Upload
judicial-watch-inc
View
221
Download
0
Embed Size (px)
Citation preview
7/30/2019 NLRB Production 9 Affidavits
1/484
PRIVACY ACT STATEMENT
Solicitation of the information on this form is authorized by the National Labor Relations Act (NLRA), 29 U.S.C. 151 et seq.
The principal use of the information is to assist the National Labor Relations Board (NLRB) in processing representationand/or unfair labor practice proceedings and related proceedings or litigation. The routine uses for the information are fullyset forth in the Federal Register, 71 Fed. Reg. 74942-43 (Dec. 13, 2006). The NLRB will further explain these uses uponrequest. Disclosure of this information to the NLRB is voluntary. However, failure to supply the information may cause theNLRB to refuse to process any further representation or unfair labor practice case, or may cause the NLRB to issue you asubpoena and seek enforcement of the subpoena in federal court.
Page 1 of 28
) Case 19-CA-32431) SS)
CONFIDENTIAL WITNESS AFFIDAVIT
I hereby state as follows:
I have been given assurances by an agent of the National Labor Relations Board that thisConfidential Witness Affidavit will be considered a confidential law enforcement record by theBoard and will not be disclosed unless it becomes necessary to produce the Confidential WitnessAffidavit in connection with a formal proceeding.
I reside at Home: Work:
My telephone number (including Area Code) is Cell:
I am employed by
1.1
2
3
4
5
6
7
2.8
9
10
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
2/484
Page 2 of 28
1
2
3
3.4
The Dreamliner5
787 was already in the developmental stage for our bargaining unit. I think at the time,6
Boeing was already assembling the prototypes. (At that point in time, the Dreamliner7
project was behind schedule due to supplier issues. has much more8
information regarding the details of the early stages of the Dreamliner.) There were9
10
11
12
13
14
15
16
17
18
4. I became involved in the negotiations for the placement of the second line of the19
Dreamliner in For purposes of providing some background regarding20
what the circumstances were like at the time I became involved in the negotiations in21
I am providing the following information22
After the 200823
strike mediations, there were a lot of stories in the press about different states that24
Boeing was considering placing the second Dreamliner line, including South Carolina.25
A few years ago, Boeing had outsourced the making of some parts of the Dreamliner to26
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
3/484
Page 3 of 28
a producer in South Carolina - Vought. (Boeing currently focuses on design, marketing1
and final assembly. They have sold off lots of its factories that made parts for2
airplanes. This outsourcing has been part of the ongoing dialogue with Boeing for3
many years4
Vought also created a joint venture with5
another manufacturer, Alenia. The joint venture was called Global Aeronautica. My6
understanding was that they were having a lot of trouble with fabrication of the7
Dreamliner parts which was putting Boeing far behind schedule. Then Vought at some8
point, entered into discussions with Boeing and at some point in 2008, Boeing bought9
Vought. The same day that this occurred, the bargaining unit in at the Vought plant10
filed a decertification petition. All of the stories in the news media stated that if IAM was11
decertified at the South Carolina plant, that Boeing would place the second Dreamliner12
line in that plant. The union was then decertified.13
5. The media reports since the 2008 strike said that Boeing didnt want to put the second14
line in the Puget Sound area because of labor strife. Then the media reports started15
saying that Boeing would put the second line in the Puget Sound area if the union16
agreed to a 20-year agreement. At some point, there was a quote in the paper or a17
press release from our union18
that if Boeing wanted to do that, it should come talk to us. I do not have those articles19
currently, but I will provide copies to the Board Agent.20
6. said wanted me to join21
in Chicago to talk to Boeing about a long-term agreement. The agreement would22
be between Boeing and the Union and entered into in order to eliminate the possibility23
of strike activity for a long period of time at Boeings airplane factories represented by24
IAM. the negotiations with Boeing about keeping the25
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
4/484
Page 4 of 28
Dreamliner in the Puget Sound area and about coming up with some sort of long-term1
agreement.2
7. not aware of any3
effort that Boeing officials made to talk directly to the Union about addressing the4
Companys concerns. My understanding from was that if Boeing wanted a long-5
term agreement, that it needed to be a long-term collective bargaining agreement that6
covered the entire multi-state bargaining unit. It was the Unions position that we didnt7
just want a strike agreement stating that if there was some sort of dispute, that we8
would just go to an arbitrator instead of striking; we wanted an overall contract9
protecting all of our unit members. (At this point in time, we were in the first year of a10
four year agreement; the current collective bargaining agreement expires in 2012).11
8. It was agreed that we would meet with Boeing in early October 2009. This was kept12
quiet - there were no press releases or anything else that I am aware of regarding our13
meetings. I was not aware that the Union had any meetings with Boeing prior to the14
15
16
9. Over the course of about three weeks in October 2009 I participated in17
meetings at which officials from the IAM and The Boeing Company met for purposes of18
negotiating Boeings request for a long-term collective bargaining agreement. I19
understood from that the purpose of these meetings was to discuss what Boeing20
wanted in order to build a second Dreamliner 787 line in Puget Sound rather than South21
Carolina.22
10. The first of these meetings took place on October 1, 2009, at a hotel in Chicago.23
Boeing headquarters is in Chicago and we also felt that having the meetings there was24
a way to keep the meetings out of the media.25
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
5/484
Page 5 of 28
11. Vice President of Human Resources for Boeing Commercial Airplanes Doug Kight, Vice1
President for Operations Ray Conner, Vice President of Labor Relations Gene2
Woloshyn, and General Counsel Joan Clarke attended on behalf of Boeing. For the3
Union,4
5
6
12. The first meeting on October 1, 2009, was very short and lasted only one or two hours.7
It was very informal. are attached as Exhibit A. Ray8
Conner was the lead spokesperson for Boeing9
although everyone spoke at some point during the meeting. We all10
introduced ourselves and then Ray said that getting the work for the Dreamliner second11
line in the Puget Sound depended on a long-term agreement so there wouldnt be any12
work stoppages. He said the customers were buying things well in advance and didnt13
want disruptions which could prevent Boeing from delivering the planes on schedule to14
the customers. He also said that historically they had15
16
That was the Rays main thrust. responded17
by saying that we were interested in exploring a long-term collective bargaining18
agreement but we had concerns about how to handle disputes under the agreement,19
that we needed to handle economic issues for the long term and we needed to create a20
new relationship with Boeing. said that we needed a process to reconfirm the21
contract every three years to deal with contract bar issues. My understanding was that22
we were both (Boeing and the Union) talking about a new collective bargaining23
agreement that would cover all employees (not just those working on the Dreamliner).24
25
26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
6/484
Page 6 of 28
bargaining unit.) Ray informed the Union that Boeing wanted to negotiate about the1
787 work, but was not open to discussing any of the 787 derivative work. (Derivative2
work is future plane models based on the Dreamliner technology and processes.) Ray3
expressed that he was concerned that we would have another strike when the contract4
expired in 2012. expressed the Unions concern that a long-term agreement5
would waive the members right to strike for many years, so we needed to have the6
contract terms clearly worked out; that we wouldnt just do a no-strike pledge with7
binding arbitration every three years. Ray also discussed other economic issues,8
specifically productivity (bonuses) and profit sharing (an incentive program). Boeing9
wanted productivity and profit sharing to get flexibility and have compensation tied to10
how the company was performing. I dont believe that the current agreement contains11
productivity and profit sharing. The primary reason to add this in to a new agreement12
was to give the company some flexibility as to what it labor costs would be. (As13
discussed in later meetings, the thought was that the company could, for example,14
lower yearly wage increases but at the same time allow employees to get bonuses15
based on production and profitability.) We didnt get into details about this, it was just a16
basic discussion about including such a program into a new agreement. Ray also17
raised the issue that if we were going to have a long-term economic package, Boeing18
would need a trigger that if something terrible happened to the economy (like 9/11),19
they could have an escape clause to get out of their economic commitment.20
21
22
Doug Kight (Doug was very involved in the 2008 strike negotiations; he was the main23
spokesperson for Boeing in the strike negotiations).24
13. The point of this whole meeting was just to figure out if we should even be talking to25
each other. The end result was yes - the Union and Boeing should talk more to see if26
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
7/484
Page 7 of 28
we could resolve the issue as to where to place the second line and at the same time1
negotiate ecomonic terms for our whole unit. Ray to make proposals that2
would result in a long-term collective bargaining agreement containing a no-strike3
clause. One of the Boeing representatives at the meeting stated that Boeing was4
seeking a minimum of an 8 to 10-year long contract tacked onto the end of our current5
agreement which didnt end until 2012 (so the new contract would end in 2020 or6
2022). I dont recall that we responded to this. I dont recall if we agreed to a new7
meeting date, but we did agree to meet again. This is all I currently recall from this8
October 1 meeting. I came out of the meeting with the thought that we would be able to9
reach an agreement.10
14. At some point after the meeting, that the next meeting would be on11
October 7.12
15.13
14
15
16
17
18
19
20
21
22
23
(Under the last contract, we were getting betwee general wage increases24
(GWI) plus COLA (usually about of inflation percentage),25
))26
Arguably E...
