Thirteenth Meeting of National Steering Committee, Delhi, 28th April, 2014 SIPMIU AGARTALA

Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

Thirteenth Meeting ofNational SteeringCommittee, Delhi,28th April, 2014

SIPMIU AGARTALA

Page 2: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

SIPMIU AGARTALA

Status of Tranche-I Project

Project Component ContractAmount

Status as on 01/04/13 Status as on 31/03/14

Phy Fin (Rs. InCr) Phy Fin (Rs. In Cr) Target date of

Completion

Procurementof ERW Pipe" 1.44 Work Completed

(100%) 1.44Work Completed (100%)

1.44Work

CompletedLOT-I(6 TubeWells) 1.14 Work Completed

(100%) 0.51Work Completed (100%) 0.88 Work

CompletedLOT-II (8 Tubewells) 0.83 – –

7 Nos. Completed (87%)Time extension for 3months given with LD

0.42 June 2014

LOT-III (8 Tubewells) 0.78 – –

6 Nos. Completed (63 %)Time extension for 3months given with LD

0.33 July 2014

Constructionof Pump housefor 16 Tubewells

1.64 – –

9 Nos. Completed3 Nos. in progress. (50%) 0.55 Dec 2014

Page 3: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

SIPMIU AGARTALA

Quarterly Target for FY 2014-15 Physical & Financial(Tranche-I (Replacement of 22 DTW’s)

ProjectComponent

ContractAmount

Status as on 01/04/14 April-June14 July – Sept 14 Oct – Dec 14 Jan – Mar 15

Phy Fin Phy Fin Phy Fin Phy Fin Phy FinProcurementof ERW Pipe" 1.44 100% 1.44 – – – – – – – –

LOT-I(6 TubeWells) 1.14 100% 0.88 – – – – – – – –

LOT-II (8 Tubewells) 0.83 87% 0.42 13% 0.25 – 0.10 – – – –

LOT-III (8 Tubewells) 0.78 63.20% 0.33 25% 0.20 12% 0.10 – – – –

Constructionof Pumphouse for 16Tube wells

1.64 50% 0.55 30% 0.40 20% 0.30 – 0.10 – –

Total 3.62 0.85 0.50 0.10

Fund required for FY 2014-15 is Rs 1.45 Crore

Page 4: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

SIPMIU AGARTALA

Status of Tranche-II Project

Project Component ContractAmount

Status as on 01/0413 Status as on 31/03/14Phy Fin Phy Fin Target date of

Completion

Installation of Bulkflow water meter. 0.88

Material received0.06

Time extension for 6 months given with LD6 Nos. Electro Magnetic meter installed(70.50%)

0.26 June 2014

Procurement ofDuctile Iron Pipe 11.03 Supply of DI Pipe

started 3.71 Supply completed (100%) 10.79 Work Completed

Laying of NewPrimary Mains(RisingMains)

NILApproval of Tender from MoUD and ADBreceived. State Government approval awaiting(after parliament Election)

Construction of 14OHSR (LoT-I)-9 Nos. 15.52

MobilizationAdvance givenand Design workstarted

0.70

7 Nos. design drawing approved and rest 2 notyet submitted Colum & bracing work of 4 Nos.OHSR is in progress. (15.80%)Time extension will be needed

2.78 April 2015

Construction of 14OHSR (LOT-II)-5 Nos.

