July-September 2014
Quarterly Progress Report No. 8
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page i
Table of Contents
1. INTRODUCTION ......................................................................................................................... 1
1.1 Necessity ........................................................................................................................ 1
1.2 General Features ............................................................................................................ 1
1.3 The Project Road ............................................................................................................ 2
1.4 The Project Road Constraints ......................................................................................... 3
1.5 Proposed Alignment ........................................................................................................ 3
1.6 Location Map .................................................................................................................. 4
1.7 Key Plan ......................................................................................................................... 4
2. PROJECT ASSIGNMENT ........................................................................................................... 4
2.1 Background..................................................................................................................... 4
3. INDEPENDENT ENGINEER ...................................................................................................... 5
3.1 Drawl of Agreement with Concessionaire ....................................................................... 5
4. EXECUTIVE PROGRESS SUMMARY ..................................................................................... 5
4.1 Independent Engineer: .................................................................................................... 5
4.2 THE SCOPE OF INDEPENDENT ENGINEER ................................................................ 5
4.2.1 Development Period Responsibility .................................................................................. 5
4.2.2 Reporting Requirement ..................................................................................................... 6
4.2.3 Mobilization of Concessionaire (Organization Chart) ..................................................... 10
4.3 Setting up of Project Implementation Unit –Shimla. ...................................................... 11
5. PRE-CONSTRUCTION ACTIVITIES ...................................................................................... 11
5.1 Land Acquisition/ Environmental/ Forest Clearance ...................................................... 11
5.2 Utilities shifting & other hindrances: Updated Status ..................................................... 18
5.3 Centre Line Marking: ............................................................................................................. 30
5.4 Soil Investigations: ........................................................................................................ 30
6. Statement –IV ............................................................................................................................. 30
7. CONSTRUCTION SCHEDULE ............................................................................................. 34
7.1 Project Milestone .................................................................................................................... 34
7.2 Documents: Correspondence ..................................................................................................... 34
8. MEETINGS/SITE VISITS/PRESENTATIONS: ................................................................... 51
9. EXECUTING AGENCY ......................................................................................................... 52
9.1 Concessionaire ......................................................................................................................... 52
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page ii
9.2. EPC Contractor: Plant/Machineries/Resources................................................................ 53
10 . ORGANIZATION CHART (IE) .............................................................................................. 54
11. INDEPENDENT ENGINEER MOBILIZATION:................................................................... 55
11.1 Invoice of Independent Engineer Services .............................................................................. 56
12. CONTRACT DATA. ................................................................................................................. 56
12.1 SANCTION /APPROVAL OF PROJECT: ........................................................................ 56
12.2 Civil works Contract Details:................................................................................................... 56
13. PROJECT PARAMETERS ................................................................................................... 57
14. UPDATED REVIEW OF DESIGN & DRAWING up to September,2014 ......................... 58
15. CONSTRUCTION ACTIVITIES. (Comments of Key Professionals on constructions
activities) ..................................................................................................................................... 61
16. Review of Physical Progress .................................................................................................... 82
17 . Road Maintenance works of existing NH-21 (Km .73+200 to 186+500). .............................. 83
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 1
Independent Engineer services for four laning of Kiratpur-Ner Chowk Section of NH-21 from Km73.200 to Km186.500 in the State of Punjab/Himachal Pradesh to be executed as BOT (Toll) on DBFOT Pattern under NHDP Phase-III.
1. INTRODUCTION
1.1 Necessity
The Ministry of Road Transport and Highway (MORT&H) has taken decision to develop National Highway NH-21 from Kiratpur –Ner Chowk section from Km 73.200 to Km 186.500 in the state of Punjab/Himachal Pradesh. The main objective of the Project is to expedite the improvement of Infrastructure in Punjab and Himachal Pradesh and also in reducing time and cost of travel for traffic, particularly heavy traffic, plying between Kiratpur and Ner Chowk .The NH-21 is an important link connecting Kiratpur in Punjab and tourist destination Manali in Himachal Pradesh.NH-21 is also a major link to connect Leh-Ladakh. NHAI have appointed the Voyant Solution Pvt. Ltd. & Inter Continental Technocrat Pvt. Ltd. as consultants to carry out the Technical &Financial feasibility study for improvement of NH-21 between Kiratpur to Ner-Chowk section from Km 73.200 to 186.500 in the state of Punjab & Himachal Pradesh.
1.2 General Features
Sl. No. Item Details
1 Project Name & Location Four laning of Kiratpur to Ner Chowk Section of NH-21 From Km73.200 to Km186.500 in the State of Punjab/Himachal Pradesh to be Executed as BOT(Toll) on DBFOT Pattern Under NHDP Phase-III Starting from Kiratpur(Punjab) & end point Ner Chowk (Himachal Pradesh)
2. Contract Package No. NHPD-Phase-III/DBFOT –NHAI/11016
3. Name of Concessionaire Kiratpur – Ner Chowk Expressway Limited
4. Name of Independent Engineer
Getinsa Ingenieria S. L. Spain in Association with Segmental Consulting &Infrastructure Advisory Pvt. Ltd
5. Date of Acceptance 2nd February-2012
6. Date of signing the Agreement
16th March 2012
7. Date of signing Substitution/Escrow Agreement
9th October 2012 (Financial closure 5th Sep 12, GM (J&K/HP) letter no. NHAI/11016/9/2011/HP-2011/1110
8. Date of Commencement 14 November, 2013.
9. Date of Completion (As per Contract)
12,November,2016 (36 months from the appointed date )
10. Project Cost (As per Concession Agreement)
Rs. 1818.47 Crs.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 2
11. Concession Period 28 years (Incl. Construction Period)
12. Construction Period 3 Years (1095 Days)
Broad Scope of Contract
12.1 Construction of Highways/Tunnels
Construction &widening of Existing Road ( Length 25.844 Km) from Km 73.200 to Km 86.000 ,Km159.070 to Km167.473,Km 179.582 to Km184.323 Construction of two Lane Road to connect Barmana cement factory to New alignment (1.971 Km) Construction of New alignment from Km12.732( Existing Ch 86.000) to Km159.070 including of Five Tunnels i.e. Long Tunnel-01No (1750 Meter), Medium Tunnel-03 No’s (1410,860,650 meter) Short Tunnel-01No (400 meters)
12.2 Construction of Escape Tunnel
Construction of Escape Tunnel - 1905 meter Long parallel to main long tunnel.
12.3 Major Bridges 15 Nos.
12.4 Minor Bridges (Less than 60 m length)
29 Nos+01(Rehabilitation /Repair of Existing Bridge at Km 0+450)
12.5 Fly Over/Grade separator 01 No
12.6 Pedestrian/Cattle underpasses
04 Nos
12.7 Culverts
12.7.1 Box Culverts 64 Nos
12.7.2 Slab Culverts 98 Nos
12.7.3 Pipe Culverts 55 Nos (in addition to this, 30 nos of culverts to be provided at different junction points).
12.8 Main Tunnels Long Tunnel-01 No (1750 Meter), Medium Tunnel-03 Nos (1410,860,650 meter) Short Tunnel-01 (400 meters)
12.9 Escape Tunnel 1905 meter long Parallel to long Tunnel T1
1.3 The Project Road
The NH-21 National Highway will be upgraded from its present two-lane layout, to a four-lane divided carriageway. The design of the road between Kiratpur –Ner Chowk section from Km 73.200 to Km 186.500 in the state of Punjab/Himachal Pradesh .The Project will require the construction of numerous structures, include Fifteen Major Bridges, One Flyover/Grade separator two hundred and forty seven culverts (in addition to this 30 nos of culverts to be provided at different junction points). And one no 1800 meters long tunnel with one escape tunnel of 1800 meter long besides three Medium tunnels and one short tunnel are also to be constructed along the proposed alignment.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 3
1.4 The Project Road Constraints
The existing road alignment of the NH-21 passes between Km 73.200 and Km 186.500 is typified by sub-standard and often steep curves with hair-pin bend and gradients, in the horizontal and vertical planes. The proposed improvement will be new alignment & construction and widening of existing two lane to four lane configuration in different section of the Highway to avoid many S-curves & steeper gradient, which will also involve the construction of many new structures, including Tunnels, bridges, Flyover/Grade Separator and retaining structures. The Project road area is within a region that is prone to erosion & landslides, earthquakes Zone-V. Much of the rock in the area is well jointed and highly fragmented. Combining seismic activity with the extreme prevailing weather conditions also means the area experiences constant landslides. The Himachal region, with its exceptional scenic landscapes, abundant wildlife, culture diversity and profuse number of historic and religious Temples, is a one of the main tourist destination for tourists from every corner of the globe. The NH-21 being the main route between the principal cities of Chandigarh via Kiratpur and from Shimla through NH-88(Connected to NH-21) carries most of the tourist for the entire area. Tourism peaks during the summer months of July and August, but spring and autumn, can also be busy.
1.5 Proposed Alignment
The Project road of NH-21 alignment starts from Kiratpur Km 73.200 terminates to Ner Chowk Km 186.500 and passes through Rup Nagar (Punjab) and Bilaspur, Mandi district of Himachal Pradesh. The important places through which the project highway traverses are Kiratpur, Dhangani, NainaDevi, BhagchhalI, Ferry Ghat, Dharadsani, Auhor, Kallar, Dehar, Dhanotu, Bhaged, Panoh, Canaid, Bhour, Dadour and end at Nagchhala village. The new alignment of Highway starts with long Tunnel T1 from Kainchi More at Km 12.750 (Design Chainage) to Km 14.550 with escape Tunnel 1800 meter long parallel to Tunnel T1, Short Tunnel T2 from Km 15.785 to Km 16.275 (490 meter long), Medium Tunnel T3 from km 23.550 to Km 24.130(580 meter long), Medium Tunnel T4 from Km 148.500 to Km 149.750 (1250 meter long), another medium Tunnel T5 km 157.660 to Km158.400 (740 meter long) through Hilly &mountainous terrain. Proposed new alignment joins the existing road near Jarhol village at Km 159.070 (Design Chainage). For Sundar Nagar Market area a bypass is proposed from Km 173.904 to 179.582. Again the project highway follows the existing road from Km179.582 (Design Chainage) to 184.400. New bypass for Ner Chowk is proposed from Dadour Chowk at Design Chainage 184.400 to Km 188.950 near Nagchhala village which is the end point of Project Highway. To cater the need of cement Industry a link road is proposed to be constructed from ACC cement Plant (Barmana) connecting new alignment of NH-21 with two lane of 1.971 km. length. The proposed four lane will open up the Himachal Pradesh and improve the socio-economic condition of the entire region beyond the Project area. It will also improve the transportation network and will provide rural communities better access to markets, social services and business. Employment opportunities will be generated and also provide impetus to tourism sector of Himachal Pradesh.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 4
1.6 Location Map
1.7 Key Plan
Fig. 1: Proposed Alignment
2. PROJECT ASSIGNMENT
2.1 Background
NHAI have appointed the Voyant Solution Pvt. Ltd. & Inter Continental Technocrat Pvt. Ltd. as consultants to carry out the Technical & Financial feasibility study and Detailed Project Report (DPR) for this section of highway in the states of Punjab & Himachal Pradesh. The proposed construction of Project Road is as under:
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 5
Km 73.200 to Km 86.000 (Existing Chainage) -12.732 km Construction & widening of Existing alignment.
Km 86.000 to Km 159.070 (Design Chainage) -56.520 Km Construction of New alignment comprises of Five No’s Tunnel Total Length 5.070 Km with one Escape Tunnel 1905 meter long.
Km 159.070 to Km 167.473 (Existing Chainage) - 8.403 Km. Construction & widening of Existing alignment.
Km 167.473 to Km 179.582 (New Alignment, Two lane Sunder Nagar Bypass)-5.678 Km (one Two lane already sanctioned by MORT&H – actually work not started).
Km 179.582 to Km 184.323 (Existing Road) 4.741 Km long Construction &Widening of Existing alignment.
Km 184.323 to Km 188.874 (New alignment Ner Chowk Bypass)-4.550Km long Construction of New Alignment.
Connection of Barmana ACC cement Factory – 1.971 Km long (Two lane).
3. INDEPENDENT ENGINEER
It was decided that Independent Engineer may be invited to participate for Project management in order to have proper management and Quality Assurance. Accordingly Bids were invited from pre-qualified and short listed consultants and the work was allotted to M/S Getinsa Ingenieria S. L. Spain in association with M/s Segmental Consulting &Infrastructure Advisory Pvt. Ltd. An agreement for Independent Engineer, services were entered into between national highways Authority of India, Plot No. G-5 and G-6 , Sector No.10, Dwarka, New Delhi- 110045 and M/s Getinsa Ingenieria S. L. Spain in association with M/s Segmental Consulting & Infrastructure Advisory Pvt. Ltd. ,Unit No 204 Vipul Trade Centre, Sector-48, Sohna Road, Gurgaon -122009 (Haryana) India by Letter No. NHAI/11016/10/2011/HP-NH-21/IE-1112 dated 10th October 2012 for commencement of service and accordingly mobilization of Key/ Sub Key Personnel’s was done.
3.1 Drawl of Agreement with Concessionaire
Agreement was drawn by NATIONAL HIGHWAY AUTHORITY OF INDIA (NHAI) with IL&FS Transportation Networks Ltd. on 16th March 2012. For this project IL&FS Transportation Networks Ltd has formed a Special Purpose Vehicle (SPV) by the name of Kiratpur Ner Chowk Expressway Ltd. (KNCEL) hereinafter referred as the “Concessionaire”
4. EXECUTIVE PROGRESS SUMMARY
4.1 Independent Engineer:
M/S Getinsa Ingenieria S. L. Spain in Association with M/s Segmental Consulting &Infrastructure Advisory Pvt. Ltd. Independent Engineer in accordance with the terms of the agreement, have been deployed personnel to supervise the Project and office building has been established which are fully functional . Team Leader Office: C/o Mr. Roshan Lal Sehgal, VPO-Lakhanpur, Ward No-11, District Bilaspur (HP)-174001.
4.2 THE SCOPE OF INDEPENDENT ENGINEER
4.2.1 Development Period Responsibility
The Independent Engineer will be responsible for detailed review of the Drawings as furnished by the Concessionaire along with supporting data, including the geo-technical and hydrological investigations, characteristics of materials from borrow areas and quarry sites, topographical
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 6
surveys and traffic surveys. Such review will be completed and send its comments/observations to the Authority and the Concessionaire within 15 (fifteen) days of receipt of such Drawings. Any modified Drawings or supporting Documents sent by the Concessionaire will be commented within 7 (seven) days of receiving. The review of the detailed design, construction methodology, quality assurance procedures and the procurement, engineering and construction time schedule sent by the Concessionaire will be commented within 15 (fifteen) days of receipt thereof. EPC Contract or any other contract for construction, operation and maintenance of the Project Highway, will be reviewed and commented within 7 (seven) days from receipt.
4.2.2 Reporting Requirement
Independent Engineer shall prepare and submit to the NHAI and Concessionaire of the following reports.
a) Design Review Phase Concessionaire is presently working on allocated activities of development period.
b) Construction Phase Monthly and Quarterly Progress report covering all aspects such as progress monitoring, Quality Assurance (QA)/Quality control (QC) etc.
c) Operation and Maintenance Phase Monthly and Quarterly report on existing condition of facility including advise on all aspects of operation and Maintenance. Toll Booths, Bridges or other Structures, Traffic Management & Safety, Telephone, Ambulance. Monthly inspection report of the Project Highway at least once a month. The Check list to monitor Concessionaire’s obligation under the provision of CA is presented in Table 4.2
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 7
Table – 4.2 Concessionaire's Obligation Check List
S. No.
Requirement of Submission by Concessionaire
Reference Submission Time Schedule Independent Engineer Action Remark
Document Clause
No. Development Period 1 Condition Precedent
Concession Agreement
4.1.3 Before Appointed Date
Monitoring the status of Conditions Precedent and subsequently applicability of claims, if any.
a Performance Security Complied b Escrow Agreement Complied c Substitution Agreement Complied
d Applicable permits as in Schedule -E
In progress
e Financing Agreement complied
f Financial Package and Financial Model
Complied
g
Confirmation of the correctness of their representation and warranties
h Legal opinion
2 Quality Assurance Plan
12.1
15 days before commencement of the Work
Monitor and review as per provisions of CA and technical Specifications
complied
3 Official Representation at site Before Appointed Date
- 4 Quarry approval
Concession Agreement
Monitor and review as per provisions of CA and technical Specifications
5 Construction Methodology Before commencement of Work
6 Inventory of Site 10.3.1 Before Appointed Date Assist Authority for establishing "The Appendix" as defined in CA
Completed
7
Detail Design of Highway Structures, Tunnels
12.1 Before Construction
First Review within 15 days and second review on resubmitted revised drawing with in 7th day from Date of Submission.
Submission in progress
i Geotechnical Investigation Report
Submission in progress
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 8
S. No.
Requirement of Submission by Concessionaire
Reference Submission Time Schedule Independent Engineer Action Remark
Document Clause
No. ii Hydrological Report iii Topographical Surveys Report iv Traffic Survey Report Submitted v Material Report In progress vi Pavement Design Submitted vii Typical Cross Section Submitted
viii Plan & Profile of MCW Submitted for 71.0 Km
ix Plan & Profile of Service Road
x Drainage Plan & Profile xi Cross section
xii Detailed Drawing for individual Culvert Drawings (pipe , Slab & Box)
In progress
xiii
Detail Design and Drawing of
individual Bridges and
structures
Concession Agreement
12.1 Before Construction
First Review within 15 days and second review on resubmitted revised drawing with in 7th day from Date of Submission.
In progress
xiv
Drawings for Road Sign,
Markings Toll Plazas. Bus
Bays, Parking Areas, Truck Lay
Bys
xv
Detailed layout drawings for
traffic circulation for service
roads, for vehicular including
cross section Drawings
through PUP, Flyover at the
Project road level and the
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 9
S. No.
Requirement of Submission by Concessionaire
Reference Submission Time Schedule Independent Engineer Action Remark
Document Clause
No. structure bed level.
xxi Traffic Management drawings for safety in construction zones
Submitted
xxii Detailed drawings of road side furniture and safety structures.
Construction Period
1 Insurances
32.3 30 days before Commencement Date of Construction or Operation.
Monitor and ensure obligation of each party is complied as per CA provisions
complied
2
Monthly Progress Report 13.1 by 7th of every month
complied
3
3 hours Video Recording in compact disc or digital video, covering the status and progress of construction works.
13.6 by 7th day from Appointed Date and subsequently by 15th day after end of each quarter
In progress
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 10
4.2.3 Mobilization of Concessionaire (Organization Chart)
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 11
4.3 Setting up of Project Implementation Unit –Shimla.
PROJECT DIRECTOR
National Highway Authority of India
Project Implementation Unit
Kamna View Bhawan, Phase-III
New Shimla-171009 (Himachal Pradesh)
5. PRE-CONSTRUCTION ACTIVITIES
Km 73.200 to Km.186.500 (Kiratpur Ner Chowk Section)
5.1 Land Acquisition/ Environmental/ Forest Clearance
(A) Land Acquisition:
July/August/September-2014
The 3D notification for land acquisition submitted by concessionaire through PIU Shimla to NHAI Headquarters for entire stretches. The same has been published in The Gazette of India through the Authority for Kiratpur-Bilaspur-Ner Chowk (Km 73.200 to Km 188.500) and status shown in Tables. Details of area for which vacant access and Right of way has been granted to the concessionaire as
on 11th Nov 2013.
(A) RUPNAGAR DISTRICT
Sr. No.
Village Name Area(in Sq m) Total land
( in Sq m ) Award
Letter No. Awarded Date
Forest Private
1
Kalyanpur
- 1707 1707
Already awarded in
previous package
14.06.2013
2 Dabur - 4454 4454 286 to 290 14.06.2013
3 Barruwal - 20146 20146 281 to 285 14.06.2013
4 Massewal - 20301 20301 291 to 295 14.06.2013
5 Dehni - 11698 11698 296 to 300 14.06.2013
6 Chamrauli - 17472 17472 301 to 305 14.06.2013
masura - 124588 124588 306 to 310 14.06.2013
TOTAL (A) 0 200366 200366
(B) BILASPUR DISTRICT
Sr. No.
Village Name Area(in Sq m) Total land (
in Sq m ) Award
Letter No. Awarded Date
Forest Private
1 Gara 25448 19766 45214 360 to 362 17.04.2013
2 Ree 8420 11144 19564 363 to 365 17.04.2013
3 Bhuai 18720 14181 32901 366 to 368 17.04.2013
4 Mehla 19870 33132 53002 932 to 934 23.09.2013
5 Thapna 50196 25037 75233 938 to 940 23.09.2013
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 12
6 Sampaytoo 2735 25828 28563 941 to 943 23.09.2013
7 Jabal 29226 5045 34271 935 to 937 23.09.2013
8 Bharadi 77648 17131 94779 946 to 966 30.09.2013
9 Padgal 23668 36801 60469 970 to 972 30.09.2013
10 Kothipura 20430 4384 24814 967 to 969 30.09.2013
11 Dharadsani 40703 39476 80179 769 to 771 27.08.2013
12 Chaat 76150 18352 94502 766 to 768 27.08.2013
13 Bhated 1939 24004 25943 756 to 758 24.08.2013
14 Mahroiyan 1092 24473 25565 753 to 755 24.08.2013
15 Behiag 5080 10902 15982 750 to 752 24.08.2013
16 Kothi 2308 39476 41784 719 to 721 16.08.2013
17 Lagheda 188 5732 5920 722 to 724 16.08.2013
18 Vahna Jatta 307 22861 23168 716 to 718 16.08.2013
19 Kallar 16254 52974 69228 713 to 715 16.08.2013
20 Bhajwani 6511 31039 37550 673 to 675 06.08.2013
21 Authar 813 25818 26631 665 to 667 05.08.2013
22 Dharyana 7936 10310 18246 662 to 664 05.08.2013
23 Palthi 867 44354 45221 659 to 661 05.08.2013
24 Vakroha 531 6971 7502 605 to 607 22.07.2013
25 Vagthedu 10537 44190 54727 617 to 819 23.07.2013
26 Khuradi 1167 10258 11425 608 to 610 22.07.2013
27 Sannor 752 33748 34500 620 to 622 23.07.2013
28 Panoh 4691 37799 42490 535 to 537 28.06.2013
29 Rohin 19124 33708 52832 532 to 534 28.06.2013
30 Amarsinghpura 13217 35525 48742 520 to 522 25.06.2013
31 Malyawar 11732 47481 59213 517 to 519 25.06.2013
32 Baloh 8776 39049 47825 538 to 540 29.062013
TOTAL (A) 507036 830949 1337985
Details of area for which vacant access and Right of way has been granted to the concessionaire as on
14th Nov 2013
(C) MANDI DISTRICT
Sr.
No. Village Name
Area(in Sq m) Total land (
in Sq m )
Award Letter
No. Awarded Date
Forest Private
1 Bhantrehad 3898 31201 35099 822 to 824 05.09.2013
2 Dehar 6691 76046 82737 825 to 827 06.09.2013
3 Aisu 115860 49066 164926 828 to 830 07.09.2013
4 Dayohi 6996 72288 79284 1117 to 1119 17.09.2013
5 Gamohu 0 10735 10735 1120 to 1122 17.09.2013
6 Jarol 12882 15585 28467 1124 to 1126 19.10.2013
7 Ropari 60695 7637 68332 1157 to 1159 30.10.2013
8 Chamukha 4712 26739 31451 1160 to 1162 31.10.2013
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 13
9 Thala 0 2014 2014 1154 to 1156 30.10.2013
10 Majethal 287 39879 40166 570 to 572 06.07.2013
11 Jarlu 23522 21705 45227 573 to 575 06.07.52013
12 Nagchala 804 46692 47496 567 to 569 05.07.2013
13 Dauhandi 0 22904 22904 564 to 566 05.07.2013
TOTAL (A) 236347 422491 658838
Grand Total (A+B+C) 743383 1453806 2197189
District wise summary of land for which vacant access and right of way has been granted to the concessionaire as on 14th Nov, 2013.
Sr. No.
District Area (in sq m ) Area (in Ha) Remarks
1 Rupnagar 200366 20.0366
2 Bilaspur 1137985 133.7985
3 Mandi 658838 65.8838
Total 2197189 219,7189
Details of area for which vacant access and right of way has not been granted to the concessionaire as on 11th Nov 2013.
Sr. No.
Village Name Area(in Sq m) Total land (
in Sq m ) Present Status
Forest Private
1 Kalyanpur 76827 - 76827
3D Completed and award pending. As Per clause 10.3.4
The Authority has to assure to procure and grant, no later 90
(ninety) days from the Appointed Date I.e. 14th of
Feb,2014 Note : 15.5799 Hect. Of forest land handed over vide letter no 11010/3/2012/forest/PIU-SML/1256 dated 09/01/2014
2 Dabur 0 - 0
3 Barruwal 0 - 0
4 Massewal 0 - 0
5 Dehni 3185 - 3185
6 Chamrauli 606 - 606
7 Maura 17151 - 17151
8 Sunhan 46160 23782 69942
9 Bhated 3680 240004 27684
10 Taali 25000 29907 54907
11 Tunnu 64120 33371 97491
12 Dalyar 9510 9030 18540
13 Patta 8680 47561 56241
14 Bhatehad Uprali 19362 26196 45558
15 Chowk 0 2424 2424
16 Kanaid 0 3510 3510
17 Bhour 1690 2025 3715
18 Jangal Dadnal 0 28219 28219
19 Kayariya 0 26581 26581
20 Jool 0 489 489
21 Dadour 2348 29406 31754
TOTAL (A) 278319 286505 564824
SUNDER NAGAR BYPASS
Sr.
No. Village Name
Area(in Sq m) Total land (
in Sq m ) Present Status
Forest Private
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 14
1 Thala
NA 245210
As per Concessionaire
Agreement only 2 lane was
included in project length but
later on additionally 2 lane is
also included in the project , the
process of land acquisition has
been initialled.(3a published)
2 Pung
3 Derdu
4 Dhoudu
5 Kalohad
6 Bhajwanoo
7 Chowk
Work Front Available Handed over As on Date
Particulars Area(in Sq m) Existing
ROW Total obtained ( in Sq m )
Forest Private
Four Laning of Kiratpur To
Nerchowk Section of NH-
21 from Km 73.200 to Km
186.500 in the State of
Punjab & Himachal
Pradesh
743383 1453806 440500 2637689
Work Front Available/Not Handed over As on Date
Particulars Area(in Sq m) Existing
ROW
Total to be obtained ( in Sq m )
Forest Private
Four Laning of Kiratpur To
Nerchowk Section of NH-
21 from Km 73.200 to Km
186.500 in the State of
Punjab & Himachal
Pradesh
278319 286505 0 564824
Sunder Nagar Bypass NA NA
(A) Total Land Required for Project (sqm.) 3202513
(B) Total Land handed over as on date (sqm) 2637689
(C) Total Land Handed over as on date (in Ha) 26.377
(D) % age of Land Handed over up to Dec-2013 82.36 %
Total Handed over land as on date vide NHAI
Letter No 11010/3/2012/forest/PIU-SML/1256 dated 09/01/2014 95%
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 15
SUMMARY OF INVETORY OF SITE Details of structure in the ROW
PUNJAB
Sr.No. Item Nos. Remarks
1. House/Shops 185
NIL
BILASPUR
Sr.No. Item Nos. Remarks
1. House/Shops 374 NIL
MANDI
Sr.No. Item Nos. Remarks
1. House/Shops 223 NIL
SUMMARY OF INVETORY OF SITE
Details of Trees Cutting In the Row of NH-21
July, 2014
Sr.No. District Nos of Pvt
Trees Nos of Govt.
Trees Total Nos. Of
Trees Remarks
1. Rupnagar - - 2150 117 Nos of tree
cutting completed
2 Bilaspur - - 22810 18590 Nos of tree cutting completed
3 Mandi
8786
1834 10620
1532 Nos of tree cutting
completed
Total 35586 20122
August, 2014
Sr.No. District Nos of Pvt
Trees Nos of Govt.
Trees Total Nos. Of
Trees Remarks
1. Rupnagar - - 2150 404 Nos of tree
cutting completed
2 Bilaspur - - 22810 18590 Nos of tree cutting completed
3 Mandi
8786
1834 10620
1532 Nos of tree cutting
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 16
completed
Total 35586 20526
September, 2014
Sr.No. District Nos of Pvt
Trees
Nos of Govt.
Trees
Total Nos. Of
Trees Remarks
1. Rupnagar - - 2150
1092 Nos of tree
cutting
completed
2 Bilaspur - - 22810
19758 Nos of
tree cutting
completed
3 Mandi
8786
1834 10620
1532 Nos of tree
cutting
completed
Total 35586 22382
Details of utilities in the ROW
PUNJAB
Sr.No. Item Nos. Hindrance Lendth,Km
1 Electrical Lines 142 7.1
2 Water Pipe Lines - 10.686 (running km)
3 Telephone poles 16
4 HT Tower
BILASPUR (HP)
Sr.No. Item Nos. Remarks
1 Electrical Lines 122 6.1
2 Water Pipe Lines - 20.886 (running km)
3 Telephone poles 98
4 HT Tower 3
MANDI (HP)
Sr.No. Item Nos. Remarks
1 Electrical Lines 148 7.4
2 Water Pipe Lines - 0.761 (running km)
3 Telephone poles 354
4 HT Tower 3
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 17
(B) Environmental Clearance: Obtained for entire project.
(1) Environmental clearance obtained from Km. 73.200 to Km. 134.500 vide letter no. F.No. 10-
118/2011-IA.III Government of India, Ministry of Environment & Forests (IA-III Division) 21st march
2013 issued to C.G.M. (LA), NHAI, G-5&6, Sector-10, Dwarka, New Delhi – 110075.
(2) Environmental clearance obtained from Km. 134+350 to Km 186+650 vide letter no. F.No. 10-
52/2011-IA.III Government of India , Ministry of Environment & Forests (IA-III Division) 21st march
2013 issued to C.G.M. (LA), NHAI, G-5&6, Sector-10, Dwarka, New Delhi – 110075.
(C) Forest Clearance: Updated Status
Proposals are under process.
Table 5.2 Updated Status of Forest Clearance
SI. Chainage Total Length Submission of
Proposal Remarks
1 Km. 0.000 to 8.800 8.800 Km. Stage-I Clearance
Obtained
Compliance for Stage-II Clearance
done and sent to MOEF ,New
Delhi
2 Km. 8.800 to 26.500 17.700Km. Stage-I Clearance
Obtained Stage-II clearance obtained.
3 Km. 26.500 (Existing
129.800) to 151.100 21.600Km.
Stage-I Clearance
Obtained Stage-II Clearance Obtained.
4 Km. 151.100 to
189.000 37.900
Stage-I Clearance
Obtained stage-II Clearance obtained
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 18
5.2 Utilities shifting & other hindrances: Updated Status
July-2014
ANNEXURE A
SN Department Circle Office
Division Sub -
Division Amount
Sanctioned Sanctioned by S.E. Client Status
1 I.P.H.
Anandpur Sahib
(Punjab) Kiratpur Kiratpur 4,14,00,000.00 Sanctioned With PD-NHAI
Bilaspur
Swarghat Swarghat 6,80,560.00 Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../165 dated
13.05.2014 for an amount of Rs. 6,34,025.00
Mandatory charges yet to be deposited.
Ghumarwin
Ghumarwin 39,81,900.00 Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../163 dated
13.05.2014 for an amount of Rs. 36,01,565.00
Mandatory charges yet to be deposited.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 19
Kandrore Kandrore 1,77,41,750.00 Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../162 dated 12.05.2014 for an amount of
Rs. 1,49,57,201.00 Mandatory charges yet to be
deposited.
Mandi S.Nagar S.Nagar 4,21,36,724.00 Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../164 dated 13.05.2014 for an amount of
Rs. 3,42,88,190.00 Mandatory charges yet to be
deposited.
Baggi Baggi 3,77,16,787.00 Sanctioned With PD-NHAI
2 Electrical Anandpur
Sahib (Punjab)
Kiratpur Kiratpur
Sahib
96,12,645.00 Sanctioned on 04-09-2013 vide letter
no. 807
Revised estimate sanctioned on 15-04-2014 vide memo no 3779/80 for Kiratpur Sahib feeder
3440350
With RO-NHAI
Revised estimate sanctioned on 16-04-2014 vide memo no 3633 for Maura feeder
8400832
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 20
Total Revised Cost Estimate
11841182
Bilaspur
Sadar
Kot 98,86,198.00 Sanctioned on 30-08-2013 vide letter no
180654(Four Lane)/2013-6254-55
Approved by RO Jammu on 20/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/240- Mandatory charges deposited on 26-12-13.
Bilaspur-I 1,07,62,855.00 Sanctioned on 13-09-2013 vide letter no
180654(Four Lane)/2013-6745-46
Approved by RO Jammu on 19/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/241 -Mandatory charges deposited on 25-03-14.
Bilaspur-II 1,48,29,955.00 Sanctioned on 13-09-2013 vide letter no
180654(Four Lane)/2013-6745-46
Approved by RO Jammu on 19/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/241- Mandatory charges deposited on 26-12-13.
Ghumarwin Kandrour 1,51,56,585.00 Sanctioned on 30-08-2013 vide letter no
180654(Four Lane)/2013-6250-51
Approved by RO Jammu on 15/01/2014 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/336-Mandatory charges deposited on 19-06-14.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 21
Mandi
S. Nagar
Salapper
3,50,89,735.00
Sanctioned on 29-08-2013 vide letter no 180654(Four Lane)/2013-6114-15 & 6116-
17
Approved by RO Jammu on 20/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/242- Mandatory charges yet to be deposited.
S. Nagar Sanctioned on 29-08-2013 vide letter no
180654(Four Lane)/2013-6114-15 & 6116-17
Approved by RO Jammu on 20/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/242- Mandatory charges deposited on 26-12-13.
