Navajo Generating StationOwners Initial Proposal

Timeline DiscussionGlen D. Reeves

February 4, 2011

2-04-11 1NGS Owners Initial Proposal - GDReeves

Page 2: NGS Owners Initial Proposal Timeline Discussion

EPA Rulings Expected

Key Challenges

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Co-Tenancy ExpiresLADWP Withdraws

Lease Expires323 Grants Expire

Coal Contract ExpiresTransmission Contracts Expire

LADWP Seeks Withdrawal

Environmental

Critical Agreements

Ownership

Equipment Installation

Requirement Expected

Water Service Contract Expires

2-04-11 2NGS Owners Initial Proposal - GDReeves

Page 3: NGS Owners Initial Proposal Timeline Discussion

2011

Timeline for Proposed Activities Surrounding NGS Efforts for Meeting the

Goal of the Regional Haze Rule

• Regional Haze Rule•Effective 2005•Natural Background Visibility by 2064•Class 1 Areas

(National Parks, Wilderness Areas)

2064

2-04-11 3NGS Owners Initial Proposal - GDReeves

53 Years

Page 4: NGS Owners Initial Proposal Timeline Discussion

2011 2064

Timeline for Proposed Activities

“Goal is to achieve natural background levels by 2064 (i.e., no manmade visibility impairment)”

53 Years

Every 10 years beginning in 2018 the previous SIP/FIP must be updated to account for current visibility and progress made toward the 2064 goal

2-04-11 4NGS Owners Initial Proposal - GDReeves

Page 5: NGS Owners Initial Proposal Timeline Discussion

2011 2064

Timeline for Proposed Activities

“Goal is to achieve natural background levels by 2064 (i.e., no manmade visibility impairment)”

2018 2028 2038 2048 2058

Every 10 years beginning in 2018 the previous SIP/FIP must be updated to account for current visibility and progress made toward the 2064 goal

2nd SIP/FIP update for RHR is

due in 2018

2-04-11 5NGS Owners Initial Proposal - GDReeves

Page 6: NGS Owners Initial Proposal Timeline Discussion

2011 2064

Timeline for Proposed Activities

2018 2028 2038 2048 2058

2nd SIP/FIP update for RHR is

due in 2018

NGS Site Lease Termination(12/23/19)

2-04-11 6NGS Owners Initial Proposal - GDReeves

Page 7: NGS Owners Initial Proposal Timeline Discussion

Key Durations

• Lease Negotiation and Navajo Nation Approval– Assume End of 2011

• NEPA Process – (EIS required)– Current average 5.9 years– Assume 6 years

• DOI Approval of all Grants and Leases– Assume 6 months

2-04-11 7NGS Owners Initial Proposal - GDReeves

Page 8: NGS Owners Initial Proposal Timeline Discussion

Key Durations

• Legal Challenges - Assume 2 years • Design, Procurement and Installation of SCR

– 43 months for 1st unit– 67 months for all 3 units

• Scheduled Unit Outages– Major Outages

• 2009, 2010, 2011• 2015, 2016, 2017• 2021, 2022, 2023• 2027, 2028, 2029

2-04-11 8NGS Owners Initial Proposal - GDReeves

Page 9: NGS Owners Initial Proposal Timeline Discussion

Key Owner Requirements

• No Major Capital Expenditures Until Lease is Approved, Grants are Issued, Ownership Resolved

• Tie-In Outages Occur Simultaneous with Planned Major Outages.– 2 Months Required for Tie-in Outages – 2 Months Required for Major Outages

2-04-11 9NGS Owners Initial Proposal - GDReeves

Page 10: NGS Owners Initial Proposal Timeline Discussion

2011

Key Dates

NGS Site LeaseTermination(12/23/19)

3 3 32 2 21 1 1

2-04-11 10NGS Owners Initial Proposal - GDReeves

Page 11: NGS Owners Initial Proposal Timeline Discussion

2011

Key Dates

NGS Site LeaseTermination(12/23/19)

3 3 32 2 21 1 1

Lease Negotiations and Approvals

(12/31/11)2-04-11 11NGS Owners Initial Proposal - GDReeves

Page 12: NGS Owners Initial Proposal Timeline Discussion

2011

Key Dates

NGS Site LeaseTermination(12/23/19)

3 3 32 2 21 1 1

Lease Negotiations and Approvals

(12/31/11)

NEPA Process(Comp - 12/31/17)

2-04-11 12NGS Owners Initial Proposal - GDReeves

Page 13: NGS Owners Initial Proposal Timeline Discussion

2011

Key Dates

NGS Site LeaseTermination(12/23/19)

3 3 32 2 21 1 1

Lease Negotiations and Approvals

(12/31/11)

NEPA Process(Comp - 12/31/17)

2-04-11 13NGS Owners Initial Proposal - GDReeves

Page 14: NGS Owners Initial Proposal Timeline Discussion

2011

Key Dates

NGS Site LeaseTermination(12/23/19)

3 3 32 2 21 1 1

Lease Negotiations and Approvals

(12/31/11)

NEPA Process(Comp - 12/31/17)

Legal Challenges(2 years ?)

2-04-11 14NGS Owners Initial Proposal - GDReeves

Page 15: NGS Owners Initial Proposal Timeline Discussion

2011

Key Dates

NGS Site LeaseTermination(12/23/19)

3 3 32 2 21 1 1

Lease Negotiations and Approvals

(12/31/11)

NEPA Process(Comp - 12/31/17)

2nd SIP/FIP update for RHR is

due in 2018 Legal Challenges(2 years ?)

2-04-11 15NGS Owners Initial Proposal - GDReeves

Page 16: NGS Owners Initial Proposal Timeline Discussion

2011

Proposed SCR Installation Period

NGS Site LeaseTermination(12/23/19)

3 3 32 2 21 1 1

Lease Negotiations and Approvals

(12/31/11)

NEPA Process(Comp - 12/31/17)

2nd SIP/FIP update for RHR is

due in 2018

SCR Design and installation

Duration

Legal Challenges(2 years ?)

2-04-11 16NGS Owners Initial Proposal - GDReeves

Page 17: NGS Owners Initial Proposal Timeline Discussion

2011

Installation Period Required if SCR is required in this BART

NGS Site LeaseTermination(12/23/19)

3 3 32 2 21 1 1

Lease Negotiations and Approvals

(12/31/11)

NEPA Process(Comp - 12/31/17)

2nd SIP/FIP update for RHR is

due in 2018

SCR Design and installation

Duration

Legal Challenges(2 years ?)

2-04-11 17NGS Owners Initial Proposal - GDReeves

Page 18: NGS Owners Initial Proposal Timeline Discussion

2011

IF Owners don’t take Risk of installing SCR without knowing NEPA outcome

NGS Site LeaseTermination(12/23/19)

3 3 32 2 21 1 1

Lease Negotiations and Approvals

(12/31/11)

NEPA Process(Comp - 12/31/17)

2nd SIP/FIP update for RHR is

due in 2018

SCR Design and installation

Duration

Legal Challenges(2 years ?)

2-04-11 18NGS Owners Initial Proposal - GDReeves

Page 19: NGS Owners Initial Proposal Timeline Discussion

2011

Proposed SCR Installation Period

NGS Site LeaseTermination(12/23/19)

3 3 32 2 21 1 1

Lease Negotiations and Approvals

(12/31/11)

NEPA Process(Comp - 12/31/17)

2nd SIP/FIP update for RHR is

due in 2018

SCR Design and installation

Duration

Legal Challenges(2 years ?)

2-04-11 19NGS Owners Initial Proposal - GDReeves