Arguabl... Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
8/484
Page 8 of 28
1
2
3
4
5
attached as Exhibit B.6
16. On October 7, 2009, we had our second session in Chicago,7
are attached as8
Exhibit C. We engaged in pleasantries, then Ray spoke. Again, although I dont recall9
the specific words, I recall Ray emphasizing the need for a long-term CBA to avoid10
strike activity. I also recall Gene Woloshyn describing what Boeing wanted in an11
economic package for the new, long-term agreement. I believe Gene, it may have12
been someone else, drew a figure on a flip chart (We will13
provide the Region with a copy of the actual flip chart used in the meeting.) At the14
bottom of the chart was COLA (we werent talking specific numbers at this time). Then15
on top of that was a general wage increase (GWI). Then on top of that was the16
incentive (bonuses) linked to the productivity plan; depending on how much you were17
above or below the target would determine the amount of the bonus. He showed this18
on the chart with a box for performance and one for over-target. The incentive would19
be based on some sort of matrix including productivity, quality, and cost. The plan20
would possibly be the same for management. Also the criteria might also include21
22
I dont recall if23
there was a response. Someone brought up24
Im not exactly sure what this means but it is something about efficiency. I think Boeing25
brought it up, but I dont recall exactly what this was but I guess it was tied to the26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
9/484
Page 9 of 28
productivity. In any event, I dont think the was ever brought up again. Someone1
from our side, I dont recall whom, didnt want included in the productivity issue2
because it might be an incentive for employees3
I dont recall Boeing responding to this comment. (But was4
never brought up again, so it seems Boeing understood our concerns on this issue.)5
There was some general discussion for the need to communicate the incentive6
programs clearly to employees. We also talked about man-hours per plane. The7
company uses something called notice of escape.8
but it deals with when a plane part has to be replaced -9
10
Then we discussed Portland which is a machine11
shop - the issue was how would their productivity be measured? Portland does12
machining work for parts put on planes in Puget Sound. The Boeing reps said they13
would have to think through on how they would have to deal with Portland on this issue.14
So the questions was what exactly was the productivity concept - do you have the15
same productivity measurement for different places that do different work, e.g. making16
machinery versus putting parts together. At some point, said that there needed to17
be a joint committee that would be reviewing all the different measurements and would18
oversee the productivity plan and the long-term agreement during the term of the19
contract. At some point, we also discussed triggers again (we also referred to it as a20
circuit breaker). Someone from the company said that some possible circuit breakers21
22
Using these types of criteria, we wold come up with a trigger resulting in the company23
having an out regarding specific economic terms such as GWI (when they could delay24
or cancel the GWI). We just talked about this in general terms; we did not determine25
what the exact numbers would be where the company could opt out. There was also26
Arguably...
Arguably E...
Arguably Ex. 4
Arguably Ex. 4 Arguably ...
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
10/484
Page 10 of 28
some discussion about how often the payouts would occur under the profit sharing1
plans. (These negotiations were not super-structured so we bounced around a lot2
regarding the different subjects.) talked about being able to reaffirm the3
CBA due to contract bar issues. Someone said whether we should write a letter to the4
Obama administration to get a longer contract bar time frame created specifically for5
Boeing talked about that there needed to be a process where the Union6
would have a trigger - that if the company broke all the agreements, that we could opt7
out too - that we wouldnt be tied into the contract under extreme circumstances. I think8
at this meeting we came up with the example that if we went to an arbitrator and the9
company did not comply with the arbitrators decision, that could possibly be a trigger to10
get out of the contract. mentioned job security and mentioned it in a way tha11
meant job security for all bargaining unit employees, not just those on the Dreamliner12
project. talked about that if we had this long-term agreement, we needed to13
have a better relationship with the company. We couldnt be holding hands in Puget14
Sound and then fighting about our unionizing drives elsewhere. There was some more15
discussion of a joint committee - who would be on it, how often they would meet, what16
type of information they would get, what information could be shared with the general17
membership, that it wouldnt be about solving grievances, and this would be the same18
joint committee that would be overseeing the profit sharing and productivity program.19
20
21
22
This meeting lasted for a few hours and was very cordial. This is all I23
recall from this meeting.24
17. The next day, October 8,25
26
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
11/484
Page 11 of 28
1
2
3
4
18.5
are attached as Exhibit D talked about the safety valve for the6
Union - the Unions trigger. Whether we would have some sort of mechanism as to7
what we could do if the company broke the agreement. Ray then said they would8
agree that there should be some sort of joint committee to try to resolve disputes. Then9
said that we should have a GWI of 3% a year plus the current COLA, plus a10
payout of under the incentive productivity plan. Ray said that the GWI could not11
be at a 3% level plus everything else said that in order to get the membership to12
ratify the agreement, we should give them a reason as to why they should vote in favor13
of it suggested that in the future the pension should increase by14
15
currently the new hires are in Boeings16
defined benefit plan. (Our current and past agreements, in general, determined17
pension in the following way -18
19
Also, in prior negotiations, Boeing had said they didnt want new hires in its20
defined benefits pension plan that is a Taft-Hartley plan, so we knew this was an issue21
for them.)22
At this point, was laying out all these ideas, so there wasnt much23
discussion - I dont recall responses. talked about how we needed strong24
neutrality language for organizing elsewhere said we cant be loving here while you25
fight us in other locations and that we must have this if we move in a new dimension. In26
Arguably ...
