Upload
lamdung
View
215
Download
1
Embed Size (px)
Citation preview
1
1
Pipe Jacking/Microtunnelling
Dr. Mark Knight
Centre for Advancement of Trenchless Technologies (CATT)University of Waterloo
2
New InstallationsNew
Installations
Non-SteeringMethods
SteeringMethods
Moling/PiercingPipe RammingAuger Boring
MicrotunnellingHorizontal Directional Drilling
Pipe Jacking
2
3
Pipe Jacking
Oldest method of trenchless technologyApplications
Larger Diameter Pipe (1050 mm and up)
Lengths can range from 3 to over 200m
4
Pipe JackingPerson entry
Pipe diameters greater than 900 mm (36”)Difficult to work in excavations of this size
Practically limited to dia. greater than or equal to 1075 mm (42”)
Pipe installation process occurs from entrance and exit shaft
Access way locations
3
5
Pipe Jacking Process
6
Pipe JackingMaterial excavation completed by persons within the excavation
Manual or machine face excavationExcavation takes place in front of an articulated shield
Designed for worker safety Maintains open bore for pipe jacking or tunnel lining construction Shield guided with individually controlled hydraulic jacks
4
7
Pipe Jacking Excavation
8
Pipe Jacking Excavation
5
9
Pipe Jacking
Types of TunnelingHand miningLiner PlateJack Reinforced Concrete PipeJack Steel LinerCap and Leg (Wood Lined Tunnel)
10
Pipe Jacking ProcessSimple cyclic procedureUtilizes thrust from hydraulic jacks to force the pipe forward
Pipe placed on cradle in the entry or jacking pit Thrust developed from thrust blocks
Concrete, steel, soil excavation
6
11
Pipe Jacking Pit
12
Pipe Jacking Pit
7
13
Pipe Jacking Process
Unstable soilFace excavated simultaneously with the jacking operation
Minimize over excavation and the risk of face collapse
After pipe jacked into place hydraulic rams are retracted and another pipe length is installed
14
Pipe Jacking Process
Stable soilFace excavation may precede the jacking operationAll spoils removed through the inside of the pipe to the jacking pit
8
15
Hand Excavation
16
Pipe Jacking Process
9
17
Pipe Jacking Pit
Jacking pit size is function of:Length of pipe segments Pipe diameterShield dimensionsThrust wall designJack sizePressure ringsGuide rail systems
18
Pipe Jacking Pit
Pit should be shoredTimber, steel piling or shaft liner plate, ground freezing
For projects requiring large thrust Design of launch pit is critical
Pit should be dry Floor preparation key for controlling alignment
10
19
Pipe Jacking PitFor a large job the placement of a concrete mud slab on the shaft floor is recommended For a smaller job the placement of a 300mm of crushed stone is recommended
20
Pipe Jacking ForceForce on jacked pipe includes:
Pipe dead weightPenetration resistanceSoil-pipe friction
Jacking force applied by two, four or six jacks
11
21
Other ForcesSoil dead loadRailway or highway live loadsJacking force must not exceed allowable pipe compressive strength
Critical design location is the jointsLow surface area - high stressWater tightness??