Ner Chowk Ner Chowk 1,64,37,975.00 Sanctioned on 01-08-2013 vide letter no
180654(Four Lane)/2013-5176-77
Approved by RO Jammu on 19/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/240- Mandatory charges deposited on 26-12-13. Utility shifting work in progress
2 Electrical
Transmission
BBMB BBMB - - -
HPSEBL Bilaspur Hamirpur 2,16,00,000.00 Sanctioned
Not Approved and modification in given estimate has been desired by NHAI vide letter no. 11009/12/2013/K-N/PIU-SML/1582 dated 31.03.2014
Note: - The Concessionaire has not started shifting of utilities for the sections approved by Authority as per clause 11.2 of C.A
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 22
August-2014
ANNEXURE A
SN Department Circle Office
Division Sub -
Division Amount
Sanctioned Sanctioned by S.E. Client Status
1 I.P.H.
Anandpur Sahib
(Punjab) Kiratpur Kiratpur 4,14,00,000.00 Sanctioned With PD-NHAI
Bilaspur
Swarghat Swarghat 6,80,560.00 Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../165 dated
13.05.2014 for an amount of Rs. 6,34,025.00
Mandatory charges yet to be deposited.
Ghumarwin
Ghumarwin 39,81,900.00 Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../163 dated
13.05.2014 for an amount of Rs. 36, 01,565.00
Mandatory charges yet to be deposited.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 23
Kandrore Kandrore 1,77,41,750.00 Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../162 dated 12.05.2014 for an amount of
Rs. 1,49,57,201.00 Mandatory charges yet to be
deposited.
Mandi S.Nagar S.Nagar 4,21,36,724.00 Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../164 dated 13.05.2014 for an amount of
Rs. 3,42,88,190.00 Mandatory charges yet to be
deposited.
Baggi Baggi 3,77,16,787.00 Sanctioned With PD-NHAI
2 Electrical Anandpur
Sahib (Punjab)
Kiratpur Kiratpur
Sahib
96,12,645.00 Sanctioned on 04-09-2013 vide letter
no. 807
Revised estimate sanctioned on 15-04-2014 vide memo no 3779/80 for Kiratpur Sahib feeder
3440350
With RO-NHAI
Revised estimate sanctioned on 16-04-2014 vide memo no 3633 for Maura feeder
8400832
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 24
Total Revised Cost Estimate
11841182
Bilaspur
Sadar
Kot 98,86,198.00 Sanctioned on 30-08-2013 vide letter no
180654(Four Lane)/2013-6254-55
Approved by RO Jammu on 20/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/240- Mandatory charges deposited on 26-12-13.
Bilaspur-I 1,07,62,855.00 Sanctioned on 13-09-2013 vide letter no
180654(Four Lane)/2013-6745-46
Approved by RO Jammu on 19/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/241 -Mandatory charges deposited on 25-03-14.
Bilaspur-II 1,48,29,955.00 Sanctioned on 13-09-2013 vide letter no
180654(Four Lane)/2013-6745-46
Approved by RO Jammu on 19/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/241- Mandatory charges deposited on 26-12-13.
Ghumarwin Kandrour 1,51,56,585.00 Sanctioned on 30-08-2013 vide letter no
180654(Four Lane)/2013-6250-51
Approved by RO Jammu on 15/01/2014 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/336-Mandatory charges deposited on 19-06-14.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 25
Mandi
S. Nagar
Salapper
3,50,89,735.00
Sanctioned on 29-08-2013 vide letter no 180654(Four Lane)/2013-6114-15 & 6116-
17
Approved by RO Jammu on 20/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/242- Mandatory charges yet to be deposited.
S. Nagar Sanctioned on 29-08-2013 vide letter no
180654(Four Lane)/2013-6114-15 & 6116-17
Approved by RO Jammu on 20/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/242- Mandatory charges deposited on 26-12-13.
Ner Chowk Ner Chowk 1,64,37,975.00 Sanctioned on 01-08-2013 vide letter no
180654(Four Lane)/2013-5176-77
Approved by RO Jammu on 19/11/2013 vide letter no. NHAI/RO-Jammu/2012/11050/K-N/240- Mandatory charges deposited on 26-12-13. Utility shifting work in progress
2 Electrical
Transmission
BBMB BBMB - - -
HPSEBL Bilaspur Hamirpur 2,16,00,000.00 Sanctioned
Not Approved and modification in given estimate has been desired by NHAI vide letter no. 11009/12/2013/K-N/PIU-SML/1582 dated 31.03.2014
Note: - The Concessionaire has not started shifting of utilities for the sections approved by Authority as per clause 11.2 of C.A
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 26
September-2014
SN Department Circle Office Division Sub - Division Amount
Sanctioned Sanctioned by S.E. Client Status
1
Bilaspur
Swarghat Swarghat 6,80,560.00 Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../165 dated 13.05.2014
for an amount of Rs. 6,34,025.00 Mandatory charges yet to be
deposited. Work awarded to contractor.
Ghumarwin Ghumarwin 39,81,900.00 Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../163 dated 13.05.2014 for an amount of Rs. 36,01,565.00
Mandatory charges yet to be deposited.
Work awarded to contractor.
Kandrore Kandrore 177,41,750.00
Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../162 dated 12.05.2014 for an amount of Rs. 1,49,57,201.00
Mandatory charges yet to be deposited.
Work awarded to contractor.
Mandi
S. Nagar S. Nagar 421,36,724.00
Sanctioned
Approved on 13-05-2014 vide letter no. 11009/.../164 dated 13.05.2014 for an amount of Rs. 3,42,88,190.00
Mandatory charges yet to be deposited.
Work awarded to contractor.
Baggi Baggi 377,16,787.00
Sanctioned NHAI CLARIFICATION-EE, IPH HAS TO
REPLY.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 27
SN Department Circle Office Division Sub - Division Amount
Sanctioned Sanctioned by S.E. Client Status
2 Electrical
Anandpur Sahib (Punjab)
Kiratpur Kiratpur Sahib
96,12,645.00 Sanctioned on 04-09-2013 vide
letter no. 807
Revised estimate
sanctioned on 15-04-2014
vide memo no 3779/80 for
Kiratpur Sahib feeder
34,40,350.
00
Submitted to NHAI Revised estimate
sanctioned on 16-04-2014
vide memo no 3633 for
Maura feeder
84,00,832.
00
Total Revised Cost Estimate
118,41,182
.00
Bilaspur Sadar
Kot 98,86,198.00
Sanctioned on 30-08-2013 vide letter no
180654(Four Lane)/2013-6254-55
Approved by RO Jammu on 20/11/2013 vide letter no. NHAI/RO-
Jammu/2012/11050/K-N/244 - Mandatory charges deposited on 26-
12-2013.
Bilaspur-I 107,62,855.0
0
Sanctioned on 13-09-2013 vide letter no
180654(Four Lane)/2013-6745-46
Approved by RO Jammu on 19/11/2013 vide letter no. NHAI/RO-
Jammu/2012/11050/K-N/241 - Mandatory charges deposited on 25-
03-2014.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 28
SN Department Circle Office Division Sub - Division Amount
Sanctioned Sanctioned by S.E. Client Status
Bilaspur-II 148,29,955.0
0
Sanctioned on 13-09-2013 vide letter no
180654(Four Lane)/2013-6745-46
Approved by RO Jammu on 19/11/2013 vide letter no. NHAI/RO-
Jammu/2012/11050/K-N/241 -Mandatory charges deposited on 26-
12-2013.
Ghumarwin Kandrour 151,56,585.0
0
Sanctioned on 30-08-2013 vide letter no
180654(Four Lane)/2013-6250-51
Approved by RO Jammu on 15/01/2014 vide letter no. NHAI/RO-
Jammu/2012/11050/K-N/336 - Mandatory charges deposited on 19-
06-2014.
Mandi
S. Nagar
Salapper
350,89,735.00
Sanctioned on 29-08-2013 vide letter no
180654(Four Lane)/2013-6114-15 &
6116-17
Approved by RO Jammu on 20/11/2013 vide letter no. NHAI/RO-
Jammu/2012/11050/K-N/242 - Mandatory charges yet to be
deposited.
S. Nagar
Sanctioned on 29-08-2013 vide letter no
180654(Four Lane)/2013-6114-15 &
6116-17
Approved by RO Jammu on 20/11/2013 vide letter no. NHAI/RO-
Jammu/2012/11050/K-N/242 - Mandatory charges deposited on 26-
12-2013.
Ner Chowk Ner Chowk 164,37,975.0
0
Sanctioned on 01-08-2013 vide letter no
180654(Four Lane)/2013-5176-77
Approved by RO Jammu on 19/11/2013 vide letter no. NHAI/RO-
Jammu/2012/11050/K-N/240 - Mandatory charges deposited on 26-12-2013. Utility shifting commenced
at site.
3 Electrical
Transmission BBMB (01 in no.) BBMB
Estimate not
yet received - -
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 29
SN Department Circle Office Division Sub - Division Amount
Sanctioned Sanctioned by S.E. Client Status
AD Hydro Pvt Ltd. (02 in nos.)
AD Hydro Pvt Ltd Estimate not
yet received - -
HPSEBL (05 in nos.)
Bilaspur Hamirpur 21600000.00 Sanctioned
Modification in given estimate has
been desired by NHAI vide letter no.
11009/12/2013/K-N/PIU-SML/1582
dated 31.03.2014 and compliance is
awaited from HPSEBL
Note: - The Concessionaire has started the shifting of Electric lines for the Nerchowk ,Bilaspur sections.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 30
5.3 Centre Line Marking: Plan & Profile of 71.0 Km has concurred as on date and Survey & setting out of balance length are in progress.
5.4 Soil Investigations:
The detailed sub soil investigation has been carried out for Tunnel 1,2,3 4 & 5 and detailed
investigation reports has been submitted by the Concessionaire on 5.9.2013 vide letter no. ITNL-
KNCEL/PRJ/TECH/ICO-581/2013/611ED 02/04/2014.
The detailed sub soil investigation has been carried out for Major Bridges (Km
0+450,1+085,17+700,19+352,20+830,24+195,26+100,130+165,133+160,135+125,143+783,152+100,
155+670,157+750,158+775,184+650,19+400,158+995) & Minor Bridges (Km 6+140,18+910,25+221,
25+300,133+830, 135+990,138+330,139+565,144+270,146+870,150+050,153+820,185+785, and the
same has been submitted by the Concessionaire .
5.5. Inventory of Cross Drainage Structures.
Joint Verification of structures with concessionaire has been completed as per Concession
Agreement & actual site conditions.
Tree Cutting Permission:
Permission for trees cutting obtained for Km 00 to Km 23+500, Km130 to Km 167+100, Km177+850
to Km186 +500 from concerned department and the same are in progress.
6. Statement –IV Obligations of the Concessionaire during Construction Period
(Based on MCA National Highways)
Sr.No. Obligations of the Project Authority
In any action required to be taken (Yes/No)
If yes, provide details of action taken
1.
Provided Performance Security (Article 9 )
Yes Provided on 10.09.2012
2.
Satisfied the Conditions Precedent (Cl.4.1.3): (a) Executed and procured
execution of the Escrow
Agreement
(b) Executed and procured
execution of the Substitution
Agreement
(c) Procured all the Applicable
Permits specified in
Schedule-E
Yes
Yes
yes
Executed on 09.10.2012 Signed on 11.03.2013 In process.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 31
(d) Delivered copies of Financial
Agreements to the Authority
(e) Delivered 3 copies of
Financial Package and
Financial Model
(f) Delivered form the
Consortium Members
confirmation of
representations and
warranties
(g) Delivered a legal opinion
with respect to the authority
of the Concessionaire
Yes
Yes
Yes
Yes
Submitted on 29.03.2012 Submitted on 29.03.2012 Submitted on 16&17.02.12 Submitted on 21.02.2012
3. Obtaining and keeping in force the Applicable Permits (Cl.5.1.4(f))
Yes All applicable permits are obtained from concerned Authorities
4. Procuring proprietary rights, licences, permissions, etc (Cl.5.1.4(b))
Yes Obtained
5. Maintaining harmony and good industrial relations (Cl.5.1.4(d))
Yes CA clause 5.1.4(d) is being followed
6. Submitted drafts of Project Agreements to the Authority (Cl.5.2.2)
Yes Details submitted
7. Obtaining consent for amendments to Project Agreements (Cl.5.2)
No
8. Obtaining approval for Change in Ownership (Cl.5.3)
No
9. Obtaining prior consent for any business other than Project (Cl.5.6)
No
10. Providing in each Project Agreement the right of Authority to step in (Cl.5.2.4)
No
11. Employed foreign nationals in accordance with Cl.5.4
No
12. Replenishing Performance Security in event of appropriation (Cl.9.2)
Yes Under Progress
13. Remedying Concessionaire Default within Cure Period (Cl.9.2)
Yes Remedy will be done as per CA Clause 9.2 as and when applicable
14. Keeping the Highway open to traffic at all times (Cl.10.2.3)
Yes
Since 80% is green alignment, hence no traffic diversion is required as such. However, at existing alignment traffic is open and shall remain same
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 32
all the times.
15.
Submitting its detailed design, methodology, time schedule, etc (Cl.12.1 (a)) Detailed Design Methodology Time Schedule
yes
yes
yes
Submitted Design as on date has been Reviewed & Concurred Review & Concurred as per site activities. Reviewed and observations made for compliance.
16. Performing all other necessary acts, deeds and things before construction (Cl.12.1(a))
Yes Details already submitted
17. Maintaining existing lanes of the Project Highway (Cl.12.2)
Yes Maintenance works is under progress.
18. Submitting a complete set of ‘as-built’ drawings (Cl.12.3(g))
Yes Will be submitted at the time of Project completion
19. Completing four-laning within the specified period (Cl.12.4.1)
Yes Will be completed in specified period 12th November,2016
20. Paying damages for failure to achieve any milestone (Cl.12.4.2)
Yes Will be liable to pay the damages for failure as per clause 12.4.2 of CA
21. Submitting monthly progress reports (Cl.13.1)
yes MPR is being submitted regularly
22. Rectifying defects pointed out in IE’s monthly report (Cl.13.2)
Yes Will be rectified, if required as per clause 13.2 of CA
23. Carrying out tests and furnishing reports (Cl.13.3.1)
Yes All const. materials are being tested at laboratory as well as at field.
24. Communicating steps taken to expedite progress (Cl.13.4)
Yes Will be intimated as and when required as per clause 13.4 of CA
25. Crediting the balance to the Safety Fund (Cl.16.3.2)
Yes CA Cl 16.3.2 shall be followed if required
26. Evolving Maintenance Manual in consultation with IE (Cl.17.3)
Yes Maintenance Manual will be evolved as per clause 17.3 of CA
27. Not displaying advertisements on the Site (Cl.17.15)
Yes Advertisements will not be displayed all the times.
28. Constructing and handing over Traffic Aid Posts (Cl.20.2)
Yes Will be provided as per CA Clause 20.2
29. Setting up and operationalizing Medical Aid Posts (Cl.21.1)
Yes Will be provided as per CA Clause 21.1
30. Achieving Financial Close within the specified period (Cl.24.1.1)
Yes Obtained on 05.09.2012
31. Paying Damages for delay in Financial Package Close (Cl.24.1.1)
No No delay was made.
32. Providing 3 copies of Financial Package and Financial Model (Cl.24.1.2)
Yes Provided on 29.03.2012
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 33
33. Depositing specified inflows and receipts in the Escrow Account (Cl.31.2)
Yes Said deposits shall be made as per CA clause 31.2
34. Payments from Escrow Account as per specified order (Cl.31.3.1)
Yes CA clause 31.3.1 shall be followed for payments from Escrow Account
35. Appropriation from Escrow Account after Termination (Cl.31.4.1)
No
36. Effecting and maintaining insurance cover (Cl. 32.1 and 32.2)
Yes Executed
37. Depositing and using the proceeds from insurance claims (Cl.32.7)
Yes Executed
38. Maintaining books of accounts(Cl.33.1)
Yes As per clause 33.1 of CA Account Book is maintained.
39. Appointing Statutory Auditors (Cl.33.2.1)
Yes
Gyanendra & Associates were appointed on 21.12.2013 as Statutory auditor as per CA clause 33.2.1.
40. Issuing notice for Force Majeure Event (Cls. 34.5.1 and 34.5.2)
Yes Notice will be issued as and when required.
41. Informing the Authority regarding intent to Terminate (Cl.34.8)
Yes Will be informed as per CA clause 34.8
42. Compensating the Authority for material default (Cl.35.1)
Yes Compensation shall be paid as per CA clause 35.1
43. Complying with the Divestment Requirements (Cl.38.1)
Yes Applicable in event of termination
44. Paying all costs incidental to divestments (Cl.38.5)
Yes Applicable in event of termination
45. Paying to the Authority the benefits arising out of Change in Law (Cl.41.2)
Yes Cl 41.2 of CA shall be followed
46. Complying with General Indemnity requirements (Cls 42.1 and 42.2)
Yes Complied as per CA clause 42.1 & 42.2
47. Allowing free access to the site at all times to the Authority (Cl.43.2)
Yes As per CA clause 43.2 NHAI will have free access at all times
48. Amicably resolving disputes (Cl.44.1 and 44.2)
Yes Disputes will be resolved as per CA clause 44.1 & 44.2
49. Availability of Specified Documents and documents for inspection (Cls.45.1 and 45.2)
Yes All documents are available at site with site Engineer.