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
12/484
Page 12 of 28
1
2
But in order to settle the strike we agreed that the3
4
So in these negotiations stated that since a new CBA5
would be long-term, the employees should get the plan improvements that Boeing had6
taken off the table during the strike negotiations (the non-union employees had7
received the improvements.) (Our mindset, again, was that the company wanted the8
long-term CBA so they needed to give the employees a reason to accept a long-term9
agreement.) Page 2 of Exhibit D lists the benefits that may have been on the table10
during the strike discussions (it was unclear exactly which ones were included so we11
discussed the items listed in Exhibit D). Gene said that employees would have to start12
sharing the cost of health care increases and it would be better to do it incrementally13
than as a big hit. talked about the need for job security for the work done by14
the bargaining unit. said that we were willing to work with Boeing for15
improvements, reduction of costs, and new technologies for all the airplane lines, not16
just the Dreamliner finally said that there needed to be some sort of ratification17
bonus if the employees agreed to the new long-term agreement such as I dont18
recall a response. Again, we were just throwing out these ideas with more specifics19
than our last meeting and without too much discussion. I do not recall details of the20
companys response to our oral proposal. This is all recall from this meeting.21
19. On October 9, 2009 an email to Doug22
Kight requesting information that the Union needed in order to consider the Companys23
ideas. information requests is attached24
as Exhibit E. The reference to St. Louis is because we have a separate machinists25
bargaining unit in St. Louis26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
13/484
Page 13 of 28
20. Doug Kight emailed The attachments to the email are1
attached here as Exhibit F.2
3
Doug provided the attachment in response to Exhibit E, page4
3, the first three items under the heading of St. Louis. The document provided was the5
6
21. On October 14, 2009, Doug Kight emailed a partial response7
to provide more information as it came available. Dougs email8
attachments included a cover letter which listed the information he provided9
10
attachments also included documents that I have not included in this affidavit due to11
some potential confidentiality issues. Those documents are:12
13
14
15
Dougs October 14 email with his October 13 letter is attached16
as Exhibit G.17
22. On October 15, 2009, we held another negotiation session in Chicago.18
19
20
21
attended this meeting. The same four individuals for Boeing attended.22
23
24
25
26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
14/484
Page 14 of 28
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
Ex. 6, 7(C), 7(D) and arguably 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
15/484
Page 15 of 28
1
2
3
4
23.5
attached as Exhibit H. Ray Conner talked about how he was going to have a meeting6
with the Board of Directors on October 26 and he wanted to give a progress report on7
our negotiations at that meeting. He said that it would be great if we had this worked8
out by them response was that there was not much time before the 26th
; we9
could negotiate a structure, but we would have to go through a process where we10
involved the local people and had them vote on the agreement said that we11
needed enhanced job security if we were giving up the right to strike. When I refer to12
job security, I mean in the broad sense issues involving outsourcing work, transferring13
work to other Boeing, non-unit facilities, and addressing changes in demands for14
products and new technologies. Then Ray gave a 15 or 20 minute explanation as to15
how Boeing sees the future developments in the market, where they see competition,16
and where they see Boeings growth. He explained why our members should view it17
important to see the Dreamliner operation in Puget Sound - that the Dreamliner is the18
future. He said the processes that support the Dreamliner will follow where the second19
line goes. (Portland does machine work to support Puget Sound, but if the Dreamliner20
leaves the Northwest, then so would the supporting machine work.) He talked about21
how we had the skills to do the work in Puget Sound and it wasnt in the Machinists22
interest to have the Dreamliner leave Puget Sound. In essence, Ray was giving us a23
sales pitch as to why we should enter into the long-term agreement responded24
tha understood what Ray was talking about but we needed to address peoples25
perceptions and the media reports about a 20-year agreement - we had been left26
Ex. 6, 7(C), 7(D) and arguably 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
16/484
Page 16 of 28
wondering why the company didnt come talk to us about i said that it was good1
that we were keeping our current talks private in that it was helping us make progress.2
said it would be a tremendous feat to get a long-term contract ratified. Ray3
responded that the two major issues from their perspective were a no-strike provision4
and reopeners (this was to deal with the contract bar issues and address unexpected5
issues that may come up that need to be fixed), and that they wanted a 20-year6
duratio responded that the 20 year contract was impossible. But said we7
could do a long-term agreement if the compensation and incentive pay was there and8
that we could keep adding extensions to the contract explained that we could,9
during a reopener occurring way before the end of a contract, add years onto the end of10
the agreement. That way, the contract could be extended long before there would be11
any need for a strike said that we would have to change the ways we did things -12
that, again, we needed a different relationship with Boeing and reemphasized a need13
for a joint committee. Gene piped in and said Boeing was willing to consult with us but14
they werent going to co-manage with us. said that on some issues, we would15
need more than just consulting. Ray then said they needed to know our duration - how16
many years of a contract we would agree to said that it would depend on how17
much money Boeing would put in the contract for wages, bonuses, and benefits. So at18
this point, we are doing a dance since Boeing had not given us a written proposal or19
spelled out the economics. It was hard for us to commit to anything without knowing20
the numbers. At that point, Ray said that Boeing needed to move towards market21
wages and benefits - they didnt want our members getting paid so much more than22
everyone else that it would make them uncompetitive. Ray said he was okay with23
talking about COLA, GWI and productivity pay, but the IAM proposal that we made in24
our last meeting would not work. So he was saying, in essence, that the concept about25
COLA, GWI, and productivity pay was good but we were asking for too much.26
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
17/484
Page 17 of 28
Specifically, Ray said that he didnt agree with our proposal; he said GWI plus COLA1
needed to be 3.5 percent or lower, but that productivity could help raise this number.2
He also said that on health care there needed to be cost-sharing but they could make3
some improvements to wellness and other items (that were on the table during strike4
negotiations). Ray also said for the health cost-sharing, after 2012 the company would5
6
In countering7
ension proposal, Ray said they could not8
9
10
11
Ray then said they only wanted new employees in a defined contribution plan rather12
than a defined pension plan. (Right now all bargaining unit members are in Boeings13
defined pension plan had been suggesting that instead of putting them in14
Boeings defined pension plan, put Gene said that15
Boeing didnt like16
Ray said that was a non-starter.17
Gene responded that any advantages were not enough to18
outweigh their opposition Gene said the UAW19
in Philadelphia agreed to and he would get us a copy of that20
agreement. I am not aware that he ever provided this to us. how much they21
would contribute for the new hires and Doug responded that he thought said22
that if you put too many things like this in the package, it is going to make it harder to23
get it ratified. We then took a break for lunch.24
24. The October 15 talks resumed at 2:00 p.m. went back to the earlier discussion25
and said that we were willing to work on a incentive/productivity pay26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
18/484
Page 18 of 28
and contribute towards health care costs,1
but we needed to get a wage increase somewhere around 3% GWI plus COLA and we2
wouldnt accept new hires not being in a defined pension pla proposed doing a3
new agreement that would go through 2018 talked about how to re-open the4
contract and add extensions onto the end of the contract to resolve issues or problems.5
said that there should also be a signing bonus to entice people to sign the6
ratification.7
then talked about how to make a new contract appealing to members so8
that they would ratify it. said we needed to plus up - give a reason why members9
should vote on a new contract.10
25. Doug then mentioned integrity and 3-year re-openers.11
Ray said that six years wouldnt get us to a deal12
(meaning having the contract end in 2018). responded again with neutrality and13
trust issues. asked about maybe doing some sort of14
Doug said the retirement average15
hen Gene threw out that they wanted newer, lower wage structures for16
new hires - this was the first time this was brought up. said we wouldnt do that.17
18
19
them). Then Ray stated that after 2012, wages and COLA couldnt be more than 3.5%.20
issue as to what if inflation was high like at 4 or 5%? Then Gene said, well21
then youd get more no, you just said we couldnt get more than 3.5%. So22
we had this whole confusing discussion as to whether 3.5% was a max or not. At this23
point, I think we took a break.24
26. When we came back, Doug started the discussion by giving us a handout that is25
attached as Exhibit I. but it is not numbered26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
19/484
Page 19 of 28
sequentially so Im not sure if pages are missing.) It was entitled Health Care Plans 1
Medical Cost Development, Plan Offerings and Plan Design October 2009. Our2
current contract plan is that our members3
4
5
cost. Doug gave examples showing what the companys proposal was.6
Previously they7
said they were proposing Now they were8
saying the company would pay9
We10
asked them to show us how this proposal would fit with the current contract language.11
We wanted to know how this proposal would work with the current language up until12
2012 when their proposal would kick in. They said they understood it was confusing,13
and would get back to us with more answers and clarification. (It seemed to us that for14
the current contract, this was a worse deal than we currently had.) We never received15
answers to our questions about the health care proposal. I believe the meeting ended16
at that point. We left planning to meet again. Im not sure when the next bargaining17
session was scheduled, but our next meeting was on October 20.18
27. I flew into Chicago the morning19
20
21
In this response, Doug added to his October 14 letter -22
it contained new and previously provided information. Exhibit J attached. Attached to23
this letter, Doug gave us 2 items: Airplane Programs which shows historical24
proprietary productivity data back to 2004 - it reflects manufacturing unit hours and25
customer introduction hours (hours added because of customers special requirements)26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
"of October 20 for another round of negotiations"
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
20/484
Page 20 of 28
per airplane. document that is entitled Performance-Based1
Incentive Plan. This was a proposal that he gave us for the specific purpose of our2
negotiations for the long-term contract and laid out the concept for a profit sharing plan.3
4
5
meeting. This 32-page document explained in much greater detail Boeings ideas6
about a productivity pay system.7