13.45

MobilizationAdvance givenand Design workstarted 1.35

2 Nos. design drawing approved and work inprogress design of rest 3 not yet submitted.Pilling work completed at one site and inanother going on.Time extension for 6 months given with LD(13%)

1.58 Sept 2014

Construction 7Nos. GWTP 39.89 – –

6 Nos. GWTP under construction (23%) 5.90 Feb 2015

WS DistributionPipelines & Alliedworks Lot-1

17.14 – –Lot-I – Out of 106 Km. total 36.00 km pipelinecompleted. Work in progress. (36%) 1.88 Aug 2014

WS DistributionPipelines & Alliedworks Lot-2

20.67 – –Lot-2 - Out of 126 Km. total 34.00 km pipelinecompleted. Work in progress. (28%) 1.54 Aug 2014

Page 5: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

SIPMIU AGARTALA

Quarterly Target for FY 2014-15 Physical & Financial(Tranche-II)

Project Component ContractAmount

Status as on 01/04/14 April-June14 July – Sept 14 Oct – Dec 14 Jan – Mar 15Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin

Installation of Bulk flowwater meter. 0.88 70.50% 0.26 15% 0.25 14.5% 0.25 – 0.10 – –

Procurement of Ductile IronPipe 11.03 100% 10.79 – – – – – – – –

Laying of New PrimaryMains(Rising Mains) NIL NIL – – – 25% 1.00 30% 2.00 30% 2.00

Construction of 14 OHSR(LoT-I)-9 Nos. 15.52 15.80% 2.78 15% 2.00 15% 2.00 20% 3.00 20% 3.00

Construction of 14 OHSR(LOT-II)-5 Nos. 13.45 13% 1.58 10% 1.50 15% 1.50 15% 1.50 25% 2.00

Construction 7 Nos.GWTP 39.89 23% 5.90 9% 4.00 15% 4.00 20% 6.00 20% 6.00

WS DistributionPipelines & Allied worksLot-1

17.14 36% 1.88 10% 3.00 15% 5.00 40% 6.00 – 1.50

WS DistributionPipelines & Allied worksLot-2

20.67 28% 1.54 10% 3.00 20% 7.00 42% 8.00 – 1.50

TOTAL 13.75 20.75 26.60 16.00Fund required for FY 2014-15 is Rs. 77.00 CroreBill pending with SIPMIU Agartala is Rs. 7.20 Cr. which is under scrutiny

Page 6: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

SIPMIU AGARTALA

Status of Fund FlowFinancial Year Fund received from

MoUD Rs. in CrExpenditure

Rs. in Cr Remarks

2008-09 0.11 –

2009-10 3.90 –

2010-11 3.22 2.84

2011-12 7.28 3.75

2012-13 5.63 6.45

2013-14 9.38 25.59Rs. 10.00 Crore has beenreleased by State FinanceDepartment as advance

TOTAL 29.52 38.63Fund required for FY 2014-15 is Rs. 78.45 Crore (Tr- I & II)Bill pending with SIPMIU Agartala is Rs. 7.20 Cr. which is under scrutiny

Page 7: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

SIPMIU AGARTALA

Preparation of Tranche-III Three following projects has been identified by MoUD on recommendation of 12th

National Steering Committee on NERUDP held on 20/11/2013 vide letter No. No. K-14011/8/2011-NERUDP dated 09/12/2013

Sl. No. Project description Cost in Rs. in Cr1 Water supply in Central Zone 65.002 Intake well for river water and rehabilitation of WTP 32.003 SWM : transport, bins etc. 12.00

TOTAL 109.00 DPRs sent to Ministry on 25/04/2014 for following components

Sl.No. Project Sub Project description Cost

Rs. in Cr

1 Water SupplySystem

a. WS Distribution Network in Central Zone of Agartala including DomesticMetering (WS-10/4)

80.42

b. Expansion and Rehabilitation of Existing Water Treatment Plants (WS-05) 9.71c. Installation of New Deep Tube wells (WS-06) 3.74d. Construction of Intake Water System, Rising mains for abstraction ofsurface water from Haora river (WS-12)

16.90

Total (A) 110.77

2Solid waste

Management

a. Procurement of equipments for primary and secondary collection ofsolid waste (SW-01)

10.06

b. Procurement of vehicles for transportation of waste (SW-03) 4.77Total (B) 14.83

GRAND TOTAL (A + B) 125.60

Page 8: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

SIPMIU AGARTALA

Accomplishment of ReformsSl.

