1
Secretariat receives Application Form & ensure required docs are complete 1 st level of approval CEO / Hon. Sec-Gen 2 nd level of approval (every Monday) Chapter Chairman Issuing Proforma Invoice Applicant to submit payment slip / cheque 3 rd level of approval (every Monday) Board Members Issuing receipt Membership certificate (official member / member in benefit) New Membership Application Process 1 week 1 week 2 days 2 days Required Supporting Documents License from Companies Commission of Malaysia (Form 9) Copy of operating license / permits from local authority / government agency Hotel brochure (if applicable) Other official documents that can proof the hotel will be set up (if the hotel is under construction) Payment slip is required as a proof of payment

New Membership Application Process

Embed Size (px)

DESCRIPTION

new membership process

Citation preview

  • Secretariat receives

    Application Form & ensure required docs are complete

    1st level of approval

    CEO / Hon. Sec-Gen

    2nd level of approval

    (every Monday)

    Chapter Chairman

    Issuing Proforma

    Invoice

    Applicant to submit

    payment slip / cheque

    3rd level of approval

    (every Monday)

    Board Members

    Issuing

    receipt

    Membership certificate

    (official member / member in

    benefit)

    New Membership Application Process

    1 week1 week 2 days2 days

    Required Supporting Documents License from Companies Commission of Malaysia (Form 9) Copy of operating license / permits from local authority / government agency Hotel brochure (if applicable) Other official documents that can proof the hotel will be set up (if the hotel is under construction)

    Payment slip is required as a