8
9
28.10
11
12
are attached as Exhibit L.13
Ray Conner again talked about Boeing being close to making its decision on the site for14
the 787 second line. He said it would be a topic of discussion at the Board meeting on15
October 26. He talked about the Dreamliner being the future of airplane production;16
how the Company expected Airbus to catch up with Boeing; and how Boeing wanted to17
use the Dreamliner technology to make other large planes. He said that we should18
want to keep all the production in Puget Sound and if the second line moved elsewhere,19
the fabrication work would follow wherever the planes were made. (Some of the20
fabrication work was produced by non-Boeing plants here in Seattle, so the implication21
was that not only would we lose Boeing unit work, we would also lose non-Boeing22
machinist work in Puget Sound.) asked if the company would commit to a23
single source (the Dreamliner being built only in Puget Sound) but received no24
response. Someone from Boeing said that they wanted a 13 year contract.25
said that 13 years for the length of the contract was a huge ask (the current 3 plus 1026
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
21/484
7/30/2019 NLRB Production 9 Affidavits
22/484
Page 22 of 28
have? said if they really wanted a long term deal then they would have a lot of1
hard questions from the unit. restated that the company needed to show2
commitment and brought up Ray then said dont discount3
if the second line goes. Again, his whole argument was that we should want the4
second line in Puget Sound because if they moved it elsewhere, there would be a5
competing center using the same technology. So he was saying dont discount the6
threat of the ramifications of moving the second line said that we understood the7
second line was important. Ray said that he needed to know what we were thinking8
about the triggers. I dont recall us responding to this said that well know if a9
deal is sellable, 9 years is a big deal, we need we need to be involved in10
work decisions, and there either has to be a profit sharing plan or some guaranteed11
money. Ray said that they would12
this was to ease our concerns that there would not be a payout. We then took a break.13
29. When we came back from break, Ray said that he felt that the Union and the Company14
were far too apart and nowhere close to a deal said that there was nothing15
looming and that Ray was the one setting the deadlines and that we believed that we16
could come to a deal. Ray said they wanted to start building the production facility for17
the second line. basically said that Ray was threatening us. Ray said that was18
the reality said, we view this as a threat. said that we didnt agree that we19
couldnt do it - referring to reaching an agreement. said there was a place we20
could get to, but not at21
said that we22
needed to move forward and asked that Boeing give us a proposal. At that point we23
took another break.24
30. After the break came to the table and proposed an additional year to the contract25
length that we previously proposed, which would mean that the contract would end in26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
23/484
Page 23 of 28
2019. went through our prior list again regarding GWI, COlA, that we would1
consider medical cost sharing in year2
and restated that we would like the improvements to the3
medical packages. said that until we agreed to the profit sharing program,4
employees should get payout yearly (this was because we would be ratifying5
the new long term agreement without the details of the profit sharing plan in place - we6
knew it would be too complicated to finalize before ratification of a new contract)7
reiterated the need for signing bonuses, mentioned that we needed to take care of8
9
restated needing10
and neutrality agreements for organizing elsewhere also brought up a11
12
Again, the company did not13
respond to this proposal. At that point, we broke for the day and agreed to meet the14
next day. Unlike all the other meeting days, there was frustration in the room - we set15
out our proposal and moved forward but the Company had not presented any proposal16
other than the changes to health care.17
18
19
20
31. We met the next day on October 21.21
attached as Exhibit M. The mood in the room was much better that morning. At that22
meeting, presented the Company with a draft concept proposal for a long-term23
agreement and the joint partnership committee. The proposal is attached as Exhibit N.24
We handed out copies to everyone in the room - they took time to read it. Someone25
asked how the proposal fit in with our current CBA Article 21.7 which is outsourcing26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4 Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
24/484
Page 24 of 28
language - they wanted to know if they could still outsource work. We responded that1
we needed to talk about this more. Ray said that he didnt know if our proposal was a2
workable solution said he heard the reluctance but we need a long-term3
agreement that shows Boeings commitment to our bargaining unit. We wanted to4
make sure that job security affected all our unit members, not just Dreamliner5
employees. So, if we were going to agree to a long term commitment, Boeing needed6
to do the same for the whole unit. At this point we took a break.7
32. When we got back, Ray responded to our proposal by saying that the job security8
discussions were only for the second line and that they were not willing to talk about9
any other plans for the 787 technology. They didnt want to make commitments10
regarding other bargaining unit work. Ray also said that a 3% GWI for perpetuity was a11
problem taking us in a wrong direction. He then stated that he still wanted a longer12
contract than we had proposed then asked them to give us a proposal, and Ray13
said, we told you (implying that they had explained their proposal) said14
job security was paramount. We then took a break for lunch.15
33. After the break we resumed our talks at 3:20 p.m. When we came back added an16
8th year to the contract extension length, bringing the new contract to 2020. He then17
went over the same issues: bonuses at ratifications and at reopeners,18
ratification bonus for each employee, 3% GWI plus COLA. said for the19
profit-sharing plan, the target would be for20
21
raised the issue as to how soon we could start the22
incentive program - that we wanted a firm date. Ray agreed that that we should start23
the joint committee as soon as possible to create the incentive program (as said above,24
we all knew that it would be too complicated for us to get something together for the25
members to vote on - that it would later be created by the joint committee). So Ray26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
25/484
Page 25 of 28
agreed that we should get the plan in place as soon as we could, and then Doug said1
that he thought 2011 was the earliest the incentive program could take place.2
3
4
said that we were willing to do the cost sharing, but5
modified the pension proposal6
7
Then Doug raised the circuit breaker/trigger issue again. We said we8
were fine with that concept but that it couldnt be too complicated. restated9
some of our other points such as neutrality, and job10
security. That was the end of the day. The mood at the end of the day was much11
better than the day before - we had made movements from our side and the Company12
seemed happier that we added another year and we had agreed that the profit sharing13
would take place as quickly as possible. We then left the meeting; I dont recall exactly14
how he worded it, but I understood that Ray was going to meet with the Board and then15
16
34.17
18
is the email correspondence at Exhibit O. His response isnt clear, but it seemd that he19
was not giving us information the Company had considered.20
21
22
35. October 26 was the day that we were expecting Ray to meet with the Boeing Board.23
36.24
25
26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4 Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
26/484
Page 26 of 28
1
2
These emails are attached as Exhibit P.3
37. Sometime later that day on October 27, someone sent me a newspaper article that4
Boeing had decided to move the 787 work to South Carolina.5
38. After the announcement,6
7
39. I was surprised when I learned of Boeings decision because I did not think we were at8
impasse. I understood we had not reached an agreement, but we were waiting for9
Boeings response to the proposal had made on October 21. I had the impression10
that when we added the eighth year that we were close to what Boeing needed. I11
thought we were still in negotiations when we left the meeting on October 21.12
40 there are several items that the13
Company failed to provide. In looking at Exhibit 19, page 3, the third bullet down, the14
Company listed examples of productivity measurements used in fabrication but did not15
provide data.16
at the time Boeing announcement the placement of the second line to17
South Carolina. On page 5 under St. Louis at the fourth bullet, we wanted to know how18
19
However, the Company did not provide information for the fourth20
bullet.21
22
23
24
25
On the last page, the second bullet, we asked for quarterly data26
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
27/484
Page 27 of 28
1
2
3
41. - this related to the triggers they wanted in case of an economic crisis. The Company4
said that they the triggers may be based on financial issues involving profit/loss and5
operating margin - so we needed to know what this information was. For example, the6
7
8
We just wanted to have a look at the history of9
Boeings finances so we could make a determination as to how we would determine a10
trigger point. These items, in addition to those discussed earlier, are the requests that11
have not been fulfilled by the Company.12
13
14
15
16
I am being provided a copy of this Confidential Witness Affidavit for my review. If,after reviewing this affidavit again I remember anything else that is relevant, or desireto make any changes, I will immediately notify the Board agent. I understand thatthis affidavit is a confidential law enforcement record and should not be shown toany person other than my attorney or other person representing me in thisproceeding.
I have read this statement consisting of 27 PAGE(S), including this page, I fully
Arguably Ex. 4
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
28/484
Page 28 of 28
understand its contents, and I state under penalty of perjury that the foregoing is trueand correct to the best of my knowledge and belief.
X__________________________________
Dated: _______________________
Subscribed and Sworn To Before Me At
__________
National Labor Relations Board
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
29/484
ase 9-C A -3243
)SS
CO NFIDE NT IAL W IT N E ss A FFID A V IT
I , hereby state as follow s:
I
have been given assuran ces
by
an agent of the N ational Labor R elations B oard that this
onfidential W itness A ffidavit will be considered a confidential law enforcem ent record
by
the
B oard and w ill
not be disclosed unless it becom es necessary
to produce the onfidential W itness
A ffidavit in connection w ith a form al proceeding.
Ireside at
M y telephon e num ber
including rea C ode)is
am em ployed by
L ocated
at:
.
2
3
4
5
6
7
8
9
0
P ffivA cy AcT
ST A T E M E N T
Solicitation
of the information
on this form is authorized
bythe National Labor Relations Act (NLRA),
29 U.S.C. 5 et seq.
The principal
use of the inform ation
is to assist the National Labor Relations Board
(NLRB) in rocessing representation
and/or unfair
labor practice proceedings and related proceedings
or litigation. The routine
uses for the information are fully
set forth in he Federal Register,
7
Fed. Reg. 74942-43
(Dec. 3, 2006). The NLRB will further explain these
uses upon
request. Disclosure
of this information to the NLRB is voluntary. How ever,
failure to supply the
inform ation m ay cause the
NLRB to refuseto process any further
representation
or unfair laborpractice case,
or m ay cause the
NLRB to issue you a
subpoena
and seek enforcem ent of
the subpoena in ederal court.
