NFL Panipat PDD_ 25 Oct- 2011

Embed Size (px)

Citation preview

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    1/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 1

    CLEAN DEVELOPMENT MECHANISM

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD)

    Version 03 - in effect as of: 28 July 2006

    CONTENTS

    A. General description of project activity

    B. Application of a baseline and monitoring methodology

    C. Duration of the project activity / crediting period

    D. Environmental impacts

    E. Stakeholders comments

    Annexes

    Annex 1: Contact information on participants in the project activity

    Annex 2: Information regarding public funding

    Annex 3: Baseline information

    Annex 4: Monitoring plan

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    2/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 2

    SECTION A. General description of project activity

    A.1. Title of the project activity:

    >> Feed Switch from FO/LSHS to Natural Gas for Ammonia & Urea Manufacture at Panipat 1

    Version -1

    Date: 1st

    September 2011

    A.2. Description of the project activity:

    >> National Fertilizers Limited (NFL) is one of the leading producers of Nitrogenous Fertilizers in India.

    NFL is presently operating a ammonia and urea plant at Panipat in India the feed stock / fuel used at the

    plant is Heavy Fuel Oil/Low Sulphur Heavy Stock. Coal is used for captive power and steam generation.

    The support / auxiliary fuel used in the coal fired boiler is the heavy oil.

    The project activity involves switching of feed stock and support fuel from Heavy fuel oil to Natural Gas.Project activity will involve modifications/changes in ammonia reforming section and the associated

    utilities. The objective of the project activity is to shift to the lesser carbon intensive feed stock and

    support fuel for production of ammonia which leads to reduction in GHG emissions

    Pre Project Scenario

    In the pre project scenario, Heavy fuel oil is used as the feed stock and support fuel for production of

    ammonia. Heavy oil is gasified with oxygen (produced separately in an air separation unit) and steam to

    produce the gaseous streams consisting H2, CO2, CO, Ar and other inert gases. Heat contained in this hot

    gas stream is recovered in the waste heat boiler. Subsequently CO2 is separated from the gaseous stream

    and argon and other inert gases are removed from the stream. Nitrogen from the air separation unit is

    added back to the gaseous stream to get the synthesis gas having hydrogen to nitrogen ratio of 1:3 (molar

    ratio). The synthesis gas is then made to react in the ammonia reactor to produce ammonia. Heavy oil is

    also used as a support fuel in the combined heat and power plant.

    Post Project Scenario

    After the implementation of project activity, Natural gas will be used as the feed stock and support fuel.

    The technology for production of ammonia using natural gas as the feedstock is different from the

    existing technology and this will require process changes in existing equipment as well as incorporation

    of new processes like Methanation section, etc.

    In the process of changeover from Heavy oil to Natural Gas, key physical changes which will be

    incorporated in the ammonia plant for the implementation of project activity are as follows:

    A new Desulphurizer section will be installed

    A new primary reformer and secondary reformer will be installed A new S-300 convertor will be installed in the existing synthesis loop

    A new CO2 removal/ recovery unit(MDEA wash) will be installed

    A new Methanation section will be installed

    A new Synthesis booster compressor will be installed

    A new Medium pressure(40K) loop boiler in synthesis loop will be installed

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    3/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    4/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 4

    The technology for production of ammonia which will be used for project is the world class and will lead

    to reduction in the consumption of hydrocarbons for the production of same volume of ammonia. Thus

    the technology will also lead to the consequent reduction in the emissions of heavy metals, particulatesand other pollutants associated with the use of hydrocarbons.

    A.3. Project participants:

    >>

    Name of Party involved (*)

    ((host) indicates a host party)

    Private and/or public entity

    (ies)

    Project participants (*)

    (as applicable)

    Kindly indicate if the Party

    involved wishes to be

    considered as project

    participant

    (Yes/ No)

    Government of India (host party) National Fertilizers Limited No

    A.4. Technical description of the project activity:

    A.4.1. Location of the project activity:

    >> Panipat, India

    A.4.1.1. Host Party(ies):

    >> Government of India

    A.4.1.2. Region/State/Province etc.:

    >> State: Haryana

    A.4.1.3. City/Town/Community etc.:

    >> PanipatA.4.1.4. Details of physical location, including information allowing the unique

    identification of this project activity (maximum one page):

    >> The proposed CDM project activity is located in National Fertilizers Limited, District Panipat,Haryana State, India. The nearest airport is Indira Gandhi International airport New Delhi and nearest

    railway station is Panipat railway station.

    The location map is given below.

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    5/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 5

    Plant Address:

    National Fertilizers Limited,

    Gohana Road,

    Panipat,

    Haryana-132106.NFL Plant Geo - Coordinates: 2921'30"N 7657'40"E

    A.4.2. Category(ies) of project activity:

    >> The project activity switches high carbon intensive feed stock and support fuel to lower carbon

    intensive feed stock and support fuel and hence reduces the GHG emissions to the atmosphere for the

    same production of ammonia. According to the CDM modalities, the project activity falls under

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    6/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 6

    Approved Large scale methodology AM0050. The project activity corresponds to sectoral scope 5,

    Chemical Industry of the UNFCCC sectoral scope list for project activities.

    A.4.3. Technology to be employed by the project activity:

    >> National Fertilizers Limited has hired M/sHalder Topse, who is the world renowned technology

    provider in fertilizer plant and have provided technology to many of the fertilizer units in India and

    abroad. National Fertilizer Limited has incorporated all necessary safety features which are required for

    the safe operation of the plant.

    The Purpose of Project activity is to adopt a cleaner and efficient technology and reduce the GHG

    emissions by switching over of feed and support fuel from heavy oil to natural gas. The change over from

    heavy oil to natural gas will reduce GHG emissions due to reduced generation of CO 2 in the reformer

    section, boilers.

    In the production process of ammonia using hydrocarbons as feed stock involves following sequential

    steps:

    Reforming of hydrocarbon with steam and oxygen / air followed by separation of carbon dioxide

    and other impurities from the output gaseous stream of the reformer to produce synthesis gas.

    Conversion of synthesis gas to Ammonia in a reactor

    Separation of ammonia and recycling of the unreached synthesis gas back to the ammonia reactor

    Apart from these main operations mentioned above the auxiliary operations in typical ammonia plant

    may include the following:

    Use of waste heat for generation of steam

    Onsite generation of power and balance steam in combined heat and power plant leading to

    emissions of GHG

    Operation of boilers for generation of process steam leading to emissions of GHG

    In the reforming section, hydrocarbon feed is reformed to make CO2, Hydrogen and Nitrogen. The CO2 is

    then separated from the main gaseous stream in the CO2 recovery section. The gaseous stream also

    contains some traces of CO, Argon and other inert gases and these traces are removed before production

    of ammonia in the synthesis reactor.