50. Maintaining public relations office and Complaints Register (Cl.46.1)
Yes Same are maintained as per CA clause 46.2
51. Inspecting Complaints Register every day and taking prompt and reasonable action (Cl.46.2)
Yes Same is being inspected as per CA clause 46.2
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 34
52. Any other observation, complaint or suggestion
- -
7. CONSTRUCTION SCHEDULE
7.1 Project Milestone
Milestone Financial
Percentage Date of Achievement of Milestone as envisaged in
Concession Agreement
Remarks
Appointed Date(As per Agreement)
0% 14 November,2013
Appointed Date of the Project vide letter No NHAI/RO-Jammu/2010/11050/K-N/252 dated 22 Nov,2013
Project Milestone 1 10% (181.847 Crores)
(12 May,2014) 180th Day
Project Milestone 2 35% (636.467 Crores)
(6 February,2015) 450th Day
Project Milestone 3 70% ((1272.929 Crores)
(3 December,2015) 750th Day
Project Milestone 4 100% (1847.00 Crores)
(12 November,2016) 1095th Day
Scheduled Completion date
7.2 Documents: Correspondence
NHAI Incoming
July, 2014
S. N. Letter No. Date Issued To Subject Remarks
1.
11009/12/2013/K-N/
PIU-SML/387
Date 25.june.2014
5.07.2014 KNCEL
Reg. Encroachment by sh.
Vijay Kumar Thakur, /s/o
Sh. Ganga Ram, VPO
Bhojpur. Tehsil
Sundernagar, Distt. Mandi
in National Highway
Sundernagar, Distt. Mandi.
(H.P)
2.
11009/12/2013/K-N/
PIU-SML/463
Date 9.july.2014
9.07.2014 SCIA
Independent engineer
services for Rehabilitation
and up gradation to four
laning of Kiratpur to
Nerchowk Section of NH-21
in the state of
Punjab/Himachal Pradesh
through Public private
partnership of DBFOT
Pattern Under NHDP-iii
Replacement of sub
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 35
Professional.
3.
11009/12/2013/K-N/
PIU-SML/470
Date 9.july.2014
10.07.2014 SCIA
Request for summer
training of B. Tech. Student
( T. R. A. M.I.E.T Regarding)
4.
11009/12/2013/K-N/
PIU-SML/500
Date 12.july.2014
14.07.2014 SCIA
Request received form
village Tehsil Shri Naina
Devi Distt. Bilaspur H.P
5.
11009/12/2013/K-N/
PIU-SML/521
Date 14.july.2014
15.7.2014 Sr. E.E. HPSEBL Sundernagar
Four Laning of Kiratpur –
Ner Chowk Section of NH-
21 Estimate amounting to
Rs. 2,91,26,250/- pertaining
to the ESD Slapper, HPSEBL
from Dehar to Chamukha.
6.
11009/12/2013/K-N/
PIU-SML/526
Date 15.july.2014
15.07.2014 SCIA Institution Mechanism for
Monitoring of PPP Project
7.
11011/1/2012/RTGS/
PIU-SML/537
Date 15.july.2014
16.07.2014 Canara Bank Transfer of Fund through
RTGS/NEFT
8.
11011/1/2012/RTGS/
PIU-SML/538
Date 15.july.2014
16.07.2014 Canara Bank Transfer of Fund through
RTGS/NEFT
9.
11009/12/2013/K-N/
PIU-SML/516
Date 14.july.2014
21.07.2014 SCIA Road Site Plantation reg.
10.
11009/12/2013/K-N/
PIU-SML/596
Date 23.july.2014
23.07.2014 SCIA/ KNCEL
Proposal for development
of Wayside Amenities along
National Highway
11.
11009/13/2013/K-N/
PIU-SML/522
Date 15.july.2014
25.07.2014 NHAI
Four laning of Kiratpur Ner
Chowk section of nh-2
Estimate amounting to Rs.
4,41,40,930/- pertaining to
the sub division no -2 W/S &
Sanitation , Anandpur
sahib(shifting of I&PH
Utilities for approval.
12.
11009/8/2012/NHAI/PI
U-SML/618
Date 24.july.2014
25.07.2014 SCIA
Independent engineer
services for Rehabilitation
and Up- gradation to four
laning of Kiratpur Ner
Chowk section of NH-21 in
the state of Punjab /
Himachal Pradesh through
public private partnership
DBFOT pattern under
NHDP-III Replacement of
sub professional.
13. 11009/5/13/2013/K-N/
PIU-SML/617 25.07.2014 SCIA
Signing of supplementary
Agreement.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 36
Date 24.july.2014
14.
11009/6/KNCL/2013/
PIU-SML/620
Date 24.july.2014
25.07.2014 KNCEL
Notification of project
milestone -1( schedule –GH,
Ref clause 12.1 CA.
15.
11011/26/2013/MR/
PIU-SML/665
Date 30.july.2014
31.07.2014 SCIA
Monthly progress report
independent engineer four
laning of Kiratpur Ner
Chowk section of NH-21
from Km. 73.200 to Km.
186.500in the state of
Punjab /HP on DBFOT
pattern under NHDP –III
(MRP No.21 & QPR-7)
16.
11011/IE/2013/K-N/
PIU-SML/664
Date 30.july.2014
31.07.2014 SCIA
Felling of eucalyptus tree
along g NH- 21 in
Sundernagar Town
17.
11011/IE/2013/K-N/
PIU-SML/663
Date 30.july.2014
31.07.2014 SCIA Submission of COS for
Major Bridge @ 0+450
18.
11011/26/2013/MR/
PIU-SML/665
Date 30.july.2014
30.07.2014 SCIA
Monthly progress report
(Independent engineer for
engineer for four laning of
Kiratpur Ner Chowk section
of NH-21 from Km. 73.200
to Km. 186.500 in state of
Punjab /HP on DEFOT
pattern under NHDP-III
(MPR No- 21. &QPR-7)
19.
11009/6/KNCL/2013/
PIU-SML/662
Date 30.july.2014
31.07.2014 KNCEL
Vehicle tracking system
(VTS) with facility or global
positing system (GPS) to
track ambulance /road
patrol vehicles.
20.
11009/10/NH-
21/2012/
PIU-SML/666
Date 30.july.2014
5.08.2014 SCIA To Grant NOC for Establishment of interstate check post.
August, 2014
1
11009/5/2013/K-N/
PIU-SML/628
Date 24.07.2014
7.08.2014 Vijay Kumar
Thakur
Encroachment no NH-21
Sunder Nager, Distt. Mandi.
2 11009/10/NH-21/NCO
/2012/PIU-SML. 666
Date 5.08.2014
30.07.2014 The Excise and
Taxation Officer (I.C.C. Dehni, Distt.
To Grant NOC for Establishment of Inter State Cheek Post.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 37
Ropar, Punjab)
3
11009/12/2013/K-N/
PIU-SML/695
Date 4.08.2014
4.08.2014 SCIA
Increasing accident
involving road medians
road dividers need for
change in construction of
medians suggestion –reg.
4
11009/12/2013/K-N/
PIU-SML/696
Date 4.07.2014
4.08.2014 SCIA Submission of COS for
Sundernagar by pass.
5
11011/1/2012/RTGS/
PIU-SML/702
Date 4.08.2014
6.08.2014 Chief Manager
Shimla.
Transfer of Funds through
RTGS /NEFT.
6
11011/1/2012/RTGS/
PIU-SML/703
Date 4.08.2014
6.08.2014 Chief Manager
Shimla
Transfer of Funds through
RTGS /NEFT.
7
11009/12/2013/K-N/
PIU-SML/713
Date 5.08.2014
6.08.2014 SCIA Procurement of the site
8
11011/13/I&PH2013/K-
N/
PIU-SML/747
Date 11.08.2014
12.08.2014 The Executive Engg. I&PH.
Reg. Shifting of I &PH
Utilities.
9
11011/13/I&PH2013/K-
N/
PIU-SML/748
Date 11.08.2014
12.08.2014 SCIA Shifting of I&PH Utilities for
approval
10
11011/32/2013/Meeting
/
PIU-SML/789
Date 14.08.2014
14.08.2014 SCIA
Training schedule at R.O Chandigarh NHAI Reg. Training – Cum Workshop programme on PMIS tool for PPP Project.
11
11009/IE/2013/K-N/
PIU-SML/848
Date 28.08.2014
28.08.2014 SCIA Himachal kishan shabha
September, 2014
1.
11011/01/2012/RTGS
PIU-SML/860
Date 01.09.2014
1.09.2014 The Chief
Manager, Canara Bank .
Transfer of funds through
RTGS/NEFT.
2.
11011/01/2012/RTGS
PIU-SML/861
Date 01.09.2014
1.09.2014
The Chief Manager, Canara
Bank .
Transfer of funds through
RTGS/NEFT.
3.
11009/12/2013/KNCEL/
PIU-SML/979
Date 17.09.2014
18.09.2014 SCIA. Legal Notice. U/S 80 C.P.C
4.
11009/12/2013/K-N/
PIU-SML/981
Date 17.09.2014
18.09.2014 IL&FS Public Grivances
5. 11011/1/2013/KNCEL/ 18.09.2014 IL&FS Public Grivances
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 38
PIU-SML/982
Date 17.09.2014
6.
11009/14/2012/K-N
PIU-SML/1016
Date 17.09.2014
18.09.2014 CGM Cum R.O
Chandigarh ,NHAI
Estimate of Safety
Measures proposed on
Exiting NH-21
7.
11009/5/2012/K-N/
PIU-SML/1025
Date 18.09.2014
18.09.2014 SCIA
For laning of Kiratpur
Nerchowk section of NH-21
from km 73+200 to Km
186+500 in state of Punjab
and Himachal Pradesh
request to released the
performance security bank
guarantee Reg.
8.
11009/7/IE/2013/K-N/
PIU-SML/949
Date 9.09.2014
23.09.2014 SCIA Public Grivances
9.
11011/26/IE/2013/MR/
PIU-SML/1056
Date 24.09.2014
24.09.2014 SCIA
Monthly Progress Report (
Independent Engineer for
four laning of Kiratpur Ner
Chowk section of NH-21
73.200 Km. 186.500 in the
state of Punjab /HP on
DBFOT pattern Under
NHDP –III (MPR.23)
10.
11011/32/IE/2013/Meet
ing/PIU-SML/1057
Date 24.09.2014
24.09.2014 SCIA Change of Scope for Sundernagar By pass.
11.
11011/01/2012/RTGS
PIU-SML/1062
Date 25.09.2014
25.09.2014 The Chief
Manager, Canara Bank.
Transfer of funds through
RTGS/NEFT.
12.
11011/01/2012/RTGS
PIU-SML/1063
Date 25.09.2014
26.09.2014 The Chief
Manager, Canara Bank.
Transfer of funds through
RTGS/NEFT.
13.
11011/01/2012/RTGS
PIU-SML/1064
Date 25.09.2014
26.09.2014 The Chief
Manager, Canara Bank.
Transfer of funds through
RTGS/NEFT.
14.
11011/01/2012/RTGS
PIU-SML/1065
Date 25.09.2014
26.09.2014 The Chief
Manager, Canara Bank.
Transfer of funds through
RTGS/NEFT.
NHAI Outgoing
July, 2014
1.
SCIA/001/14-
15/TL/NHAI-
00412
4.07.2014 NHAI
3rd R.A. bill for
Maintenances of Existing
NH-21 from Km 73.200 to
190.000.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 39
2. SCIA/001/14-
15/TL/NHAI-00413 4.07.2014
NHAI
Commencement of
services Traffics &
Transportation .
3. SCIA/001/14/15/TL/
NHAI-00417 9.07.2014
NHAI
Commencement of
services Mobilization of
Traffic & Transport
Expert.
4. SCIA/001/14/15/TL/
NHAI-00418 9.07.2014
NHAI
Replacement of sub
Professional for the
position of Asst. Highway
Engineer.
5. SCIA/001/GEN/TL/
NHAI-10007 10.07.2014
NHAI
Request for summer
training of B. Tec student
( T.R.A.M.I.T regarding )
6. SCIA/001/14/15/TL/
NHAI-00419 9.07.2014
NHAI
Submission of Monthly
Progress Report (MPR
No-21)
7. SCIA/001/14/15/TL/
NHAI-00420 9.07.2014
NHAI
Submission of Quarterly
Progress Report (QPR NO.
7).
8. SCIA/001/14/15/TL/
NHAI-00423 10.07.2014
NHAI
Accident Report for
Kiratpur Nerchowk
Project.
9. SCIA/001/14/15/TL/
NHAI-00426 15.07.2014
NHAI
Regarding to grant of
NOC for establishment of
interstate check post.
10. SCIA/001/GEN/TL/
NHAI-00432 23.07.2014
NHAI
Request received form
village Tali, Tehsil Naina
Devi Bilaspur, (HP)
Section NH-21.
August, 2014
1
SCIA/001/14-
15/TL/NHAI-
00438
8.08.2014 NHAI
Commencement of
services mobilization of
Assistant highway
engineer.
2 SCIA/001/14-
15/TL/NHAI-00439 9.08.2014
NHAI
Accident Report for
Kiratpur Nerchowk
Project.
3 SCIA/001/14-
15/TL/NHAI-00440 8.08.2014
NHAI
Submission of Monthly
Progress Report ( MPR
No. 22)
4 SCIA/001/14- 12.08.2014
NHAI Submission of Service Tax
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 40
15/TL/NHAI-00451 Challan for the Period
from (1th April 2014) for
reimbursement of service
Tax.
5 SCIA/001/14-
15/TL/NHAI-00452 12.08.2014
NHAI
Commencement of
services submittal C.V of
Horticulture cum
Landscaping Expert.
6 SCIA/001/14-
15/TL/NHAI-00454 14.08.2014
NHAI
Site visit of tunnel Design
Engineer.
7 SCIA/001/14-
15/TL/NHAI-00469 27.08.2014
NHAI
Estimate amounting Rs.
4, 41, 40,930/-pertaining
to sub division no -2 W.S
and sanitation. Anandpur
sahib ( Shifting of I&PH
Utilities
) for approval.
September, 2014
1.
SCIA/001/14-
15/TL/NHAI-
00474
1.09.2014 NHAI Submission of COS for
Sunder Nagar By pass.
2.
SCIA/001/14-
15/TL/NHAI-
00475
4.09.2014 NHAI
Felling of Eucalyptus tree
along NH-21 in Sunder
Nagar Town.
3.
SCIA/001/14-
15/TL/NHAI-
00476
4.09.2014
NHAI
Issue of Additional
measurements Books for
Maintenance works.
4.
SCIA/001/14-
15/TL/NHAI-
00477
8.09.2014
NHAI
Lighting of tunnel with
captive solar power with
LED Lights
5.
SCIA/001/14-
15/TL/NHAI-
00478
8.09.2014
NHAI
Submission of Monthly
Progress Report (MPR
No. 23)
6.
SCIA/001/14-
15/TL/NHAI-
00480
9.09.2014
NHAI
Accident Report for
Kiratpur Nerchowk
Project.
7.
SCIA/001/14-
15/TL/NHAI-
00486
23.09.2014 NHAI Submission of C.V sub
professional.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 41
8.
SCIA/001/14-
15/TL/NHAI-
00490
29.09.2014
NHAI
Proposal for service road
in Naulakha- Dadour.
9.
SCIA/001/14-
15/TL/NHAI-
00491
30.09.2014 NHAI
Regarding issue of
additional measurements
books for maintenance
works.
Concessionaire Incoming
July, 2014
1.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/764
Dated 1.07.2014
1.07.2014 SCIA
Regarding vendor
Approval for swellex type
rock bolts
2.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/765
Dated 4.07.2014
5.07.2014 SCIA
Submission of design &
drawing slope protection
system with reinforced soil
3.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/733
Dated 5.07.2014
7.07.2014 SCIA
Submission of Design and
Drawing of superstructure
o minor bridge @ Ch.
152+835 as per clause 12.3
of CA.
4.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/774
Dated 5.07.2014
7.07.2014 SCIA
Submission of design and
drawing of pier P3 to P5 of
major bridge @ Ch. 23+155
as per clause 12.3 of CA.
5.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/775
Dated 5.07.2014
7.07.2014 SCIA
Submission of design and
drawing of Abutment A1 of
Minor Bridge @ Ch.
150+050 as per clause CA.
6.
ITNL-KNCL/PRJ/TECH/
CLO-579/2014/776
Dated:7.07.2014
9.07.2014 NHAI
Obstruction by Local
people in 4 – Lane work at
NauLakha
7.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/777
Dated :9.07.2014
10.07.2014 SCIA
Submission of design and
drawing of pier cap of
roper P3, P4, P6 & P7 of
Major Bridge @ Ch.
23+155 as per clause 12.3
of CA.
8.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/778
Dated:9.07.2014
10.07.2014 SCIA
Submission of compliance
related to foundation
(Piles) for Major bridge
26+184 , 23+155 and
130+165 .
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 42
9.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/780
Dated:8.07.2014
10.07.2014 SCIA Compliance for typical
cross section for highway
10.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/781
Dated:9.07.2014
10.07.2014 SCIA Monthly Progress Report.
11.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/782
Dated:10.07.2014
10.07.2014 SCIA Submission of Road
Accident Report – June 14
12.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/786
Dated:14.07.2014
15.07.2014 SCIA
Submission of Drawing for
Junction Improvements at
various Locations.
