Network Tech

  • Upload
    onworld

  • View
    223

  • Download
    0

Embed Size (px)

Citation preview

  • 8/7/2019 Network Tech

    1/25

    Project ManagementProject Management

    Karen J Kirkby DJ 18 01

    School of Electronics & Physical Sciences

  • 8/7/2019 Network Tech

    2/25

    ContentsC

    ontents

    2 Lectures + 1 Assignment

    Why Plan?

    What Plan

    Project Manager/ Leader

    Network Analysis

    Critical Path

    Gantt charts

    PERT

  • 8/7/2019 Network Tech

    3/25

    AssignmentAssignment

    Week 6

    Friday Lab groups

    Tuesday 15:00 - 17:00

    Tuesday Lab groupsFriday 15:00 - 17:00

    (see timetable)

  • 8/7/2019 Network Tech

    4/25

    WHY PLAN?WHY PLAN?

    Why do projects fail?

    Failing to plan is planning to fail

  • 8/7/2019 Network Tech

    5/25

    Reappraise

    Project

    What Plan?What Plan?Define Project

    Define Tasks

    Define Plan

    MonitorProgress

    CommenceWork

    AimsSpecFeasibility

    Subprojects

    DependenciesTime

    Resources

    Facilities

    ReviewsTargetsCosts

    CompleteProject

    RedefineProject

    CorrectiveAction

  • 8/7/2019 Network Tech

    6/25

    The Project ManagerThe Project ManagerAbilities

    * Organise & plan

    * People Management* Communication skills

    * Problem solving

    *Technical knowledge

    * Enthusiasm & ability to motivate

    * Focussed

    * Ability to change

  • 8/7/2019 Network Tech

    7/25

    Network AnalysisNetwork Analysis

    * Break project down into manageable sub-groups

    * Define tasks in sub-group

    * Establish linkages & dependencies between tasks

    * Establish order in which tasks undertaken

    * Establish sequential and parallel tasks

    * Determine time & resources for each task

    * Project objectives clearly defined

  • 8/7/2019 Network Tech

    8/25

    Network AnalysisNetwork Analysis

    Activity on node diagrams

    activity - rectangular box

    linked by arrows - order

  • 8/7/2019 Network Tech

    9/25

    NETWORK ANALYSISNETWORK ANALYSIS

    1. open cereal box

    1

    2. put cereal in bowl

    2

    3. fetch milk from fridge

    3 4

    4. add milk to cereal EAT

    Simple example - Breakfast

  • 8/7/2019 Network Tech

    10/25

    Network AnalysisNetwork Analysis

    OK that was a simple example

    Now move on to a more realistic case

    Same principles

    Break down problem into activities

    What is the activityWhat has to precede that activity

    How long does the activity take

    Dont panic

  • 8/7/2019 Network Tech

    11/25

    Network AnalysisNetwork Analysis

    ACTIVITY DURATION PRECURSORSA 4 -B 3 -C 6 A,BD 1 BE 7 DF 2 CG 5 C,EH 8 E

    J 4 GK 5 F,GL 6 J,HM 3 L,K

    DURATION

    L

    6

    START

    0

    A

    4

    C6

    D

    1

    F

    2

    E

    7

    B

    3

    K

    5

    H

    8

    FINISH

    0

    M

    3

    G

    5

    J

    4

  • 8/7/2019 Network Tech

    12/25

  • 8/7/2019 Network Tech

    13/25

  • 8/7/2019 Network Tech

    14/25

    Project ManagementProject Management

    Karen J Kirkby DJ 18 01

    School of Electronics & Physical Sciences

  • 8/7/2019 Network Tech

    15/25

    ContentsC

    ontents2 Lectures + 1 Assignment

    Why Plan?

    What Plan

    Project Manager/ Leader

    Network Analysis

    Critical Path

    Gantt charts

    PERT

  • 8/7/2019 Network Tech

    16/25

  • 8/7/2019 Network Tech

    17/25

  • 8/7/2019 Network Tech

    18/25

    NETWORK ANALYSISNETWORK ANALYSIS

    Activity on node diagrams in which finish to start

    (F-S) links have a duration will now be considered

    Nature and duration of link shown on arrow(F-S) Activity 2 cannot start until 1 week after

    completion of activity 1.

    1 2F-S (1) 3F-S (2)

    Activity 3 cannot start until 2 weeks after completion of

    activity 2

  • 8/7/2019 Network Tech

    19/25

    NETWORK ANALYSISNETWORK ANALYSIS

    Activity Duration Precursor Link L duration

    C 12 B S-S 6

    F-F 3

    A

    A 4 -

    0 4

    40 4 B

    F-S (0)

    B 24 A F-S 0

    4 28

    284 24

    C

    10 31

    3119 12

    S-S (6)

    Can start 6 weeks after the start of B 4+6 = 10

    F-F (3)

    Has to finish 3 weeks after the end of B 28+3 = 31

    Critical Path

  • 8/7/2019 Network Tech

    20/25

    Gantt ChartsGantt ChartsDeveloped by Henry Gantt during the first world war

    Activities drawn as bars across a time map

    A

    B

    C

    D

    E

    F

    GH

    J

    K

    L

    M

    Critical path Non critical activity

  • 8/7/2019 Network Tech

    21/25

    PERTPERT

    Programme Evaluation & Review Technique

    Developed by US Navy 58-60 for Polaris submarine

    construction programme

    PERT takes into account the difficulty of estimating duration

    of activity

    So uses:

    most optimistic duration

    most pessimistic duration

    most likely duration

  • 8/7/2019 Network Tech

    22/25

    PERTPERT

    6bm4ate !

    6

    abs

    !

    uses a F frequency distribution

    calculates the expected mean duration and the

    standard deviation as follows:

    te = expected mean duration

    a = most optimistic duration b = most pessimistic

    duration

    m = most likely duration s = standard deviation

  • 8/7/2019 Network Tech

    23/25

    PERTPERTACTIVITY a m b PRECURSORS

    A 3 5 9 -

    B 4 6 8 -

    C 5 8 10 A,B

    D 3 6 9 B

    E 6 9 15 D

    F 3 4 5 C

    G 8 12 15 C,E

    H 2 6 8 E

    J 4 7 9 G

    K 3 5 10 F,G

    L 7 9 11 J,H

    M 10 12 15 L,K

    ACTIVITY te s

    A 5.3 1

    B 6 0.67

    C 7.8 0.83

    D 6 1

    E 9.5 1.5

    F 4 0.33

    G 11.8 1.17

    H 5.7 1

    J 6.8 0.83

    K 5.5 1.17

    L 9 0.67

    M 12.2 0.83

  • 8/7/2019 Network Tech

    24/25

    PERTPERTThe variance for the project duration is the sum of

    the variances of the activities along the critical path

    The standard deviation for the duration of

    the project is the square root of the variance

  • 8/7/2019 Network Tech

    25/25

    ConclusionsC

    onclusions

    Why Plan?

    What Plan

    Project Manager/ Leader

    Network Analysis

    Critical Path

    Gantt charts

    PERT