Upload
rajeshkumar-elango
View
214
Download
0
Embed Size (px)
Citation preview
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
1/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 1
CLEAN DEVELOPMENT MECHANISM
PROJECT DESIGN DOCUMENT FORM (CDM-PDD)
Version 03 - in effect as of: 28 July 2006
CONTENTS
A. General description of project activity
B. Application of a baseline and monitoring methodology
C. Duration of the project activity / crediting period
D. Environmental impacts
E. Stakeholders comments
Annexes
Annex 1: Contact information on participants in the project activity
Annex 2: Information regarding public funding
Annex 3: Baseline information
Annex 4: Monitoring plan
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
2/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 2
SECTION A. General description of project activity
A.1. Title of the project activity:
>> Feed Switch from FO/LSHS to Natural Gas for Ammonia & Urea Manufacture at Panipat 1
Version -1
Date: 1st
September 2011
A.2. Description of the project activity:
>> National Fertilizers Limited (NFL) is one of the leading producers of Nitrogenous Fertilizers in India.
NFL is presently operating a ammonia and urea plant at Panipat in India the feed stock / fuel used at the
plant is Heavy Fuel Oil/Low Sulphur Heavy Stock. Coal is used for captive power and steam generation.
The support / auxiliary fuel used in the coal fired boiler is the heavy oil.
The project activity involves switching of feed stock and support fuel from Heavy fuel oil to Natural Gas.Project activity will involve modifications/changes in ammonia reforming section and the associated
utilities. The objective of the project activity is to shift to the lesser carbon intensive feed stock and
support fuel for production of ammonia which leads to reduction in GHG emissions
Pre Project Scenario
In the pre project scenario, Heavy fuel oil is used as the feed stock and support fuel for production of
ammonia. Heavy oil is gasified with oxygen (produced separately in an air separation unit) and steam to
produce the gaseous streams consisting H2, CO2, CO, Ar and other inert gases. Heat contained in this hot
gas stream is recovered in the waste heat boiler. Subsequently CO2 is separated from the gaseous stream
and argon and other inert gases are removed from the stream. Nitrogen from the air separation unit is
added back to the gaseous stream to get the synthesis gas having hydrogen to nitrogen ratio of 1:3 (molar
ratio). The synthesis gas is then made to react in the ammonia reactor to produce ammonia. Heavy oil is
also used as a support fuel in the combined heat and power plant.
Post Project Scenario
After the implementation of project activity, Natural gas will be used as the feed stock and support fuel.
The technology for production of ammonia using natural gas as the feedstock is different from the
existing technology and this will require process changes in existing equipment as well as incorporation
of new processes like Methanation section, etc.
In the process of changeover from Heavy oil to Natural Gas, key physical changes which will be
incorporated in the ammonia plant for the implementation of project activity are as follows:
A new Desulphurizer section will be installed
A new primary reformer and secondary reformer will be installed A new S-300 convertor will be installed in the existing synthesis loop
A new CO2 removal/ recovery unit(MDEA wash) will be installed
A new Methanation section will be installed
A new Synthesis booster compressor will be installed
A new Medium pressure(40K) loop boiler in synthesis loop will be installed
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
3/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
4/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 4
The technology for production of ammonia which will be used for project is the world class and will lead
to reduction in the consumption of hydrocarbons for the production of same volume of ammonia. Thus
the technology will also lead to the consequent reduction in the emissions of heavy metals, particulatesand other pollutants associated with the use of hydrocarbons.
A.3. Project participants:
>>
Name of Party involved (*)
((host) indicates a host party)
Private and/or public entity
(ies)
Project participants (*)
(as applicable)
Kindly indicate if the Party
involved wishes to be
considered as project
participant
(Yes/ No)
Government of India (host party) National Fertilizers Limited No
A.4. Technical description of the project activity:
A.4.1. Location of the project activity:
>> Panipat, India
A.4.1.1. Host Party(ies):
>> Government of India
A.4.1.2. Region/State/Province etc.:
>> State: Haryana
A.4.1.3. City/Town/Community etc.:
>> PanipatA.4.1.4. Details of physical location, including information allowing the unique
identification of this project activity (maximum one page):
>> The proposed CDM project activity is located in National Fertilizers Limited, District Panipat,Haryana State, India. The nearest airport is Indira Gandhi International airport New Delhi and nearest
railway station is Panipat railway station.
The location map is given below.
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
5/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 5
Plant Address:
National Fertilizers Limited,
Gohana Road,
Panipat,
Haryana-132106.NFL Plant Geo - Coordinates: 2921'30"N 7657'40"E
A.4.2. Category(ies) of project activity:
>> The project activity switches high carbon intensive feed stock and support fuel to lower carbon
intensive feed stock and support fuel and hence reduces the GHG emissions to the atmosphere for the
same production of ammonia. According to the CDM modalities, the project activity falls under
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
6/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 6
Approved Large scale methodology AM0050. The project activity corresponds to sectoral scope 5,
Chemical Industry of the UNFCCC sectoral scope list for project activities.
A.4.3. Technology to be employed by the project activity:
>> National Fertilizers Limited has hired M/sHalder Topse, who is the world renowned technology
provider in fertilizer plant and have provided technology to many of the fertilizer units in India and
abroad. National Fertilizer Limited has incorporated all necessary safety features which are required for
the safe operation of the plant.
The Purpose of Project activity is to adopt a cleaner and efficient technology and reduce the GHG
emissions by switching over of feed and support fuel from heavy oil to natural gas. The change over from
heavy oil to natural gas will reduce GHG emissions due to reduced generation of CO 2 in the reformer
section, boilers.
In the production process of ammonia using hydrocarbons as feed stock involves following sequential
steps:
Reforming of hydrocarbon with steam and oxygen / air followed by separation of carbon dioxide
and other impurities from the output gaseous stream of the reformer to produce synthesis gas.