22
Pipe Jacking ForceSoil-pipe frictional force minimized by the application of lubricant to the outer pipe surface
Can reduce jacking force by 50% Manual application or pumping of bentonite slurry around pipePolymers
Advantage only small amount required
12
23
Pipe Jacking ForceTo minimize pipe damage during jacking
Packing material can be placed between the pipe joints
12 to 19mm plywood12 to 25mm manila rope, jute, oakum
Provides joint cushioning and flexibility
24
Pipe Jacking ForceFor long pipe installations
Intermediate jacking stations may be used
Set of hydraulic jacks placed between pipe segments
13
25
Intermediate Jacking Station (IJS)
26
Intermediate Jacking Station (IJS)
14
27
Intermediate Jacking Station (IJS)
Total drive expected to exceed capacity of main jacksCapacity 100 to 1600 tonsDiameter around 36” length 56”IJS assembled in four segmentsIJS must match pipe dia. for proper operation
28
Intermediate Pipe JackingThree step pipe jacking process:1. Intermediate jacks are used to jack
the forward sections of pipeThrust is provide by the pipe section behind the intermediate jacks
2. Intermediate jacks are retracted3. Back section of pipe is jacked using
the launching pit cradle
15
29
CLAY PIPE
REINFORCED CONCRETE PIPE
Jacking Pipe
30
Jacking Pipe MaterialReinforced concrete (RCP)Polymer concreteFibreglass (Hobas)Vitrified clay (VCP)SteelDuctile IronComposites
16
31
32
PIPE JOINTS
17
33
Pipe JointsMust withstand high jacking forcesCreate water tight sealsFlush joints to decrease jacking forces
34
PJ ApplicationsSewers, and drainage constructionGas and watermainsOil pipelinesIndustrial pipelinesTelecommunication Pedestrian subways (access tunnels)
18
35
PJ Advantages
Quick set-upWhen grade is criticalVersatile in various ground conditionsCost efficient for large diameter pipeSmall surface settlements
Settlement controlled by face excavation
36
PJ LimitationsAccess to the face of the tunnel is needed at all timesSpeed of the mining operation is reliant on:
Speed of labour (workers)Soil Matrix
Rock Soft Soil Water Table
Dewatering of tunnel path is usually required
19
37
New Installation
Steering Methods
MicrotunnellingHorizontal directional drilling (HDD)
38
MicrotunnellingNew
Installations
Non-SteeringMethods
SteeringMethods
MolingPipe RammingAuger Boring
MicrotunnellingHorizontal Directional Drilling
Pipe Jacking
20
39
MicrotunnellingRemotely controlled and guided pipe jacking technique that provides support to the excavation face and does not require personnel entry into the tunnelLaser guided micro TBM used for soil excavationDrive from access way to access way (manhole locations)Mainly used for gravity sewers but can be used for large water mains
40
Microtunnelling
•Non-person entry
•Machine excavated (mini TBM)
•Remote controlled
•Similar to pipe jacking
•Pipe OD less than 1.0m
21
41
Tunnel Boring (TBM)
Chunnel
World largest tunneling machine(14.2 m in diameter)
people
42
Microtunnelling
22
43
Microtunnelling
44
MicrotunnellingAccuracy typically better than ± 25 mm per driveLaser controlledVariety of machines for different soil conditionsMain applications: deep systems
23
45
MicrotunnellingAccurate monitoring and adjusting of the alignment and grade as work proceeds
Pipe can be installed on precise line and grade
Generally used for pipe diameters less than 900mm (36 inches)Can be used for larger diameters
46
Launching and Exit PitsUse same design procedure as for pipe jacking Length of tunneling machine can control launch and exit pit size
24
47
Entrance and Exit Pit ShieldsNeopreme sheet stock held in steel ring
48
Entrance and Exit Pit ShieldsPrevents slurry and ground water from entering into shafts
25
49
Jacking System
50
History
Originated in Japan and Germany in 1970’sDevelopment government sponsored
Need for pipe construction method with minimum surface disruption in over congested areasKomatsu introduced first Microtunnelling machine in 1975 - IRONMOLEISEKI inc introduced there machine in 1976
Ability to counter balance earth pressure mechanically and hydraulically
26
51
History
First Microtunnelling project in North America