Page of
32
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
30/484
2. w ill
be discussing
various m eetings in
this affidavit.
2
3
3.
In 2008, the IAM
w as negotiating
w ith B oeing
over
a successor
collective
4
bargaining agreem ent
for a
unit Including those
em ployees
in the
Puget Sound
5 area.
A
strike
began after
negotiations broke
dow n.
6
7
Ido not
recall that there
had
8
been any m ention prior
to o r
d urin g th is
tim e ab o u t a "first"
787
line,
it w as just
9 "th e 787 prog ram ."
It
w as m y und erstanding
from
0
and
th e m edia th at
th e S tatelh ad
succ essfu lly
n eg o tiated th at
the
com plete
787 program w ould be placed
in W ashing ton ;
I
to ok th is
to m ean th at
12
all
787 assem bly w ould
be in
W ashing ton .
T he o nly th in g
th at
w e had heard
from
3 anyone
a s o f th e tim e of
the 2008
n eg o tiatio n s, including
14
an d m edia rep o rts,
w as
th at
th e
787
w as secured
and aw arded to
5 W ashing ton ,
so there w as no exp ectation
that w e w ould have
less th an
th e entire
6 787
prog ram . A s part of th e effort to aw ard th e
787
to W ashing ton , th e U nion
7
lobbied
th e S tate to m ake
leg islative
changes
ben eficial
to B oeing, including
tax
8
in cen tiv es v alued
at
$3.2
billion,
in o rde r for
th e
787 to be sited
in W ashing ton
9 S tate.
20
21
-
at
this
22
po int,
w e
h ad no t heard
th at
th e B oeing
w as contem plating
a second
line.
W e
23
believ ed it
w as
already in th e
b ag ,
th at
all of th e
787
final
assem bly
w as
go ing to
24
be located
in P u g et
S oun dl
if exp ansion
of th e
787 w as
ever
n eed ed , th ere
w as
25
already plenty
of room
in E verett
to h an d le
any needed
ad ditional
cap ac ity .
The
26 w ay th e
E verett
plant is
configured
is th at
B oeing
rearranges
its
Page
2
of
32
"in 2003"
"due to the Project Olympus agreement"
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
31/484
production/assem bly
areas w hen they need
m ore room in any given area. It
is
2 not
unusual to do this. So, if they needed
to expand production of the
787
3 beyond w hat w as being done at that tim e, w e just figured that they w ould m ake
4 room as they had
in the past for other projects. That
is w hy the om pany is
5 placing the so
called "surge line" there
-I'll
talk
about this at a later
point.
6
4. A s m ention ed,
the IA M m em bers w ent on strike on S eptem ber
6, 2008,
after their
7
co n tract
ex pired w ithout th e p arties reac h in g an
ag reem en t. T he strik e lasted
57
8
d ay s. A fter th e co n tract ex pired ,
9
0
The
p arties failed to reach an y
agreem ent. T he L ocal
U nion L ead ers w ere gettin g a lot of
flack from U nion
12 m em bers w ho w anted to
strike w hile th e U nion
lea d ersh ip w as still
trying to w ork
3
th in g s ou t. In th e en d , a con tract w as reach ed
an d th e strik e en d ed in O cto be r
14
2008.
5
.
atten d ed th e B oeing-IA M sum m it m eeting held A pril
5- 6, 2009, in h icag o.
6
P rior to this m eeting,
I
had no t heard an y rep o rts a b o u t an ex pan sion to th e
787
7 produ ction. T he sum m it m eeting
w as a forum
for th e h ea d s of v ario u s B oeing
8
dep artm ents
to hav e face-to-face
discussions
w ith th e IA M an d to talk op en ly and
9 co nfiden tially.
20
B oeing
C E O
Jim M cN erney
w as the chief spo kesm an
21
for B oeing
an d talke d ab o u t th e
com pany's
b u sin ess p lan s an d th e com p etitio n
it
22 w as facing.
H e w as cordial, as w ere th e U nion
rep rese n tativ es.
T here w as no
23 m ention of th e om pan y's
d esire for a long-term
agreem ent w ith
a n o-strike
24 clau se
-
at
th is point in tim e,
I
had n ot h eard an yth ing ab o u t a lon g-term
n o -str ike
25 agreem ent. W e
w ere at th e m eeting
to talk ab o u t ho w to do th in g s
b etter
26 to g eth er. T he on ly thing
I
recall b eing
said about
strik es w as th at bo th sid es
Page
3
of
32
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
32/484
briefly expressed
that
it w as unfortunate that
a strike had
occurred. (H ow ever,
2 prior to this m eeting,
M cN erney
had repeatedly said
in the m edia
that the 787 w as
3
delayed b eca u se of o ur
strik e
-
he had
alw ays blam ed u s for
th e delay . T his
is
4
totally u n true - 57
d ay s o f strik e d o es n o t eq u ate
to a d elay of 2 y ears.
H e w as
5
m aking th ese statem en ts
to th e p ress
startin g in D ecem ber
2008
an d all th e
w ay
6
up throu gh
th e sp rin g
of 20 09 .
believ e th at
Jim A lbaugh
also m ad e sim ilar
7
statem en ts
du ring the sam e
tim e
p eriod.)
8
6.
D uring the sum m it
m eeting,
th ere w ere
p resen tatio n s ab o u t ev eryth in g
th e
9
B o ein g o m p an y
w as inv olved in from m ilitary c o n trac ts
to co m m ercial rep o rts.
0
D uring th e com m ercial
aiE ftad s by M cN ern ey
and
h is ex ecu tiv es,
th ey talked
abo ut
th e co m p etitio n for th e v ario u s p ro g ram s,
sa les, etc.
In th is g en eral
12 co n tex t,
th ey ju st said th at
there w ere go od
sales for th e
787
bu t th ey had m ajor
3
p rob lem s w ith sup p liers so th ere
w ere d elay s.
B y
th is tim e, th e p lan e w as
14
prob ably ov er
tw o y ears delaye d.
W e ju st talked gen erally a b o u t th e
state of
5
B oeing. T he talks w ere
gen eral as th e p o in t
of th e m eeting w as really to try
to
, 6
nurture a better relatio n ship an d learn h ow to spe ak cand idly w ith each o th er.
I
7
do n o t recall an y fu rth er
d etails from th is
m eeting.
I
d o n 't believ e th at at this
8
m eeting th ere w as a d iscu ssio n a b o u t B o ein g 's rep u tatio n , B o ein g 's
cu sto m ers,
9
or if the cu sto m ers w ere dem and ing
an y ch an g es. A t no po in t in th is
m eeting do
20
rem e m b er
th at
a second
787 line m en tion ed .
(H ow ever,
ju st a
few
m on ths ago,
21 w e fou nd o u t th at a t th e tim e of th e A pril 200 9 m eeting , bu t u n b ek n o w n st to u s,
22 th e o m p any h ad alread y hired a S o u th arolina lob by ist to n eg o tiate w ith S o u th
23 arolina leg islato rs
for a relocation initiative. S o
by
th e tim e of th e sum m it
24
m eeting , lo b b y ists h ad alread y
reg istered th em selv es
on behalf of B oeing in
25
S o uth aro lin a.
W e fo u n d th is o u t in repo rting req u irem en ts
by
th e S tate of
26
S o uth aro lin a. W e w ill be providing
th is inform ation
to th e B oard
A gen t.)
Page 4 of
32
"reports"
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
33/484
7.
A fter the A pril
m eeting,
m aybe som etim e
in M ay or
June 2009,
m edia reports
2
started
c om in g
ou t ab o u t
B oeing w anting
to ex pan d
th e p ro d u ctio n
of th e
787.
3
T his is th e
first tim e I
had
heard ab o ut
any
exp an sion to
the 787
production
line.
4
S hortly
afterw ards,
there w ere com m ents
throug h
the n ew s m edia
an d politician s
5
th at
B oeing
w as look ing
for a 20-year
co n tract
w ith th e
IAM . T his w as
th e first
6
tim e I had heard
an y th in g
abo ut
a long-term co n tract.