13.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/788
Dated: 14.07.2014
15.07.2014 SCIA
Submission of credentials
and third party test results
of vender Chambord for
Admixture
14.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/789
Dated: 14.07.2014
15.07.2014 SCIA
Submission of work
method statement for
Initial & Routine Load Test
for Pile.
15.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/791
Dated: 15.07.2014
16.07.2014 SCIA
Submission of Design and
Drawing of superstructure
of major bridge @ Ch.
26+784 with compliance as
per clause 12.3 of CA.
16.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/792
Dated:19.07.2014
19.07.2014 SCIA
Submission of
Environmental Monitoring
Report for the month of
June ‘14
17.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/793
Dated:18.07.2014
19.07.2014 SCIA
Compliance for
construction of gabion wall
by M/s Maccaffaerri
environmental solution
Pvt.
18.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/794
Dated:19.07.2014
19.07.2014 SCIA
Submission of monthly
progress report ( MPR) for
the month of June’14
19.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/795
Dated:19.07.2014
19.07.2014 SCIA Submission of COS for
major bridge @ 0+450.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 43
20.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/796
Dated:19.07.2014
19.07.2014 SCIA
Compliance of construction
of tecco system of slope
stabilization by M/s
Geobrugg India Pvt.
21.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/797
Dated:19.07.2014
19.07.2014 SCIA
Submission of COS for
sunder Nagar By Pass
22.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/800
Dated:19.07.2014
21.07.2014 SCIA
Submission of Plan &
Profile From KM. 0+00 to
01+00( R2 as per clause
12.3 of CA.
August, 2014
1
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/799
Dated 21.07.2014
25.07.2014 SCIA
Regarding Maintenance of
existing road Kiratpur- Ner
Chowk section (Km 73.200
to Km190.000)
2
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/808
Dated 4.08.2014
5.08.2014 SCIA Procurement of the site
3
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/810
Dated 5.08.2014
6.08.2014 SCIA
Submission of pile cap &
pier for P4to P6 as per
clause 12.3 of CA.
4
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/709
Dated 1.06.2014
8.08.2014 SCIA M/s K.L Steel Private Ltd.
5
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/811
Dated 7.08.2014
8.08.2014 SCIA
Submission of GAD of Ch.
14+927,15+120,15+165
&16+470 and box culver at
Ch. 14+925 as per clause
12.3 of CA.
6
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/812
Dated:25.07.2014
8.08.2014 NHAI
Submission of Design &
Drawing of abutment of
Ch. 152+100 as per 12.3 o f
CA.
7
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/814
Dated :7.08.2014
8.08.2014 SCIA
Submission of Bearing
Inspection Report of M/s
Magaba Bridge products
Pvt. Ltd. As per clause 12.3
of CA.
8
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/815
8.08.2014 SCIA
Submission of Geological
Mapping of Portals &
Tunnel.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 44
Dated:5.08.2014
9
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/816
Dated:4.08.2014
9.08.2014 SCIA Construction of Tunnel 5
with Umbrella Pipe Roofing
10
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/817
Dated:8.08.2014
9.08.2014 SCIA
Submission of Road
Accident Report for the
Month of July 2014.
11
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/818
Dated:9.08.2014
9.08.2014 SCIA
Submission of Drawing of
Superstructure for Major
Bridge at Ch. 23+155 as per
clause 12.3 of CA.
12
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/819
Dated:9.08.2014
9.08.2014 SCIA
Submission of Drawing &
Design of superstructure
for Major Bridge at ch.
130+165 as per clause
12.3 of CA.
13
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/820
Dated: 7.08.2014
9.08.2014 SCIA Submission of Undertaking
Letter.
14
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/821
Dated: 9.08.2014
9.08.2014 SCIA
Submission of QAP for
Welded Steel Bridge
Girders.
15
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/825
Dated: 13.08.2014
14.08.2014 SCIA
Labour Licence form –V
(Contract Labour
Regulation & Abolition Act,
1970.
16
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/827
Dated:14.08.2014
14.08.2014 SCIA
Submission of Monthly
Progress Report for the
Monthly of July ‘2014
17
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/828
Dated:14.08.2014
14.08.2014 SCIA MTC & Third Party Test
Report for M/s Drucar.
18
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/829
Dated:12.08.2014
14.08.2014 SCIA
Submission of GAD for
Mjb@ Ch. 1+137
LINKROAD (CA :1+085)
19
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/830
Dated:13.08.2014
14.08.2014 SCIA
Submission of Profile of
structural steel vendors
namely M/s Spacechem
Enterprise, M/s HMM Infra
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 45
& M/s Fodders Lloyd.
20
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/832
Dated:16.08.2014
20.08.2014 SCIA
Submission of
Geotechnical Report for
Below Mentioned
structures of KNCEL.
21
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/833
Dated:16.08.2014
20.08.2014 SCIA
Submission of Pier & Pipe
Cap for P4 toP8 and pier &
footing for P9 & P10 @ Ch.
130+165 as per clause 12.3
of CA.
22
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/839
Dated:21.08.2014
22.08.2014
SCIA
Submission of design and
drawing for Abutments LA1
– RA2 for MnB@ 14+708
23
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/840
Dated:22.08.2014
22.08.2014
SCIA
Submission of
Geotechnical Technical
Reports for various
bridges.
24
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/841
Dated:22.08.2014
23.08.2014 SCIA Submission of COS for
Major @ Ch. 0+450.
25 ITNL-KNCL/PRJ/TECH/
ICO-581/2014/843 23-08-2014 SCIA
Submission of
Geotechnical Technical
Reports for various
bridges.
26 ITNL-KNCL/PRJ/TECH/
ICO-581/2014/850 26-08-2014 SCIA
Submission of Pre Final
Electro Mechanical Report
of Tunnel-1, Tunnel-2,
Tunnel-3, Tunnel-4,
Tunnel-5.
27
ITNL-KNCL/PRJ/TECH/
CLO-579/2014/856
Dated:29.08.2014
28-08-2014 NHAI Shimla Utilization of Flyash.
28
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/858
28-08-2014 SCIA
Submission of Design Mix
M-15, M-25 and M-30 for
Section-III.
29
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/859
27-08-2014 SCIA
Submission of Design &
Drawing of Major Bridge at
Ch. 130+165 as per clause
12.3 of C.A.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 46
Dated:29.08.2014
30 ITNL-KNCL/PRJ/TECH/
ICO-581/2014/860 30-08-2014 SCIA
Compliance for
construction of Tecco
System for slope
stabilization by M/s
Geobrugg India Pvt. Ltd.
September, 2014
1.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/863
Dated 3.09.2014
3.09.2014 SCIA
Submission of third party
test report for M/S
Geobrugg Pvt. Ltd Wire
mesh.
2.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/866
Dated 4.09.2014
4.09.2014 SCIA
Submission of routine load
test on working pile of
Abutment 2 of major
bridge ch 0+450 as per
clauses 12.3 of C.A
3.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/870
Dated 9.09.2014
9.09.2014 SCIA
Submission of Road
Accident report for the
month of August 2014.
4.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/871
Dated 9.09.2014
9.09.2014 SCIA
Submission of Design and
Drawing of Superstructure
details at ch 23+155 of
40.0m
5.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/872
Dated 9.09.2014
10.09.2014 SCIA
Submission of Drawing of
superstructure details at ch
130+165 of 40.0m curved
as per clause 12.3 of CA.
6.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/873
Dated:9.09.2014
10.09.2014 NHAI
Submission of Revised
Drawing for bearings of
various bridge as per
clause 12.03 CA.
7.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/874
Dated :10.09.2014
10.09.2014 SCIA
Submission of Approval of
Borrow area -03 (B) at Ch.
179+550 LHS (Vertical
extension)of M/s GHV Pvt
Ltd.
8.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/867
Dated:5.09.2014
10.09.2014 SCIA
Request to release the
performance security bank
guarantee.
9.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/877
Dated: 11.09.2014
12.09.2014 SCIA
Submission of monthly
Progress Report for the
month of August 2014
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 47
10.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/882
Dated:17.09.2014
17.09.2014 SCIA Issue of Notice for COS as
per clause 16.2 of CA.
11.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/886
Dated: 20.09.2014
20.09.2014 SCIA
Approval of M/s Dashmesh
Industries Pvt. For Welded
wire Mesh .
12.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/887
Dated 20.09.2014
20.09.2014 SCIA
Submission of compliance
for observation raised in
GAD of bridge at km
16+700
13.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/890
Dated: 23.09.2014
24.09.2014 SCIA Naulakha Dadour proposal
for service road.
14.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/891
Dated: 25.09.2014
25.09.2014 SCIA
Submission of statutory
auditor certificate up to 15
Sep 2014.
15.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/894
Dated: 25.09.2014
25.09.2014 SCIA
Submission of third party
test report of cement
/steel/ water/ admixture of
M/s GHV Pvt. Ltd.
Concessionaire Outgoing
July, 2014
Sr. No.
Letter No. Date Issued To Subject Remarks
1.
SCIA/001/14-15/TL/ KNCEL-00416 Dated:8.07.2014
8.07.2014 KNCEL
Submission of design and drawing for slope protection system with reinforced soil as per clause 12.3 of CA.
2.
SCIA/001/14-15/TL/ KNCEL-00421 Dated:9.07.2014
9.07.2014 KNCEL
Submission of revised
Design ( R1) and Drawing
of Abutment A1 for minor
bridge at chainage 150+050
as per clause 12.3 of CA.
Review & Concurred
3.
SCIA/001/14-15/TL/ KNCEL-00422 Dated:9.07.2014
9.07.2014 KNCEL
Reg – Concurrence of source for procurements of TMT reinforcing bars from Jindal steel and power limited ( JSPL)
Review & Concurred
4.
SCIA/001/14-15/TL/ KNCEL-00427 Dated:16.07.2014
16.07.2014 KNCEL Plan for junction improvement at Ch. 12+573
5. SCIA/001/14-15/TL/ KNCEL-00428
17.07.2014 KNCEL
Submission of GAD Major Bridge at 23+155(23+082), 1+127(1+085) and
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 48
Dated:17.07.2014 CH.130+165(130+171.525) as per clause 12.3 of CA.
6.
SCIA/001/14-15/TL/ KNCEL-00429 Dated:22.07.2014
22.07.2014 KNCEL Submission of COS for Major Bridge @ 0+450.
7.
SCIA/001/14-15/TL/ KNCEL-00430 Dated:23.07.2014
23.07.2014 KNCEL
Concurrence of source (Material) for filter media, section-ii (M/S IL&FS Engineering Construction Co.)
Review & Concurred
8.
SCIA/001/14-15/TL/
KNCEL-00431
Dated:23.07.2014
23.07.2014 KNCEL
Construction chemicals (
Admixture ) Of M/S Cham
bond Pvt. Ltd.
9.
SCIA/001/14-15/TL/
KNCEL-00433
Dated:26.07.2014
28.07.2014
KNCEL Monthly Inspection of
project Highway.
10.
SCIA/001/14-15/TL/
KNCEL-00434
Dated:28.07.2014
28.07.2014
KNCEL
Compliance for construction
of tecco system for slope
stabilization by M/S
Geobrugg India Pvt. Ltd.
Review &
observations of
I.E. to be
incorporated
11.
SCIA/001/14-15/TL/
KNCEL-00435
Dated:31.07.2014
31.07.2014
KNCEL Progress of works.
August, 2014
1 SCIA/001/14-15/TL/ KNCEL-00437
2.08.2014 KNCEL
Procurement of fore poling pipes, swellex rock bolts and ISHB 200*200.
Reviewed & Concurred
2 SCIA/001/14-15/TL/ KNCEL-00442
8.08.2014 KNCEL
Submission work method statement for initial and routine Load test for pile.
Reviewed & Concurred
3 SCIA/001/14-15/TL/ KNCEL-00443
12.08.2014 KNCEL
Submission of GAD (R1) , Design and Drawing for pile , pile cap, pier from pierP2 to P 7 of major @ Ch. 26+184 as per clause 12.3of CA.
Reviewed & Concurred
4 SCIA/001/14-15/TL/ KNCEL-00444
12.08.2014 KNCEL
Submission of design and drawing of pier P1, p8, P9 for major bridge 26+184 as per clause 12.3 of CA.
Reviewed & Concurred
5 SCIA/001/14-15/TL/
KNCEL-00445 12.08.2014 KNCEL
Submission of design and
drawing of major bridge @
Ch.26+184 as per clause 12.3
of CA.
Reviewed &
Concurred
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 49
6 SCIA/001/14-15/TL/
KNCEL-00446 12.08.2014 KNCEL
Submission of design and
drawing of test pile for major
bridge @ ch 26+184 as per
clause 12.3 of CA.
Reviewed &
Concurred
7 SCIA/001/14-15/TL/
KNCEL-00447 12.8.2014 KNCEL
Submission of revised design
and drawing of pier LP1, RP1
& P2, for Major Bridge @ Ch.
152+100 as per clause 12.3
of CA.
Reviewed &
Concurred
8 SCIA/001/14-15/TL/
KNCEL-00448 9.08.2014 KNCEL
Submission of Dearing
inspection Report of Mageba
Bridge Products Pvt. As per
clause 12.3 of CA.
Reviewed &
Concurred
9 SCIA/001/14-15/TL/
KNCEL-00449 9.08.2014
KNCEL
Submission of pile Load Test
Report for Minor Bridge at
chainage 0+450 as per clause
12.3 of CA.
Reviewed &
Concurred
10 SCIA/001/14-15/TL/
KNCEL-00450 12.08.2014 KNCEL
Submission of Design and
Drawing of super structure
for Major bridge @ Ch.
152+100 as per clause 12.3
of CA.
Reviewed &
Concurred
11 SCIA/001/14-15/TL/
KNCEL-00453 12.08.2014
KNCEL
Concurrence of P&P ( R2 )
from Km. 0+000 to 1+000 as
per clause 12.3 of CA.
.
12 SCIA/001/14-15/TL/
KNCEL-00455 14.08.2014
KNCEL
Records of Escrow account
details at site office.
13 SCIA/001/14-15/TL/
KNCEL-00456 19.08.2014
KNCEL
I.E Monthly Inspection of
Project Highway.
14 SCIA/001/14-15/TL/
KNCEL-00457 19.08.2014
KNCEL
Pavement Design Report –
RP001, Rev-2 and Traffic
Report final reminder III.
Reminder
15 SCIA/001/14-15/TL/
KNCEL-00458 19.08.2014
KNCEL
Procurement of fore poling
Umbrella supports ) Pipes ,
swellex rock bolts ,SDA make
of M/s Drucar Inc. Supplied
by M/s Geo cornstarch Pvt.
Ltd. Mathur Road jasola ,
New Delhi.
Reviewed &
Concurred
16 SCIA/001/14-15/TL/
KNCEL-004559 20.08.2014
KNCEL
Comments on compliance
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 50
observation regarding pipe
roofing system.
17 SCIA/001/14-15/TL/
KNCEL-00460 20.08.2014
KNCEL
Site Inspection comments of
tunnel 5, Portal 2 fissures.
By Tunnel Design
Engineer
18 SCIA/001/14-15/TL/
KNCEL-00461 20.08.2014
KNCEL
Comments on compliance of
Tunnel -1 final design.
By Tunnel Design
Engineer
19 SCIA/001/14-15/TL/
KNCEL-00462 22.08.2014
KNCEL
Submission of GAD for
VIADUCT at Ch. 15+100
(Minor Bridges at
Ch.14+927,15+120,15+165
and Box Culverts Ch 14+925
20 SCIA/001/14-15/TL/
KNCEL-00463 22.08.2013
KNCEL
Over Topping flooding of
rain water over earthwork at
Nerchowk by pass.
21 SCIA/001/14-15/TL/
KNCEL-00464 22.08.2014
KNCEL
Submission of design and
drawing of abutments of
bridge at ch.152+100 as per
clause 12.3 of C.A.
IE Observations
to be
incorporated
22 SCIA/001/14-15/TL/
KNCEL-00465 22.08.2014 KNCEL Comments on Tunnel -1
By Tunnel Design
Engineer
23 SCIA/001/14-15/TL/
KNCEL-00466 26.08.2014 KNCEL
Submission of GAD of Bridge
at Km 16+700 as per clause
12.3 of CA.
IE Observations
to be
incorporated
24 SCIA/001/14-15/TL/
KNCEL-00467 26.08.2014 KNCEL
Site Inspection comment on
Tunnel -4 Portal 1 Slope.
By Tunnel Design
Engineer
25 SCIA/001/14-15/TL/
KNCEL-00468 26.08.2014 KNCEL
Procurement of Steel Ribs
(ISHB) 200x200) for umbrella
Roofing of tunnel from M/s
K.L Steels Pvt Ltd. Ghaziabad
(UP.)
26 SCIA/001/14-15/TL/
KNCEL-00470 29.08.2014 KNCEL
Concurrences of final design
and Drawing of tunnel -1
Reviewed &
Concurred
27 SCIA/001/14-15/TL/
KNCEL-471 29.08.2014 KNCEL
Representation of regional
unit balh , Himachal Kishan
sabha.
28 SCIA/001/14-15/TL/
KNCEL-472 29-08-2014 KNCEL
Comments on crack fall
along natural Slope near
Tunnel -4 Portal 2.