    Pre Project Scenario

    In the scenario prior to the implementation of Project activity, Heavy oil is used as feedstock for the

    reforming. The generation of ammonia using Heavy oil as feed involves following steps:

    Gasification of heavy oil

    CO Shift

    CO2 recovery section Ammonia Synthesis

    The process diagram shown below gives the details about the process equipment and various GHG

    emissions sources in the existing practice of heavy oil as feed stock

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    7/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 7

    Emission - Utility

    Emission - Grid

    Combined

    Heat and

    Power(CH

    P) Plant /

    Process

    Boilers /

    Waste

    HeatRecovery

    Boilers

    Fossil Fuel for Boilers

    (coal)

    Gasifier

    Separation

    of CO2

    Ammonia Reactor

    Urea Production

    Supply Header / Hydrocarbon Storage Bunker

    Heavy Fuel Oil

    Emission

    Feedstock

    CO2 In Excess of

    that used for

    Urea

    Production

    Air

    CO2

    Power From / To Grid

    Ammonia

    Synthesis Gas

    CO2

    Emission - Heat

    Auxiliary /

    Support FuelFeed / Fuel

    Urea

    Hot Gas Stream

    Waste

    Heat

    Recovery

    Pre Project Scenario

    CO2

    The main GHG emission sources are emissions due to venting of Excess CO2 over and above used for

    urea production , GHG emissions from the utilities like steam generators, GHG emissions due to import

    of power from Grid.

    A detailed residual life cycle assessment was carried out by National Fertilizers Limited and all the

    existing units had adequate lifetime. The decision taken by NFL Panipat is based on the urge to adopt the

    cleaner and efficient technology which will reduce consumption of hydrocarbons and hence the GHG

    emissions for the same volume of production.

    Post Project Scenario

    In the scenario after the implementation of Project activity, Natural Gas will be used as a source of feed

    and support fuel for the production of ammonia. The generation of ammonia using Natural Gas as feed

    involves following steps:

    Feed gas compression, pre heating and desulphurization section

    Primary and Secondary Reforming

    Process air compression

    CO Shift conversion

    CO2 recovery section

    Methanation section

    Dryer and Purifier section

    Ammonia Synthesis

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    8/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 8

    Loop purge ammonia recovery

    Ammonia refrigeration

    Process condensate stripper

    The process diagram shown below gives details about the process equipment and various GHG emissions

    sources after implementation of project activity with Natural Gas as feed stock and support fuel.

    Emission - Utility

    Emission - Grid

    Combined

    Heat and

    Power(CH

    P) Plant /

    Process

    Boilers /

    Waste

    Heat

    Recovery

    Boilers

    Fossil Fuel for Boilers

    (coal)

    Gasifier

    Separation

    of CO2

    Ammonia Reactor

    Urea Production

    Supply Header / Hydrocarbon Storage Bunker

    Natural Gas

    Emission

    Feedstock

    CO2 In Excess of

    that used for

    Urea

    Production

    Air

    CO2

    Power From / To Grid

    Ammonia

    Synthesis Gas

    CO2

    Emission - Heat

    Auxiliary /

    Support FuelFeed / Fuel

    Urea

    Hot Gas Stream

    Waste

    Heat

    Recovery

    Post Project Scenario

    CO2

    The main GHG emission sources at after the project activity remains the same however the emission

    intensity reduces.

    The project activity is being implemented in an existing ammonia production unit and involves

    replacement of the existing front end section of ammonia plant with integration to existing back end

    section of ammonia plant with a new S -300 convertor and MP boiler, keeping the existing off site and

    utilities for production of ammonia.

    List of new section that will be added for the implementation of CDM project activity are as follows:

    Desulphurization section

    Modification in the reformer section

    CO2 removal/recovery unit (MDEA wash)

    Methanation section

    Synthesis gas booster compressor

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    9/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 9

    S-300 convertor

    Medium Pressure loop boiler in synthesis loop

    Ammonia recovery unit MP process condensate stripper

    Natural gas pipeline network

    The list of equipment that will become redundant/replaced after the implementation of project activity

    are as follows:

    Oxygen generation plant and its associated utilities

    Front section of Ammonia plant

    Rectisol unit of CO2 removal

    Heavy oil storage section and piping network

    In the absence of the project activity, NFL Panipat would have continued to use current practice of heavy

    oil as feed stock and support fuel hence pre project scenario is also the baseline scenario.

    Emission reduction due to the project activity would happen due to lower carbon intensity of Natural gas.

    A.4.4. Estimated amount of emission reductions over the chosen crediting period:

    >> The estimated amount of emission reduction due to the proposed project activity for the ten (10) years

    under fixed crediting period option would be 4517960 tCO2e as per details on annual emission reductions

    provided below:

    Years Annual estimation of emission

    reductions in tonnes of CO2 e

    2012-13 451796

    2013-14 451796

    2014-15 451796

    2015-16 451796

    2016-17 451796

    2017-18 451796

    2018-19 451796

    2019-20 451796

    2020 -21 451796

    2021-22 451796

    Total estimated reductions

    (tonnes of CO2e)

    4517960

    Total number of crediting years 10 years (Fixed)Annual average over the crediting

    period of estimated reductions

    (tonnes of CO2e)

    451796

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    10/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 10

    A.4.5. Public funding of the project activity:

    >> There is no public funding involved in the proposed CDM project activity.

    SECTION B. Application of a baseline and monitoring methodology

    B.1. Title and reference of the approved baseline and monitoring methodology applied to the

    project activity:

    >> The title of the baseline and monitoring methodology applicable to the proposed project activity is

    Technology up-gradation and / or Fuel / Feed switch in integrated Ammonia manufacturing industry---

    Version XX.

    Reference: AM0050, Version XX, Sectoral Scope: 05.

    It has been referred from the list of approved methodologies for CDM project activities in the UNFCCC

    CDM website (http://cdm.unfccc.int/methodologies/PAmethodologies/approved.html).

    AM0050 (Version XX) draws upon the following tools, which have been used in the PDD:

    Combined tool to identify the baseline scenario and demonstrate additionality

    Tool to calculate the emission factor for electricity system

    B.2. Justification of the choice of the methodology and why it is applicable to the project

    activity:

    >> The proposed CDM project activity is a feed and a support fuel switch over from heavy oil to natural

    gas and meets the applicability and non-applicability conditions of the chosen methodology (i.e. AM0050

    VersionXX) as follows

    Applicability Condition as per the approvedmethodology

    Scenario in the Project activity

    The project activity is carried out in an ammonia

    plant, where, ammonia is sold as a merchant product

    or converted to derivatives e.g., urea, ammonium

    nitrate etc.

