1 | Page FINANCIAL SUMMARY AS OF March 20th, 2020 1. Oregon School Capitol Improvement Matching (OSCIM) Grant. The district qualified to receive a matching grant through the state program. These funds are restricted to the High School Project. 2. State Grants: Seismic Rehabilitation grants. These funds are restricted to specific projects. BUDGET SUMMARY AS OF March 20th, 2020 Paid to Date $27,949,008 Remaining Committed to Date $23,717,676 Projected Cost to complete $3,640,469 TOTAL PROJECT COST $55,307,154 Reserve Funds $697,328 TOTAL REQUIREMENTS $56,004,482 NORTH MARION SD #15 BOND PROGRAM UPDATE March 20, 2020

NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

1 | P a g e

FINANCIAL SUMMARY AS OF March 20th, 2020

1. Oregon School Capitol Improvement Matching (OSCIM) Grant. The district qualified to receive a matching grant through the state program. These funds are restricted to the High School Project.

2. State Grants: Seismic Rehabilitation grants. These funds are restricted to specific projects.

BUDGET SUMMARY AS OF March 20th, 2020

Paid to Date $27,949,008

Remaining Committed to Date $23,717,676

Projected Cost to complete $3,640,469

TOTAL PROJECT COST $55,307,154

Reserve Funds $697,328

TOTAL REQUIREMENTS $56,004,482

NORTH MARION SD #15

BOND PROGRAM UPDATE

March 20, 2020

Page 2: NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

2 | P a g e

NORTH MARION HIGH SCHOOL Project Manager: Wenaha Group

MAJOR ADDITION AND REMODEL Architect: DLR Group

Contractor: Todd Construction

PROJECT DESCRIPTION: Project consists on complete new construction of a two story educational wing connecting the existing commons, CTE and music wings to make an enclosed campus. Once completed the existing educational and administration wings will be demolished and a new single story Administration wing built with additional student parking lot. Project also included the complete remodel of the Vocational building for CTE programs and Music wing providing a new SPED suite. School will be a complete closed campus when complete with a secure vestibule at entrance and additional security throughout.

SCHEDULE

Key Milestones Start Completion % Complete

Comments

Pre-Design Feb 2018 100%

Design & Permitting Spring 2019 100%

Construction May 2019 Dec 2020 55%

CURRENT ACTIVITIES

• Completing the roofing at Solar Panel connections

• Working the Mechanical and electrical finish

• Working on all flooring and ceiling components

• Working on metal panel and fiber cement exterior panel installation.

• Casework and finish carpentry installation

• Greenhouse nearly complete

ACTIVITIES SCHEDULED FOR NEXT MONTH: • Continuing flooring installation

• Continuing ceiling grid and tile installation.

• Complete metal panel and fiber cement exterior panels.

• Continue with Electrical and Mechanical systems.

• Installation of all TV’s/ Marker boards and Tack surfaces.

NORTH MARION SD #15

BOND PROGRAM UPDATE

March 20, 2020

Page 3: NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

3 | P a g e

HIGHLIGHTS

• Music wing and CTE building have been able to function as a school environment since the

first day of school.

CHALLENGES AND SOLUTIONS • Working to eliminate water intrusion through concrete wall of Gym #1. – Proposal Request

out being priced.

• Continue presence of manpower / materials due to current Global Pandemic.

• Schedule: Challenges with unknown regarding Pandemic – Construction complete on time / Teachers able to pack up old classroom for move / School Closure

PROJECT PHOTO GALLERY:

Greenhouse

Exterior Pictures

Page 4: NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

4 | P a g e

1st floor Science Rooms

Classrooms

2nd Floor Corridor

Page 5: NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

5 | P a g e

Elevator

Single Classroom Wing Restroom

1st Floor Main Restrooms

Media Center

Page 6: NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

6 | P a g e

NORTH MARION SEISMIC PROJECTS Project Manager: Wenaha Group

MAJOR ADDITION AND REMODEL Architect: ZCS Architecture

Contractor: DSL Construction

PROJECT DESCRIPTION Project consisted of the following scope: High School: Complete demolition of the basement; seismic work including 18 steel columns around perimeter of structure and new structural diaphragm at gym floor level and roof, hazardous material abatement, new locker rooms, new weight room, new storage areas. Structure received new mechanical and electrical systems, new fire sprinkler system installed in both gym and basement, new LED lighting and a complete new roof. Middle School: Seismic work including concrete separation wall between multipurpose and gym to support roof structure and new structural diaphragm at roof elevation. Received new boilers for school heating system, new ductwork within gym space and new LED lighting.

SCHEDULE

Key Milestones Start Completion % Complete

Comments

Pre-Design 100%

Design & Permitting 100%

Construction 99%

CURRENT ACTIVITIES

• Closing project out

• Working on repairing gym floor that slight warped due to a leaking pipe to the mechanical unit

in attic. Working on ways to eliminate this risk in the future.

ACTIVITIES SCHEDULED FOR NEXT QUARTER N/A

HIGHLIGHTS

• Acoustical issues solved within Gym.

• The new flexible locker rooms.

• Reduction of maze feel in the basement.

• Fresh new look of the gym and gym markings.

CHALLENGES AND SOLUTIONS

PROJECT PHOTO GALLERY: N/A

NORTH MARION SD #15

BOND PROGRAM UPDATE

March 20, 2020

Page 7: NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

7 | P a g e

NORTH MARION PARKING LOTS Project Manager: Wenaha Group

MAJOR ADDITION AND REMODEL Architect: DLR Group

Contractor: All-Ways Excavating

PROJECT DESCRIPTION Project consisted of a parking lot remodel at the Primary School and a new parking lot at the Middle School. Primary School: Project added an additional 28 parking stalls and a second entrance. Also included updated lighting. Middle School: Project consisted of a new parking lot extending over the Johnson property to include 86 parking stalls, a bus drop off and loading zone as well as a parent drop off and loading zone. Includes new lighting, drainage swales and concrete seat walls. Provides designated crossing zones for student safety and a large concrete plaza adjacent the front door.

