Conference: Design-Build for Water/Wastewater Conference 2016 Paper/Presentation Title: Never Give Up! Strategies for Overcoming Project Delivery Challenges and Roadblocks Authors: David Schwartz, CDM Smith; Brent Christ, DC Water/DBIA; Mike Angeli, PC Construction/DBIA; Brian Hagerich, CDM Smith/DBIA; Leonard Benson, DC Water; Phil Braswell, Brown and Caldwell Contact: Phil Braswell - [email protected] Abstract Never Give Up! Strategies for Overcoming Project Delivery Challenges and Roadblocks You've heard the success stories; now you can hear the unfiltered reality of what goes on behind the scenes of a complicated and pressure-packed project, and learn how one team worked together to slay the dragons and make the effort a success and point of pride for all involved. This battle-tested project team will frankly address the major challenges they faced and worked their way through, share strategies for design-building innovative technologies on a large scale, and emphasize the vital importance of intensive partnering to overcome potential roadblocks. Learning Objectives:
• Project lessons learned: We share some hard-earned lessons from our project about the need to effectively address change management, unforeseen conditions and administrative hurdles.
• Challenges of complexity: the innovative, large projects that DB is ideal for can also present difficulties. Here's what to expect and how to overcome those challenges.
• Prioritize partnering: Partnering on a tricky DB project isn't merely an occasional "kumbaya" meeting. Learn how our team of design-builders and owner worked intensively together to overcome challenges, manage change and make the project work.
• Best practices for challenging projects: with lessons learned from this project, we leave the audience with our recommendations to plan for the struggles, overcome the obstacles and reach the finish line as a team.
Never Give Up! Strategies for OvercomingProject Delivery Road Blocks
Brent Christ, DBIA, DC WaterLeonard Benson, DC WaterDavid Schwartz, CDM SmithMike Angeli, DBIA, PC ConstructionBrian Hagerich, DBIA, CDM SmithPhil Braswell, Brown and Caldwell
Project Overview Major HurdlesOutcome:
Were Objectives Met?
Agenda
370 mgd (1400 mega-liter/day) treatment facility
World’s largest advanced (nutrient removal) wastewater treatment plant
Class A biosolids
Overview
Key Contributors
Bringing a Complex, World Class Project to Life
Owner │ DC Water
Biosolids Program Manager │ Brown and Caldwell
Main Process Train Design Build Team│ PC Construction/CDM Smith JV
CHP Design, Construction, and Operation│ Pepco Energy System (PES) with Black & Veatch and Ulliman Shutte
Construction Mgmt for MPT, CHP, and FDF│ Arcadis
Final Dewatering Facility Design│ CH2M
Final Dewatering Facility (1C) Construction│ Corinthian Contractors
Final Dewatering Facility (2C) Construction│ PC Construction
Site Preparation Construction Management│ Earth Tech (AECOM)
Site Presentation Construction│ Alberici Construction
Objectives
Reduce quantity of biosolids and hauling
Increase marketability of biosolids
Recover energy
Reduce greenhouse gas emissions
Convert Class B, lime stabilization sludge facility into an innovative sustainable Class A biosolids system
Components
4 Contracts
3 Delivery Methods
Why Alternative Delivery?
The Result …
Screening Storage BinsCentrifuges
The Result …
Cambi Digesters Flares
Project Overview Major HurdlesOutcome:
Were Objectives Met?
Agenda
Contract Negotiations
Bonding company issues
Liability
Primary and secondary specifications
Industry Outreach Lowered Hurdles
Owner Requirements
Price certainty at an early phase for budget management
Still allowed for competitive pricing amongst the best shortlist teams in addition to a technical evaluation at the RFP stage
Fixed Price
Owner Requirements
A Term Sheet is Not a Complete Contract
• Commercial Terms
• Backcharges
• Liquidated Damages
• Actual Damages
Sole Source to Cambi
Owner Requirements
Keeping the Faith
Cambi’s first US project
LOTS of opportunities in the US
We knew Cambi would not let this fail
Reasonable protection in the prime contract
Challenges of a Prescriptive Contract
Owner and Program Manager developed concepts for bridging documents
Owner preferences vs. design builder preferences
A lot of work by DB to demonstrate benefits
Overcoming “Pride of Ownership”
Challenges of a Prescriptive Contract
Would DB be reimbursed?