    The project activity is carried out in an existing

    ammonia plant hence this condition is applicable

    to project activity

    Ammonia manufacturing plants that are not

    prevented by local regulations from using feedstock

    and /or fuel other than natural gas

    The project activity does not prevented by any

    local regulation to switch to Natural gas and hence

    this condition is applicable to project activity.

    Project activities that do not result in the increase ofthe production capacity of ammonia plant. However,

    the design capacity of ammonia plant may increase

    marginally (say maximum up to 10 % of the design

    capacity) and remain same throughout the crediting

    period due to the need for line balancing. This is

    required to be validated by the validating DOE by

    In the Project scenario, name plate capacity of

    ammonia plant will remain within the prescribedlimits as defined in the methodology hence this

    condition is applicable.

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    11/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 11

    validating the design capacity of the ammonia reactor

    before and after the project.

    .

    Natural gas is sufficiently available in the region or

    country, e.g. future natural gas based capacity

    additions, comparable in size to the project activity,

    are not constrained by the use of natural gas in the

    project activity1;

    NFL has signed a long term MOU with Gas

    Authority of India Limited(GAIL) for the reliable

    and continuous supply of Natural Gas and hence

    there will be ample gas available for the project

    activity.

    The ammonia manufacturing plant is an existing

    plant with a historical operation of at least three years

    prior to the implementation of the project activity;

    NFL is operating this plant since 1974. The last

    three year production details will be made

    available to DOE during validation hence this

    condition is applicable.

    Although Project activities may result in changes in

    the production process but there is no change in the

    capacity and product mix to produce different

    product types e.g., the proportion of a particular type

    of product produced in the total product mix should

    remain same before and after the implementation of

    project activity.

    The capacity for different product types and mix

    before and after the implementation of project

    activity remains same hence this condition is

    applicable

    Prior to the implementation of the project activity, nonatural gas has been used in the ammonia

    manufacturing plant

    No Natural Gas has been used prior to the start of

    project activity hence this condition is applicable

    In case of historic use of ammonia for the production

    of urea, percentage of ammonia used for production

    of urea historically should not decrease (except minor

    variation of up to 5%)

    The percentage of ammonia consumed for the

    production of Urea will not decrease hence this

    condition is applicable.

    B.3. Description of the sources and gases included in the project boundary:

    1In some situations, there could be price-inelastic supply constraints (e.g. limited resources without possibility of

    expansion during the crediting period) that could mean that a project activity displaces natural gas that would

    otherwise be used elsewhere in an economy, thus leading to possible leakage. Hence, it is important for the project

    proponent to document that supply limitations will not result in significant leakage as indicated.

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    12/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 12

    >> According to the approved methodology AM0050 (Version xx, the spatial extent of the project

    boundary includes the ammonia plant and power generation plant.

    Emission - Utility

    Emission - Grid

    Combined

    Heat and

    Power(CH

    P) Plant /Process

    Boilers /

    Waste

    Heat

    Recovery

    Boilers

    Fossil Fuel for Boilers

    Gasifier / Reformer

    Separation

    of CO2

    Ammonia Reactor

    Ammonia Storage

    /Derivative

    Production

    Supply Header / Hydrocarbon Storage Bunker

    Hydrocarbon Feedstock /Fuel

    Emission Feedstock

    CO2 In Excess of

    that used for

    Derivatives

    Air

    CO2

    Power From / To Grid

    Ammonia

    Synthesis Gas

    CO2

    Emission - Heat

    Auxiliary /

    Support FuelFeed / Fuel

    Ammonia /

    Ammonia

    Derivative

    Hot Gas Stream

    Waste

    Heat

    Recovery

    Project Boundary

    CO2

    Source Gas Included? Justification / Explanation

    Baseline

    Processing

    of feedstock

    CO2 Yes Main emission source. CO2 is produced in the reforming

    of the feed

    CH4 No Negligible fugitive CH4 emissions may occur during the

    processing of the feed. These emissions (if any) would be

    essentially the same as in the project activity. Therefore,

    they are excluded for simplification.

    N2O No Not applicable.

    Fuel used infurnaces

    (thermal

    energy)

    CO2 Yes Depending upon the process technology used in the

    baseline it may be a main emission source (flue gases) due

    to the combustion of fossil fuel to provide thermal energy

    for feed treatment (sulphur removal in hydrotreater andprimary desulphurization unit and the synthesis-gas

    production).

    CH4 No Excluded for simplification, this is conservative.

    N2O No Excluded for simplification, this is conservative.

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    13/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 13

    Source Gas Included? Justification / Explanation

    Fuel used inboilers

    (Steam and /

    or power

    generation)

    CO2 Yes Main emission source.

    CH4 No These emissions are expected to be the same or higher as

    compared to the project scenario. Excluded for

    simplification and because this is conservative.

    N2O No These emissions are expected to be the same or higher as

    compared to the project scenario. Excluded for

    simplification and because this is conservative.

    Grid

    Electricity

    requirement

    CO2 Yes Main emission source

    CH4 No These emissions are expected to be the same or higher as

    compared to the project scenario. Excluded for

    simplification and because this is conservative.

    N2O No These emissions are expected to be the same or higher as

    compared to the project scenario. Excluded for

    simplification and because this is conservative.

    ProjectActivity

    Processing

    of feed

    CO2 Yes Main emission source. CO2 is produced in the reforming

    of the feed and may be partially recovered for the

    production of ammonia . CO2 in excess of that required

    for ammonia, if any, is released into atmosphere.

    CH4 No Negligible fugitive CH4 emissions may occur during the

    processing of the feed. These emissions (if any) would be

    essentially the same as in the baseline scenario.

    Therefore, they are excluded for simplification.

    N2O No Not applicable

    Fuel used in

    furnaces

    (thermal

    energy)

    CO2 Yes Main emission source due to the combustion of fossil

    fuels. The project activity may result in lower thermal

    energy required, Any CO2 recovered from flue gasesresulting from combustion of fossil fuel is deducted from

    this emission source.

    CH4 No These emissions are expected to be the same or lower as

    compared to the baseline scenario.

    N2O No These emissions are expected to be the same or lower as

    compared to the baseline scenario.