Conversion of synthesis gas to Ammonia in a reactor
Separation of ammonia and recycling of the unreached synthesis gas back to the ammonia reactor
Apart from these main operations mentioned above the auxiliary operations in typical ammonia plant
may include the following:
Use of waste heat for generation of steam
Onsite generation of power and balance steam in combined heat and power plant leading to
emissions of GHG
Operation of boilers for generation of process steam leading to emissions of GHG
In the reforming section, hydrocarbon feed is reformed to make CO2, Hydrogen and Nitrogen. The CO2 is
then separated from the main gaseous stream in the CO2 recovery section. The gaseous stream also
contains some traces of CO, Argon and other inert gases and these traces are removed before production
of ammonia in the synthesis reactor.
Pre Project Scenario
In the scenario prior to the implementation of Project activity, Heavy oil is used as feedstock for the
reforming. The generation of ammonia using Heavy oil as feed involves following steps:
Gasification of heavy oil
CO Shift
CO2 recovery section Ammonia Synthesis
The process diagram shown below gives the details about the process equipment and various GHG
emissions sources in the existing practice of heavy oil as feed stock
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
7/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 7
Emission - Utility
Emission - Grid
Combined
Heat and
Power(CH
P) Plant /
Process
Boilers /
Waste
HeatRecovery
Boilers
Fossil Fuel for Boilers
(coal)
Gasifier
Separation
of CO2
Ammonia Reactor
Urea Production
Supply Header / Hydrocarbon Storage Bunker
Heavy Fuel Oil
Emission
Feedstock
CO2 In Excess of
that used for
Urea
Production
Air
CO2
Power From / To Grid
Ammonia
Synthesis Gas
CO2
Emission - Heat
Auxiliary /
Support FuelFeed / Fuel
Urea
Hot Gas Stream
Waste
Heat
Recovery
Pre Project Scenario
CO2
The main GHG emission sources are emissions due to venting of Excess CO2 over and above used for
urea production , GHG emissions from the utilities like steam generators, GHG emissions due to import
of power from Grid.
A detailed residual life cycle assessment was carried out by National Fertilizers Limited and all the
existing units had adequate lifetime. The decision taken by NFL Panipat is based on the urge to adopt the
cleaner and efficient technology which will reduce consumption of hydrocarbons and hence the GHG
emissions for the same volume of production.
Post Project Scenario
In the scenario after the implementation of Project activity, Natural Gas will be used as a source of feed
and support fuel for the production of ammonia. The generation of ammonia using Natural Gas as feed
involves following steps:
Feed gas compression, pre heating and desulphurization section
Primary and Secondary Reforming
Process air compression
CO Shift conversion
CO2 recovery section
Methanation section
Dryer and Purifier section
Ammonia Synthesis
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
8/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 8
Loop purge ammonia recovery
Ammonia refrigeration
Process condensate stripper
The process diagram shown below gives details about the process equipment and various GHG emissions
sources after implementation of project activity with Natural Gas as feed stock and support fuel.
Emission - Utility
Emission - Grid
Combined
Heat and
Power(CH
P) Plant /
Process
Boilers /
Waste
Heat
Recovery
Boilers
Fossil Fuel for Boilers
(coal)
Gasifier
Separation
of CO2
Ammonia Reactor
Urea Production
Supply Header / Hydrocarbon Storage Bunker
Natural Gas
Emission
Feedstock
CO2 In Excess of
that used for
Urea
Production
Air
CO2
Power From / To Grid
Ammonia
Synthesis Gas
CO2
Emission - Heat
Auxiliary /
Support FuelFeed / Fuel
Urea
Hot Gas Stream
Waste
Heat
Recovery
Post Project Scenario
CO2
The main GHG emission sources at after the project activity remains the same however the emission
intensity reduces.
The project activity is being implemented in an existing ammonia production unit and involves
replacement of the existing front end section of ammonia plant with integration to existing back end
section of ammonia plant with a new S -300 convertor and MP boiler, keeping the existing off site and
utilities for production of ammonia.
List of new section that will be added for the implementation of CDM project activity are as follows:
Desulphurization section
Modification in the reformer section
CO2 removal/recovery unit (MDEA wash)
Methanation section
Synthesis gas booster compressor
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
9/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 9
S-300 convertor
Medium Pressure loop boiler in synthesis loop
Ammonia recovery unit MP process condensate stripper
Natural gas pipeline network
The list of equipment that will become redundant/replaced after the implementation of project activity
are as follows:
Oxygen generation plant and its associated utilities
Front section of Ammonia plant
Rectisol unit of CO2 removal
Heavy oil storage section and piping network
In the absence of the project activity, NFL Panipat would have continued to use current practice of heavy
oil as feed stock and support fuel hence pre project scenario is also the baseline scenario.
Emission reduction due to the project activity would happen due to lower carbon intensity of Natural gas.
A.4.4. Estimated amount of emission reductions over the chosen crediting period:
>> The estimated amount of emission reduction due to the proposed project activity for the ten (10) years
under fixed crediting period option would be 4517960 tCO2e as per details on annual emission reductions
provided below:
Years Annual estimation of emission
reductions in tonnes of CO2 e
2012-13 451796
2013-14 451796
2014-15 451796
2015-16 451796
2016-17 451796
2017-18 451796
2018-19 451796
2019-20 451796
2020 -21 451796
2021-22 451796
Total estimated reductions
(tonnes of CO2e)
4517960
Total number of crediting years 10 years (Fixed)Annual average over the crediting
period of estimated reductions
(tonnes of CO2e)
451796
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
10/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 10
A.4.5. Public funding of the project activity:
>> There is no public funding involved in the proposed CDM project activity.
SECTION B. Application of a baseline and monitoring methodology
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
project activity:
>> The title of the baseline and monitoring methodology applicable to the proposed project activity is
Technology up-gradation and / or Fuel / Feed switch in integrated Ammonia manufacturing industry---
Version XX.
Reference: AM0050, Version XX, Sectoral Scope: 05.
It has been referred from the list of approved methodologies for CDM project activities in the UNFCCC
CDM website (http://cdm.unfccc.int/methodologies/PAmethodologies/approved.html).
AM0050 (Version XX) draws upon the following tools, which have been used in the PDD:
Combined tool to identify the baseline scenario and demonstrate additionality
Tool to calculate the emission factor for electricity system
B.2. Justification of the choice of the methodology and why it is applicable to the project
activity:
>> The proposed CDM project activity is a feed and a support fuel switch over from heavy oil to natural
gas and meets the applicability and non-applicability conditions of the chosen methodology (i.e. AM0050
VersionXX) as follows
Applicability Condition as per the approvedmethodology
Scenario in the Project activity
The project activity is carried out in an ammonia
plant, where, ammonia is sold as a merchant product
or converted to derivatives e.g., urea, ammonium
nitrate etc.
