Upload
sarah-tulej
View
224
Download
0
Embed Size (px)
Citation preview
8/7/2019 Nine Elms masterplan
1/20
8/7/2019 Nine Elms masterplan
2/20
NINE ELMS MASTERPLAN
8/7/2019 Nine Elms masterplan
3/20
THE NORTHERN LINE EXTENSION
The NLE is a 1.75 km extension of LondonUndergrounds Northern Line
The NLE will be the first privately fundedextension to the Underground network inCentral London.
The NLE is being promoted by TreasuryHoldings (TH)
Project Description
8/7/2019 Nine Elms masterplan
4/20
OURNEY SO FAR
8/7/2019 Nine Elms masterplan
5/20
THE NORTHERN LINE EXTENSION
PublicAcces
(PTAL
Avera
8/7/2019 Nine Elms masterplan
6/20
8/7/2019 Nine Elms masterplan
7/20
THE NORTHERN LINE EXTENSION
January 2009; SKM for the GLA the NLE would be theonly scheme that could provide the necessary capacitywithout overloading Vauxhall station or causingsignificant congestion on the road network
Journey So Far
July 2009; the Mayor confirmed his support inwriting to TH In principle I support theproposed NLE
October 2009; TIF Test Case submitted toGovernment with support of GLA, TfL, LBL &LBW.
8/7/2019 Nine Elms masterplan
8/20
THE NORTHERN LINE EXTENSION
March 2010; SDG prepared a draft NATA reportrecommending Route 2
May 2010; Public consultation was formally launched.
August 2010; Reference Design work completed
September 2010; Balfour Beatty provide commercial
confirmation of costs
September 2010; LUL confirms no objections on atechnical basis to the proposals and the projectprogressing towards a TWAO application
Journey So Far
8/7/2019 Nine Elms masterplan
9/20
Nine Elms station
Kennington Loop turnouts
Intermediate shaft
Battersea station
Crossover
Crossover
Ventilation shaft
Ventilation shaf
8/7/2019 Nine Elms masterplan
10/20
FUNDING
8/7/2019 Nine Elms masterplan
11/20
THE NORTHERN LINE EXTENSION
The NLE would traditionally competefor funding from TfL
This route is not available in theshort-term
The Challenge was to create afunding strategy that did not requireany capital from TfL and did notplace any of the risk with them.
Funding the NLE
8/7/2019 Nine Elms masterplan
12/20
THE NORTHERN LINE EXTENSION
In 2008 PwC were employed to consider options and long-list wascreated including;
Developer Contributions
Development levies and planning gain including CIL Asset Transfer Existing Development Value
Taxes Exchequer or Central Government Funding Accelerated Development Zone / Tax IncrementalFinancing Grants
Direct User Charges Securitisation of ticketing sales Securitisation of third party revenues
Indirect User Charges Operator concession contract
Funding - Sources
8/7/2019 Nine Elms masterplan
13/20
THE NORTHERN LINE EXTENSION
Additionality is Key
The PwC brief was to identify the most viable /deliverable funding sources
The shortlist had a strong common theme:Additionality: i.e. the most appropriate source offunding for the NLE is from those that benefitmost from it.
The shortlist was;
Capturing value from the increaseddevelopment densities (Development Tarif)
Capturing increased taxation flows (TIF)
Capturing increased net revenue to TfL/LUL(Availability Charge)
Option 3 was discounted after further analysis as thenet increase was small / non-existent
Funding - Additionality
8/7/2019 Nine Elms masterplan
14/20
THE NORTHERN LINE EXTENSION
Development Levy Progress
Development Infrastructure Funding Study (DIFS) - Sept2010 confirms requirement for 908m of Infrastructure inNine Elms including NLE.
DIFS also concludes that 850m of Levy, Masterplan, s106and other funding will be available in Nine Elms.
Gap is considered manageable and recent GLA pressrelease states NLE is Viable
Funding - Development Levy
8/7/2019 Nine Elms masterplan
15/20
THE NORTHERN LINE EXTENSION
Tax Increment Financing (TIF)
On 20th September 2010 the Deputy PM announced thatLocal Authorities in England will be granted new borrowingpowers (TIF).
TIF will allow Local Authorities to borrow against thepredicted growth in locally raised business rates in order tofund key infrastructure.
The NLE has been the subject of a detailed TH Case Studywhich show annual incremental business rates of around89m per annum.
Alongside income generated by the Development Tarif, only50% of the increment would be needed to fund the NLE.
This partial business rates retention would only be neededfor 13 years.
In addition studies have shown that over 800m pa of othertaxes would be generated by the OA.
Funding
8/7/2019 Nine Elms masterplan
16/20
THE NORTHERN LINE EXTENSION
The NLE in Nine Elms meets all the fundamentals of a
successful TIF being;
1. Genuine Regeneration Need (BPS)
2. A Well Defined Area (VNEB OA)
3. An Agreed Development Plan (OAPF)
4. Public Infrastructure is the catalyst for Regeneration (NLE)
5. The But for test (Development Levies cannot do it alone)
6. Leverages a significant amount of Private Sector Investment(The Whole OA)
7. Developers are in place
Funding
8/7/2019 Nine Elms masterplan
17/20
THE NORTHERN LINE EXTENSION
Demonstrating Additionality
The proposals have a low take of the incremental businessrates
The scheme is in the CAZ, improving amalgamation benefits
Work is about to start on a full economic case
Income Lag
Often the business rates generated can be insucient tomeet the TIF funding requirements in the early years
The delivery of BPS with over 1m sqft of commercial spacealleviates this
Risk
Allocation and mitigation strategies to be developed
Size
Further work required to reduce size of TIF required
Phasing strategies to be considered
Funding - Hurdles to Jump
8/7/2019 Nine Elms masterplan
18/20
THE NORTHERN LINE EXTENSION
Accepted as being the only transport infrastructuresolution.
TfL / LUL approve current design and costs.
Preparation for the TWAO application well advanced.
DIF study confirms available levy funding.
TIF legislation will support funding stream.
Summary
8/7/2019 Nine Elms masterplan
19/20
8/7/2019 Nine Elms masterplan
20/20