Upload
onworld
View
223
Download
0
Embed Size (px)
Citation preview
8/7/2019 Network Tech
1/25
Project ManagementProject Management
Karen J Kirkby DJ 18 01
School of Electronics & Physical Sciences
8/7/2019 Network Tech
2/25
ContentsC
ontents
2 Lectures + 1 Assignment
Why Plan?
What Plan
Project Manager/ Leader
Network Analysis
Critical Path
Gantt charts
PERT
8/7/2019 Network Tech
3/25
AssignmentAssignment
Week 6
Friday Lab groups
Tuesday 15:00 - 17:00
Tuesday Lab groupsFriday 15:00 - 17:00
(see timetable)
8/7/2019 Network Tech
4/25
WHY PLAN?WHY PLAN?
Why do projects fail?
Failing to plan is planning to fail
8/7/2019 Network Tech
5/25
Reappraise
Project
What Plan?What Plan?Define Project
Define Tasks
Define Plan
MonitorProgress
CommenceWork
AimsSpecFeasibility
Subprojects
DependenciesTime
Resources
Facilities
ReviewsTargetsCosts
CompleteProject
RedefineProject
CorrectiveAction
8/7/2019 Network Tech
6/25
The Project ManagerThe Project ManagerAbilities
* Organise & plan
* People Management* Communication skills
* Problem solving
*Technical knowledge
* Enthusiasm & ability to motivate
* Focussed
* Ability to change
8/7/2019 Network Tech
7/25
Network AnalysisNetwork Analysis
* Break project down into manageable sub-groups
* Define tasks in sub-group
* Establish linkages & dependencies between tasks
* Establish order in which tasks undertaken
* Establish sequential and parallel tasks
* Determine time & resources for each task
* Project objectives clearly defined
8/7/2019 Network Tech
8/25
Network AnalysisNetwork Analysis
Activity on node diagrams
activity - rectangular box
linked by arrows - order
8/7/2019 Network Tech
9/25
NETWORK ANALYSISNETWORK ANALYSIS
1. open cereal box
1
2. put cereal in bowl
2
3. fetch milk from fridge
3 4
4. add milk to cereal EAT
Simple example - Breakfast
8/7/2019 Network Tech
10/25
Network AnalysisNetwork Analysis
OK that was a simple example
Now move on to a more realistic case
Same principles
Break down problem into activities
What is the activityWhat has to precede that activity
How long does the activity take
Dont panic
8/7/2019 Network Tech
11/25
Network AnalysisNetwork Analysis
ACTIVITY DURATION PRECURSORSA 4 -B 3 -C 6 A,BD 1 BE 7 DF 2 CG 5 C,EH 8 E
J 4 GK 5 F,GL 6 J,HM 3 L,K
DURATION
L
6
START
0
A
4
C6
D
1
F
2
E
7
B
3
K
5
H
8
FINISH
0
M
3
G
5
J
4
8/7/2019 Network Tech
12/25
8/7/2019 Network Tech
13/25
8/7/2019 Network Tech
14/25
Project ManagementProject Management
Karen J Kirkby DJ 18 01
School of Electronics & Physical Sciences
8/7/2019 Network Tech
15/25
ContentsC
ontents2 Lectures + 1 Assignment
Why Plan?
What Plan
Project Manager/ Leader
Network Analysis
Critical Path
Gantt charts
PERT
8/7/2019 Network Tech
16/25
8/7/2019 Network Tech
17/25
8/7/2019 Network Tech
18/25
NETWORK ANALYSISNETWORK ANALYSIS
Activity on node diagrams in which finish to start
(F-S) links have a duration will now be considered
Nature and duration of link shown on arrow(F-S) Activity 2 cannot start until 1 week after
completion of activity 1.
1 2F-S (1) 3F-S (2)
Activity 3 cannot start until 2 weeks after completion of
activity 2
8/7/2019 Network Tech
19/25
NETWORK ANALYSISNETWORK ANALYSIS
Activity Duration Precursor Link L duration
C 12 B S-S 6
F-F 3
A
A 4 -
0 4
40 4 B
F-S (0)
B 24 A F-S 0
4 28
284 24
C
10 31
3119 12
S-S (6)
Can start 6 weeks after the start of B 4+6 = 10
F-F (3)
Has to finish 3 weeks after the end of B 28+3 = 31
Critical Path
8/7/2019 Network Tech
20/25
Gantt ChartsGantt ChartsDeveloped by Henry Gantt during the first world war
Activities drawn as bars across a time map
A
B
C
D
E
F
GH
J
K
L
M
Critical path Non critical activity
8/7/2019 Network Tech
21/25
PERTPERT
Programme Evaluation & Review Technique
Developed by US Navy 58-60 for Polaris submarine
construction programme
PERT takes into account the difficulty of estimating duration
of activity
So uses:
most optimistic duration
most pessimistic duration
most likely duration
8/7/2019 Network Tech
22/25
PERTPERT
6bm4ate !
6
abs
!
uses a F frequency distribution
calculates the expected mean duration and the
standard deviation as follows:
te = expected mean duration
a = most optimistic duration b = most pessimistic
duration
m = most likely duration s = standard deviation
8/7/2019 Network Tech
23/25
PERTPERTACTIVITY a m b PRECURSORS
A 3 5 9 -
B 4 6 8 -
C 5 8 10 A,B
D 3 6 9 B
E 6 9 15 D
F 3 4 5 C
G 8 12 15 C,E
H 2 6 8 E
J 4 7 9 G
K 3 5 10 F,G
L 7 9 11 J,H
M 10 12 15 L,K
ACTIVITY te s
A 5.3 1
B 6 0.67
C 7.8 0.83
D 6 1
E 9.5 1.5
F 4 0.33
G 11.8 1.17
H 5.7 1
J 6.8 0.83
K 5.5 1.17
L 9 0.67
M 12.2 0.83
8/7/2019 Network Tech
24/25
PERTPERTThe variance for the project duration is the sum of
the variances of the activities along the critical path
The standard deviation for the duration of
the project is the square root of the variance
8/7/2019 Network Tech
25/25
ConclusionsC
onclusions
Why Plan?
What Plan
Project Manager/ Leader
Network Analysis
Critical Path
Gantt charts
PERT