A t the sam e
tim e, w e h eard
7
th ro ug h
m ed ia repo rts th at
B oeing w as
say in g th at th is
w asn 't ju st
an exp ansion
a
of th e
original
787
project;
B oeing
w as ch aracterizin g
th is as a
"new "
787
line (a
9
second
line) to b e p laced
so m e
place
else
-
they
m ad e it
so u n d as if it
w as a
0
com pletely
different
p ro ject th an
th e original 787
project
in ex isten ce .
W e w ere
b o m b a rd e d
in a v ery sh o rt
period
of tim e w ith th ese
rep o rts
from th e
m edia. A s
12
far
as
I
know ,
the U nion had
not
b een con tacted
at th at
tim e
by
B oeing
abo ut
3
th ese issu es -
w e
ju st h eard th e
inform ation
throug h
the m edia
rep o rts.
14
5
6
7
O n July 8,2009,
The
S ea ftle T im es
reported
U .S.
R ep resen tativ es
N orm D icks and
8
Jay
Inslee saying th at
Jim M cN erney
h ad m ad e
it clear
to th em th at the
9
M achinists'
strik es h ad driven
the om pany
to consider
locating
a second
line
20 for
th e
787
o u tsid e
of
W ashing ton state and
th at th e
m ain com petitor
w as S outh
21
arolina.
T he m edia rep ort
stated
th at R ep resen tative
D icks
said M cN erney
told
22
him th at
u n less B oeing g o t
a lon g-term
agreem ent
w ith a n o-strike
clause
from
23
th e M ach inists,
the om pany
w ou ld b uild
th e
787
o u tsid e o f W ashing ton .
T his
is
24
th e first
I
recall
abo ut B oeing
statin g th at
they w ould
place th e
2
d
line here in
25
W ashington
S tate only if w e
agreed to a
long-term no -strike
co n tract.
M y
first
26
reaction
w h en
I
heard
th is rep o rt w as th at th is
w as a ruse b ecause
the re w as no
Page
5
of
32
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
34/484
such thing
as a second line. The w hole notion of a second line forthe
787
w as
2 an invention o n
the p art of the om pany. W ashington state had already w on the
3
787 - as explained above,
our understanding from the m edia and
4 w as that
all 787 production w as going to occur in W ashington. The idea of a
5
seco n d line w as ju st dribbled o u t
by
the com pany in
th e p ress ov er tim e. T he
6 om pany had no t talked
to u s ab o ut their d em an d s.
7 9.
T here w as nev er a d iscu ssio n
betw een m yself and the B oeing com pany abou t
8 w hat their sp ecific in ten t w as reg ardin g
th e
787. B y th is
I
m ean tha t
I
never
9 d iscussed w ith them
w hether they intend ed to assem b le
all
787
p lan es in
th e
0
S tate
of W ashington
indefinitely.
(I
am no t aw are th at other
U nion officials
d iscussed
th is issu e w ith B oeing .) H ow ever,
as
I
stated ab ov e,
it w as th e U nion 's
12
im p ressio n ,
3
th at th e S tate h ad n eg o tiated to estab lish th e
787
assem b ly lines
-
all of them
-
in
14 th e S tate of W ashin gton .
If
the com pany
had told th e S tate in
2003
th at th ey
w ere
5
ju st talking
ab o u t placing
ju st o n e line o f all th e 7 8 7 's fu tu re lin es
in W ashin gton ,
6
th ink th e d iscu ssio n s w ith th e S tate w ould h ave turned o u t differen tly
-
the S tate
7 w ould not hav e
ag reed to all th e eco n o m ic
in cen tiv es th at it g av e to B oein
8
0.
A fter th e n ew s rep o rts,
9
20
21
22
23
24
25
26
Page
6
of
32
Redacted by affiant upon review
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
35/484
2
3
4
5
6
7
8
9
0
A s
far as
I heard, B o ein g 's
th reat
to place th e
12
second line
outside
of
W ashington
w as
solely dependent
on w hether
the
union
3
agreed
to the long-term
no-strike
contract.
14
5
. believe
th e o m p an y
w as
aw are
of
("'
q
ssl",I do
/,,
w
6
W ashing tor R A M and reinyufneeded political cover in light of th e
$3.2
Incentives
7
they have
received
back
in late
2003. believe
it w as
B o ein g 's
strateg y
to blam e
8 th e
U n ion 's
u nw illin gn ess
to ag ree
to a
long -term
no-strike
agreem ent
for
9
B o ein g 's d ecisio n
to site th e
second
line in S o u th
arolina
because
th ey
didn't
20
w ant
to lo se
the support
of th ese
p oliticians.
B y
th is
I m ean that
I
think
th at
21
B oeing
th ou gh t
w e
w ould
never
agree
to
a long-term
no-strike
agreem ent
and
22
th ey co uld
use
th at refusal
as
an excu se
to
place
the secon d
line
elsew h ere.
23
w e m ad e
it
very
clear to th e
p oliticians,
and
later to B oeing
a s detailed
24
below ,
th at
w e w o u ld
n eg o tiate
for a
lon g-term
agreem ent.
25 12. B oeing
announced
th rou gh
th e
m edia
in
July 20 09
th at
it w as b uy ing
the V ought
26
787
plan t
in S o u th
arolina.
In A ug ust
2009, th e
m edia repo rted
th at
B oeing
w as
Page
7 of
32
Upon review, r
"Congressional Delegation hold in Congress"
"the important leadership positions members of"
"Boeing"
Below, redacted by affiant upon review.
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
36/484
applying for building perm its
to construct a
building and clear
82 acres of land
2
for
parking and taxiw ays
adjacent
to the V ought
plant at the
harleston airport.
3
B oeing's continued
acquisitions
of facilities in South
arolina
heightened
anxiety
4
am ong the
business, governm ent
and labor com m unities
in W ashington State
5
that
the
787
second
line m ight
go elsew here.
A t this tim e,
w e knew
w e had a
6 problem
- it w as
clear B oeing w as
thinking
about m oving to S.
arolina.
B ut, at
7
the tim e,
I
still did not have
any d irect
contacts w ith
B oeing regarding the
above
8
issues.
9 13.A t
the request
of Scott arson,
B oeing's CEO
of om m ercial
A irplanes
at the
0
tim e,
a Portland
m eeting w as held
on A ugust
27, 2009.
elieve he arranged
this
m eeting
M y understanding
of the m eeting w as
that Scott
12
w anted
to continue
the dialogue
about how to w ork w ith
each other.
B esides
3
m yself, attending
for
the U nion
14
Scott
arson, D oug
5
K ight, R ay
onner
and G ene W oloshyn
w ere the
B oeing officials
present at
the
6
m eeting.
7
This A ugust
8 m eeting
w asn't
hostile and w e talked
openly.
arson
said "the future
of the
9
Puget Sound
is at stake." H e seem ed
genuinely concerned.
arson then said
20
that the only
w ay the com pany
w ould
place the second 787 line
in W ashington
21
w as if
w e agreed to a 20-year
agreem ent w ith
a no-strike clause. This
w as the
22
first tim e that
Ihad heard anything
directly from B oeing about their need
for a
23 second
line or a long-term agreem ent (previously
it had just
been m edia reports
24
and
A gain, B oeing m ay
have had conversations
w ith
25
or others about these issues,
26
It w as
clear
from w hat
he w as saying that
the long-term
agreem ent
Page
8
of
32
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
37/484
w as a com prehensive agreem ent that w ould cover all com m ercial airplane
2 em ployees. In this m eeting,
w e w ere looking
back at our history and looking
3 forw ard
to se e ho w th e c o n d u ct b etw een th e p arties co uld c han g e. if
4 B oeing w anted a long term
ag reem en t, w e need ed to do b u sin ess differently.
5
6
described a nu m ber of ac tio n s B oeing officials had
tak en to
7
m align our officers an d rep resen tativ es
in th e p ast. w e had had
8 problem s w ith
w ho , du ring th e 2008 n eg o tiatio n s, had d on e thing s
9 w here
it seem ed like w as deliberately
trying to cause a strike w ould leave
0
th e n ego tiation table an d th en go directly to the e m p lo ye es and ask them w hat
they w an ted in the co n tract (w e had filed a U L P ab o u t th is at th e tim e).