The project activity is carried out in an existing
ammonia plant hence this condition is applicable
to project activity
Ammonia manufacturing plants that are not
prevented by local regulations from using feedstock
and /or fuel other than natural gas
The project activity does not prevented by any
local regulation to switch to Natural gas and hence
this condition is applicable to project activity.
Project activities that do not result in the increase ofthe production capacity of ammonia plant. However,
the design capacity of ammonia plant may increase
marginally (say maximum up to 10 % of the design
capacity) and remain same throughout the crediting
period due to the need for line balancing. This is
required to be validated by the validating DOE by
In the Project scenario, name plate capacity of
ammonia plant will remain within the prescribedlimits as defined in the methodology hence this
condition is applicable.
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
11/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 11
validating the design capacity of the ammonia reactor
before and after the project.
.
Natural gas is sufficiently available in the region or
country, e.g. future natural gas based capacity
additions, comparable in size to the project activity,
are not constrained by the use of natural gas in the
project activity1;
NFL has signed a long term MOU with Gas
Authority of India Limited(GAIL) for the reliable
and continuous supply of Natural Gas and hence
there will be ample gas available for the project
activity.
The ammonia manufacturing plant is an existing
plant with a historical operation of at least three years
prior to the implementation of the project activity;
NFL is operating this plant since 1974. The last
three year production details will be made
available to DOE during validation hence this
condition is applicable.
Although Project activities may result in changes in
the production process but there is no change in the
capacity and product mix to produce different
product types e.g., the proportion of a particular type
of product produced in the total product mix should
remain same before and after the implementation of
project activity.
The capacity for different product types and mix
before and after the implementation of project
activity remains same hence this condition is
applicable
Prior to the implementation of the project activity, nonatural gas has been used in the ammonia
manufacturing plant
No Natural Gas has been used prior to the start of
project activity hence this condition is applicable
In case of historic use of ammonia for the production
of urea, percentage of ammonia used for production
of urea historically should not decrease (except minor
variation of up to 5%)
The percentage of ammonia consumed for the
production of Urea will not decrease hence this
condition is applicable.
B.3. Description of the sources and gases included in the project boundary:
1In some situations, there could be price-inelastic supply constraints (e.g. limited resources without possibility of
expansion during the crediting period) that could mean that a project activity displaces natural gas that would
otherwise be used elsewhere in an economy, thus leading to possible leakage. Hence, it is important for the project
proponent to document that supply limitations will not result in significant leakage as indicated.
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
12/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 12
>> According to the approved methodology AM0050 (Version xx, the spatial extent of the project
boundary includes the ammonia plant and power generation plant.
Emission - Utility
Emission - Grid
Combined
Heat and
Power(CH
P) Plant /Process
Boilers /
Waste
Heat
Recovery
Boilers
Fossil Fuel for Boilers
Gasifier / Reformer
Separation
of CO2
Ammonia Reactor
Ammonia Storage
/Derivative
Production
Supply Header / Hydrocarbon Storage Bunker
Hydrocarbon Feedstock /Fuel
Emission Feedstock
CO2 In Excess of
that used for
Derivatives
Air
CO2
Power From / To Grid
Ammonia
Synthesis Gas
CO2
Emission - Heat
Auxiliary /
Support FuelFeed / Fuel
Ammonia /
Ammonia
Derivative
Hot Gas Stream
Waste
Heat
Recovery
Project Boundary
CO2
Source Gas Included? Justification / Explanation
Baseline
Processing
of feedstock
CO2 Yes Main emission source. CO2 is produced in the reforming
of the feed
CH4 No Negligible fugitive CH4 emissions may occur during the
processing of the feed. These emissions (if any) would be
essentially the same as in the project activity. Therefore,
they are excluded for simplification.
N2O No Not applicable.
Fuel used infurnaces
(thermal
energy)
CO2 Yes Depending upon the process technology used in the
baseline it may be a main emission source (flue gases) due
to the combustion of fossil fuel to provide thermal energy
for feed treatment (sulphur removal in hydrotreater andprimary desulphurization unit and the synthesis-gas
production).
CH4 No Excluded for simplification, this is conservative.
N2O No Excluded for simplification, this is conservative.
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
13/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 13
Source Gas Included? Justification / Explanation
Fuel used inboilers
(Steam and /
or power
generation)
CO2 Yes Main emission source.
CH4 No These emissions are expected to be the same or higher as
compared to the project scenario. Excluded for
simplification and because this is conservative.
N2O No These emissions are expected to be the same or higher as
compared to the project scenario. Excluded for
simplification and because this is conservative.
Grid
Electricity
requirement
CO2 Yes Main emission source
CH4 No These emissions are expected to be the same or higher as
compared to the project scenario. Excluded for
simplification and because this is conservative.
N2O No These emissions are expected to be the same or higher as
compared to the project scenario. Excluded for
simplification and because this is conservative.
ProjectActivity
Processing
of feed
CO2 Yes Main emission source. CO2 is produced in the reforming
of the feed and may be partially recovered for the
production of ammonia . CO2 in excess of that required
for ammonia, if any, is released into atmosphere.
CH4 No Negligible fugitive CH4 emissions may occur during the
processing of the feed. These emissions (if any) would be
essentially the same as in the baseline scenario.
Therefore, they are excluded for simplification.
N2O No Not applicable
Fuel used in
furnaces
(thermal
energy)
CO2 Yes Main emission source due to the combustion of fossil
fuels. The project activity may result in lower thermal
energy required, Any CO2 recovered from flue gasesresulting from combustion of fossil fuel is deducted from
this emission source.
CH4 No These emissions are expected to be the same or lower as
compared to the baseline scenario.
N2O No These emissions are expected to be the same or lower as
compared to the baseline scenario.
Fuel used in
boilers
(Steam and
Power
generation)
CO2 Yes Main emission source.