29 SCIA/001/14-15/TL/
KNCEL-473 30.08.2014 KNCEL
Concurrence of final design
and drawing of Tunnel -4.
September, 2014
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 51
1. SCIA/001/13-14/TL/ KNCEL-00481
10.09.2014 KNCEL Compliance for Typical Cross Sections for Highway.
2. SCIA/001/13-14/TL/ KNCEL-00482
13.09.2014 KNCEL
Regarding performance to Tecco system and sliding of slopes.
3. SCIA/001/14-15/TL/ KNCEL-00483
15.09.2014 KNCEL Monthly Inspection of project Highway.
4. SCIA/001/14-15/TL/ KNCEL-00484
16.09.2014 KNCEL
Submission of GAD for Major Bridge @ Ch. 1+0137 Link Road as per clause 12.3 of Ca.
5. SCIA/001/14-15/TL/
KNCEL-00485 22.09.2014 KNCEL
Requested for no
construction of culvert and
Drawing of water through
the land of the application at
Ch 166+840
6. SCIA/001/14-15/TL/
KNCEL-00487 23.09.2014 KNCEL
Approval of M/s Dashmesh
Ind. Pvt, for welded wire
mesh of Kiratpur Ner chowk
road project.
7. SCIA/001/14-15/TL/
KNCEL-00488 24.09.2014 KNCEL
Submission of GAD for minor
Bridge @ Ch 16+700 as per
clause 12.3 of CA.
8. SCIA/001/14-15/TL/
KNCEL-00489 25.09.2014 KNCEL
IE Monthly Inspection Report
of Project highway.
9. SCIA/001/14-15/TL/
KNCEL-00492 30.09.2014
KNCEL
Submission of design &
Drawing for MJB AT Ch
152+100 as per clause 12.3
8. MEETINGS/SITE VISITS/PRESENTATIONS: Meetings
July,2014
No meeting held in this month.
August-2014. Progress review Meeting held under the Chairmanship of member (Finance) on 22nd August, 2014 at
NHAI Head Quarter, New Delhi.
September-2014. Meeting held under the chairmanship of D.C (Mandi) regarding provisions for additional service road in Naulakha-Dadour section . GM cum PD (NHAI) , representatives of IE and Concessionaire attended the meeting on 30th September,2030 at the office of Dy.Commisionor,District-Mandi.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 52
Site Visits July,2014 Team Leader along with key professionals visited the site on 11th & 12th July, 2014 regarding progress of the Project and maintenance of the existing road. August-2014 Team Leader along with key professionals visited the site on 26th & 27th August, 2014 regarding
progress of the Project and maintenance of the existing road.
September-2014 Member Finance (NHAI), CGM (NHAI), PD cum GM (PIU -Shimla, NHAI). Project Director (KNCEL) ,Team
Leader (IE) have inspected the Project site on 27th September, 2014 and reviewed the progress of the
Project Highway.
Team Leader along with key professionals visited the site on 19th & 20th September, 2014 regarding
progress of the Project and maintenance of the existing road.
Team Leader visited the site on 17th, 18th & 19th June, 2014 regarding progress of the Project and maintenance of the existing road
9. EXECUTING AGENCY 9.1 Concessionaire
M/s IL & FS Transportation Networks Ltd is the Concessionaire. They have created SPV in the name of M/s KNCEL for this Project. KNCEL has mobilized staff and established its office at Bilaspur (HP). M/s KNCEL is executing agency for the package.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 53
9.2. EPC Contractor: Plant/Machineries/Resources
The Concessionaire has appointed three BOQ Contractor for execution of project works.
I. M/s IL &FS Engineering and Construction Company IL & FS Engineering House, 6-3-1186/1&2 Bugempet, Hyderabad-500016 Establishments of Base Camp at Village-Kuddi (Ghagas). 9 Nos of Concrete Batching Plant established, Stone crusher Plant, WMM Plant, Hot mix Plant to be erected. II. M/s Vijay Infra Limited Pankaj Galaxy, Second Floor Plot No-8, Sector-12 Dwarka, New Delhi-110075 Establishments of Base Camp at Masewal (Km 78.700 L/S 2km from existing NH-21) and mobilization of Equipments /Machineries are in progress at site. III. M/s GHV Projects (India) Pvt Limited AML Centre-I, 8 Mahal Industrial Areas Mahakali Caves Road, Andheri (East), Mumbai-400093 Establishments of Base Camp at Rampur (Kanaid), Near Sunder Nagar . Concrete Batching Plant, Stone Crusher Plant are operational WMM Plant erected and to be commissioned, Erection of Hot Mix Plant is in progress.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 54
10 . ORGANIZATION CHART (IE)
M/s Getinsa Ingenieria S. L. Spain in association with M/s Segmental Consulting & Infrastructure Advisory Pvt. Ltd.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 55
11. INDEPENDENT ENGINEER MOBILIZATION:
No. Position Name Date of Joining Key Personnel 1 Team Leader cum Sr. Highway
Engineer Mr. Sanjay Kumar Singh 28-09-2012
2 Sr. Bridge Design Engineer Mr. Ramesh Chand Gupta 16-10-2012
3 Resident cum Highway Engineer Mr. Dinesh Kumar Jain 09-01-2014, mobilized as replacement candidate
4 Highway Design Engineer Mr. Mangat Ram Verma 24-09-2012
5 Bridge/Structural Engineer Mr. Sanjay Kumar 16-10-2012
6 Sr. Tunnel Engineer Mr. Rajesh Kumar Thakur 01-10-2012
7 Tunnel Design Engineer Mr. Manuel Romana Garcia 05-06-2013
8 Geologist Mr. Kuldeep Singh Jamwal 20-11-2012
9 Sr. Pavement Specialist & Project Coordinator
Mr. Shanker Lal Mahipal 16-10-2012
10 Sr. Quality cum Material Expert Mr. Girish Chandra Tiwari 16-10-2012
11 Traffic & Transportation Expert Mr. Miguel Angel Lopez De Nieta
08-07-2014
12 Road Safety Expert Mr. Louis Polonia Sanchez 20-02-2014
13 Financial Expert Mr. Mihir Kumar Sahu 09-06-2014
14 Legal Expert Mr. Manish Kumar Sharma 10-04-2014
Sub-Professional
1 2
Survey Engineer-1 Survey Engineer-2
Mr. Ambresh Prasad Tripathi
15-12-2012
Mr. Vidhya Bushan 06-12-2012 (Demobilized in April 2014)
3 4
Assistant Highway Engineer-1 Assistant Highway Engineer-2
Mr. Hasan Ahmar 08-08-2014
Mr. Eshant Sonkar 29-04-2014
5 CAD Expert Mohd. Zia Saleem 14-11-2012
6 Environmental Engineer Mr. Raman Padha 20-11-2012
7 8
Assistant Bridge Engineer-1 Assistant Bridge Engineer-2
Mr. Hemant Sharma 05-06-2014
Mr. Pankaj Kumar Sharma 01-04-2014
9 10
Assistant Quality cum Material Engineer -1 Assistant Quality cum Material Engineer -2
Mr. Vinod Kumar Mishra 02-11-2012
Mr. Pradeep Kumar Pandey 02-11-2012
11 Electrical Engineer TBN To be Mobilized
12 HTMS/Toll Expert TBN To be Mobilized
13 Quantity Surveyor TBN To be Mobilized
14 Horticulture cum Landscaping Expert TBN To be Mobilized
15 16
Tunnel Engineer-1 Tunnel Engineer-2
Mr. Shashi Kumar 21-11-2012
Mr. Himanshu Kapoor 10-12-2012
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 56
No. Position Name Date of Joining 17 E&M Expert TBN To be Mobilized
18 Tunnel Ventilation Engineer TBN TBN
To be Mobilized
19 Tunnel Safety Engineer To be Mobilized Support Staff
1. Office Manager Mr. Ravi Sharma 16-10-2012 2. Accountant Mr. Ambikesh Tripathi 01-09-2013 3. Cashier Mr. Murari Lal Sharma 12-11-2012 4. Computer Operator Mr. Vikas Chand 17-10-2012 5. Steno Mr. Sanjeev Thakur 01-05-2014
6. Photo Copy Machine Operator Mr. Deepak Mishra 16-10-2012 7. Office Boy Mr. Lekh Ram 01-12-2012 8. Guard-1 Mr. Sanjay Kumar 01-11-2013 9. Guard-2 Mr. Raghuveer 01-04-2013
11.1 Invoice of Independent Engineer Services
Sl. Months Letter No Amount
Claimed(Rs) Amount Paid (Rs)
Amount Balance (Rs)
Remarks
1 June - 2014 SCIA/001/ 13-14/ TL/NHAI-00424
Rs 42,35,484.00 Paid Nil
2 July -2014 SCIA/001/ 13-14/ TL/NHAI-00441
Rs 41,56,302.00 Paid Nil
3 August-2014
SCIA/001/ 13-14/ TL/NHAI-00479
Rs 42,65,298.00 Paid Nil
Note: - Payment for foreign currency invoice for the month of June 2013 (Invoice no 9), August 2013 (Invoice no 11) , February 2014 (Invoice no 17), July 2014(Invoice no 22) and August 2014 (Invoice no 23) Total payment of $ 53041 USD is outstanding till date.
12. CONTRACT DATA.
12.1 SANCTION /APPROVAL OF PROJECT:
Project Cost (As per Concession Agreement) - Rs. 1818.47 Crs.
12.2 Civil works Contract Details:
a) Concessionaire Kiratpur-Ner Chowk Expressway Ltd. b) Contract Section Kiratpur to Ner Chowk Section of NH -21 From Km 73.200 to 186.500
c) Contract Length 82.4 Km + 1.971 Km (two lane Link Road to ACC cement Factory
Barmana)
d) Agreement /MOU
Date
16th March 2012
e) Agreement Amount Rs. 1818.47 Crs.
f) Bid quoted by the
bidder
Grant Rs. 134.56 Crs.
g) Date of signing 9th October 2012 (Financial closure 5th Sep 12, GM (J&K/HP) letter no.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 57
Substitution/Escrow
Agreement
NHAI/11016/9/2011/HP-2011/1110
h) Appointed Date 14 November,2013
i) Construction Period 36 Months (1095 days)
j) Performance
Security
Rs. 90.92 Crs.
Note- The Concessionaire has submitted the Statutory Auditor Certificate showing financial progress up to 15th September,2014 is enclosed for reference.
13. PROJECT PARAMETERS
S. No. Important
Parameters
Original Contract Revised
1.
Total Length
82.400 Km +1.971 Km ( Two Lane link Road)
2. Carriageway width 17.50 meter wide in Plain/Rolling Terrain Excluding
Median 14.00 Meter wide in Hilly/Mountainous
terrain Excluding Median Two lane Bi-directional
Tunnel as per IRC:SP91 :2010
3. Paved Shoulders 1.5 m
4. Earthen Shoulders 2.0 m
5. Median Width 2.50 m – 4.5 m
6. Pavement type Flexible/Rigid
7. Bridges/ Culverts
Major Bridges 17 Nos.
Minor Bridge 27 Nos +01 (Rehabilitation/Repair)
Box Culverts 64 Nos.
Slab Culverts 98 Nos. .
HP Culverts 55 Nos. (In addition to these 30 nos.
8. Flyover 01 No. at Km 142.680 (Length 41.375 meter)
9.
10.
Pedestrian/Cattle
Underpass
Tunnels
04 Nos
05 Nos
Tunnel T1 ( Km12.750 to Km14.550) 1800 meter
long with Escape Tunnels 1800 meter long,
Tunnel T2 (Km 15.785 to 16.275) 490 meter long
Tunnel T3 (Km 23.550 to Km24.130) 580 meter long,
Tunnel T4 (Km 148.500 to Km 149.750) 1250 meter
long.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 58
Tunnel T5 (Km 157.660 to Km 158.400) 740 meter
long.
14. UPDATED REVIEW OF DESIGN & DRAWING up to September,2014
Updated Status: Review of Drawing &Design of Kiratpur to Nerchowk Section of NH-21 Highways
Sl No
Chainage Length (Km)
Subject Remarks
1 000.000 to 012.000 12.00 Plan &Profile Drawing reviewed
&Concurred
P&P of 70.297
Km out of
84.38 Km as
submitted by
Concessionaire
reviewed
&Concurred
2 126.500 to 155+000 28.5 Plan &Profile Drawing reviewed
&Concurred
3 178.000 to 182.000 4.0 Plan &Profile Drawing reviewed
&Concurred
4 155.000 to 167+000 12.0 Plan &Profile Drawing reviewed
&Concurred
5 12.000 to 26+297 14.297 Plan &Profile Drawing reviewed
&Concurred
Total
Pavement Design
The pavement design for flexible pavement has been reviewed & Concurred for New alignment.
The Design of widening/strengthening of existing pavement and rigid pavement could not be
concurred due to non compliance of observations raised by IE.
Tunnels
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 59
Escape Tunnel- Design & drawing of escape tunnel design length 1802.25 meter (As per CA-1905 meter) parallel to Tunnel T1 has been reviewed &concurred.
Pre Final Design of Electromechanical works of Tunnel -1, T-2, T-3, T-4, and T-5 Submitted by the concessioner and is under review.
Structures.
Minor Bridges –
Minor Bridge General Arrangement Drawing Design
Submitted Concurred Submitted Concurred
24 16 16 14 14
Note 1. 5 Nos Minor Bridge have been converted into Major Bridge.
2. 3 Nos of Minor Bridges (Ch 14+708, 14+927, 15+077) and one Box Culvert Ch 14+970 has been
combined to make Viaduct.
Major Bridges –
Sl
No
Proposed
C.A
Chainage
Design
Chainage
Design
Length
(Meter)
Tunnels Subject Remarks
1 12.732 to
14.482 (1750M)
12.732 to 14.568
(1836M)
1836
Portals of T1 Final Design & Drawing
Reviewed & Concurred
Tunnel
T1(Linear
portion)
Final Design & Drawing
Reviewed & Concurred
2
15.810 to
16.460
( 650M)
15.783 to
16.277
(494M
494
Tunnel T2
(Linear portion)
including Portals
Final Design & Drawing is under
review.
3 23.700 to
24.100 (400M)
23.548 to 24.102 (554M)
554
Portals of T3 Final Design & Drawing
Reviewed & Concurred
Tunnel
T3(Linear
portion)
Final Design & Drawing
Reviewed & Concurred
4 148.580 to
149.990 (1410M
148.468 to 149.752 (1284M)
1284
Portals of T4 Final Design & Drawing
Reviewed and concurred.
Tunnel
T4(Linear
portion)
Final Design & Drawing
Reviewed and concurred Except
30 m Cut& Cover Portion.
Structural Design
calculation yet not
submitted for cut &
cover portion. (
volume 3 Final lining)
5 157.800 to
158.660 (860M)
157.658 to 158.402 (744M)
744
Portals of T5 Final Design & Drawing
Reviewed & Concurred
Tunnel
T5(Linear
portion)
Final Design & Drawing
Reviewed & Concurred
Total 5070 4912
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 60
Major Bridge General Arrangement Drawing Design
Submitted Concurred Submitted Concurred
20 20 17 20 15
Note I - 2 Nos Minor Bridge Converted to Major Bridge as per site condition II - 3 Nos Minor Bridge converted to Major Bridges by Concessionaire. III - Out of 15 Major Bridges, only 11 Major Bridges of all components have been
Submitted & concurred. Part Design & Drawing for Balance of 4 bridges as submitted has been reviewed & concurred.
Box Culverts:- Culverts of Size 2x2 have been concurred. Culverts of Size 3x3 have been concurred up to surcharge height 6.2 mts. Culverts of Size 3x2 have been concurred without surcharge. Slab Culverts:- Culverts of Single span up to 6 mts single vent have been concurred. Pipe Culverts:-
Culverts of Single Row have been concurred.
Gabions Wall:-
Design of Gabions wall up to 13.5 meter height has been concurred.
Retaining Wall
RCC retaining wall design up to 12 Mts height has been concurred.
RRM retaining wall design up to 4 Mts height has been concurred.
Condition Survey and Chainage demarcation for all Culverts have been completed for Entire corridor
except Sunder Nagar Bypass.
Construction Materials
Concurrence of Source for Hume pipes, Aggregates, cement, steel, Admixture, Gabions/Terramesh
System has Design & Drawing been accorded. Three Independent Laboratory for testing of materials,
Concrete Mix Designs for grade M15 /M20/M25/M30/M35/M40/M45/M50, design of Filter media have
been reviewed & concurred. Review of Materials for slop protection by Tecco System are under
Progress.
Utilities Shifting
The estimates of utility shifting I&PH Pipe lines from Km 8.8 to 26.2 ,Km154 to 183.7 & Electrical lines
from Km 25.5 to 138.9 (Bilaspur Sadar), 164.3 to 182.25 (Sunder Nagar Section) have approved by NHAI
and rest of the estimates for same has been also submitted to NHAI for approval.
Estimate of Existing Road repair
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 61
The estimates of road repair estimate have been approved by NHAI and road repair works are in
progress.
Inventory for Procurement of Site ( As per clause 10.3 of C.A)
An inventory of the site of the entire Project corridor has been done with Concessionaire
representative in accordance with clause 10.3 of C.A.