    Fuel used in

    boilers

    (Steam and

    Power

    generation)

    CO2 Yes Main emission source.

    CH4 No These emissions are expected to be the same or lower as

    compared to the baseline scenario.

    N2O No These emissions are expected to be the same or lower as

    compared to the baseline scenario.

    Grid

    Electricity

    requirement

    CO2 Yes Main emission source.CH4 No These emissions are expected to be the same or lower as

    compared to the baseline scenario.

    N2O No These emissions are expected to be the same or lower as

    compared to the baseline scenario.

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    14/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 14

    B.4. Description of how the baseline scenario is identified and description of the identified

    baseline scenario:

    >> Selection of Baseline scenario

    The methodology applicable in case of the proposed CDM project is AM 0050 Version XX. The

    approved methodology specifies the use of combined tool for identification of baseline scenario and

    demonstrate additionality.

    Accordingly the baseline scenario has been identified as per the provisions in the approved methodology

    and the combined tool for identification of baseline scenario and demonstrates additionality.

    The various alternatives to the CDM project activity, identified are as under:

    Alternative 1: The continuation of current practice, i.e. usage of hydrocarbon feedstock / fuel with higheremission intensity and / or continuation of the present process technology for the production of ammonia /

    ammonia derivatives ,

    Alternative 2: Partial substitution of hydrocarbon feedstock / fuel with higher emission intensity with NG

    for similar output of ammonia

    Alternative 3: Complete switchover from hydrocarbon feedstock / fuel with higher emission intensity to

    NG

    Alternative 4: Usage of hydrocarbon feedstock / fuel with higher emission intensity as feed and

    production of CO2 surpluses, but with capture of the CO2 surpluses.

    All the four alternatives given above are in compliance with the applicable laws and regulations.Among the various alternatives given above, Alternative 4 cannot be a probable baseline scenario as this

    is not a general industrial practice as well as there is no facility at NFL Panipat plant to capture the CO2

    surpluses for its use in other applications further there is no opportunity to use captured CO2. Hence it

    has been excluded from further analysis.

    Alternative 2 cannot be the alternative scenario because the technology involved in heavy oil as feed stock

    and Natural gas as feed stock is entirely different and the hybrid two hydrocarbon stocks cannot be used

    as feed stock due to technological limitations.

    Among Alternative 1, 3 there is no investment required for alternative 1 and it also does not faces any

    financial barriers as explained in the subsequent sections hence alternative 1 i.e continuation of current

    practice of using heavy oil as feed stock and support fuel is the baseline scenario to the project activity.

    B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below

    those that would have occurred in the absence of the registered CDM project activity (assessment

    and demonstration of additionality):

    >> Additonality

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    15/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 15

    The current version of the approved methodology AM 0050 Version XX asks for the use of combined

    tool to determine the baseline and demonstrate additionality. Further the current version of the

    methodology mandates the use of benchmark investment analysis to demonstrate additionality.

    In 1977 Government of India introduced Retention Pricing Scheme (RPS) to provide urea to the farmers

    at affordable price and also make the fertilizer business sustainable. Under this scheme, different

    manufacturers of Urea are provided a subsidy by the government of India to cover the difference of the

    cost of production (plus a predetermined profit margin) and the administered sales price. As the cost of

    production in different units producing urea is different (due to difference in technology, scale of

    operation, difference in the feed stock used, difference in the norms of consumption of feed and fuel,

    etc.) the extent of subsidy (in terms of per ton of Urea produced) to different units for producing urea is

    different. The annual subsidy bill on account of this being footed by the government is quite huge. A

    circular by government of India in this regard has specified the policy of Government of India to provide

    incentives to the producers of Urea who switch from Oil/Naphtha to Natural Gas Feedstock . From the

    above the following is evident:

    The very reason that the government of India had to provide fiscal incentives for implementationof the feed switch project clearly demonstrates that such projects are not commercially viable at

    their own for the producers of urea.

    Promotion of feed switch from naphtha / oil to gas for urea production is a policy for the

    government. It is not a regulatory directive by the government.

    As is clear Urea manufacturing is not commercially viable under current market conditions and the

    Indian Government has to subsidize this activity.

    In the proposed CDM project the ground for project additionality originates from the fact that the project

    activity requires complete replacement of some sections of the existing plant and equipment with the new

    ones. This is in spite of the remaining lifetime of the equipment being replaced.

    Apart from this revenue government will also give subsidy to NFL in the way of special fixed cost. Due

    to the high capital cost for implementing the proposed project activity the return on the capital deployed

    is not adequate

    To summarize this, the following benefits would be available to NFL.

    As there is no substantial gain to fertilizers plants in return of huge capital investment being borne by the

    fertilizers plant. Government of India has will also be providing the capital subsidy to fertilizer plants in

    terms of special fixed cost.

    The components of special fixed cost would be as follows:

    1. Reimbursement of capital cost to fertilizer plant in five years from the date of commissioning

    2. Reimbursement of interest on borrowed capital in five years from the date of commissioning

    All these revenue streams has been taken for the computation of financials and the results of these

    computations are shown in subsequent Paragraphs.

    The methodology follows for the demonstration of additionality as per the latest version of combined

    tool to identify baseline and demonstrate additionality is as follows:

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    16/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    17/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 17

    Step 3b: Calculation of the suitable financial Indicator

    Detailed calculations considering all the revenue and cost streams have been done and internal rate ofreturn has been computed based on the entire investment and anticipated revenues.

    The results of the calculations are as shown below:

    IRR % without CDM revenue

    IRR of the CDM Project activity 5.45%

    IRR % with CDM revenue

    IRR of the CDM Project activity 9.42%

    It can be clearly analysed that the project has the IRR of 5.45% which is below the Benchmark PLR of

    RBI and the project crosses the hurdle of the benchmark only after taking into account the CDM revenue.

    Step3c: Sensitivity Analysis

    A detailed sensitivity analysis was also carried out for the dominant contributors and following results

    were obtained.

    Sensitivity on 10% decrease in capital cost

    The results of the calculations are as shown below:

    IRR % without CDM revenue

    IRR of the CDM Project activity 8.60%

    IRR % with CDM revenue

    IRR of the CDM Project activity 12.58%

    It is clear that in-spite of 10% decrease in capital cost the IRR does not crosses the hurdle rate and hence

    project activity clears the sensitivity test.