CH4 No These emissions are expected to be the same or lower as
compared to the baseline scenario.
N2O No These emissions are expected to be the same or lower as
compared to the baseline scenario.
Grid
Electricity
requirement
CO2 Yes Main emission source.CH4 No These emissions are expected to be the same or lower as
compared to the baseline scenario.
N2O No These emissions are expected to be the same or lower as
compared to the baseline scenario.
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
14/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 14
B.4. Description of how the baseline scenario is identified and description of the identified
baseline scenario:
>> Selection of Baseline scenario
The methodology applicable in case of the proposed CDM project is AM 0050 Version XX. The
approved methodology specifies the use of combined tool for identification of baseline scenario and
demonstrate additionality.
Accordingly the baseline scenario has been identified as per the provisions in the approved methodology
and the combined tool for identification of baseline scenario and demonstrates additionality.
The various alternatives to the CDM project activity, identified are as under:
Alternative 1: The continuation of current practice, i.e. usage of hydrocarbon feedstock / fuel with higheremission intensity and / or continuation of the present process technology for the production of ammonia /
ammonia derivatives ,
Alternative 2: Partial substitution of hydrocarbon feedstock / fuel with higher emission intensity with NG
for similar output of ammonia
Alternative 3: Complete switchover from hydrocarbon feedstock / fuel with higher emission intensity to
NG
Alternative 4: Usage of hydrocarbon feedstock / fuel with higher emission intensity as feed and
production of CO2 surpluses, but with capture of the CO2 surpluses.
All the four alternatives given above are in compliance with the applicable laws and regulations.Among the various alternatives given above, Alternative 4 cannot be a probable baseline scenario as this
is not a general industrial practice as well as there is no facility at NFL Panipat plant to capture the CO2
surpluses for its use in other applications further there is no opportunity to use captured CO2. Hence it
has been excluded from further analysis.
Alternative 2 cannot be the alternative scenario because the technology involved in heavy oil as feed stock
and Natural gas as feed stock is entirely different and the hybrid two hydrocarbon stocks cannot be used
as feed stock due to technological limitations.
Among Alternative 1, 3 there is no investment required for alternative 1 and it also does not faces any
financial barriers as explained in the subsequent sections hence alternative 1 i.e continuation of current
practice of using heavy oil as feed stock and support fuel is the baseline scenario to the project activity.
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered CDM project activity (assessment
and demonstration of additionality):
>> Additonality
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
15/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 15
The current version of the approved methodology AM 0050 Version XX asks for the use of combined
tool to determine the baseline and demonstrate additionality. Further the current version of the
methodology mandates the use of benchmark investment analysis to demonstrate additionality.
In 1977 Government of India introduced Retention Pricing Scheme (RPS) to provide urea to the farmers
at affordable price and also make the fertilizer business sustainable. Under this scheme, different
manufacturers of Urea are provided a subsidy by the government of India to cover the difference of the
cost of production (plus a predetermined profit margin) and the administered sales price. As the cost of
production in different units producing urea is different (due to difference in technology, scale of
operation, difference in the feed stock used, difference in the norms of consumption of feed and fuel,
etc.) the extent of subsidy (in terms of per ton of Urea produced) to different units for producing urea is
different. The annual subsidy bill on account of this being footed by the government is quite huge. A
circular by government of India in this regard has specified the policy of Government of India to provide
incentives to the producers of Urea who switch from Oil/Naphtha to Natural Gas Feedstock . From the
above the following is evident:
The very reason that the government of India had to provide fiscal incentives for implementationof the feed switch project clearly demonstrates that such projects are not commercially viable at
their own for the producers of urea.
Promotion of feed switch from naphtha / oil to gas for urea production is a policy for the
government. It is not a regulatory directive by the government.
As is clear Urea manufacturing is not commercially viable under current market conditions and the
Indian Government has to subsidize this activity.
In the proposed CDM project the ground for project additionality originates from the fact that the project
activity requires complete replacement of some sections of the existing plant and equipment with the new
ones. This is in spite of the remaining lifetime of the equipment being replaced.
Apart from this revenue government will also give subsidy to NFL in the way of special fixed cost. Due
to the high capital cost for implementing the proposed project activity the return on the capital deployed
is not adequate
To summarize this, the following benefits would be available to NFL.
As there is no substantial gain to fertilizers plants in return of huge capital investment being borne by the
fertilizers plant. Government of India has will also be providing the capital subsidy to fertilizer plants in
terms of special fixed cost.
The components of special fixed cost would be as follows:
1. Reimbursement of capital cost to fertilizer plant in five years from the date of commissioning
2. Reimbursement of interest on borrowed capital in five years from the date of commissioning
All these revenue streams has been taken for the computation of financials and the results of these
computations are shown in subsequent Paragraphs.
The methodology follows for the demonstration of additionality as per the latest version of combined
tool to identify baseline and demonstrate additionality is as follows:
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
16/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
17/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 17
Step 3b: Calculation of the suitable financial Indicator
Detailed calculations considering all the revenue and cost streams have been done and internal rate ofreturn has been computed based on the entire investment and anticipated revenues.
The results of the calculations are as shown below:
IRR % without CDM revenue
IRR of the CDM Project activity 5.45%
IRR % with CDM revenue
IRR of the CDM Project activity 9.42%
It can be clearly analysed that the project has the IRR of 5.45% which is below the Benchmark PLR of
RBI and the project crosses the hurdle of the benchmark only after taking into account the CDM revenue.
Step3c: Sensitivity Analysis
A detailed sensitivity analysis was also carried out for the dominant contributors and following results
were obtained.
Sensitivity on 10% decrease in capital cost
The results of the calculations are as shown below:
IRR % without CDM revenue
IRR of the CDM Project activity 8.60%
IRR % with CDM revenue
IRR of the CDM Project activity 12.58%
It is clear that in-spite of 10% decrease in capital cost the IRR does not crosses the hurdle rate and hence
project activity clears the sensitivity test.