Change Of Scope (COS)
COS for additional two lane for Sundernagar Bypass, and Major Bridge at Ch 0+450 submitted by
Concessionaire for change of scope notice under clause 16.2 of C.A. The same has been reviewed and
observations made for the compliance of Concessionaire.
Additional service road in Naulakha-Dadour section as per the letter from NHAI has been proposed by
Concessionaire; same is verified and submitted to NHAI.
15. CONSTRUCTION ACTIVITIES. (Comments of Key Professionals on constructions activities) Construction Materials
The EPC Contractors M/S IECCL and M/S GHV Infra have established the stone crusher and
aggregate production for concrete works and road works is to be expedited. Aggregates for
concrete works are also being procured from local supplier. The Concessionaire is advised to buffer
the stocks of aggregates during monsoon season.
Earth works.
Kiratpur to Ner Chowk Road Project-NH 21
Present Status Road Work As On Date
30.09.14
Sr. No
Location(RHS)
Length RHS Status
Location(LHS)
Length LHS Status From To From To
1 0 820 820 Tree Cutting in Progress
0 820 820 Tree Cutting in Progress
2 820 870 50 Embankment 9th Layer in Progress
920 1300 380 C & G in progress
3 870 920 50 Embankment 7th Layer in Progress
1300 1920 620 C & G Complete
4 8700 9250 550 Excavation in Progress
1920 1960 40 Subgrade 1st Layer Completed
5 9340 11500 2160 Excavation in Progress
1960 2060 100 C & G in progress
6 11600 12700 1100 Excavation in Progress
2060 2150 90 Subgrade 1st Layer In Progress
7 17090 17140 50 Excavation in Progress
2150 4000 1850 C & G in progress
8 17235 18000 765 Tree Cutting in Progress
4000 6000 2000 Tree Cutting in Progress
9 18000 20500 2500 Tree Cutting 8700 9250 550 Excavation In
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 62
Completed Progress
10 20500 21000 500 Tree Cutting in Progress
9250 9340 90 Excavation In Progress
11 21000 21500 500 Excavation In Progress
9340 11500 2160 Excavation In Progress
12 25270 25340 70 Emb layer in progress
11500 11600 100 Sub Grade 2nd Completed
13 25340 25440 100 Emb layer in progress
11600 12700 1100 Excavation In Progress
14 26120 26300 180 Excavation in Progress
17090 17150 60 Excavation In Progress
15 126860 126980 120 C&G 17235 18000 765 Tree Cutting in Progress
16 126980 127000 20 Excavation in Progress
18000 20500 2500 Tree Cutting Completed
17 128850 129000 150 Excavation in Progress
20500 21000 500 Tree Cutting in Progress
18 129000 129110 110 Excavation in Progress
21000 21500 500 Excavation In Progress
19 129160 129580 420 Subgrade 2nd layer in progress
25254 25270 16 Excavation in progress
20 129750 129820 70 Emb layer in progress
25270 25340 70 Emb layer in progress
21 130540 130560 20 OGL 25340 25440 100 Emb layer in progress
22 130560 130680 120 Embankment Layer In Progress
25440 25650 210 Excavation in progress
23 130680 130870 190 OGL 26120 26300 180 Excavation in progress
24 130870 130980 110 Embankment Layer In Progress
126860 126980 120 C&G
25 130980 131110 130 Embankment Layer In Progress
126980 127000 20 Excavation in Progress
26 131170 131500 330 Clearing And Grubbing Completed
127100 127370 270 Emb layer in progress
27 131500 132490 990 OGL 128750 128850 100 Emb layer in progress
28 132490 132530 40 Embankment Layers In Progress
128850 129000 150 OGL
29 132530 133140 610 OGL 129000 129110 110 Excavation In Progress
30 133140 133160 20 Embankment Layers In Progress
129110 129580 470 Excavation in progress
31 133160 133180 20 Embankment Top 130540 130560 20 OGL
32 133180 133200 20 Excavation in progress
130560 130770 210 Excavation In Progress
33 133200 133300 100 Embankment Top 130770 130870 100 Clearing And Grubbing Completed
34 133300 133560 260 Excavation in progress
130870 131000 130 Embankment Layers in Progress
35 133560 133620 60 Subgrade 1st Layer in progress
131000 131100 100 Excavation In Progress
36 133720 133770 50 OGL 131100 131110 10 Embakment Layers in Progress
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 63
37 133830 133880 50 Excavation In Progress
131170 131460 290 Excavation In Progress
38 133880 133980 100 Excavation in progress
131460 132020 560 OGL
39 133980 134170 190 Excavation in progress
132020 132130 110 Excavation In Progress
40 134170 134240 70 OGL 132130 133200 1070 OGL
41 134240 134340 100 Embankment Layer In Progress
133200 133620 420 Subgrade layer in progress
42 134340 134390 50 Excavation in progress
133720 133770 50 OGL
43 134390 134500 110 Embankment Top in progress
133830 134100 270 Excavation In Progress
44 134500 134740 240 Excavation In Progress
134100 134170 70 Subgrade Top layer in progress
45 134780 134860 80 Excavation in progress
134170 134240 70 OGL
46 134860 135000 140 Excavation In Progress
134240 134340 100 Embankment Top in progress
47 135160 135250 90 Embankent 3rd Layer in progress
134340 134410 70 Excavation In Progress
48 135250 135400 150 Embankent 4th Layer in progress
134410 134540 130 Embankment Top in progress
49 135450 135700 250 OGL 134540 134740 200 Excavation In Progress
50 135700 135900 200 Excavation in Progress
134780 134860 80 Excavation In Progress
51 136150 136280 130 Excavation in Progress
134860 135000 140 Excavation In Progress
52 136280 136350 70 Embankment 25 th Layer completed
135160 135250 90 Excavtion in progress
53 136350 136430 80 OGL 135280 135310 30 Excavation In Progress
54 136430 136500 70 Embankment 19 th Layer In Progress
135310 135400 90 Clearing And Grubbing Completed
55 136500 136600 100 OGL 135450 135700 250 OGL
56 136600 136710 110 Clearing And Grubbing In Progress
135700 135900 200 Clearing And Grubbing Completed
57 136710 136920 210 OGL 136200 136250 50 Excavation In Progress
58 136920 137000 80 Clearing And Grubbing Completed
136250 136400 150 OGL
59 137000 137270 270 Clearing And Grubbing Completed
136400 136450 50 Embankment Layer in Progress
60 137270 137430 160 Embankment Layer In Progress
136450 136800 350 OGL
61 137430 137500 70 Excavation in Progress
136800 137270 470 Excavation In Progress
62 137500 137630 130 Embankment Layer In Progress
137270 137300 30 Embankment Layer In Progress
63 137630 137710 80 Embankment Layer In Progress
137300 137440 140 OGL
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 64
64 137710 137770 60 OGL 137440 137500 60 OGL
65 137770 137910 140 Embankment Layer In Progress
137500 137630 130 Embakment Layer in Progress
66 137910 137950 40 OGL 137630 137730 100 Excavation in Progress
67 137950 138040 90 Embankment Layer In Progress
137730 138050 320 Excavation in Progress
68 138040 138190 150 Excavation Work In Progress
138050 138190 140 Excavation in Progress
69 138250 138460 210 OGL 138190 138240 50 Embankment Layer In Progress
70 139000 141600 2600 OGL and Tree cutting in progress
138250 138300 50 Excavation in Progress
71 143550 143640 90 Clearing And Grubbing Completed
138300 138460 160 OGL
72 143640 143820 180 OGL 138460 138560 100 OGL
73 143820 143850 30 Embankment Top Layer In Progress
138560 138700 140 Excavation in Progress
74 143850 144010 160 S.G 2nd Layer Completed
138700 139000 300 OGL
75 144010 144060 50 Embankment 22th Layer In Progress
139000 141600 2600 OGL and Tree cutting in progress
76 144130 144250 120 Embankment Top Layer In Progress
143550 143640 90 Clearing And Grubbing Completed
77 144250 144990 740 Excavation In Progress
143640 143820 180 OGL
78 144990 145000 10 Excavation In Progress
143820 143850 30 Embankment Top Layer In Progress
79 145000 145130 130 Excavation In Progress
143850 144010 160 Subgrade 2nd Layer Completed
80 145130 145360 230 Embankment Top Layer In Progress
144010 144050 40 Embankment 15th Layer In Progress
81 145360 145410 50 Subgrade 1 Layer In Progress
144130 144200 70 Embankment Top Layer In Progress
82 145410 145500 90 Excavation In Progress
144200 144400 200 Excavation In Progress
83 145500 145580 80 Embankment 14th Layer In Progress
144400 144990 590 Excavation In Progress
84 145580 145950 370 Excavation In Progress
144990 145000 10 Embankment Top Layer In Progress
85 145950 146000 50 Excavation In Progress
145000 145130 130 excavation Completed
86 146000 146050 50 Embankment 26 th Layer In Progress
145130 145360 230 Embankment Top Layer In Progress
87 146050 146110 60 Excavation In Progress
145360 145410 50 Subgrade 2nd In Progress
88 146110 146130 20 Excavation In Progress
145410 145510 100 Excavation In Progress
89 146180 146240 60 Excavation In Progress
145510 145580 70 Embankment 12th Layer In Progress
90 146240 146300 60 Excavation In Progress
145580 145720 140 OGL
91 146300 146340 40 Embankment 14th Layer In Progress
145720 145820 100 Excavation In Progress
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 65
92 146340 146520 180 OGL 145820 145950 130 OGL
93 146520 146620 100 Excavation In Progress
145950 146000 50 Excavation In Progress
94 146620 146930 310 OGL 146000 146050 50 Excavation In Progress
95 146930 147010 80 Excavation In Progress
146050 146110 60 Excavation In Progress
96 147010 147040 30 Embankment 8 th layer in progress
146110 146130 20 Excavation In Progress
97 147040 147070 30 Embankment 8 th layer in progress
146130 146240 110 Excavation In Progress
98 147100 147210 110 Excavation In Progress
146240 146340 100 OGL
99 147210 147240 30 Embankment 6th layer in progress
146340 146520 180 Excavation In Progress
100 147240 147440 200 Excavation In Progress
146520 146620 100 Excavation In Progress
101 147520 147850 330 Excavation In Progress
146620 146720 100 OGL
102 147850 147950 100 Excavation In Progress
146720 146780 60 Excavation In Progress
103 147950 148400 450 Clearing And Grubbing Completed
146780 146930 150 OGL
104 149980 150260 280 Excavation In Progress
146930 147050 120 Slop Protection work in Progress
105 150260 151220 960 OGL 147050 147320 270 Excavation In Progress
106 151220 151250 30 Excavation In Progress
147320 147500 180 Slop Protection work in Progress
107 159400 159680 280 Excavation in progress
147500 147800 300 OGL
108 160340 160420 80 Excavation in progress
147800 147930 130 Embankment Layer In Progress
109 161090 161230 140 Excavation in progress
147930 148100 170 OGL
110 161680 161740 60 Excavation in progress
148100 148400 300 Clearing And Grubbing Completed
111 162000 162140 140 Excavation in progress
149980 150260 280 Excavation In Progress
112 162440 162650 210 Excavation in progress
150260 151220 960 OGL
113 163100 163200 100 Excavation in progress
151220 151250 30 Excavation In Progress
114 163200 163320 120 Excavation in progress
163480 163530 50 Excavation in progress
115 163480 163630 150 Excavation in progress
178380 178520 140 The works is held up in this section due to revision of FRL is required as the flood water has over topped near 1 meter height from sub grade level
116 163860 164060 200 Excavation in progress
178560 178850 290
117 178400 178530 130 The works is held up in this section due to revision of FRL is required as the flood water has over
178930 179020 90
118 178530 178545 15 179100 179300 200
119 178560 178700 140 179350 179450 100
120 178710 178850 140 179360 179450 90
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 66
121 178930 179020 90 topped near 1 meter height from sub grade level
179470 179600 130
122 179100 179450 350 179600 179700 100
123 179470 179600 130 179710 179780 70
124 179610 179700 90 179800 179870 70
125 179710 179780 70 179880 179980 100
126 179800 180000 200 179980 180000 20
127 180000 180100 100 180000 180080 80
128 180100 180200 100 180100 180200 100
129 180260 180450 190 180260 180450 190
130 180450 180550 100 180450 180550 100
131 180560 180600 40 180560 180580 20
132 180610 180640 30 180600 180640 40
133 180650 180680 30 180650 180690 40
134 180710 180820 110 180710 180750 40
135 180820 180980 160 180820 180980 160
136 181000 181250 250 181000 181250 250
137 181350 181450 100 181350 181450 100
138 181560 181780 220 181560 181780 220
139 181820 182000 180 181820 182000 180
In the section-1, tree cutting and earth works are in progress Since last inspection, construction of gabion wall has also taken up at Km 9+350, Tree cutting in 5 Km area has been completed . work progress is still behind the schedule. To catch up the shortfall in progress, concessionaire is required to augment the resources and expedite the work progress by proper planning to achieve the schedule target. In the Sections II & III , Construction of retaining wall and protection works should be expedite to make front for earth works, the earth works in cutting/filling section is also to be expedited , shifting of utilities/electric line should be done on priority basis to create the working area. Concessionaire is advised to plan the sequence of the works to ensure the construction activities without interruption.
