Network Investment Plan

Embed Size (px)

Citation preview

  • 8/2/2019 Network Investment Plan

    1/16

    Network Investment Plan2010-2015

  • 8/2/2019 Network Investment Plan

    2/16

    Contents

    1. Welcome Page 3

    2. The Electricity Supply Industry Page 4

    3. Our Assets and Key Facts Page 5

    4. Our Investment Programme and its Structure Page 6

    4.1 Load Related Programme

    4.1.1 Customer Connections

    4.1.2 General Reinforcement

    4.1.3 Distributed Generation

    4.2 Non Load Related Programme

    4.2.1 Asset Replacement

    4.2.2 Losses

    4.2.3 Flooding

    4.2.4 Quality of Supply

    4.2.5 Visual Amenity

    4.2.6 Diversions

    4.2.7 Environment

    4.2.8 Safety

    4.2.9 Operational IT

    4.3 Network Maintenance

    4.3.1 Inspections & Maintenance

    4.3.2 Faults

    4.4 Trees

    4.5 Non Operational Programme

    4.6 R&D

    4.7 Programme Deliverables

    5. Contact Us Page 15

    2 Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    3/16

    We are entering an interesting and exciting period in the

    industry with climate change and green energy playing a

    greater part in our plans together with the application of new

    technology. