4
ID Subject Outline Level WBS Duration Start Finish Predeces Resource Names 0 New Jersey 0 New Jersey Assessment Item Development ELA and Mathe 524 days? Tue 4/23/13 Fri 4/24/15 1 Initiate 1 1 New Jersey Item Dev Project Initiation 4 days Tue 4/23/13 Fri 4/26/13 Project Director 2 Initiate 2 1.1 Review Inputs to Initiation 4 days Tue 4/23/13 Fri 4/26/13 Project Director 3 Initiate 3 1.1.1 Review Contract 1 day Tue 4/23/13 Tue 4/23/13 Project Manager 4 Initiate 3 1.1.2 Review Project Statement of Work 1 day Thu 4/25/13 Thu 4/25/13 Project Manager 5 Initiate 3 1.1.3 Review ASDS and WestEd Environmental Factors 1 day Thu 4/25/13 Thu 4/25/13 Project Manager 6 Initiate 3 1.1.4 Review Organizational Process Assets 1 day Thu 4/25/13 Thu 4/25/13 Project Manager 7 Initiate 2 1.2 Produce Outputs from Initiation 3 days Tue 4/23/13 Thu 4/25/13 2SS Project Manager 8 Initiate 3 1.2.1 Develop Project Charter (3.2.1.1) 3 days Tue 4/23/13 Thu 4/25/13 2SS Project Manager 9 Initiate 3 1.2.2 Develop Preliminary Project Scope Statement (3.2.1.2) 2 days Tue 4/23/13 Wed 4/24/13 2SS Project Manager 10 Initiate 2 1.3 Initiation Phase COMPLETE 0 days Tue 4/23/13 Tue 4/23/13 7SS Project Director 11 Plan 1 3 Planning Processes (3.2.2.1) 22 days? Wed 4/24/13 Thu 5/23/13 Content,Language C 12 Plan 2 3.1 Scope Management Processes 10 days? Wed 4/24/13 Tue 5/7/13 10SS Project Manager 13 Plan 3 3.1.1 Perform Scope Planning (3.2.2.2) 5 days? Wed 4/24/13 Tue 4/30/13 10SS Project Manager 14 Plan 3 3.1.2 Complete Scope Definition (3.2.2.3) 5 days? Wed 4/24/13 Tue 4/30/13 10SS Project Manager 15 Plan 3 3.1.3 Create WBS to level of Work Packages and Task Orders (3.2.2.4) 5 days? Wed 5/1/13 Tue 5/7/13 10SS Project Manager 16 Plan 2 3.2 Activity Planning 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Project Manager 17 Plan 3 3.2.1 Define Activities (3.2.2.5) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord 18 Plan 3 3.2.2 Determine Activity Sequence (3.2.2.6) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord 19 Plan 3 3.2.3 Define Activity Resource Estimates (3.2.2.7) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord 20 Plan 3 3.2.4 Define Activity Duration Estimates (3.2.2.8) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord 21 Plan 2 3.3 Cost Planning 5 days? Wed 4/24/13 Tue 4/30/13 16SS Project Director 22 Plan 3 3.3.1 Develop cost estimates (3.2.2.10) 5 days? Wed 4/24/13 Tue 4/30/13 16SS Test Development Dir 23 Plan 3 3.3.2 Develop cost budget (3.2.2.11) 5 days? Wed 4/24/13 Tue 4/30/13 16SS Operations Director 24 Plan 2 3.4 Complete Quality Plan (3.2.2.12) 3 days Wed 4/24/13 Fri 4/26/13 16SS Project Manager 25 Plan 2 3.5 Complete Human Resource Plan (3.2.2.13) 3 days Wed 4/24/13 Fri 4/26/13 16SS Project Director 26 Plan 2 3.6 Complete Communication Plan (3.2.2.14) 3 days Wed 4/24/13 Fri 4/26/13 12SS Project Manager 27 Plan 2 3.7 Risk Management Processes 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager 28 Plan 3 3.7.1 Establish Risk Management Plan (3.2.2.15) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager 29 Plan 3 3.7.2 Perform Initial Risk Identification (3.2.2.16) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager 30 Plan 3 3.7.3 Establish Qualitative Risk Analysis Process (3.2.2.17) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager New Jersey Assessment Item Development ELA and Mathematics 201315 Page 1

NJ_RFP_Project-Schedule_v2_cfc_03-02-13

Embed Size (px)