    Step 4:Common practice analysis

    In India, there are four plants which are being operated on furnace oil as feed stock. It includes three

    plants from NFL Panipat, Bathinda and Nangal and Gujarat Naramda Valley Fertilizer Plant. This

    changeover will involve a complete technological shift as the technologies involved with heavy oil and

    natural gas are entirely different and involves major modifications/changes in the front end section of

    ammonia plant. The similar exercise is also been done by Gujarat Naramda Valley Fertilizer Plant and

    they have also gone for the CDM route. This analysis clearly indicates that all the similar activities

    happening across the regions are opting for CDM and hence it is not a common practice.

    The project activity satisfies all four steps as defined in combined tool for identification of Baseline and

    demonstrate addtionality are fulfilled and hence project is additional

    B.6. Emission reductions:

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    18/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    19/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 19

    procedures actually

    applied :

    Any comment: Computed once at the start of the crediting period and kept fixed throughout thecrediting period

    Parameter: QFeed, Hist

    Data unit: (in tons Per Year)

    Description: Historical quantity of feed stock used for production of ammonia / ammonia

    derivative

    Source of data: Obtained from data logs, measurements and plant records at the project site

    Value Applied 244205

    Justification of the

    choice of data or

    description of

    measurement

    methods and

    procedures actually

    applied :

    Computed based on historical production of ammonia / ammonia derivative, three

    years prior to the start of the project activity

    Any comment: Computed once at the start of the crediting period and kept fixed throughout the

    crediting period

    Parameter: BEFFeed,Hist

    Data unit: (in tCO2)

    Description: Emission factor for the feedstock used in the baseline (Quantity of CO2 that would be

    produced from the feedstock per ton of feedstock)

    Source of data: Obtained from data logs, measurements and plant records at the project site

    Value applied 3.16

    Measurementprocedures (if any):

    Computed from the net calorific value of the feedstock and the emission factor of thefeedstock

    Any comment: Although in this case the hydrocarbon is used as a feedstock and not as a fuel, it is

    considered that the emission of CO2 is related to the NCV in the same manner as in

    the case of use as a fuel.

    Parameter: EFFeed,

    Data unit: (in tonCO2/TJ)

    Description: CO2 emission factor of the feedstock used prior to the implementation of the project

    activity in the yearX

    Source of data: IPCC default values at the lower limit of the uncertainty at a 95% confidence

    interval as provided in table 1.4 of chapter 1 of Vol. 2 (Energy) of the 2006 IPCC

    Guidelines on National GHG InventoriesValue Applied 77.4

    Justification of the

    choice of data or

    description of

    measurement

    methods and

    For (a) and (b): Measurements should be undertaken in line with national or

    international fuel standards

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    20/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 20

    procedures actually

    applied

    Any comment:

    Parameter: NCV Feed,

    Data unit: (TJ / Ton of feedstock)

    Description: Net caloric value of the feedstock used prior to the implementation of the project

    activity in the year X

    Source of data: The following data sources may be used if the relevant conditions apply:

    Data source Conditions for using the data source

    Values provided by the feedstock in

    invoices

    Regional or national average default

    values

    If values are reliable and

    documented in regional or national

    energy statistics / energy balances

    IPCC default values at the lower

    limit of the uncertainty at a 95%

    confidence interval as provided in

    Table 1.2 of Chapter 1 of Vol. 2

    (Energy) of the 2006 IPCC

    Guidelines on National GHG

    Inventories

    If above two data source is not

    available.

    Value Applied 0.041Justification of the

    choice of data or

    description of

    measurement

    methods and

    procedures actually

    applied

    Any comment:

    Parameter: QHeat, Hist Data unit: (in tons)

    Description: Historical quantity of fossil fuel used in the furnaces for production of ammonia /ammonia derivative

    Source of data: Obtained from the data logs, measurements and plant records at project site

    Value Applied: 0

    Justification of the

    choice of data or

    description of

    Computed based on historical consumption of fossil fuels used in the furnaces three

    years prior to the start of the project activity

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    21/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 21

    measurement

    methods and

    procedures actuallyapplied

    Any comment:

    Parameter: EFheat,iData unit: (in tCO2)

    Description: Emission factor for the fossil fuel used in the baseline (Quantity of CO2 that would

    be produced per ton of fuel)

    Source of data: The following data sources may be used if the relevant conditions apply:

    Data source Conditions for using the data source

    (a) Values provided by the fuelsupplier in invoices

    This is the preferred source

    (b) measurements by the project

    participants

    Applicable if (a) is not available

    (c) Regional or national default

    values

    These sources can only be used for

    liquid fuels and should be based on

    well-documented, reliable sources

    (such as national energy balances)

    (d) IPCC default values at the

    lower limit of the uncertainty

    at a 95% confidence interval

    as provided in table 1.4 ofchapter 1 of Vol. 2 (Energy)

    of the 2006 IPCC Guidelines

    on National GHG Inventories.

    If (a) is not available

    Value Applied 0

    Measurement

    procedures (if any):

    For (a) and (b): Measurements should be undertaken in line with national or

    international fuel standards

    Any comment: For (a): If the fuel supplier does provide the NCV value and the CO2 emission factor

    on the invoice and these two values are based on measurements for this specific fuel,

    this CO2 factor should be used. If another source for the CO2 emission factor is used

    or no CO2 emission factor is provided, Options (b), (c) or (d) should be used

    Parameter: NCVHeat,iData unit: (TJ / Ton of fuel)

    Description: Net caloric value of the fossil fuel used in the furnaces prior to the implementation of

    the project activity in the year X

    Source of data: The following data sources may be used if the relevant conditions apply:

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    22/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    23/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 23

    Parameter: EFUtility coal

    Data unit: (in tCO2/TJ)Description: Emission factor for the coal used in the boilers in the baseline (Quantity of CO2 that

    would be produced per ton of fuel)

    Source of data: IPCC default values at the lower limit of the uncertainty at a 95% confidence

    interval as provided in table 1.4 of chapter 1 of Vol. 2 (Energy) of the 2006 IPCC

    Guidelines on National GHG Inventories

    Value Applied: 96.1

    Justification of the

    choice of data or

    description of

    measurement

    methods and

    procedures actually

    applied

    For (a) and (b): Measurements should be undertaken in line with national or

    international fuel standards

    Any comment:

    Parameter: EFUtility FO,Data unit: (in tCO2/TJ)

    Description: Emission factor for the fossil fuel used in the boilers in the baseline (Quantity of CO2

    that would be produced per ton of fuel)

    Source of data: IPCC default values at the lower limit of the uncertainty at a 95% confidence

    interval as provided in table 1.4 of chapter 1 of Vol. 2 (Energy) of the 2006 IPCC