Hill Cutting at Ch. 134+620 to 134+680
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 67
Structure Works
Box Culvert
Structure Component (Progress Up to September 2014)
Sr. No
Proposed Chainage
Excavation P.C.C Bottom Slab Walls Slab Returnwall Curtain
Wall
Back Filing/ Filter
Media
Flexible/ Rigid Appron
Stone Pitching
Remarks
1 137+526 complete complete complete In Progress
2 144+314 Complete complete complete A1 & A2 final
Lift completed
Slab Culvert
3 145+025 complete complete complete Completed Completed
4 145+125 complete complete complete complete complete Raft
Completed
5 145+325 complete complete complete complete complete RHS
Completed LHS 1st Lift
6 146+024 complete complete complete Completed Completed
7 146+845 complete complete complete complete complete RHS
Completed
8 147+310 LHS
complete LHS complete LHS Complete LHS Complete LHS Complete
9 147+578 complete complete BHS Complete BHS Complete BHS Completed Completed
10 148+444 complete complete complete A1 Ist & A2 3rd lift completed
11 150+885 LHS
complete LHS complete LHS Complete
3rd lift completed LHS
& RHS
12 178+550 complete complete complete complete complete complete Complete
d
13 178+920 complete complete complete complete complete Completed Complete
d
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 68
14 179+790 complete complete complete complete complete in progress
15 180+080
16 180+250 complete complete complete Completed Completed
17 180+555
18 180+690 complete complete complete complete complete in progress
19 180+990 complete complete complete complete complete Completed in
progress
20 181+350 Completed Completed LHS
Completed LHS
Completed LHS
Completed
21 181+500 complete complete complete complete complete in progress
22 181+800 complete
23 2+856 LHS
complete LHS complete LHS complete LHS complete LHS complete
24 3+000 LHS
complete LHS complete LHS complete LHS complete LHS complete
25 3+508 LHS
complete LHS complete LHS complete LHS complete LHS complete
26 7+508 LHS
complete LHS complete LHS complete
A1 & A2 final Lift completed
Slab
Culvert
27 7+383 LHS
complete LHS complete LHS Complete
A1 & A2 final Lift completed
Slab
Culvert
28 0+823 RHS
Complete RHS
Complete
Pipe Culvert
29 1+260 LHS
complete LHS complete
Head wall LHS Complete
Pipe
Culvert
30 2+348 LHS
complete LHS complete LHS Complete LHS Complete LHS Complete
31 3+864 LHS
complete LHS complete
32 5+511 LHS
complete LHS complete LHS Complete LHS Complete LHS Complete
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 69
Major Bridges
Major Bridge
Structure Component (Progress Up To September 2014) Sr. No
Proposed Chainage
Excavatuion P.C.C Foundation Substructure Superstructure Deck Slab
Crash Barrier
Expansion Joint
Remarks
1 0+450 Piling A1 & A2
completed A1& A2 Completed
Pile cap A1& A2 Completed
2 17+700
3 19+352
4 20+830
5 23+155
6 24+915
7 26+100
Piling in P7 in
Progress 8 no
completed, P9
and A2 Comp
P9&A2 PCC Completed
P9 & A2foundation Completed A2 Lifts
Completed A2 cap completed
8 130+171
Piling of P1
completed &
A1, P2,P3 & P4
in Progress
9 131+180
10 133+160 LP1 & RP1
Completed
LP1& RP1
Completed
LP1& RP1& LA1 Raft Completed Lifts in
progress
11 135+070 A2
,RP2Completed
A1& Rp2 Completed
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 70
12 141+100 LP1,LP2,LP3 &
RP1,RP2,RP3
LP1,LP2,LP3 &
RP1,RP2,RP3
Raft LP1,LP2,LP3 &
RP1,RP2,RP3
Lift of Pier LP1,LP2,LP3 &
RP1,RP2,RP3 in Progress
13 143+783 A1 Completed A1 Completed A1 & RP1 Raft
completed
14 152+100
15 152+835
16 155+880
17 157+750
18 158+775
19 178+013
Well Sinking
completed at
LA1 &
RA1,while In
progress inLP1
& LP2 ,RP2 &
LA2 & RA2,
bottom Pluging
of RP1
Completed
20 1+085
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 71
Minor Bridge
Minor Bridge
Structure Component (Progress Up to September 2014) Sr. No
Proposed Chainage
Excavatuion P.C.C Foundation Substructure Superstructure Deck Slab
Crash Barrier
Expansion Joint
Remarks
1 6+140 IN Progress LA 1& LA2
2 14+750
3 14+927
4 15+120
5 15+165
6 15+785
7 16+696
8 16+865
9 17+584
10 18+323
11 18+910
12 20+594
13 22+604
14 25+221
15 25+300
16 133+830 A2 LHS &RHS Completed A2 LHS & RHS
Completed
LA2& RA2 Raft BHS Completed Lifts in
progress
17 135+990 A1 LHS,RHS &A2 LHS
Completed A1, A2 LHS,RHS
Completed LA1 Raft Completed
18 138+330
19 138+828 P1,P2 completed P1 LHS & RHS
Completed Raft LP1, RP1
completed
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 72
20 144+090 LA1 &RA1 Completed LA1 &RA1 Completed
LA1 &RA1 Completed LA1&RA1
lifts in Progress
21 146+702 LP1,RP1&LA1, RA1
completed LP1,RP1& LA1 & RA1Completed
Raft LP1,RP1 ,LA1&RA1 completed
LP1&RP1 completed and A1 BHS
Lifts in progress
22 150+050 A2 completed & A1 in
progress A2 completed A2 raft completed
A2 4th lift in progress
23 153+820
24 179+060 Completed Completed Completed A21st lift
comp
Retaining Wall
Retaining Wall (September 2014 )
Sr. No Proposed Chainage Site Excavation
Wall Wall Wall Wall wall
PCC Raft 1st
(Lift(M-25)
2nd
(Lift(M-25)
3rd
(Lift(M-25)
4rd(Lift(M-25)
5th(Lift(M-25)
Remark
1 150+240 150+260 RHS Completed completed completed Completed Completed Completed completed
2 145+550 145+570 RHS Completed completed completed Completed Completed
3 145+700 145+715 RHS Completed completed completed Completed Completed Completed completed
4 145+715 145+734 RHS Completed completed completed
5 145+680 145+700 RHS Completed Completed Completed Completed Completed Completed completed completed
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 73
6 147+070 147+090
RHS Completed Completed Completed Completed Completed Completed completed completed
7 147+090 147+110
RHS Completed Completed Completed Completed Completed completed completed
8 147+110 147+130 RHS Completed completed completed Completed Completed Completed completed
9 147+130 147+150
RHS Completed Completed Completed
10 147+169 147+183 RHS Completed completed completed
11 147+183 147+200 RHS Completed completed completed
12 147+200 147+260
RHS Completed Completed Completed Completed Completed Completed completed completed Final
13 147+260 147+280
RHS Completed Completed Completed Completed Completed completed completed Final
14 147+280 147+290
RHS Completed
15 147+520 147+540
RHS Completed Completed Completed Completed Completed Final
16 147+540 147+582.5
RHS Completed Completed Completed Completed Completed Final
17 148+020 148+040
RHS Completed completed completed Completed Completed Final
18 148+040 148+060
RHS Completed Completed Completed Completed Completed completed
19 131+260 131+300
RHS
20 132+680 132+710
RHS Completed Completed Completed Completed
21 132+770 132+810
RHS Completed completed
22 137+080 137+100
RHS Completed completed completed Completed Completed Completed
23 137+100 137+120
RHS Completed Completed Completed Completed Completed Completed
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 74
24 137+120 137+140
RHS Completed Completed completed Completed Completed Completed
25 137+140 137+160
RHS
26 137+350 137+370
RHS Completed Completed completed Completed
27 138+200 138+300
RHS Completed
20 meter completed
28 138+460 138+480
RHS Completed
29 138+480 138+500 RHS Completed completed completed Completed Completed Completed
30 138+500 138+520 RHS Completed completed completed Completed Completed Completed final
31 138+520 138+560
RHS Completed Completed Completed Completed Completed Completed final
32 138+750 138+770 RHS Completed Completed completed Completed Completed Completed final
33 138+770 138+790 RHS Completed completed completed final
34 138+790 139+810 RHS Completed completed final
35 138+810 138+840 RHS Completed Completed completed Completed Completed final
36 138+840 138+860
RHS Completed Completed Completed Completed Completed Completed final
37 160+280 160+295 LHS Completed completed completed completed completed completed
38 160+295 161+310 LHS Completed completed completed completed completed completed
39 160+320 160+330 LHS Completed completed
40 160+530 160+550 LHS Completed completed
41 160+550 160+560 LHS Completed completed completed
42 160+560 160+570 LHS Completed completed completed Completed
43 160+570 160+580 LHS Completed completed completed Completed
44 160+580 160+590 LHS Completed completed completed Completed
45 160+590 160+600 LHS Completed completed completed Completed
46 160+600 160+620 LHS Completed completed completed Completed
47 160+810 160+820 LHS Completed completed completed
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 75
48 161+390 161+400 LHS Completed completed completed
49 161+400 161+420 LHS Completed completed
50 161+450 161+470 LHS Completed completed
51 161+470 161+490 LHS Completed completed
52 161+770 161+790 LHS Completed completed Completed completed
53 161+790 161+805 LHS Completed completed completed Completed Completed Completed
54 161+805 161+810 LHS Completed completed completed
55 161+810 161+820 LHS Completed completed completed Completed
56 161+860 161+880 LHS Completed completed completed Completed
57 161+880 161+890 LHS Completed completed completed Completed
58 162+320 162+360 LHS Completed Completed Completed Completed Completed
59 162+360 162+390 LHS Completed
60 162+390 162+400 LHS Completed completed completed In Progress
61 162+400 162+430 LHS Completed completed completed In Progress
62 166+610 166+620 LHS Completed completed completed
63 166+790 166+800 LHS Completed completed completed Completed Completed
64 166+800 166+810 LHS Completed completed completed Completed
65 166+810 166+820 LHS Completed completed completed Completed Completed Completed
66 166+820 166+830 LHS Completed completed completed Completed Completed Completed
67 166+830 166+850 LHS Completed completed completed Completed Completed Completed In
Progress
68 166+850 166+865 LHS Completed completed completed Completed Completed Completed In
Progress
69 127+360 127+380 RHS Completed completed completed
70 127+380 127+400 RHS Completed completed completed
71 129+740 129+760 RHS Completed completed completed
72 129+625 129+650 RHS Completed completed completed completed Completed completed
73 129+600 129+625 RHS Completed completed completed completed completed
74 129+720 129+730 RHS Completed Completed Completed completed
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 76
75 129+730 129+740 RHS Completed completed completed completed
76 178+090 178+100 RHS Completed completed completed completed
77 178+100 178+120 RHS Completed completed completed completed
78 178+120 178+150 RHS Completed completed completed
79 178+150 178+180 RHS Completed completed completed
80 178+180 178+210 RHS Completed completed completed
81 178+210 178+240 RHS Completed completed completed Completed
82 178+240 178+260 RHS Completed Completed
83 178+090 178+100 LHS Completed completed
84 178+100 178+120 LHS Completed completed
85 178+120 178+150 LHS Completed completed completed Completed
86 178+150 178+180 LHS Completed
87 178+180 178+210 LHS Completed Completed Completed Completed
88 178+210 178+240 LHS Completed Completed completed Completed
89 178+240 178+255 LHS Completed completed completed Completed
90 178+255 178+270 LHS Completed Completed completed Completed
91 178+270 178+320 LHS Completed Completed completed
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 77
The overall physical progress of structure works is behind schedule in spite some concrete works for
retaining wall and partly available section for major &minor structures. Concessionaire can expedite the
work progress by succeding activities on already ongoing works.
Construction of Retaing wall ( Raft) at Ch 145+550 to 570 RHS
Tunnel Works
Tunnel -T1
Portal -1 (Main &Escape Tunnel ) Slope Stabilization (Ch. 12+740 to Ch.12+700)
Frontal & lateral (right and left) slopes including all primary supports from Elevation 758 to 720 has been
completed except final coloring layer yet to be done.
Excavation of frontal & lateral slopes at an EL. 720 to 718.5, spraying of shotcrete, Fixing of wire
Mesh, sub horizontal drain, PG Rock Bolts (10m at Frontal slope and 4m at Lateral slope), pullout testing of rock
bolts, Laying of concrete for trapezoidal intercepting channel and half circular intercepting channel are under
progress. Multipoint borehole extensometers and inclinometers have been Installed and installation of optical
survey targets at portal benches are under progress.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 78
Main Tunnel T-1 (Portal P1 )
Monthly Progress of Tunnel 1 (P1 )
Sr.
No
Description of
works
Total
length
of
tunnel
(m)
Length
completed
up to last
month
(m)
Length
achieved
during
the
month
(m)
Cumulative
Length
(m)
Balance
(m) Remarks
1
Underground
Excavation
Heading
1800 02 07 09 1791
This tunnel will have total of
1836 m Length, being 1800
m of underground
excavation and an additional
18m each portal
Corresponding to the
ventilation buildings.
2 Benching
4
Geotextile and
water
proofing
5 Overt Lining
6 ventilation Slab
7
Invert Lining
(Rigid
Pavement)
8
Grouting
/Drainage/
E& M & other
Misc. Work.
Rock Classification : Main Tunnel Support class L
Rock primary Support: Umbrella pipe roof 12m long with 40mm dia Tor steel (fully grouted), ISHB
200X200mm Steel Rib erection at 1m c/c with two layers of wire mesh and 250mm thick shotcrete
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 79
Escape Tunnel (T1P1 side)
Monthly Progress of Escape Tunnel (T1-P1
Sr.No. Description of
works
Total length of
tunnel (m)
Length completed up to last
month (m)
Length achieved
during the
month (m)
Cumulative Length
(m)
Balance (m)
Remark
1
Under Ground Excavation Heading (full face)
1802.25 19 23 42 1760.25
2
Geotextile and water proofing membrane
3 Overt Lining
4 Invert Lining (Rigid Pavement)
5
Grouting /Drainage/ E& M & other Misc. Work.
Rock Classification : Escape Tunnel Support class C1
Rock primary Support: Lattice girder erection at 1m c/c with two layers of wire mesh and 250 mm
thick shotcrete applied in five layers and fixing of 5.0 m long Swellex & SN rock bolts.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 80
Inspection of Escape Tunnel T-1 Portal- 1 by Member (Finance)
Portal -2 (Main &Escape Tunnel Area) Slope Stabilization (Ch. 14+530 to Ch. 14+600)
Frontal & right lateral slope including all primary supports from Elevation 713 to 691 has been completed except final coloring layer yet to be done. From elevation 691 to 688 excavation of Frontal and lateral (right &left) slopes, spraying of shotcrete,
Fixing of wire mesh, sub horizontal drain, Drilling and installation of P.G Rock bolts ,pullout testing of rock
bolts, Laying of concrete for Trapezoidal intercepting channel and half circular intercepting channel and
installation of optical survey targets at portal benches are under progress.
Tunnel -3 Portal-1 Slope Stabilization (Ch. 23+550 to 23+570) Excavation of frontal and right lateral slopes including all supports from elevation 572 to 566 has been
completed except multi- point borehole extensometer, optical survey target and inclinometer.
From EL.566 to EL.560 Excavation of frontal & right lateral slopes ,Drilling & installation of 8 m long PG rock bolts(heavy galvanized) , fixing of high tensile steel wire mesh (Tecco G 65/3) with geomat,Laying of concrete for Trapezoidal intercepting channel , half circular intercepting channel and grouted stone works in stepped drain is under progress. Tunnel -4 Portal-1 Slope Stabilization (Ch.148+465 to Ch.148+500) Excavation of left lateral slope including all primary supports from Elevation 611 to 590 has been completed except final coloring layer yet to be done. Excavation of Frontal slope from El. 617.5 to 590 including primary supports has been completed except final coloring layer yet to be done.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 81
From EL.590 to EL.588 Excavation of frontal and lateral(right &left)slopes, spraying of shotcrete, Fixing of two layer wire mesh, sub horizontal drain, Drilling &installation of PG Rock Bolts ,pullout testing of rock bolts, Laying of concrete for trapezoidal intercepting channel are under progress. Installation of optical survey targets at portal benches are under progress.
Tunnel-5 (P2 side)
Monthly Progress of Tunnel 5 (P2 Side)
Sr. No. Description of
works
Total
length of
tunnel
(m)
Length
completed
up to last
month
(m)
Length
achieved
during the
month
(m)
Cumulative
Length
(m)
Balance
(m) Remarks
1
Underground
Excavation
Heading
744 18 18 36 708
2 Benching
4 Geotextile and
water proofing
3 Overt Lining
4 Invert Lining (Rigid Pavement)
5
Grouting
/Drainage/ E&
M & other Misc.
Work.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 82
Rock Classification : Tunnel-5 Support class L andC2
16. Review of Physical Progress
July-2014
Overall physical progress has slow down due to dominent rainfal in this region. However Concessionaire is advised to expedite the progress of works which may creat work fronts for coming dry season. Also buffer of aggregates is required in all the three sections to be utilised in coming month ahead.The progress of tunnel works has picked up but still behind the schedule and required to be expedited at all fronts. S-curve showing Physical progress- Independent Engineer vide letter No-SCIA/001/14-15/TL/KNCELl-00435 dated 31st July 2014 has already asked to submit the same and it is awaited from concessionaire. The letter written to the concessionaire is enclosed as annexure-A for reference.
Financial details of Escrow Account: Financial transactions of the Project through Escrow account is being submitted quarterly by Concessionaire and financial expert scrutinized up to April -30th 2014 carried out and accordingly achievement of financial Progress M.S.-01 as per concession Agreement vide letter no- SCIA/001/14-15/TL/NHAI-00404, Dated 26th June,2014, issued to the concessionaire. The same letter is enclosed as Annexure.-B for Reference. After submission of quarterly transaction details of Escrow Account from the Concessionaire, the same will be incorporated in subsequent MPR after Scrutiny of Financial expert I.E.
August-2014
This month also overall physical progress has not been picked up due to dominent rainfal in this region. Concessionaire is advised to expedite the progress of works in the area where work fronts may be created for coming dry season i.e continue with the working in construction of retaining wall/Gabion wall in all the three section expedite to increase the production of Tunnel works by working in day/night shifts. Expeditig the structure works
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 83
where no effect/minimal effect of rising of Govind Sagar reservoir and production/procurements of aggregates in all the three sections in order to have sufficient stock to be utilised in coming month ahead. S-curve showing Physical progress- Independent Engineer vide letter No-SCIA/001/14-15/TL/KNCELl-00435 dated 31st July 2014 has already asked to submit the same and it is awaited from concessionaire. Financial details of Escrow Account: Financial transactions of the Project through Escrow account is being submitted quarterly by Concessionaire and financial expert scrutinized up to April -30th 2014 carried out and accordingly achievement of financial Progress M.S.-01 as per concession Agreement vide letter no- SCIA/001/14-15/TL/NHAI-00404, Dated 26th June,2014, issued to the concessionaire.
September-2014
This month also overall physical progress has improved since last month however it is behind the schedule. Concessionaire is advised to expedite the progress in road works especially in section -1 where due to tree cutting sufficient work front is available. In section II &III the completed retaining wall sectin should be backfilled and road works can be started in sections , Put maximum man power in retaining walls to creat more work fronts as noe the rai nfall has receeded in coming momnth dry season ahead. Some more efforts is required to expedite the tunnel works by proper utilization of man power & machinaries. It is expected that in coming month the progress may be speed up by augmenting more resources in coming dry working season. S-curve showing Physical progress- Independent Engineer vide letter No-SCIA/001/14-15/TL/KNCELl-00435 dated 31st July 2014 and No-SCIA/001/14-15/TL/KNCELl-00489 dated 25th September 2014 has already asked to submit the same and it is awaited from concessionaire. Financial details of Escrow Account: Statutory Auditor Certificate certifying the financial progress up to 15th September, 2014 is enclosed (Annexure A) for your ready reference vide letter No ITNL-KNCEL/PRJ/TECH/ICO-581/2014/891 dated 15th September,2014
17 . Road Maintenance works of existing NH-21 (Km .73+200 to 186+500).
July-2014
73+200 to 100+00 Maintenance Works partialy balance .
100+000 to 121+700 Pot Holes ,DBM Completed .
131+800 to 142+000 Pot Holes DBM ,SDBC completed.
142+000 to 145+900 Pot Holes completed.
145+900 to 186+500 Maintenance works are in progress.
Quarterly Progress Report No. 8 : July-September, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 84
August-2014
Road Maintenance works during dry spells in section–I ,the balance repaire works with bituminouse materials was in progress at the end of this reporting period.Section-II &III were repaired with granular material,Concessionaire has assured that once the rainfall stops the balance portion will be repaired with bituminouse materials.
September-2014
Road Maintenance works in progress during the month in Nerchowk-SunderNagar Section-III and balance repair works with bituminouse materials yet to be taken up in Section-II (Ghagas to Slapper ).Concessionaire is advised to complete the balance road repair works for traffic worthy condition.