Citation preview

Page 1: NJ_RFP_Project-Schedule_v2_cfc_03-02-13

ID Subject OutlineLevel

WBS        Duration Start Finish PredecesResource Names

0 New Jersey 0 New Jersey ‐ Assessment Item Development ‐ ELA and Mathe 524 days? Tue 4/23/13 Fri 4/24/151 Initiate 1 1 New Jersey Item Dev Project Initiation 4 days Tue 4/23/13 Fri 4/26/13 Project Director2 Initiate 2 1.1 Review Inputs to Initiation 4 days Tue 4/23/13 Fri 4/26/13 Project Director3 Initiate 3 1.1.1 Review Contract 1 day Tue 4/23/13 Tue 4/23/13 Project Manager4 Initiate 3 1.1.2 Review Project Statement of Work 1 day Thu 4/25/13 Thu 4/25/13 Project Manager5 Initiate 3 1.1.3 Review ASDS and WestEd Environmental Factors 1 day Thu 4/25/13 Thu 4/25/13 Project Manager6 Initiate 3 1.1.4 Review Organizational Process Assets 1 day Thu 4/25/13 Thu 4/25/13 Project Manager7 Initiate 2 1.2 Produce Outputs from Initiation 3 days Tue 4/23/13 Thu 4/25/13 2SS Project Manager8 Initiate 3 1.2.1 Develop Project Charter (3.2.1.1) 3 days Tue 4/23/13 Thu 4/25/13 2SS Project Manager9 Initiate 3 1.2.2 Develop Preliminary Project Scope Statement (3.2.1.2) 2 days Tue 4/23/13 Wed 4/24/13 2SS Project Manager10 Initiate 2 1.3 Initiation Phase COMPLETE 0 days Tue 4/23/13 Tue 4/23/13 7SS Project Director11 Plan 1 3 Planning Processes (3.2.2.1) 22 days? Wed 4/24/13 Thu 5/23/13 Content,Language C12 Plan 2 3.1 Scope Management Processes 10 days? Wed 4/24/13 Tue 5/7/13 10SS Project Manager13 Plan 3 3.1.1 Perform Scope Planning (3.2.2.2) 5 days? Wed 4/24/13 Tue 4/30/13 10SS Project Manager14 Plan 3 3.1.2 Complete Scope Definition (3.2.2.3) 5 days? Wed 4/24/13 Tue 4/30/13 10SS Project Manager15 Plan 3 3.1.3 Create WBS to level of Work Packages and Task Orders 

(3.2.2.4)5 days? Wed 5/1/13 Tue 5/7/13 10SS Project Manager

16 Plan 2 3.2 Activity Planning 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Project Manager17 Plan 3 3.2.1 Define Activities (3.2.2.5) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord18 Plan 3 3.2.2 Determine Activity Sequence (3.2.2.6) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord19 Plan 3 3.2.3 Define Activity Resource Estimates (3.2.2.7) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord20 Plan 3 3.2.4 Define Activity Duration Estimates (3.2.2.8) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord21 Plan 2 3.3 Cost Planning 5 days? Wed 4/24/13 Tue 4/30/13 16SS Project Director22 Plan 3 3.3.1 Develop cost estimates (3.2.2.10) 5 days? Wed 4/24/13 Tue 4/30/13 16SS Test Development Dir23 Plan 3 3.3.2 Develop cost budget (3.2.2.11) 5 days? Wed 4/24/13 Tue 4/30/13 16SS Operations Director24 Plan 2 3.4 Complete Quality Plan (3.2.2.12) 3 days Wed 4/24/13 Fri 4/26/13 16SS Project Manager25 Plan 2 3.5 Complete Human Resource Plan (3.2.2.13) 3 days Wed 4/24/13 Fri 4/26/13 16SS Project Director26 Plan 2 3.6 Complete Communication Plan (3.2.2.14) 3 days Wed 4/24/13 Fri 4/26/13 12SS Project Manager27 Plan 2 3.7 Risk Management Processes 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager28 Plan 3 3.7.1 Establish Risk Management Plan (3.2.2.15) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager29 Plan 3 3.7.2 Perform Initial Risk Identification (3.2.2.16) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager30 Plan 3 3.7.3 Establish Qualitative Risk Analysis Process (3.2.2.17) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager

New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15

Page 1

Page 2: NJ_RFP_Project-Schedule_v2_cfc_03-02-13

ID Subject OutlineLevel

WBS        Duration Start Finish PredecesResource Names

31 Plan 3 3.7.4 Establish Quantitative Risk Analysis Process (3.2.2.18) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager32 Plan 3 3.7.5 Create Risk Response Planning Process (3.2.2.19) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager33 Plan 2 3.8 Procurement Management Processes 5 days Wed 4/24/13 Tue 4/30/1316SS,21SSProject Director34 Plan 3 3.8.1 Plan purchases and acquisitions (3.2.2.20) 5 days Wed 4/24/13 Tue 4/30/1316SS,21SSProject Manager35 Plan 3 3.8.2 Plan project contracting (3.2.2.21) 5 days Wed 4/24/13 Tue 4/30/1316SS,21SSProject Manager36 Plan 2 3.9 Complete Schedule Development (3.2.2.9) 17 days Wed 5/1/13 Thu 5/23/13 33 Project Manager37 Plan 2 3.10 Planning Phase COMPLETE 0 days Wed 5/1/13 Wed 5/1/13 36SS Project Manager38 Transition 1 5 Transition Planning, Execution  & Hand‐offs 5 days Tue 4/23/13 Mon 4/29/13 2SS Project Manager39 Transition 2 5.1 Transition Planning ‐ WestEd Protocols 5 days Tue 4/23/13 Mon 4/29/13 2SS Project Manager40 Transition 2 5.2 Transition Planning ‐ Subcontract Partners Protocols 4 days Wed 4/24/13 Mon 4/29/13 2SS Project Manager41 Transition 2 5.3 Transition Planning by Assessment Content Areas 5 days Tue 4/23/13 Mon 4/29/13 2SS Project Manager42 2 5.5 Trasition Phase COMPLETE 0 days Wed 4/24/13 Wed 4/24/13 Project Manager43 Execute 1 7 Execution and Monitoring & Controlling Processes 523 days? Wed 4/24/13 Fri 4/24/15 42SS Product manager44 Execute 2 7.1  Direct and Manage Project Execution (3.2.3.1) 50 days Thu 5/30/13 Wed 8/7/13 Project Manager,Proj45 Execute 3 7.1.1 Scheduled Project Status Meetings 50 days Thu 5/30/13 Wed 8/7/13 Project Coordinator46 Execute 3 7.1.2 Ad‐hoc Project Status Meetings 30 days Thu 5/30/13 Wed 7/10/13 Project Coordinator47 Execute 2 7.2  Monitoring and Controlling Processes (3.2.4) 50 days Thu 5/30/13 Wed 8/7/13 Project Coordinator,P48 Execute 3 7.2.1 Scheduled Project Status Reporting (Monthly and Weekly) 50 days Thu 5/30/13 Wed 8/7/13 2SS Project Coordinator49 Execute 3 7.2.2 Ad‐hoc Project Status Reporting 30 days Thu 5/30/13 Wed 7/10/13 2SS Project Coordinator50 Execute 2 7.3 NJ Scope of Work for 2013‐14 (YEAR ONE) 236 days? Wed 4/24/13 Wed 3/19/14 ASDS51 Execute 3 7.3.1 3.0  Kick‐off ‐ NJ  ASSESSMENT ITEM DEVELOPMENT 2 days Wed 4/24/13 Thu 4/25/13 2SS Project Manager52 Execute 3 7.3.2 3.1  ESSENTIAL REQUIREMENTS 30 days Wed 4/24/13 Tue 6/4/13 2SS Project Director53 Execute 3 7.3.3 3.2  GENERAL REQUIREMENTS 30 days Wed 4/24/13 Tue 6/4/13 2SS Project Director54 Execute 4 7.3.3.1 3.2.1  WORK PLANS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager55 Execute 4 7.3.3.2 3.2.2  DOCUMENTS AND PRINTED MATERIALS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator56 Execute 4 7.3.3.3 3.2.3  MONTHLY PROGRESS REPORTS AND MEETING MIN 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager57 Execute 4 7.3.3.4 3.2.4  YEARLY SCHEDULE 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager58 Execute 4 7.3.3.5 3.2.5  TECHNICAL QUALITY 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Director59 Execute 4 7.3.3.6 3.2.6  WEBSITE HOSTING 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator60 Execute 4 7.3.3.7 3.2.7  DELIVERY OF MATERIALS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator61 Execute 4 7.3.3.8 3.2.8  PROGRAM DOCUMENTS ELECTRONIC FOLDER 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator62 Execute 4 7.3.3.9 3.2.9  ALTERNATIVE PROCEDURES 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager

New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15

Page 2

Page 3: NJ_RFP_Project-Schedule_v2_cfc_03-02-13

ID Subject OutlineLevel

WBS        Duration Start Finish PredecesResource Names

63 Execute 3 7.3.13 3.3  ASSESSMENT ITEM DEVELOPMENT 26.33 days? Wed 4/24/13 Thu 5/30/13 2SS Content64 Execute 4 7.3.13.1 3.3.1MATHEMATICS 26.33 days? Wed 4/24/13 Thu 5/30/13 2SS Content65 Execute 5 7.3.13.1.3 3.3.1.1GRADES K‐2 MATHEMATICS TASKS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content66 Execute 5 7.3.13.1.4 3.3.1.2GRADES 3‐12 MATHEMATICS ASSESSMENT ITEM 26.33 days Wed 4/24/13 Thu 5/30/13 2SS Content67 Execute 6 7.3.13.1.4.5 3.3.1.2.1MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content68 Execute 6 7.3.13.1.4.6 3.3.1.2.2OPEN‐ENDED/PERFORMANCE BASED TASK 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content69 Execute 7 7.3.13.1.4.6 3.3.1.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content70 Execute 4 7.3.13.2 3.3.2ENGLISH LANGUAGE ARTS (ELA) 26.33 days Wed 4/24/13 Thu 5/30/13 2SS Content71 Execute 5 7.3.13.2.3 3.3.2.1GRADE K‐2 ELA TASKS 1 day? Wed 4/24/13 Wed 4/24/13 Content72 Execute 5 7.3.13.2.4 3.3.2.2ELA GRADE 3‐12 ELA ASSESSMENT ITEMS 1 day? Wed 4/24/13 Wed 4/24/13 Content73 Execute 6 7.3.13.2.4.5 3.3.2.2.1READING PASSAGES 1 day? Wed 4/24/13 Wed 4/24/13 Content74 Execute 6 7.3.13.2.4.6 3.3.2.2.2WRITING PROMPTS 1 day? Wed 4/24/13 Wed 4/24/13 Content75 Execute 7 7.3.13.2.4.6 3.3.2.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Wed 4/24/13 Wed 4/24/13 Content76 Execute 7 7.3.13.2.4.6 3.3.2.2.3MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Wed 4/24/13 Wed 4/24/13 Content77 Execute 7 7.3.13.2.4.6 3.3.2.2.4OPEN‐ENDED 1 day? Wed 4/24/13 Wed 4/24/13 Content78 8 7.3.13.2.4.6 3.3.2.2.4.1 ITEM‐SPECIFIC RUBRIC DEVELOPM 1 day? Wed 4/24/13 Wed 4/24/13 Content79 Execute 3 7.3.29 3.4  ASSESSMENT ITEM CODING 236 days Wed 4/24/13 Wed 3/19/1464SS,70SSContent80 Execute 3 7.3.30 3.5  ASSESSMENT ITEM TRANSLATION 25 days Wed 4/24/13 Tue 5/28/13 63SS Language Center81 Execute 3 7.3.31 3.6  PLANNING MEETINGS 234 days Wed 4/24/13 Mon 3/17/14 2SS Project Coordinator82 Execute 3 7.3.32 3.7  CONTRACTOR STAFF 234 days Wed 4/24/13 Mon 3/17/14 2SS Content83 Execute 2 7.4 NJ Scope of Work for 2014‐15 (YEAR TWO) 246 days? Thu 4/24/14 Thu 4/2/15 50 ASDS84 Execute 3 7.4.33 3.0  Kick‐off ‐ NJ  ASSESSMENT ITEM DEVELOPMENT 2 days Thu 4/24/14 Fri 4/25/14 82 Project Manager85 Execute 3 7.4.34 3.1  ESSENTIAL REQUIREMENTS 236 days Thu 4/24/14 Thu 3/19/15 82 Project Director86 Execute 3 7.4.35 3.2  GENERAL REQUIREMENTS 236 days Thu 4/24/14 Thu 3/19/15 82 Project Director87 Execute 4 7.4.35.10 3.2.1  WORK PLANS 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager88 Execute 4 7.4.35.11 3.2.2  DOCUMENTS AND PRINTED MATERIALS 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator89 Execute 4 7.4.35.12 3.2.3  MONTHLY PROGRESS REPORTS AND MEETING MIN 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager90 Execute 4 7.4.35.13 3.2.4  YEARLY SCHEDULE 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager91 Execute 4 7.4.35.14 3.2.5  TECHNICAL QUALITY 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Director92 Execute 4 7.4.35.15 3.2.6  WEBSITE HOSTING 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator93 Execute 4 7.4.35.16 3.2.7  DELIVERY OF MATERIALS 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator94 Execute 4 7.4.35.17 3.2.8  PROGRAM DOCUMENTS ELECTRONIC FOLDER 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator

New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15

Page 3

Page 4: NJ_RFP_Project-Schedule_v2_cfc_03-02-13

ID Subject OutlineLevel

WBS        Duration Start Finish PredecesResource Names

95 Execute 4 7.4.35.18 3.2.9  ALTERNATIVE PROCEDURES 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager96 Execute 3 7.4.36 3.3  ASSESSMENT ITEM DEVELOPMENT 1 day? Thu 4/24/14 Thu 4/24/14 63 Content97 Execute 4 7.4.36.3 3.3.1MATHEMATICS 1 day? Thu 4/24/14 Thu 4/24/14 Content98 Execute 5 7.4.36.3.5 3.3.1.1GRADES K‐2 MATHEMATICS TASKS 1 day? Thu 4/24/14 Thu 4/24/14 Content99 Execute 5 7.4.36.3.6 3.3.1.2GRADES 3‐12 MATHEMATICS ASSESSMENT ITEM 1 day? Thu 4/24/14 Thu 4/24/14 Content100 Execute 6 7.4.36.3.6.7 3.3.1.2.1MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Thu 4/24/14 Thu 4/24/14 Content101 Execute 6 7.4.36.3.6.8 3.3.1.2.2OPEN‐ENDED/PERFORMANCE BASED TASK 1 day? Thu 4/24/14 Thu 4/24/14 Content102 Execute 7 7.4.36.3.6.8 3.3.1.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Thu 4/24/14 Thu 4/24/14 Content103 Execute 4 7.4.36.4 3.3.2ENGLISH LANGUAGE ARTS (ELA) 1 day? Thu 4/24/14 Thu 4/24/14 Content104 Execute 5 7.4.36.4.5 3.3.2.1GRADE K‐2 ELA TASKS 1 day? Thu 4/24/14 Thu 4/24/14 Content105 Execute 5 7.4.36.4.6 3.3.2.2ELA GRADE 3‐12 ELA ASSESSMENT ITEMS 1 day? Thu 4/24/14 Thu 4/24/14 Content106 Execute 6 7.4.36.4.6.7 3.3.2.2.1READING PASSAGES 1 day? Thu 4/24/14 Thu 4/24/14 Content107 Execute 6 7.4.36.4.6.8 3.3.2.2.2WRITING PROMPTS 1 day? Thu 4/24/14 Thu 4/24/14 Content108 Execute 7 7.4.36.4.6.8 3.3.2.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Thu 4/24/14 Thu 4/24/14 Content109 Execute 7 7.4.36.4.6.8 3.3.2.2.3MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Thu 4/24/14 Thu 4/24/14 Content110 Execute 7 7.4.36.4.6.8 3.3.2.2.4OPEN‐ENDED 1 day? Thu 4/24/14 Thu 4/24/14 Content111 8 7.4.36.4.6.8 3.3.2.2.4.1 ITEM‐SPECIFIC RUBRIC DEVELOPM 1 day? Thu 4/24/14 Thu 4/24/14 Content112 Execute 3 7.4.37 3.4  ASSESSMENT ITEM CODING 236 days Thu 4/24/14 Thu 3/19/15 96SS Content113 Execute 3 7.4.38 3.5  ASSESSMENT ITEM TRANSLATION 236 days Fri 4/25/14 Fri 3/20/15 96 Language Center114 Execute 3 7.4.39 3.6  PLANNING MEETINGS 236 days Fri 4/25/14 Fri 3/20/15 82 Project Coordinator115 Execute 3 7.4.40 3.7  CONTRACTOR STAFF 245 days Fri 4/25/14 Thu 4/2/15 82 Content116 Execute 2 7.5 Execution, Monitoring & Controlling COMPLETE 263 days Wed 4/23/14 Fri 4/24/15 Project Manager117 3 7.5.3 Year One ‐ Project Effort Complete 0 days Wed 4/23/14 Wed 4/23/14 50SS Project Manager118 3 7.5.4 Year Two ‐ Project Effort Complete 0 days Fri 4/24/15 Fri 4/24/15 Project Manager119 Close 1 8  Close Project (3.2.5.1) 11 days Fri 4/10/15 Fri 4/24/15 Project Manager120 Close 2 8.5 Year One ‐ Project Close 10 days Fri 4/10/15 Thu 4/23/15 Project Coordinator121 Close 2 8.6 Year Two ‐ Project Close 10 days Fri 4/10/15 Thu 4/23/15 Project Coordinator122 Close 2 8.2 Complete Contract Closure (3.2.5.2) 10 days Mon 4/13/15 Fri 4/24/15 Project Manager123 Close 2 8.7 Closing Processes COMPLETE 0 days Fri 4/24/15 Fri 4/24/15 122 Project Director124 Close 1 10 Project COMPLETE 0 days Fri 4/24/15 Fri 4/24/15 123 Project Director

New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15

Page 4