    Guidelines on National GHG Inventories

    Value Applied: 77.4

    Justification of the

    choice of data ordescription of

    measurement

    methods and

    procedures actually

    applied

    For (a) and (b): Measurements should be undertaken in line with national or

    international fuel standards

    Any comment: For (a): If the fuel supplier does provide the NCV value and the CO2 emission factor

    on the invoice and these two values are based on measurements for this specific fuel,

    this CO2 factor should be used. If another source for the CO2 emission factor is used

    or no CO2 emission factor is provided, Options (b), (c) or (d) should be used

    Parameter: NCVUtility coal

    Data unit: (TJ / Ton of fuel)Description: Net caloric value of the fossil fuel used in the boilers prior to the implementation of

    the project activity in the year X

    Source of data: The following data sources may be used if the relevant conditions apply:

    Data source Conditions for using the data source

    Values provided by the feedstock in

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    24/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 24

    invoices

    Regional or national average default

    values

    If values are reliable and

    documented in regional or nationalenergy statistics / energy balances

    IPCC default values at the lower

    limit of the uncertainty at a 95%

    confidence interval as provided in

    Table 1.2 of Chapter 1 of Vol. 2

    (Energy) of the 2006 IPCC

    Guidelines on National GHG

    Inventories

    If above two data source is not

    available.

    Value Applied: 0.017

    Justification of the

    choice of data or

    description ofmeasurement

    methods and

    procedures actually

    applied

    Any comment:

    Parameter: NCVUtility FOData unit: (TJ / Ton of fuel)

    Description: Net caloric value of the fossil fuel used in the boilers prior to the implementation of

    the project activity in the year X

    Source of data: The following data sources may be used if the relevant conditions apply:

    Data source Conditions for using the data source

    Values provided by the feedstock in

    invoices

    Regional or national average default

    values

    If values are reliable and

    documented in regional or national

    energy statistics / energy balances

    IPCC default values at the lower

    limit of the uncertainty at a 95%

    confidence interval as provided in

    Table 1.2 of Chapter 1 of Vol. 2

    (Energy) of the 2006 IPCC

    Guidelines on National GHGInventories

    If above two data source is not

    available.

    Value Applied: 0.041

    Justification of the

    choice of data or

    description of

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    25/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    26/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    27/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 27

    = 295751 MT per Year

    Baseline Emissions due to the use of feed (BEFeed,Hist)

    The emissions due to the use of hydrocarbon feedstock for the production of ammonia / ammonia

    derivative are calculated as follows:

    HistFeedHistFeedHistFeed BEFQBE ,, *,=

    Where:

    QFeed, Hist Historical quantity of feed stock used for production of ammonia / ammonia

    derivative (in tons)

    BEFFeed,Hist Emission factor for the feedstock used in the baseline (Quantity of CO2 that would

    be produced from the feedstock per ton of feedstock) (in tCO2)

    HistFeedBE , = (244205 tonnes of feed stock per Year * 3.16 tCO2/tonne of feed stock)

    = 771436 tCO2/Year

    ),,.( 1,1,,, = xFeedxFeedxFeedHistFeed BEFBEFBEFMinBEF

    Where:

    BEFFeed,x = Average CO2 emission factor for the feedstock used prior to the implementation of the

    project activity in the yearx (in tons per ton of feedstock)

    3

    3

    1

    ,,

    ,

    =

    =x

    xHistFeed

    HistFeed

    Q

    Q

    Where:

    QFeed,Hist = Historical quantity of feedstock used (in tons)

    QFeed, Hist,-x = Quantity of feedstock used prior to the implementation of the project activity in yearx

    (in tons)

    Emission Factor for the feedstock (BEFFeed) is calculated as

    HistFeedQ , = 30.834 tonnes per hour * 24 hrs/day * 330 days/year

    = 244205 MT per Year

    XFeedXFeedXFeed EFNCVBEF = ,,, *

    Where:

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    28/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 28

    EFFeed, -X CO2 emission factor of the feedstock used prior to the implementation of the project

    activity in the yearX(in tonCO2/TJ)

    NCV Feed,-X Net calorific value of the feedstock used prior to the implementation of the project

    activity in the year X (TJ / Ton of feedstock)

    XFeedBEF , = 77.4tCO2/TJ x 0.041 TJ/tonne of feed stock

    = 3.16 tCO2/tonne of feed stock

    Baseline Emissions due to the thermal energy used in the furnaces (BEHeat,y)

    Baseline CO2 emissions from thermal energy are calculated as follows:

    iheatiHeatHistiHeat

    n

    iHistHeatEFNCVQBE ,,,,, **=

    Where:

    QHeat i, HistAnnual average Historical quantity of fossil fuel i used in the furnaces for

    production of ammonia (in tons)

    NCVi,heat

    iheatEF ,

    Net Calorific value of fossil fuel i used for thermal energy in the furnaces(in

    TJ/tonne)

    CO2 Emission factor for the fossil fuel i(in tCO2)

    3

    3

    1

    ,,,

    ,,

    =

    =x

    xHistiHeat

    HistiHeat

    Q

    Q

    Where:

    QHeat,i,, Hist,-x = Quantity of feedstock type I used prior to the implementation of the project activity in

    yearx (in tons)

    QHeat,iHist = 0 tonnes

    HistHeatBE , = 0 tCO2/Year

    Baseline Emissions due to use of fossil fuel in the Boilers (BEUtility,)

    Baseline CO2 emissions due to the use of fossil fuel in the boilers for the process steam and power arecalculated as follows:

    3

    ** ,,,,,,

    3

    1,

    =

    =

    n

    i

    xiutilityxiutilityxiutility

    xHistUtility

    EFNCVQ

    BE

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    29/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 29

    Where:

    xiutility

    Q

    ,,

    Historical quantity of fossil fuel i used in the boilers for production of steam

    and power (in tonne per year) in the year x before the year of project activity,x

    xiutilityNCV ,,

    xiutilityEF ,,

    Net calorific value of fossil fuel i used (TJ/Tonne)

    CO2 Emission factor for the fossil fuel i (in tCO2/TJ)

    HistUtilityBE , = (67.972 tonnes per hour x 330 days in Year x 24 hrs/day x 1.67 tCO2/tonne of coal)+ (4.179 tonnes per hour x 330 days in Year x 24 hrs/day x 3.16 tCO2/tonne of FO)

    = 1003278 tCO2/Year

    Baseline Emissions due to use of grid electricity (BEGrid,)

    Baseline CO2 emissions due to the use of fossil fuel in the boilers for the process steam and power are

    calculated as follows:

    HistGridHistGridHistGrid BEFQBE ,, *,=

    Where:

