Non-Title V Permit Elements for Enforceable Permits. Dan Blair, Willard Antone III Gila River Indian Community (GRIC) Department of Environmental Quality. Permits. Permits are your main enforcement tool Permits are stand alone documents supported by Tribal or Federal regulations - PowerPoint PPT Presentation

Citation preview

Page 1: Non-Title V  Permit Elements for Enforceable Permits

Non-Title V Non-Title V Permit Elements for Permit Elements for Enforceable Permits Enforceable Permits

Dan Blair,

Willard Antone III

Gila River Indian Community (GRIC)

Department of Environmental Quality

Page 2: Non-Title V  Permit Elements for Enforceable Permits

Permits

• Permits are your main enforcement tool

• Permits are stand alone documents supported by Tribal or Federal regulations

• Permits should be clear, concise and all inclusive

Page 3: Non-Title V  Permit Elements for Enforceable Permits

Types of Permits

• Title V Permits– Pre-Construction Permits (NSR, PSD)– Operating Permits

• Non-Title V Permits– Individual Operating Permits– Synthetic Minor Permits

• General permits

Page 4: Non-Title V  Permit Elements for Enforceable Permits

WHO Needs a permit???

• Emission Inventory

• Permit Thresholds – 1 ton of Criteria Pollutant– 1000#s of Hazardous Pollutant– 300#s Ultra-hazardous Pollutant– Aggregate of all uncontrolled sources with >

3# VOC or PM-10 in any day– Aggregate of all sources with > 5.5# of any

other regulated pollutant in any day

Page 5: Non-Title V  Permit Elements for Enforceable Permits

GRIC Permit Process

• Send out cover letter and permit application forms (certified mail) to facilities

• Require completed permit application within 120 days of receipt of App.

• Provide assistance with completion of App. (pre submittal meetings)

• Extensions

Page 6: Non-Title V  Permit Elements for Enforceable Permits

GRIC Permit Process

• Department review of App for completeness (60 days)

• Request supplemental information

• Draft Permit, TSD’s, Calculations, BRDT

• Facility review of permit

• 30 day Public Comment Period

• Permit decision by Director within 12 months of complete App.

Page 7: Non-Title V  Permit Elements for Enforceable Permits

Permit Application Content

• Facility information• Hours of operation• Signature of

responsible party• Emissions

calculations• Process description &

flow chart• Certification of Truth

and Accuracy

• Certification of Compliance and/or Compliance Plan

• Equipment List• Voc content• Throughput• Control Equipment

Page 8: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

• Technical Support Document– Description of Source– Allowable Emissions– Applicable Regulations (Tribal, Federal)– Emissions Calculations

Page 9: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

• General Permit Conditions– Affirmative Defense– Certification of Truth and Accuracy– Confidentiality– Controls – Duty to Comply– Duty to Provide information– Fees

Page 10: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

• General Permit Conditions– Maintenance (O&M Plan)– Nuisance Provisions– Performance Testing– Permit Term– Permit Revisions– Permit Re-openings (Revocation,

Termination)

Page 11: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

General Permit Conditions (cont.)

– Permit Transfers– Record Keeping/Reporting– Right of Entry– Severability

Page 12: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

• Specific Conditions:

– Allowable Production Rate– Emission Limits (Daily, Annual)

• Through put limits• Hours of operation• Equipment capacities• Material content (e.g., VOC Content etc.)

Page 13: Non-Title V  Permit Elements for Enforceable Permits

Jawcrusher

Page 14: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

• Specific Conditions (cont)

– Process Emission Limitations• Transfer points 7% opacity• Baghouse stack 20%• Grain loading limit from baghouse stack 0.02

gr/dscf

Page 15: Non-Title V  Permit Elements for Enforceable Permits

Transfer Points

Page 16: Non-Title V  Permit Elements for Enforceable Permits

Baghouse

Page 17: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

• Specific Conditions (cont)– Controls

• Baghouse (magnehelic gauge/pressure drop)• Cement silo overflow warning/shutoff system• Scrubbers (flow rate/nozzle inspection)• Electro Static Precipitators (ESPs)• Spray Bars• Etc.

Page 18: Non-Title V  Permit Elements for Enforceable Permits

Cement Silo Overflow

Page 19: Non-Title V  Permit Elements for Enforceable Permits

Magnehelic Gauge

Page 20: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

• Specific Conditions (cont)– Recordkeeping and Reporting Requirements

• Hours of operation• Through puts• Fuel usage • Control device records (flows, pressure drop etc)

– Operational Restrictions• Fuel restriction (no off spec used oil, solvent)• Clean Aggregate only (no petroleum/solvents)

Page 21: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

• Specific Conditions (cont)– Performance testing (test protocol)

• Grain Loading• Percent reduction• Concentrations• EPA Method 9 opacity readings• Appendix A test methods• Retest every 5 years

Page 22: Non-Title V  Permit Elements for Enforceable Permits
Page 23: Non-Title V  Permit Elements for Enforceable Permits
Page 24: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

• Specific Conditions (cont)– Operation and Maintenance Plan

• Describes control unit monitoring devices, temps, flow rates and other parameters to ensure proper operation

• List maintenance frequencies, calibrations and log sheets

• List corrective actions and shutdown procedures• Upset log and corrective actions

Page 25: Non-Title V  Permit Elements for Enforceable Permits

Elements of an Enforceable Permit

• Specific Conditions (cont)– Open Burning– Solvent Cleaning– Fugitive Dust– Etc.