13
Ngauranga to Petone Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation

Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

Ngauranga to Petone Cycleway/Walkway Upgrade

A component of the Hutt Corridor Plan currently out for consultation

Page 2: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing
Page 3: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

The ‘Missing Link’ in the regional Cycle network is going to be fixed

Upgrade and complete walkway/cycleway

Ngauranga to Petone

The Great Harbour Way Coalition is thrilled

Page 4: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

Today

Page 5: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

When Complete

Page 6: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

The case for the project is very strong

• It will fix the ‘missing link’ in our key cycling/walking networks

Page 7: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

The case for the project is very strong

• It will fix the ‘missing link’ in our key cycling/walking networks

• For every dollar invested there will be a return of more than 3 dollars – NZTA

– Sole contribution to benefits -Biking to work

Page 8: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

The case for the project is very strong

• It will fix the ‘missing link’ in our key cycling/walking networks

• For every dollar invested there will be a return of more than 3 dollars – NZTA

– Sole contribution to benefits -Biking to work

• Feeling safe and comfortable on the separated path will unlock further long term community benefits– Biking for fun

– Family outing

– Cycle tourism

Page 9: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

The TimingScheduled for

Investigation 2012-13 Construction 2013-15

Page 10: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing
Page 11: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

We sayBring it forward a year

Page 12: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing

Submissions close June 15

GHW will submit

We encourage other submissions

•Rotary Club of Hutt City

•Hutt River Trail

•Individuals

•Press releases

•Facebook page for supporters

•Other media

Page 13: Ngauranga to Petone Cycleway/Walkway Upgradegreathar/wp-content/... · Cycleway/Walkway Upgrade A component of the Hutt Corridor Plan currently out for consultation. The ‘Missing