New page for summary of test status. https://espace.cern.ch/mddb/Systems%20Dry%20Run%20Tests/Home.aspx. Dry Run week 19. Pulse injection kickers in point 2 BIS arming and frequency control (linking, starting) through sequencer Trigger BPMs with pre-pulses Prepulse coming 900 ms too late - PowerPoint PPT Presentation

Citation preview

Page 1: New page for summary of test status

R. Alemany & V. Kain, 19th of May 09

LHC

New page for summary of test status

o https://espace.cern.ch/mddb/Systems%20Dry%20Run%20Tests/Home.aspx

1

Page 2: New page for summary of test status

R. Alemany & V. Kain, 19th of May 09

LHC

Dry Run week 19o Pulse injection kickers in point 2

o BIS arming and frequency control (linking, starting) through sequencer

o Trigger BPMs with pre-pulses

o Prepulse coming 900 ms too late

o New LHC mastership scheme

o New mastership scheme: can become master on spare (remove user request)

o Logging of transfer lines

o Independent of user and extraction time (for PCs)

o Solution for power converter logging will be tested next dry run

2

Page 3: New page for summary of test status

R. Alemany & V. Kain, 19th of May 09

LHC

FGCs – operational settings

o Slides by Alick

3

Page 4: New page for summary of test status

R. Alemany & V. Kain, 19th of May 09

LHC

“Dry run” week 21 - cancelledo Extract to TT40 and TT60

o Check mastership: extract under LHC master, re-phasing, check pre-pulse

o Verify that cannot have any dynamic destination when under injection test mode

o Pulse MKIs (new softstart for MKI 8?)

postponed to next week

o Run collimators through sequencer this week

4

Page 5: New page for summary of test status

R. Alemany & V. Kain, 19th of May 09

LHC

Dry run week 22o BLM online-check

o Transfer line logging: new PC logging

o BPM triggered by pre-pulses

o BCTs – SMP?

o Test RF power:

o Sequencer tasks, status fixed display, application

o Trim + incoorporate

o 26th of May: RBAC dry run:

o Mode: operational/ non-operational

o PIQUET role5

Page 6: New page for summary of test status

R. Alemany & V. Kain, 19th of May 09

LHC

Dry run VI June > week 23

o RF low level:

o All tasks:

o Load actual settings: gains, voltages, frequencies

o Load gains, voltages, frequencies

o Reset F-rev [before first injection]

o Re-phase [before collisions]

o All applications ready and settings for operational hyper-cycle available:

o RF low level application: status of loops, plus possibility to switch loops

o Injection signals fixed displays available

o Follow-up issues

6

Page 7: New page for summary of test status

R. Alemany & V. Kain, 19th of May 09

LHC

Dry run week 26o MKQA AC-Dipole

o All applications: tune, multiturn

o Timing events

o Interlocking tests (keys,...)

o Transverse feedback

o Application

o Cleaning

o Sequencer task

o Follow-up issues

7

Page 8: New page for summary of test status

R. Alemany & V. Kain, 19th of May 09

LHC

8

Page 9: New page for summary of test status

R. Alemany & V. Kain, 19th of May 09

LHC

9