Step 4:Common practice analysis
In India, there are four plants which are being operated on furnace oil as feed stock. It includes three
plants from NFL Panipat, Bathinda and Nangal and Gujarat Naramda Valley Fertilizer Plant. This
changeover will involve a complete technological shift as the technologies involved with heavy oil and
natural gas are entirely different and involves major modifications/changes in the front end section of
ammonia plant. The similar exercise is also been done by Gujarat Naramda Valley Fertilizer Plant and
they have also gone for the CDM route. This analysis clearly indicates that all the similar activities
happening across the regions are opting for CDM and hence it is not a common practice.
The project activity satisfies all four steps as defined in combined tool for identification of Baseline and
demonstrate addtionality are fulfilled and hence project is additional
B.6. Emission reductions:
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
18/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
19/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 19
procedures actually
applied :
Any comment: Computed once at the start of the crediting period and kept fixed throughout thecrediting period
Parameter: QFeed, Hist
Data unit: (in tons Per Year)
Description: Historical quantity of feed stock used for production of ammonia / ammonia
derivative
Source of data: Obtained from data logs, measurements and plant records at the project site
Value Applied 244205
Justification of the
choice of data or
description of
measurement
methods and
procedures actually
applied :
Computed based on historical production of ammonia / ammonia derivative, three
years prior to the start of the project activity
Any comment: Computed once at the start of the crediting period and kept fixed throughout the
crediting period
Parameter: BEFFeed,Hist
Data unit: (in tCO2)
Description: Emission factor for the feedstock used in the baseline (Quantity of CO2 that would be
produced from the feedstock per ton of feedstock)
Source of data: Obtained from data logs, measurements and plant records at the project site
Value applied 3.16
Measurementprocedures (if any):
Computed from the net calorific value of the feedstock and the emission factor of thefeedstock
Any comment: Although in this case the hydrocarbon is used as a feedstock and not as a fuel, it is
considered that the emission of CO2 is related to the NCV in the same manner as in
the case of use as a fuel.
Parameter: EFFeed,
Data unit: (in tonCO2/TJ)
Description: CO2 emission factor of the feedstock used prior to the implementation of the project
activity in the yearX
Source of data: IPCC default values at the lower limit of the uncertainty at a 95% confidence
interval as provided in table 1.4 of chapter 1 of Vol. 2 (Energy) of the 2006 IPCC
Guidelines on National GHG InventoriesValue Applied 77.4
Justification of the
choice of data or
description of
measurement
methods and
For (a) and (b): Measurements should be undertaken in line with national or
international fuel standards
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
20/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 20
procedures actually
applied
Any comment:
Parameter: NCV Feed,
Data unit: (TJ / Ton of feedstock)
Description: Net caloric value of the feedstock used prior to the implementation of the project
activity in the year X
Source of data: The following data sources may be used if the relevant conditions apply:
Data source Conditions for using the data source
Values provided by the feedstock in
invoices
Regional or national average default
values
If values are reliable and
documented in regional or national
energy statistics / energy balances
IPCC default values at the lower
limit of the uncertainty at a 95%
confidence interval as provided in
Table 1.2 of Chapter 1 of Vol. 2
(Energy) of the 2006 IPCC
Guidelines on National GHG
Inventories
If above two data source is not
available.
Value Applied 0.041Justification of the
choice of data or
description of
measurement
methods and
procedures actually
applied
Any comment:
Parameter: QHeat, Hist Data unit: (in tons)
Description: Historical quantity of fossil fuel used in the furnaces for production of ammonia /ammonia derivative
Source of data: Obtained from the data logs, measurements and plant records at project site
Value Applied: 0
Justification of the
choice of data or
description of
Computed based on historical consumption of fossil fuels used in the furnaces three
years prior to the start of the project activity
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
21/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 21
measurement
methods and
procedures actuallyapplied
Any comment:
Parameter: EFheat,iData unit: (in tCO2)
Description: Emission factor for the fossil fuel used in the baseline (Quantity of CO2 that would
be produced per ton of fuel)
Source of data: The following data sources may be used if the relevant conditions apply:
Data source Conditions for using the data source
(a) Values provided by the fuelsupplier in invoices
This is the preferred source
(b) measurements by the project
participants
Applicable if (a) is not available
(c) Regional or national default
values
These sources can only be used for
liquid fuels and should be based on
well-documented, reliable sources
(such as national energy balances)
(d) IPCC default values at the
lower limit of the uncertainty
at a 95% confidence interval
as provided in table 1.4 ofchapter 1 of Vol. 2 (Energy)
of the 2006 IPCC Guidelines
on National GHG Inventories.
If (a) is not available
Value Applied 0
Measurement
procedures (if any):
For (a) and (b): Measurements should be undertaken in line with national or
international fuel standards
Any comment: For (a): If the fuel supplier does provide the NCV value and the CO2 emission factor
on the invoice and these two values are based on measurements for this specific fuel,
this CO2 factor should be used. If another source for the CO2 emission factor is used
or no CO2 emission factor is provided, Options (b), (c) or (d) should be used
Parameter: NCVHeat,iData unit: (TJ / Ton of fuel)
Description: Net caloric value of the fossil fuel used in the furnaces prior to the implementation of
the project activity in the year X
Source of data: The following data sources may be used if the relevant conditions apply:
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
22/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
23/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 23
Parameter: EFUtility coal
Data unit: (in tCO2/TJ)Description: Emission factor for the coal used in the boilers in the baseline (Quantity of CO2 that
would be produced per ton of fuel)
Source of data: IPCC default values at the lower limit of the uncertainty at a 95% confidence
interval as provided in table 1.4 of chapter 1 of Vol. 2 (Energy) of the 2006 IPCC
Guidelines on National GHG Inventories
Value Applied: 96.1
Justification of the
choice of data or
description of
measurement
methods and
procedures actually
applied
For (a) and (b): Measurements should be undertaken in line with national or
international fuel standards
Any comment:
Parameter: EFUtility FO,Data unit: (in tCO2/TJ)
Description: Emission factor for the fossil fuel used in the boilers in the baseline (Quantity of CO2
that would be produced per ton of fuel)
Source of data: IPCC default values at the lower limit of the uncertainty at a 95% confidence
interval as provided in table 1.4 of chapter 1 of Vol. 2 (Energy) of the 2006 IPCC
Guidelines on National GHG Inventories
Value Applied: 77.4
Justification of the
choice of data ordescription of
measurement
methods and
procedures actually
applied
For (a) and (b): Measurements should be undertaken in line with national or
international fuel standards
Any comment: For (a): If the fuel supplier does provide the NCV value and the CO2 emission factor
on the invoice and these two values are based on measurements for this specific fuel,
this CO2 factor should be used. If another source for the CO2 emission factor is used
or no CO2 emission factor is provided, Options (b), (c) or (d) should be used
Parameter: NCVUtility coal
Data unit: (TJ / Ton of fuel)Description: Net caloric value of the fossil fuel used in the boilers prior to the implementation of
the project activity in the year X
Source of data: The following data sources may be used if the relevant conditions apply:
Data source Conditions for using the data source
Values provided by the feedstock in
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
24/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 24
invoices
Regional or national average default
values
If values are reliable and
documented in regional or nationalenergy statistics / energy balances
IPCC default values at the lower
limit of the uncertainty at a 95%
confidence interval as provided in
Table 1.2 of Chapter 1 of Vol. 2
(Energy) of the 2006 IPCC
Guidelines on National GHG
Inventories
If above two data source is not
available.
Value Applied: 0.017
Justification of the
choice of data or
description ofmeasurement
methods and
procedures actually
applied
Any comment:
Parameter: NCVUtility FOData unit: (TJ / Ton of fuel)
Description: Net caloric value of the fossil fuel used in the boilers prior to the implementation of
the project activity in the year X
Source of data: The following data sources may be used if the relevant conditions apply:
Data source Conditions for using the data source
Values provided by the feedstock in
invoices
Regional or national average default
values
If values are reliable and
documented in regional or national
energy statistics / energy balances
IPCC default values at the lower
limit of the uncertainty at a 95%
confidence interval as provided in
Table 1.2 of Chapter 1 of Vol. 2
(Energy) of the 2006 IPCC
Guidelines on National GHGInventories
If above two data source is not
available.
Value Applied: 0.041
Justification of the
choice of data or
description of
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
25/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
26/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
27/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 27
= 295751 MT per Year
Baseline Emissions due to the use of feed (BEFeed,Hist)
The emissions due to the use of hydrocarbon feedstock for the production of ammonia / ammonia
derivative are calculated as follows:
HistFeedHistFeedHistFeed BEFQBE ,, *,=
Where:
QFeed, Hist Historical quantity of feed stock used for production of ammonia / ammonia
derivative (in tons)
BEFFeed,Hist Emission factor for the feedstock used in the baseline (Quantity of CO2 that would
be produced from the feedstock per ton of feedstock) (in tCO2)
HistFeedBE , = (244205 tonnes of feed stock per Year * 3.16 tCO2/tonne of feed stock)
= 771436 tCO2/Year
),,.( 1,1,,, = xFeedxFeedxFeedHistFeed BEFBEFBEFMinBEF
Where:
BEFFeed,x = Average CO2 emission factor for the feedstock used prior to the implementation of the
project activity in the yearx (in tons per ton of feedstock)
3
3
1
,,
,
=
=x
xHistFeed
HistFeed
Q
Q
Where:
QFeed,Hist = Historical quantity of feedstock used (in tons)
QFeed, Hist,-x = Quantity of feedstock used prior to the implementation of the project activity in yearx
(in tons)
Emission Factor for the feedstock (BEFFeed) is calculated as
HistFeedQ , = 30.834 tonnes per hour * 24 hrs/day * 330 days/year
= 244205 MT per Year
XFeedXFeedXFeed EFNCVBEF = ,,, *
Where:
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
28/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 28
EFFeed, -X CO2 emission factor of the feedstock used prior to the implementation of the project
activity in the yearX(in tonCO2/TJ)
NCV Feed,-X Net calorific value of the feedstock used prior to the implementation of the project
activity in the year X (TJ / Ton of feedstock)
XFeedBEF , = 77.4tCO2/TJ x 0.041 TJ/tonne of feed stock
= 3.16 tCO2/tonne of feed stock
Baseline Emissions due to the thermal energy used in the furnaces (BEHeat,y)
Baseline CO2 emissions from thermal energy are calculated as follows:
iheatiHeatHistiHeat
n
iHistHeatEFNCVQBE ,,,,, **=
Where:
QHeat i, HistAnnual average Historical quantity of fossil fuel i used in the furnaces for
production of ammonia (in tons)
NCVi,heat
iheatEF ,
Net Calorific value of fossil fuel i used for thermal energy in the furnaces(in
TJ/tonne)
CO2 Emission factor for the fossil fuel i(in tCO2)
3
3
1
,,,
,,
=
=x
xHistiHeat
HistiHeat
Q
Q
Where:
QHeat,i,, Hist,-x = Quantity of feedstock type I used prior to the implementation of the project activity in
yearx (in tons)
QHeat,iHist = 0 tonnes
HistHeatBE , = 0 tCO2/Year
Baseline Emissions due to use of fossil fuel in the Boilers (BEUtility,)
Baseline CO2 emissions due to the use of fossil fuel in the boilers for the process steam and power arecalculated as follows:
3
** ,,,,,,
3
1,
=
=
n
i
xiutilityxiutilityxiutility
xHistUtility
EFNCVQ
BE
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
29/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 29
Where:
xiutility
Q
,,
Historical quantity of fossil fuel i used in the boilers for production of steam
and power (in tonne per year) in the year x before the year of project activity,x
xiutilityNCV ,,
xiutilityEF ,,
Net calorific value of fossil fuel i used (TJ/Tonne)
CO2 Emission factor for the fossil fuel i (in tCO2/TJ)
HistUtilityBE , = (67.972 tonnes per hour x 330 days in Year x 24 hrs/day x 1.67 tCO2/tonne of coal)+ (4.179 tonnes per hour x 330 days in Year x 24 hrs/day x 3.16 tCO2/tonne of FO)
= 1003278 tCO2/Year
Baseline Emissions due to use of grid electricity (BEGrid,)
Baseline CO2 emissions due to the use of fossil fuel in the boilers for the process steam and power are
calculated as follows:
HistGridHistGridHistGrid BEFQBE ,, *,=
Where:
QGrid, Hist Historical quantity of power imported from the grid (in MWh)
BEFGrid,Hist Baseline emission factor for the power imported from the grid (in tCO2 /MWh)
HistUtilityBE , = (67.972 tonnes per hr * 24 hrs per day * 330 days per year *1.67tCO2/tonne of coal)+(4.179 kNM3/hr * 24 hrs per day *330 days per
year * 3.1667tCO2/tonne of heavy oil)= 1003278 tCO2/year
3
3
1
,,
,,
=
= xxHistUtility
HistiUtility
Q
Q
Where:
QUtility, Hist,-x = Historical quantity of fossil fuel i used in the boilers for production of steam and
power (in tonne per year) in the year x before the year of project activity ,x
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
30/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 30
),,.( 2,1,,,
= xGridxGridxGridHistGrid
EFBEEFMinBEF
Where:
BEFGrid,x = Historical CO2 emission factor for power imported from the grid (in tCO2 / MWh))