Engineering costs
Construction costs
Credit expected
No cost shared for VE ideas
Stifled Creativity
Working within Fixed Price
Maintaining Communications: Weekly Coordination
DC Water Project Manager
Program Management Leadership
Construction Management Leadership
DB Leadership: Design Team, Construction Team, Commissioning Team
Key Stakeholders
Project Charter
We will work collaboratively to deliver to DC Water a reliable and easy to maintain biosolids Main Process Train that will consistently and cost-effectively produce a Class A biosolids, generate digester gas and meet all performance and schedule requirements. The team will demonstrate the viability of the design-build process for DC Water while enhancing the reputations of all partners. We will accomplish this by achieving the following team goals:
Safety BudgetScheduleQuality TeamworkCommissioning Community
Issue Resolution/Partnering
Maintain Relationships
Track Performance
Issues Escalation Log
Weekly Coordination of Key Stakeholders
Issue Resolution/Partnering
Issue Escalation Log Example
Issue
Target Resolution
DateFor
Path Forward
Current Issue
Location(Level/
Individuals)
Scheduled Date for
EscalationChampion
Estimated Close-Out
Date
Ball In Court
Organization
Next step in processAcceptable Solution
Comments
Centrifuges: centrateventing
11/20/15 Level 3 NA Mike Angeli
January 15, 2015
JV JV providing a test to ensure no particulate matter is exiting the vent stack over a long period of time, thru all modes of operation.
Issue Resolution/Partnering
Go/No Go Final Pre-Meeting
What Does it Take to Resolve an Issue? Clearly identify the issue An issue is everyone’s – we win/lose
together Assign a champion Communicate Plan for Resolution Review progress Track/celebrate successes
Going Live!
First truck of seed sludge from Alex Renew
Issue Resolution/Partnering
Case Study: SeedingTracked potential showstoppers up until decision date
Decision on notices to communities about intent to haul sludge starting 9/30
Decision on purging digester head space with nitrogen
Decision on pre-heating water in the digesters
Go-No Go Final Pre-Meeting to tracking commissioning efforts and status of control systems
Project Overview Major HurdlesOutcome:
Were Objectives Met?
Agenda
Outcome: Were the Objectives Met?
Processes up to 450 dry metric tons of solids per day
Requires half the digestion capacity of conventional digestion
Class A digested sludge is conveyed to sixteen, 2-meter belt filter processes for final dewatering
Outcome: Were the Objectives Met?
Specification conformance inspection during installation and continuous performance monitoring helped ensure that the new facilities operated as intended
Outcome: Were the Objectives Met?
Generates 13 megawatts of green electrical power for plant operations
Reduces annual grid electrical draw by one-third
Reduces number of trucks by over half
Considered to be One of the Greenest and Most Sustainable Wastewater Projects Ever Conceived
Class A Biosolids
DB Lessons Learned
Implement an issues resolution process in order to solve issues at the appropriate level with a clear escalation process
Performance guarantees proved to be valuable
- Flexibility with durations and or overlap
- Operations and Maintenance buy-in is valuable
Transition of owner’s roles from design phase to construction phase for reviews needs to be addressed – bring in the right players without loss of project history/knowledge
1
2
3
DB Lessons Learned
Receiving detailed submittals proved beneficial
“Good engineering practices” is not a recognized standard
Changes after Final Design Drawings are approved must be identified to the owner
Named manufacturers might take exception to specifications: Ensure in RFP that named manufacturers will meet code and/or specifications required
4
5
6
7
Questions
Project Charter
We will work collaboratively to deliver to DC Water a reliable and easy to maintain biosolids Main Process Train that will consistently and cost-effectively produce a Class A biosolids, generate digester gas and meet all performance and schedule requirements. The team will demonstrate the viability of the design-build process for DC Water while enhancing the reputations of all partners. We will accomplish this by achieving the following team goals:
Safety BudgetScheduleQuality Teamwork
Zero Accidents
Zero OSHA Incidents
Maintain awareness
Earn national award
Establish a common understanding of requirements and maintain or exceed
Establish, implement, maintain and document thorough QA/QC program
Establish, implement, and maintain a document control system
Communicate all project performance guarantees to team
Meet all intermediate and contractual milestones
Maintain and communicate a valid, well-coordinated, cost loaded and updated schedule
Maintain a realistic three-week look ahead schedule
Timely resolution of issues
Complete within all organizations’ budgets
Avoid scope creep
Maintain an efficient and fair management of the change process
Timely invoicing and payment
Commissioning
Ensure operations and maintenance are familiar with process early in the project, attend FAT and PCS demonstrations
Identify and involve the DC Water Operations and Maintenance “champions” early
and establish relationship with the Commissioning Manager
Ensure adequate and useable documentation and knowledge retention after completion
Community
Meet/exceed MBE/WBE participation goals
Meet First Source hiring goals
Identify and coordinate with all inter-related projects
Eliminate surprises
Earn global acclaim and awards
Have fun