12 did no t defen d at th is point, ju st sat tjiere s ilen tly
- th is w as su rp risin g
3 because it w as expected that if w e a Isible o fficer like som eone
14
/w ould com e to defense, but they didn't.
W e also talked how another B oeing
5 official, had circulated
a m em o during the 2008 bargaining
about how to
6 have m em bers resign their m em bership.
w e didn't w ant these type of
7 people to
poison the w ell. W e explained that w e w anted m utual respect in our
8 relationship with Boeing. W e needed to do things in a respectful m anner.
9
said that
the U nion
20
didn't want to be in a position of negotiating with a com pany w hile that com pany
21 w as trying to get
rid of us. arson said that w as a reasonable
request
22
they couldn't act like they w anted to negotiate
a contract with us for Vought
and
23
then support a decert at that plant. W hen sensed that
24
m ight go
along with that shouted out, "I'm
not giving that up!"
By
this
25
understood to m ean that they w ouldn't agree to stop these tactics. Idon't
26
recall exactly how we said it, but we left Boeing with the clear im pression that we
Page 9 of32
E...
Ex. 6
Ex. 6
Ex. 6
Ex. 6
Ex. 6
"criticized"
Ex. 6"from Boeing's side of the table"
Ex. 6
Ex. 6
Ex. 6
Ex. 6
Ex. 6
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
38/484
w ere w illing to w ork som ething out, but
that it w asn't going to be a 20-year
no-
2 strike contract. This is all I
recall from that m eeting
-
it w as fairly
straight
3
forw ard.
4
5 14. The B oard A gent has asked m e
if, during the A ugust m eeting, or at som e other
6
tim e, w e
discussed w ith B oeing w hy it thought
it could p lace the second
787
line
7 outside of the State of W ashington or if the 2
d
line w as un it w ork. W e did n ot
8 have
th ese d iscu ssio n s. A s I stated , w e already rep resen ted th e em plo y ees
at
9 V ought - altho ugh I'm no t saying th at w e th o u g h t it w ou ld be ok ay to place the
0
seco n d line th ere. I'm ju st saying w e ha d th e V ou gh t plan t.
I
w ant to em ph asize
that the A ug ust m eeting w as very fo cu sed
on us explaining w hy w e needed a
12 new relation ship w ith th e com pan y. W e w ere also very fo cu sed on saying th at
3 an y n ew lon g-term co n tract w ou ld co ver all com m ercial p lan es, no t ju st th e 787.
14
L oo k, th e co n tract for th e
787 assem bly w ork in W ashington w as
w ith th e S tate of
5 W ashington , no t w ith u s.
6
7
8 N either in th is m eeting n or in any o ther m eeting
th at I had w ith B oeing
9 officials ov er th e
placem en t of th e 2
d
787 line did w e
d iscu ss th e issu e a s to
20
w hether B oeing had th e righ t to place th e 2
d
line out side of W ashington or
21 w hether th e w ork w as un it w ork. T he U nion ag reed to en g ag e in neg otiation s
22 ov er th e lon g term ag reem en t b ecau se B oeing had linked th e
need for a long-
23 term agreem ent to
th e p lacem ent of
the secon d 787 line. O ur go al w as to
co m e
24 to a reso lution w ith B oeing in order
to c on vince them to place the secon d
line in
25
W ashing ton .
P a g e 0 of 32
Ex. 6
Ex. 6
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
39/484
5.Som etim e around late O ctober 2009, just days after B oeing announced the
2 p lacem en t of th e 787 in S o u th arolina,
3
4
5
M m m m
6
7
8
9
0 0.
6.
F ollow ing the A ug ust
2009
m eeting, th e U nion received a letter d ated S ep tem b er
12 21,
2009,
from Jim M cN erney
3
14
5 0.
T his is
attach ed as E xh ibit
A . I
u n d erstan d th at
M cN erney sen t th e letter
6
after ag reein g to d o so
7
8
9
20
21 7.
w e agreed on
22
hicag o a s th e location
for sub seq u en t
m eeting s as that w ould be aw ay from
the
23 public
eye.
24
W e thou ght w e could m ake
p ro g ress w ith ou t
publicity; th e big
25
concern
w as the m edia and ex p ectatio n s of
th e pu blic and B oeing
em ploy ees.
26 T his w ou ld helpfully
allev iate th e p ressu re
of th e
ex p ectatio n s as to w hat w as
Page
of
32
Redacted by affiant upon review
Redacted by affiant upon review
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
40/484
going to happen w ith the negotiations. (W e norm ally tried to keep contract
2
negotiations outside of the m edia's reach.)
3
4
agreed to a
5 less form al stru ctu re for th e m eeting s; w e w anted everyon e to sit do w n an d hav e
6 op en and h o n est d iscu ssio n s.
7
8.
8
9
0
9.W e m et several tim es in O ctob er 2009. F or th e
first m eeting, O ctober , w e had
12
ad eq uate n o tice,
but all th e rest of th e m eetings w ere b ased
on very sh o rt no tice.
3
14
5
6
7
8
9
20
21
22
23
24
25 20.
IA M rep resen tativ es
to travel to hicag o on sh o rt
notice from
26
various p arts of
th e co un try to m eet on O ctob er 7-9
and 5- 6 only to
have
Page 12
of
32
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
41/484
B oeing
out the m eetings short.
2
3
4
I'll
talk about this m ore below . It w as
like they w anted
to m ake it appear
as if they
5
w ere neg otiating
but it w as clear they
w eren't serio u s
ab o u t it.
6 21.
did not
hav e any d iscussio n s ab ou t the pu rpo se
of th e O ctob er
7 m eeting s
other than w e w anted
to co n tin ue th e co n v ersatio n s
from th e A ug ust
8
m eeting
9 22. Prior to our first m eeting,
proposed to the om pany that
w e
0
hav e a fed eral m ed iator in th e roo m an d co n tacted a poten tial m ed iator.
B u t, G ene W oloshyn said they w eren 't interested in involving a
12
third p arty. S o n o m ediator
participated in th e m eetin g s.
3 23.
14
5
6 w e w ere
go ing to b e talking w ith B oeing ab o u t
a long -term no -
7 strike ag reem en t th at w ou ld secu re w ork for th e IA M th ro u g h o u t th e en tire m ulti-
8 state b argaining un it. O ur position w as very clear - if w e entered into a long-term
9 ag reem en t, w e d id n 't w ant to be
threatened w ith the m ov em ent of prog ram
w ork
20 o ut of th e bargaining unit a year after w e en tered into a long-term no -strike
21 ag reem en t (alm o st all of th e p lan es are up for red esig n, not ju st th e 787, and w e
22 d id n 't w ant B oeing to th reaten to m ov e th e up da ted p ro gram s o u t of P u get
23 S ou nd ). W e w ere loo king for job secu rity regarding th e assem b ly of ou r
24 airp lan es. W e w an ted to m aintain th e integrity of th e p ro gram s into th e fu ture.
25 F or exam ple, if B oeing w as going to create a new m od el
of th e 737, say the 737-
26 A , w e w anted assu ran ces that the new
737-A w ould be assem b led in o ur un it.
I'm
Page
3
of
32
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
42/484
not talking about w ork other than
assem bly.
2
3
4
5
6 24.T he first of the hicago m eetings w as held on O ctober ,2009.
7 R ay onner w as B oeing's lead negotiator. W e
8 arranged all the
chairs in a big circle and w e w ere all m ixed up together. Ican't
9 recall w ho opened. told
0
them that right now w e w ere proposing a six year agreem ent but that w asn't
chiseled in stone.
12 said th at w e d id n 't need to
3 get into
th e g eneral w age in creases and sig ning b o n u ses th at day , bu t th at if they
14 w anted th is new agreem ent, w e nee ded to think ab ou t new ideas. W e talked
5 briefly ab o u t th e need for incentive
prog ram s and som e type of a b on us
pay ou t
6 link ed to quality, productivity an d sa les so th at th ere w ould be a tran sp aren cy
7
com pon ent.
8
9
20
21 told th e om pan y th at th e
U nion w as w illing
22 to reach an agreem ent w ith them if there
is a deal to be m ad e w e w ill
23
m ake th e d eal.