EFGrid,X = Emission factor of the grid from which the power is imported (in tCO2 / MWh). This
is computed using the latest version of the Tool for determination of emissions from
an electrical system
3
3
1
,,
,
=
= xxHistGrid
HistGridy
Q
Q
Where:
QGrid,Hist = Historical quantum of power imported from the grid (MWH)QGrid, Hist,-x = Quantum of power imported prior to the implementation of the project activity in year
x (in MWh)
HistGridyQ , = 13615 MWh
HistGridBE , = 13615 MWh x 0.8 tCO2/MWh
` = 10892 tCO2/year
For the determination of emission factors of the fuels and the feedstock, guidance from the 2006 IPCC
Guidelines for National Greenhouse Gas Inventories has been followed where appropriate
Project Emissions
Project activity emissions are calculated as follows:
yGridyUtilityyHeatyFeedy PEPEPEPEPE ,,,, +++=
Where:
PEFeed,y Emissions due to the use of feedstock for the production of ammonia / ammonia derivative in
each year Y of the crediting period,(in tCO2)
PEHeat,y Emissions due to the production of thermal energy used in the furnaces (feed treatment and
reforming) after deducting the CO2 recovered by the CDR plant (if any) in each year y of the
crediting period, in tCO2.
PEUtility,y Emissions due to use of fossil fuels in the boilers for onsite production of steam and power in
each year y of the crediting period, in tCO2.
PEGrid,y Emissions due to import/ export of power from the grid in the year y of the crediting period
(in tCO2)
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
31/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
32/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 32
For determination of emission factors, guidance from the 2006 IPCC Guidelines for National Greenhouse
Gas Inventories has been followed where appropriate.
yHeatPE , = 6.154kNM3/hr * 24hrs/day *330 days/year*0.036TJ/NM3*56.1tCO2/TJ
= 98160 tCO2/Year
Emissions due to use of fossil fuels in the boilers (PEUtility,y)
Emissions due to the production of thermal energy used in the furnaces (feed treatment and reforming) are
calculated as follows:
YiutilityPJCO
i
YiutilityYiUtilityYUtility EFNCVFCPE ,,,,2,,,,, =
yUtilityPE , = (47.314T/hr *24 hrs/day *330days/year*1.67tCO2/tonne of fuel) + (3.242*24 hrs/day
*330days/year*2.01tCO2/tonne of NG)
= 677289 tCO2/Year
Where:
FCUtility,i,Y Quantity of fuel type i consumed in the boilers of the power plant for producing power and
steam in year y of the crediting period, in mass or volume units.
NCVi,Y Net calorific value of fuel type i in each year y of the crediting period, in (TJ/mass or volume
units.)
EFCO2,PJ,utility
,,i,Y
CO2 emission factor of the fuel type i used in the boilers of the power plant in the year y of
the crediting period, (in tCO2/TJ).
For determination of emission factors, guidance from the 2006 IPCC Guidelines for National Greenhouse
Gas Inventories has been followed where appropriate.
Emissions due to import / export of power from the grid (PEGrid,y)
The emissions / emission reductions due to import / export of power from the grid can be computed as
follows:
YGridYPRGridYGrid EFQPE ,,,, =
Where:
QGrid,PR,Y, Quantum of electricity imported from the grid in the year y of the crediting period, in MWh.
EFGrid,Y CO2 emission factor for the power from the grid in the year y of the crediting period, in
tCO2/MWh.
EFgrid,Y, is the emission factor of the grid that must be calculated as the generation-weighted average
emissions per electricity unit of all generating sources serving the system.
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
33/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
34/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
35/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 35
Any comment: Volumetric units should be at normal pressure and temperature
Data / Parameter: QGrid,PR,yData unit: MWh
Value Applied: 13615
Description: Quantity of electricity obtained from / supplied to the grid by the project activity
during each year y of the crediting period. Measured at the project site.
Source of data: Measured in the project activity by digital control systems and/or data logs.
Measurement
procedures (if any):
Electrical Energy Meter
Monitoring frequency: Continuously
QA/QC procedures: Electrical Energy Meter used for measurement should be calibrated regularly as
per ISO procedures or according to manufacturers guidelines
Any comment: In case of net export of power to the grid. Negative sign will be used
Data / Parameter: FCUtility coal, y
Data unit: Tonnes Per Year
Description: Quantity of fuel type i consumed in the boilers of the power plant generation of
steam and power in each year y of the crediting period.
Value Applied: 374726
Source of data: On-site measurements
Measurement
procedures (if any):
Flow-rate meters
Monitoring frequency: Continuously
QA/QC procedures: Meters should be calibrated regularly according to manufacturers guidelines.
Any comment: Volumetric units should be at normal pressure and temperature
Data / Parameter: FCUtility Natural Gas, y
Data unit: kNM3 Per Year
Description: Quantity of fuel type i consumed in the boilers of the power plant generation of
steam and power in each year y of the crediting period.
Value Applied: 25676
Source of data: On-site measurements
Measurement
procedures (if any):
Flow-rate meters
Monitoring frequency: Continuously
QA/QC procedures: Meters should be calibrated regularly according to manufacturers guidelines.
Any comment: Volumetric units should be at normal pressure and temperature
Parameter: NCVcoal,yData unit: TJ/tonnes of coal
Description: Average net calorific value of coal in year y of the crediting period.
