule con’t• Evaluation Committee presents recommendation to GM –

late October, 2013

• GM/Staff recommendation to the FasTracks Monitoring Committee – November 5, 2013

• Board Approval/Notice of Award – November 26, 2013

• Financial Close – December 19, 2013

• Notice to Proceed Phase 1 – December 19, 2013

Page 14: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013

Stakeholder Participation

• Representatives from Denver, Adams County, Commerce City, Thornton, Northglenn, CDOT and NATA will serve on evaluation committee.

• Confidentiality is required. Authorized Stakeholders cannot share information with anyone outside of the Stakeholders Group until after November 5

Page 15: North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013