24 25. R ay beg an w ith w riting th e n um bers "737" ou t on a bo ard. H e then talked ab out
25 th e 737 co m petition w ith
A irbu s and th en co ntinu ed w ith other
p rod u ct lines and
26 ho w the hine se and other co m petitors w ere ou t there. T hen h e talked ab out the
Page 14 of32
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
43/484
cargo
planes, the 737
again and w hat w as com peting w ith
the 737. H e then
2 m oved
to the 747 and w here they w ere
looking at grow ing in that area and that
3
the com petition
w as targeting these m arkets
including the R ussians. H e then
4
talked generally about the 787 and that they w ere having problem s
w ith the
5 suppliers. H e just gave a lengthy broad-brushed statem ent about the existing
6 program s and future program s. R ay onner said a six-year agreem ent
(to 20 8)
7
w ouldn't
w ork. That w as fine
R ay said they w ere only interested
8
in do ing an ag reem en t for th e
787
said th at w asn 't acce p tab le. W hat this
9
m eant w as th at he w anted a lon g-term co n tract cov ering
all of th e em p lo y ees in
0
th e ex istin g unit b ut w ou ld only talk a b o u t gu aran teeing assem b ly w ork for the
787
assem b ly em p lo y ees. w e have u n d er th e co n tract
-
12 th at w e are cu ffing th is long co n trac t bu t w ill only provide
3
secu rity
for a fraction of th em ? H e gen erally
talked about the
787
being the
14 future.
I
d o n 't recall if he said an y thing specifically ab o u t the p lace m en t of the
5 787
oth er
th an sayin g th at if th ey p laced th e s eco n d
line elsew h ere, th ey w ou ld
6 hav e to d u p licate sup p liers (no t u se th e
sam e su p p liers th ey
cu rren tly u se for the
7 787
line in E verett).
8 26.
th e
U nion w as in terested in exp loring
a long-term co llective
9
bargaining agreem ent bu t w e had co n cerns ab ou t how
to h and le d ispu tes un der
20
the ag reem en t.
w e w ere
co n cern ed th at a lon g-term
21
agreem ent
w ould w aive
th e
m em bers' righ t to
strik e for
m any y ears, so
w e
22 n eed ed to h av e th e co n tract term s clearly w orked ou t; w e w eren 't
g o in g to ju st
23 do a n o-strik e p led g e
w ith binding arbitration
every th ree y ears. W e talked
about
24
som e econo m ic issues:
ab o u t th e
nA ion b eing a defined
b en efit rath er
than
25
defined
ab o u t productivity
bonuses and an
incen tive pro gram
If
26
w ere
open to negotiate
all th ese su b jects.
R ay said B oeing w anted
Page
5
of
32
"contribution"
"benefit as Boeing wanted"
Arguably Ex. 4
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
44/484
em ployees to share in the costs of health c are
insurance
2 w anted to talk about things
that they had
3 offered in the p ast but had taken off the table. T hese
w ere all discussed in
4 general term s. w as
proposing a different kind of
5 relationship
6 how w e h ad to d o things
7 differently in th e future an d h aving the parties create an a tm o sph ere of m utual
8 resp ect. w e tak e do w n th e trad itio nal b arriers w e had b etw een u s an d
9
have a tran sparen t
relation ship. G ene W oloshyn
resp o n d ed , "E ven if no thing
0
h ap p en s, th is is a go od start." T his w as a clear indication to m e that he w as not
w ith u s in th at roo m . H e is th e n um ber tw o gu y in th e roo m . T his is how the
12 m eeting en d ed , he m ade th e com m ent
and then they w alked o ut. W e
did no t g et
3
into future w ork based on th e
787
tech n o lo g y . T his m eeting lasted all day.
14 for the m eeting w as to set o u t broad, co m p reh en siv e policies an d th en
5 ad d ress d etails at later m eeting s. B oeing said th at w e h ad given them a lot to
6 co n sid er and the y w ou ld g et back to u s.
7 27.
T he next set of m eeting s w ith B oeing
w as held o n O ctob er 7 and 8.
8 p re se ntin g o u r p ro p o sa ls. o p en e d by talking ab o u t in th e 2008
9 neg otiation s and con du ct. T his w as stated to begin talk abo ut
m utual resp ect
20 about bringing forth neutrality. to give an exam ple of past
21
problem s an d th en talk ab o u t ho w to fix th e p rob lem . If there w as
organizing
22
cam paign o r decertification, w e
needed basic rules that neither party
w ould
23
violate. th at w e d id n 't expect th e com p an y to lay dow n if w e
24 w ere organ izing/
w an ted a certain qu ality of co n d u ct betw een
th e p arties.
25
th is statem en t
throug ho ut
neg o tiatio n s.
26
w e
w eren't
hung
up
over
a
tim e
period
for
the
length
of
th e
co n tract,
rather
m o re
Page
6
of
32
"[ ] proposed a problem solving procedure" "outside of the normal grievance"
"procedures to address some issues like" "the incentive pay system Boeing wanted
Ex. 6
"but we had concerns about raids or decerts" "after the 3 yr bar expired, as it would
"in a long term a
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
45/484
on the content
of w hat
w e w ere doing.
that
if w e agreed
to
the
2 co n cep ts,
w e
cou ld extend
th e len gth
of th e co n tract.
I d o n 't recall
th at w e set
3 out
a spec ific
length of
th e c o n tract
in that
m eeting.
th is
w as like
4
any other negotiation
process
an d reiterated
w ere w illing
to
5 n eg o tiate.
W e
talk ed
m o re
ab o u t p roductiv ity
prob lem s.
needed
6
a trigg er
w hich w ould
allow it
to o pt o u t if th e
o m p an y
broke
all th e ag reem en ts;
7 w e
d id n 't
w ant to
be tied to th e
co n tract
un der extrem e
circu m stan ces.
T his
w as
8 to g et
them to
be
tran sp aren t
in
th eir
n eg o tiatio n s
-
if
their nu m be rs
they
9
n eg o tiated for th e b o n u ses and p rod uctiv ity m ea sures
w ere tran sp aren t, g reat,
0
B ut, w e needed a trig g er so th at w e could opt out if B oeing
did n o t
fulfill
its
p ro m ises.
I d o n ot recall
B oeing
talking a b o u t
need ing
th eir ow n trig g er.
12
if
w e w ere
to a g ree
to a long-term
deal, w e w ou ld
need
job
sec u rity
for
3 all
bargaining
unit
em ploy ees,
not
ju st th o se
w orking
on
th e
787, an d w e
w ould
14
need to
have
a b etter relatio n sh ip
w ith the om pan y.
T here
w as n o
resp o n se,
5
bu t th is
w asn 't
un usual
since
O n
6
m edical
7
8
9
20
talked
abo u t
hav ing
lab or
p eace .
th at th is
w as
not
ab o u t the
21
co m p an y
surrendering
an y th ing ,
it w as
abo ut
creating
a peaceful
environ m ent.
22
th e
U nion
soug ht
a code
of co n d u ct
aim ed
at creatin g
a
civil
23
relatio n ship
w h ere w e
cou ld
w ork
co n stru ctiv ely
w ith ho nesty
and m utual
24
resp ec t.
O u r
g ene ral to n e
w as
that w e w anted
to
w ork to g eth er.
25
28. R egarding
an incen tive
(productivity)
plan
ag ree to
a bo nu s
plan
26
tied to
quality,
productivity
and
sales.
Page
7
of
32
"we could a
Arguably Ex. 4
Arguably Ex. 4
"to tha
NLRB-FOIA-000
7/30/2019 NLRB Production 9 Affidavits
46/484
to d iscu ss how to
2
craft a produ ctivity program th at w ou ld be an o ffset to w ag es. W e w anted
3 tran sp aren cy so w e w ould kn ow all th e facto rs affecting quality and productivity.
4 th ey sho u ld tell u s so w e could g et th e righ t
5 peo ple in w ho cou ld w ork ou t th e n um bers. B oeing agreed.
6 29. T he E m ploy er d id n 't p ut forth any p ro p o sals th em selv es. T hey ju st m ade so m e
7 general statem en ts regarding w hat I recall th at they stated on health
8 co sts th at th ey w anted em ploy ees to sha re th e c o sts an d w anted to ren eg o tiate
9 th e ben efits ev ery th ree y ears and u se an arbitrator to m ake th e final d ecisio n .
0
w asn't go ing to w ork and
by
th e n ext day th ey ag reed th at w e co uld lock
in a plan up fron t for th e d uration of th e co n tract. Ifthere w ould be any ch an g es,
12 then the p arties w ou ld n eg o tiate and ag ree to ch an g