Value Applied: 0.017
Source of data: IPCC Guidelines for National Greenhouse Gas Inventories.
Measurement
procedures (if any):
-
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
36/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 36
Monitoring frequency
QA/QC procedures -
Any comment: -
Parameter: CV G,y
Data unit: TJ/NM3 of NG
Description: Average net calorific value of fuel type i and NG/LNG respectively, in year y of
the crediting period.
Value Applied: 0.036
Source of data: IPCC Guidelines for National Greenhouse Gas Inventories.
Measurement
procedures (if any):
-
Monitoring frequency
QA/QC procedures -
Any comment: -
Data / Parameter: EFCO2, PJ coal i,y
Data unit: tCO2/TJ
Description: CO2 emission factor of fuel type i used for steam generation in the boilers in the
year y.
Value Applied: 96.1
Source of data: IPCC Default Values
Measurement
procedures (if any):
Monitoring frequency: Yearly
QA/QC procedures:
Any comment:
Data / Parameter: EFCO2, PJ Natural Gas i,y
Data unit: tCO2/TJ
Description: CO2 emission factor of fuel type i used for steam generation in the boilers in the
year y.
Value Applied: 56.1
Source of data: IPCC default values
Measurement
procedures (if any):
Monitoring frequency: Yearly
QA/QC procedures:
Data / Parameter: QGrid,PR,y
Data unit: MWh
Value Applied: 13615
Description: Quantity of electricity obtained from the grid by the project activity during each
year y of the crediting period. Measured at the project site.
Source of data: Measured in the project activity by digital control systems and/or data logs.
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
37/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 37
Measurement
procedures (if any):
Electrical Energy Meter
Monitoring frequency: ContinuouslyQA/QC procedures: Electrical Energy Meter used for measurement should be calibrated regularly as
per ISO procedures or according to manufacturers guidelines
Any comment:
Data / Parameter: EFgrid,y
Data unit: tCO2/MWh
Value Applied: 0.80
Description: CO2 emission factor for grid electricity during the yeary.
Source of data: Use the latest approved version of Tool to calculate emission factor for an
electricity system to calculate the grid emission factor.
Measurement
procedures (if any):
-
Monitoring frequency: Either once at the start of the project activity or updated annually, consistent
with guidance in Tool to calculate emission factor for an electricity system.
QA/QC procedures: Apply procedures as in Tool to calculate emission factor for an electricity
system
Any comment: All data and parameters to determine the grid electricity emission factor, as
required by Tool to calculate emission factor for an electricity system, shall
be included in the monitoring plan.
Any comment:
Data / Parameter: EFCO2,upstream,LNG,y
Data unit: tCO2/TJ
Description: Emission factor for upstream CO2 emissions due to fossil fuel combustion /
electricity consumption associated with the liquefaction, transportation, re-gasification and compression of LNG into a natural gas transmission or
distribution system in year y.
Value Applied: 6
Source of data: Default Value given in the methodology
Measurement
procedures (if any):
Where reliable and accurate data on upstream CO2 emissions due to fossil fuel
combustion / electricity consumption associated with the liquefaction,
transportation, re-gasification and compression of LNG into a natural gas
transmission or distribution system is available, project participants should use
this data to determine an average emission factor. Where such data is not
available, project participants may assume a default value of 6 tCO2/TJ as a
rough approximation2.
Monitoring frequency: Yearly
2This value has been derived on data published for North American LNG systems. Barclay, M. and N. Denton,
2005. Selecting offshore LNG process. http://www.fwc.com/publications/tech_papers/files/LNJ091105p34-36.pdf
(10th April 2006).
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
38/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
39/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 39
The unit head is responsible for the overall functioning and maintenance of the project activity. The Shift
operator maintains all the data records and ensures the completeness and reliability of the data. The ShiftIn-charge maintains a day to day power generation log. The monitoring reports are checked periodically
by the Plant In-charge and discussed thoroughly with the data monitoring personnel. Corrective action is
taken immediately if any improper functioning or operation problem with the equipment is observed. The
archived data shall be kept for two years after the crediting period or issuance of CERs.
After verification of the data and due diligence on the correctness if required, an annual report on
monitoring and estimations shall be maintained by the CDM team and record to this effect shall be
maintained for verification.
QA & QC Procedures to be followed
Necessary check meters as required would be installed, to operate in standby mode or when the main
meters are not working. All meters will be calibrated and sealed as per industry practices at regularintervals. Records of calibration certificates will be maintained for verification. Hence, high quality is
ensured with the above parameters.
B.8. Date of completion of the application of the baseline study and monitoring methodology
and the name of the responsible person(s)/entity(ies):
>> The date of completion of baseline and monitoring methodology is 31/07/2011. Contact details of the
person responsible for development of baseline and monitoring methodology is given below
Mr. K.K. Goel
National Fertilizers Limited
A-11 Sector 24
NOIDA, Uttar Pradesh201301
E-mail: [email protected]
SECTION C. Duration of the project activity / crediting period
C.1. Duration of the project activity:
C.1.1. Starting date of the project activity:
>> 29th January 2010
C.1.2. Expected operational lifetime of the project activity:
>> 20 Years
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
40/43
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
41/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 41
Annex 1
CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY
Organization: National Fertilizers Limited
Street/P.O.Box: Sector 24
Building: A-11
City: NOIDA
State/Region: Uttar Pradesh
Postcode/ZIP: 201301
Country: India
Telephone: 0120-2412383
FAX: 0120-2412384
E-Mail: [email protected]
URL: www.nationalfertilizers.comRepresented by: -
Title: Chief Manager Mechanical
Salutation: Mr.
Last name: Goel
Middle name: -
First name: K.K
Department: Technical Department
Mobile: +919910575722
Direct FAX: +911202412397
Direct tel: +911202412294
Personal e-mail: [email protected]
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
42/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 42
Annex 2
INFORMATION REGARDING PUBLIC FUNDING
7/29/2019 NFL Panipat PDD_ 25 Oct- 2011
43/43
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM Executive Board
page 43
Annex 3
BASELINE INFORMATION
Annex 4
MONITORING INFORMATION
- - - - -