SCHEDULE

Key Milestones Start Completion % Complete

Comments

Pre-Design 100%

Design & Permitting 100%

Construction 100%

CURRENT ACTIVITIES: N/A

ACTIVITIES SCHEDULED FOR NEXT QUARTER: N/A

HIGHLIGHTS:

• Additional parking stalls to reduce the number of cars on Grim Road.

• PS: Second entrance has reduced the amount of vehicles that sit on Grim Road at drop off and

pick up times.

CHALLENGES AND SOLUTIONS: • Slopes on drainage swales are too steep for maintenance to maintain the grass. Working with

design team to lessen the steepest, so maintenance can cut the grass for efficiently.

PROJECT PHOTO GALLERY: N/A

NORTH MARION SD #15

BOND PROGRAM UPDATE

March 20, 2020

Page 8: NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

8 | P a g e

NORTH MARION PRIMARY SCHOOL Project Manager: Wenaha Group

MAJOR REMODEL Architect: DLR Group

Contractor: Par-Tech Construction

PROJECT DESCRIPTION Add secure vestibule with additional security, provide access control at specified locations, small administration remodel to accommodate secure vestibule, additional staff restroom, paint exterior of building and remodel exterior play area including new covered play structure.

SCHEDULE

Key Milestones Start Completion % Complete

Comments

Pre-Design 100%

Design & Permitting 100%

Construction 0%

CURRENT ACTIVITIES

• Project Bid Late February / Contractor approved by Board March XXX, 2020.

• Contract Executed with Par-Tech Construction, Inc for $9,463,000.00 on March 16th, 2020 for

Combined Package of Middle, Intermediate and Primary School Projects.

• Working on Logistics, submittals and material procurement.

ACTIVITIES SCHEDULED FOR NEXT MONTH

• Onsite work to commence as soon as School is released for the summer.

• Working on Logistics, submittals and material procurement.

HIGHLIGHTS

• N/A

CHALLENGES AND SOLUTIONS

• School Logistics – Due to Pandemic – multiples issues have risen: Summer Classes conflicting with Construction? Logistics of moving out of Administration space for construction

PROJECT PHOTO GALLERY: N/A

NORTH MARION SD #15

BOND PROGRAM UPDATE

March 20, 2020

Page 9: NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

9 | P a g e

NORTH MARION INTERMEDIATE SCHOOL Project Manager: Wenaha Group

MAJOR REMODEL Architect: DLR Group

Contractor: Par-Tech Construction

PROJECT DESCRIPTION Add secure vestibule with additional security, provide access control at specified locations, small administration remodel to accommodate secure vestibule, additional staff & SPED restrooms, Mechanical system replacement in Library, Multipurpose area and administration, complete re-roof of the building, exterior door placement and remodel exterior play area including new covered play structure.

SCHEDULE

Key Milestones Start Completion % Complete

Comments

Pre-Design 100%

Design & Permitting 100%

Construction 0%

CURRENT ACTIVITIES

• Project Bid Late February / Contractor approved by Board March XXX, 2020.

• Contract Executed with Par-Tech Construction, Inc for $9,463,000.00 on March 16th, 2020 for

Combined Package of Middle, Intermediate and Primary School Projects.

• Working on Logistics, submittals and material procurement.

ACTIVITIES SCHEDULED FOR NEXT MONTH

• Onsite work to commence as soon as School is released for the summer.

• Working on Logistics, submittals and material procurement.

HIGHLIGHTS

• N/A

CHALLENGES AND SOLUTIONS • School Logistics – Due to Pandemic – multiples issues have risen:

Summer Classes conflicting with Construction? Logistics of moving out of Administration space for construction

PROJECT PHOTO GALLERY: N/A

NORTH MARION SD #15

BOND PROGRAM UPDATE

March 20, 2020

Page 10: NORTH MARION SD #15 BOND PROGRAM UPDATE March 20 , 2020 · • Working on metal panel and fiber cement exterior panel installation. • Casework and finish carpentry installation

10 | P a g e

NORTH MARION MIDDLE SCHOOL Project Manager: Wenaha Group

MAJOR REMODEL Architect: DLR Group

Contractor: Par-Tech Construction

PROJECT DESCRIPTION Add secure vestibule with additional security, provide access control at specified locations, extensive administration remodel with infill of exterior area adjacent present staff room, additional restrooms, remodel existing student restrooms, locker room remodel, complete roof replacement and mechanical system replacement.

SCHEDULE

Key Milestones Start Completion % Complete

Comments

Pre-Design 100%

Design & Permitting 95 %

Construction 0%

CURRENT ACTIVITIES

• Project Bid Late February / Contractor approved by Board March XXX, 2020.

• Contract Executed with Par-Tech Construction, Inc for $9,463,000.00 on March 16th, 2020 for

Combined Package of Middle, Intermediate and Primary School Projects.

• Working on Logistics, submittals and material procurement.

ACTIVITIES SCHEDULED FOR NEXT MONTH

• Onsite work to commence as soon as School is released for the summer.

• Working on Logistics, submittals and material procurement.

HIGHLIGHTS

• N/A

CHALLENGES AND SOLUTIONS • School Logistics – Due to Pandemic – multiples issues have risen:

Summer Classes conflicting with Construction? Logistics of moving out of Administration space for construction

PROJECT PHOTO GALLERY: N/A

NORTH MARION SD #15

BOND PROGRAM UPDATE

March 20, 2020