    QGrid, Hist Historical quantity of power imported from the grid (in MWh)

    BEFGrid,Hist Baseline emission factor for the power imported from the grid (in tCO2 /MWh)

    HistUtilityBE , = (67.972 tonnes per hr * 24 hrs per day * 330 days per year *1.67tCO2/tonne of coal)+(4.179 kNM3/hr * 24 hrs per day *330 days per

    year * 3.1667tCO2/tonne of heavy oil)= 1003278 tCO2/year

    3

    3

    1

    ,,

    ,,

    =

    = xxHistUtility

    HistiUtility

    Q

    Q

    Where:

    QUtility, Hist,-x = Historical quantity of fossil fuel i used in the boilers for production of steam and

    power (in tonne per year) in the year x before the year of project activity ,x

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    30/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 30

    ),,.( 2,1,,,

    = xGridxGridxGridHistGrid

    EFBEEFMinBEF

    Where:

    BEFGrid,x = Historical CO2 emission factor for power imported from the grid (in tCO2 / MWh))

    EFGrid,X = Emission factor of the grid from which the power is imported (in tCO2 / MWh). This

    is computed using the latest version of the Tool for determination of emissions from

    an electrical system

    3

    3

    1

    ,,

    ,

    =

    = xxHistGrid

    HistGridy

    Q

    Q

    Where:

    QGrid,Hist = Historical quantum of power imported from the grid (MWH)QGrid, Hist,-x = Quantum of power imported prior to the implementation of the project activity in year

    x (in MWh)

    HistGridyQ , = 13615 MWh

    HistGridBE , = 13615 MWh x 0.8 tCO2/MWh

    ` = 10892 tCO2/year

    For the determination of emission factors of the fuels and the feedstock, guidance from the 2006 IPCC

    Guidelines for National Greenhouse Gas Inventories has been followed where appropriate

    Project Emissions

    Project activity emissions are calculated as follows:

    yGridyUtilityyHeatyFeedy PEPEPEPEPE ,,,, +++=

    Where:

    PEFeed,y Emissions due to the use of feedstock for the production of ammonia / ammonia derivative in

    each year Y of the crediting period,(in tCO2)

    PEHeat,y Emissions due to the production of thermal energy used in the furnaces (feed treatment and

    reforming) after deducting the CO2 recovered by the CDR plant (if any) in each year y of the

    crediting period, in tCO2.

    PEUtility,y Emissions due to use of fossil fuels in the boilers for onsite production of steam and power in

    each year y of the crediting period, in tCO2.

    PEGrid,y Emissions due to import/ export of power from the grid in the year y of the crediting period

    (in tCO2)

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    31/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    32/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 32

    For determination of emission factors, guidance from the 2006 IPCC Guidelines for National Greenhouse

    Gas Inventories has been followed where appropriate.

    yHeatPE , = 6.154kNM3/hr * 24hrs/day *330 days/year*0.036TJ/NM3*56.1tCO2/TJ

    = 98160 tCO2/Year

    Emissions due to use of fossil fuels in the boilers (PEUtility,y)

    Emissions due to the production of thermal energy used in the furnaces (feed treatment and reforming) are

    calculated as follows:

    YiutilityPJCO

    i

    YiutilityYiUtilityYUtility EFNCVFCPE ,,,,2,,,,, =

    yUtilityPE , = (47.314T/hr *24 hrs/day *330days/year*1.67tCO2/tonne of fuel) + (3.242*24 hrs/day

    *330days/year*2.01tCO2/tonne of NG)

    = 677289 tCO2/Year

    Where:

    FCUtility,i,Y Quantity of fuel type i consumed in the boilers of the power plant for producing power and

    steam in year y of the crediting period, in mass or volume units.

    NCVi,Y Net calorific value of fuel type i in each year y of the crediting period, in (TJ/mass or volume

    units.)

    EFCO2,PJ,utility

    ,,i,Y

    CO2 emission factor of the fuel type i used in the boilers of the power plant in the year y of

    the crediting period, (in tCO2/TJ).

    For determination of emission factors, guidance from the 2006 IPCC Guidelines for National Greenhouse

    Gas Inventories has been followed where appropriate.

    Emissions due to import / export of power from the grid (PEGrid,y)

    The emissions / emission reductions due to import / export of power from the grid can be computed as

    follows:

    YGridYPRGridYGrid EFQPE ,,,, =

    Where:

    QGrid,PR,Y, Quantum of electricity imported from the grid in the year y of the crediting period, in MWh.

    EFGrid,Y CO2 emission factor for the power from the grid in the year y of the crediting period, in

    tCO2/MWh.

    EFgrid,Y, is the emission factor of the grid that must be calculated as the generation-weighted average

    emissions per electricity unit of all generating sources serving the system.

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    33/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    34/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    35/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 35

    Any comment: Volumetric units should be at normal pressure and temperature

    Data / Parameter: QGrid,PR,yData unit: MWh

    Value Applied: 13615

    Description: Quantity of electricity obtained from / supplied to the grid by the project activity

    during each year y of the crediting period. Measured at the project site.

    Source of data: Measured in the project activity by digital control systems and/or data logs.

    Measurement

    procedures (if any):

    Electrical Energy Meter

    Monitoring frequency: Continuously

    QA/QC procedures: Electrical Energy Meter used for measurement should be calibrated regularly as

    per ISO procedures or according to manufacturers guidelines

    Any comment: In case of net export of power to the grid. Negative sign will be used

    Data / Parameter: FCUtility coal, y

    Data unit: Tonnes Per Year

    Description: Quantity of fuel type i consumed in the boilers of the power plant generation of

    steam and power in each year y of the crediting period.

    Value Applied: 374726

    Source of data: On-site measurements

    Measurement

    procedures (if any):

    Flow-rate meters

    Monitoring frequency: Continuously

    QA/QC procedures: Meters should be calibrated regularly according to manufacturers guidelines.

    Any comment: Volumetric units should be at normal pressure and temperature

    Data / Parameter: FCUtility Natural Gas, y

    Data unit: kNM3 Per Year

    Description: Quantity of fuel type i consumed in the boilers of the power plant generation of

    steam and power in each year y of the crediting period.

    Value Applied: 25676

    Source of data: On-site measurements

    Measurement

    procedures (if any):

    Flow-rate meters

    Monitoring frequency: Continuously

    QA/QC procedures: Meters should be calibrated regularly according to manufacturers guidelines.

    Any comment: Volumetric units should be at normal pressure and temperature

    Parameter: NCVcoal,yData unit: TJ/tonnes of coal

    Description: Average net calorific value of coal in year y of the crediting period.

