Long Beach Unified School District 1
New Browning High School Construction
New Browning High School Construction
Community Update April 16, 2014
Long Beach Unified School District 2
New Browning High School Construction
TEAM MEMBERS
Meet the Team
• Tova K. Corman – Executive Director, Facilities, Development & Planning
• Nghi Nghiem – Project Manager • Helena Jubany & Richard Hernandez – NAC Architecture • John Bernardy, Charles Brown, Randall Joiner, and John Atherton
- Balfour Beatty – Construction Manager
Long Beach Unified School District 3
New Browning High School Construction
Project Goals
1. Creating 21st century learning environments for the next generation
2. Changing type and size of high schools • Construction of new state of the art small
high school
3. School safety and security • Student drop-off separate from parking • Managed single point of entry to campus • State of the art fire alarm, intercom, and
security cameras
4. Joint-use • Facilities could be available for community
use
PROJECT GOALS & OBJECTIVES
Long Beach Unified School District 4
New Browning High School Construction
BROWNING HS SITE PLAN
Facility Program • Proposed enrollment - 840
students • Grades 9-12 • 10.3 acre site • Buildings: 4
• Admin/CR • Library/CR • MPR/CR • Gym
• Classrooms: 31 • Thematic Focus (SLC):
• Food Science/Food Service
• Hospitality • Tourism • Recreation
North West View
Admin/ CR
MPR/ CR
Gym
Library/ CR
Fields
Long Beach Unified School District 5
New Browning High School Construction
Education Program • Learning laboratories • Science laboratories • Technical educational laboratories • Special education classrooms • Visual arts classrooms • Teaching stations • Administration building • Media center • Gymnasium • Multi-purpose room • Food services
EDUCATION PROGRAM
Long Beach Unified School District 6
New Browning High School Construction
RENDERINGS OF NEW BUILDINGS
Obispo Street View
View of Courtyard
Long Beach Unified School District 7
New Browning High School Construction
TYPICAL DESIGN OF NEW BUILDINGS
Cut thru of Academic Building
Cut thru of Library
Long Beach Unified School District 8
New Browning High School Construction
CONSTRUCTION PHASE
START DATE
COMPLETION DATE
Phase 1: Site Prep May 2014 September/ October 2014
Phase 2: Building New High School
October 2014 September 2016
CONSTRUCTION PHASING
View from Obispo facing the entrance
View of Courtyard from the Fields
Long Beach Unified School District 9
New Browning High School Construction
Construction Safety and Logistics • District site supervision • Full time on site Construction Management firm • Monitor and control construction traffic • Hours of operation are: Monday – Friday: 7:00 am – 7:00 pm; Saturday:
9:00 am – 6:00 pm • Install fencing and barricades to separate construction from the
community • Keep site and surrounding areas clean of construction debris and dust
control • Implement continuous safety training of construction personnel • Maintain open communication with the community
Equipment you may see: Scrapers, skip loaders, trucks hauling in and out, back hoes, cranes, various equipment/machinery, and water trucks
CONSTRUCTION SAFETY & LOGISTICS
Long Beach Unified School District 10
New Browning High School Construction
CONSTRUCTION TRAFFIC ROUTE
Long Beach Unified School District 11
New Browning High School Construction
CONSTRUCTION TRAFFIC ROUTE
Long Beach Unified School District
Browning High School Project Materials & Loading Access Route
Construction traffic to utilize the Lakewood Avenue Exit from 405 North or South.
Construction Route: 1. South on Lakewood Avenue 2. West on Willow Street 3. South on Redondo Avenue
Future Browning High School
Long Beach Unified School District 12
New Browning High School Construction
Q & A