No. Reforms Status Remarks

State-Level Mandatory Reforms1 Implementation of 74th CAA In Progress

Out of 18 functions in 12th Schedule Roads &Bridges, Fire Services and Urban Forestry could notbe handed over fully.DWS Division, Agartala merged withAgartala Municipal Corporation (AMC)

Score : 13.5(15)

2 Integration of City Planning andDelivery Functions

In ProgressDelivery of Services in respect of Roads & Bridges,Fire Services and Urban Forestry could not beintegrated fully

Score : 3(5)

3 Reform in Rent Control COMPLETED Score : 10(10)4 Stamp Duty Rationalization to 5% In Progress

Periodicity for revising guidance value for levy ofstamp duty to be fixed.

Score : 5(10)

5 Repeal of ULCRA COMPLETED Score : 10(10)6 Enactment of Community

Participation Law COMPLETED Score : 10(10)

7 Enactment of Public DisclosureLaw COMPLETED Score : 10(10)

TOTAL Score : 61.5(70)

Page 9: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

SIPMIU AGARTALA

Accomplishment of ReformsSl.

No. Reforms Status Remarks

ULB-Level MandatoryReforms

1 Municipal Accounting COMPLETED Score: 10(10)2 E-Governance In Progress

GIS based Software prepared by IDC for Property Tax.Awaiting for Government approval Score: 5(10)

3 Property Tax In ProgressSurvey, Software & Property Tax Rules (for implementingUnit Area Method) prepared by IDC.Awaiting for Government approval

Score: 6(10)

4 User Charges In ProgressStructure of User charge manual prepared by IDC and willbe implemented after completion of ADB Project

Score: 5(10)

5 Internal Earmarking of Funds COMPLETED Score: 10(10)6 Provision of Basic Service to

Urban Poor COMPLETED Score: 10(10)

TOTAL Score: 46(60)

Page 10: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

SIPMIU AGARTALA

Accomplishment of ReformsSl.

No. Reforms Status Remarks

Optional Reforms

1 Introduction of Property Title CertificationSystem in ULBs In Progress Score: 0(10)

2 Revision of Building Byelaws -Streamlining the Approval Process

In ProgressEstablishment of interactive citizen enquirysystem on building plan to achieved

Score: 7.5(10)

3 Revision of Building Byelaws - MakingRainwater Harvesting Mandatory COMPLETED Score: 10(10)

4 Earmarking 20-25% Developed Land inAll Housing Projects for EWS/LIG

In ProgressTime line to improve the % of reservationEWS/LIG in housing project to be achieved.

Score: 5(10)

5 Simplification of Legal and ProceduralFramework for Conversion of AgriculturalLand for Non-agricultural Purpose

In Progress Score: 5(10)

6 Introduction of Computerized Process ofRegistration of Land and Property COMPLETED Score: 10(10)

7 Byelaws on Reuse of Recycled Water COMPLETED Score: 10(10)

8 Administrative ReformsIn Progress

IDC imparted training toMuncipal StaffScore: 610)

9 Structural Reforms In Progress Score: 4(10)

10 Encouraging Public-Private Participation In Progress IDC prepared PPP manualScore: 610)

TOTAL Score: 63.5(100)

Page 11: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

TR-I

Rentus Colony _ Pump House

Pratapgarah Bazar _ Pump House

Page 12: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

TR-I

Page 13: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

TR-II

ONGC _ OHSR

Gurudas Para _ OHSR

Page 14: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

TR-II

Badharghat _ OHSR

Page 15: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

TR-II

Page 16: Ninth Meeting of National Steering Committee, Delhi, 7th May, … · 2017-02-10 · 1 Implementation of 74th CAA In Progress Out of 18 functions in 12th Schedule Roads & Bridges,

TR-II

Sadhutilla _ GWTP

Pragati _ GWTP