    Value Applied: 0.017

    Source of data: IPCC Guidelines for National Greenhouse Gas Inventories.

    Measurement

    procedures (if any):

    -

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    36/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 36

    Monitoring frequency

    QA/QC procedures -

    Any comment: -

    Parameter: CV G,y

    Data unit: TJ/NM3 of NG

    Description: Average net calorific value of fuel type i and NG/LNG respectively, in year y of

    the crediting period.

    Value Applied: 0.036

    Source of data: IPCC Guidelines for National Greenhouse Gas Inventories.

    Measurement

    procedures (if any):

    -

    Monitoring frequency

    QA/QC procedures -

    Any comment: -

    Data / Parameter: EFCO2, PJ coal i,y

    Data unit: tCO2/TJ

    Description: CO2 emission factor of fuel type i used for steam generation in the boilers in the

    year y.

    Value Applied: 96.1

    Source of data: IPCC Default Values

    Measurement

    procedures (if any):

    Monitoring frequency: Yearly

    QA/QC procedures:

    Any comment:

    Data / Parameter: EFCO2, PJ Natural Gas i,y

    Data unit: tCO2/TJ

    Description: CO2 emission factor of fuel type i used for steam generation in the boilers in the

    year y.

    Value Applied: 56.1

    Source of data: IPCC default values

    Measurement

    procedures (if any):

    Monitoring frequency: Yearly

    QA/QC procedures:

    Data / Parameter: QGrid,PR,y

    Data unit: MWh

    Value Applied: 13615

    Description: Quantity of electricity obtained from the grid by the project activity during each

    year y of the crediting period. Measured at the project site.

    Source of data: Measured in the project activity by digital control systems and/or data logs.

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    37/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 37

    Measurement

    procedures (if any):

    Electrical Energy Meter

    Monitoring frequency: ContinuouslyQA/QC procedures: Electrical Energy Meter used for measurement should be calibrated regularly as

    per ISO procedures or according to manufacturers guidelines

    Any comment:

    Data / Parameter: EFgrid,y

    Data unit: tCO2/MWh

    Value Applied: 0.80

    Description: CO2 emission factor for grid electricity during the yeary.

    Source of data: Use the latest approved version of Tool to calculate emission factor for an

    electricity system to calculate the grid emission factor.

    Measurement

    procedures (if any):

    -

    Monitoring frequency: Either once at the start of the project activity or updated annually, consistent

    with guidance in Tool to calculate emission factor for an electricity system.

    QA/QC procedures: Apply procedures as in Tool to calculate emission factor for an electricity

    system

    Any comment: All data and parameters to determine the grid electricity emission factor, as

    required by Tool to calculate emission factor for an electricity system, shall

    be included in the monitoring plan.

    Any comment:

    Data / Parameter: EFCO2,upstream,LNG,y

    Data unit: tCO2/TJ

    Description: Emission factor for upstream CO2 emissions due to fossil fuel combustion /

    electricity consumption associated with the liquefaction, transportation, re-gasification and compression of LNG into a natural gas transmission or

    distribution system in year y.

    Value Applied: 6

    Source of data: Default Value given in the methodology

    Measurement

    procedures (if any):

    Where reliable and accurate data on upstream CO2 emissions due to fossil fuel

    combustion / electricity consumption associated with the liquefaction,

    transportation, re-gasification and compression of LNG into a natural gas

    transmission or distribution system is available, project participants should use

    this data to determine an average emission factor. Where such data is not

    available, project participants may assume a default value of 6 tCO2/TJ as a

    rough approximation2.

    Monitoring frequency: Yearly

    2This value has been derived on data published for North American LNG systems. Barclay, M. and N. Denton,

    2005. Selecting offshore LNG process. http://www.fwc.com/publications/tech_papers/files/LNJ091105p34-36.pdf

    (10th April 2006).

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    38/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    39/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 39

    The unit head is responsible for the overall functioning and maintenance of the project activity. The Shift

    operator maintains all the data records and ensures the completeness and reliability of the data. The ShiftIn-charge maintains a day to day power generation log. The monitoring reports are checked periodically

    by the Plant In-charge and discussed thoroughly with the data monitoring personnel. Corrective action is

    taken immediately if any improper functioning or operation problem with the equipment is observed. The

    archived data shall be kept for two years after the crediting period or issuance of CERs.

    After verification of the data and due diligence on the correctness if required, an annual report on

    monitoring and estimations shall be maintained by the CDM team and record to this effect shall be

    maintained for verification.

    QA & QC Procedures to be followed

    Necessary check meters as required would be installed, to operate in standby mode or when the main

    meters are not working. All meters will be calibrated and sealed as per industry practices at regularintervals. Records of calibration certificates will be maintained for verification. Hence, high quality is

    ensured with the above parameters.

    B.8. Date of completion of the application of the baseline study and monitoring methodology

    and the name of the responsible person(s)/entity(ies):

    >> The date of completion of baseline and monitoring methodology is 31/07/2011. Contact details of the

    person responsible for development of baseline and monitoring methodology is given below

    Mr. K.K. Goel

    National Fertilizers Limited

    A-11 Sector 24

    NOIDA, Uttar Pradesh201301

    E-mail: [email protected]

    SECTION C. Duration of the project activity / crediting period

    C.1. Duration of the project activity:

    C.1.1. Starting date of the project activity:

    >> 29th January 2010

    C.1.2. Expected operational lifetime of the project activity:

    >> 20 Years

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    40/43

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    41/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 41

    Annex 1

    CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY

    Organization: National Fertilizers Limited

    Street/P.O.Box: Sector 24

    Building: A-11

    City: NOIDA

    State/Region: Uttar Pradesh

    Postcode/ZIP: 201301

    Country: India

    Telephone: 0120-2412383

    FAX: 0120-2412384

    E-Mail: [email protected]

    URL: www.nationalfertilizers.comRepresented by: -

    Title: Chief Manager Mechanical

    Salutation: Mr.

    Last name: Goel

    Middle name: -

    First name: K.K

    Department: Technical Department

    Mobile: +919910575722

    Direct FAX: +911202412397

    Direct tel: +911202412294

    Personal e-mail: [email protected]

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    42/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 42

    Annex 2

    INFORMATION REGARDING PUBLIC FUNDING

  • 7/29/2019 NFL Panipat PDD_ 25 Oct- 2011

    43/43

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 43

    Annex 3

    BASELINE INFORMATION

    Annex 4

    MONITORING INFORMATION

    - - - - -