Fort Lauderdale Florida in 1984 615 feet of 72 inch pipe under I-95
Second project Bridgeport CT in 1986 3610 feet of 72 inch pipe
52
HistoryAs of October 1996
Total MT North America footage 547,100 feetTotal number of projects = 254
27
53
MT Classification MethodsBased on mode of operation
Slurry methodAuger method
54
Slurry MethodTunnel face is supported mechanically or by a pressurized slurrySpoils (cuttings) removed hydraulically in the form of a slurryConveying fluid is used to counteract hydrostatic forces caused by ground water pressure and soil removal
28
55
Slurry MethodLOVAT MTS 1000
56
Slurry Method
29
57
Slurry MethodSoil cut mechanically
Cutting head designs depends of soil or rock type
Cuttings removed by hydraulic actionCuttings enter bore head through inlet openings and placed in suspension in the slurry chamber - water and bentonite
58
Slurry Method
30
59
Lubrication SystemTypical system components:
Variable speed discharge pumpCharge pumpIntermediate pumpsFlow meterFlow controllerPit by pass to permit diversion of flowsPiping, flexible hoses and cabling
60
Slurry SeparationTypical separation plant components:
Vibrating screensCyclones for small particle separationClay ball separatorSettlement tank
31
61
Slurry SystemDepth of ground water up to 30m can be managedDue to efficiency of shield small pipes can be usedFull measurement and control of slurry flows
62
Auger MethodSoil cutting at the face by a bore head and soil removal by means of a continuous flight of augersAugers run in a separate guiding pipeBetter suited for cohesive soils
32
63
Auger Method
64
Auger MethodLOVAT MTS 1000
33
65
Auger Method (Drill)Phase I
a steerable pilot tube is jacked into the ground displacing the soil.
66
Steerable pilot tube
34
67
Phase I
68
Guidance System
35
69
Phase I
70
Auger Method (Drill)Phase II
install a temporary steel casing
36
71
Standard Reaming Heads
72
Phase II
37
73
Standard Reaming Heads
74
Phase II
38
75
Full face with Ground water control
76
Phase II – Casing with Augers
39
77
Phase II – Casing Installation
78
Auger Method (Drill)Phase III
the product pipe is installed
40
79
Auger Method (Drill)Phase III
the product pipe is installed
80
Phase III
41
81
Auger Method (Drill)Steered pilot tubeCombined Phase II & III (<150mm OD)Phase III (150 to 225mm)Shafts 2m diaDrive lengths 60m plus
82
MT Equipment SelectionVariety of machine typesChoice depends on ground condition
Type of soil/rockSand, gravel, clay, boulders, etcGround water table
Project success depends on have a proper soil investigation
42
83
MT Equipment
84
MT Advantages
Grade and alignment accuracy (± 25 mm)Works well in a wide variety of soil conditions
Some problems with boulders
Works well below groundwater tableNo expensive dewatering systems requiredUp to approx 30m below GWT
Increasing line depths does not significantly increase cost
43
85
MT Advantages
Worker safetyNo ground surface settlement
86
MT Disadvantages
High equipment capital costLateral connections?Difficulty with bouldersChanging ground conditionsWood and debris
44
87
Microtunnelling PipeSame as for pipe jacking
88
Other RecommendationsEnsure sufficient room adjacent to the launch pit for:
Pipe and machine storageDrill fluid mixing and recyclingSpoil/cutting removal
45
89
Safety PrecautionsSafe pit designOverhead clearance for equipment
Lower pipe and machine into the access launch pitsRetrieve machine from exit pits
Underground utility clearance
90
MT RisksPipe diameter
Risk decreases as diameter increases
LengthRisks increases as length increases
46
91
Cost36” (900 mm) = $650 to 850/ft48” (1200 mm) = $800 to 1200/ftShafts
50 to 100kDepends on groundwater, depth & soil conditions
Need over 1million dollar project to start to look at Microtunnelling
92
Microtunnelling in KL
47
93
Microtunnelling in KLApprox. 70km 1800mm OD sewerLOVAT MTS (Toronto Canada)3 to 4 pipe sections 2950mm long per dayDrive length 64 sections (~190m long)~RM90,000,000 Project
94
Microtunnelling in KL
EXIT SHAFT
48
95
Microtunnelling in KLMT machine currently stuck under the riverWill sink rescue shaft to recover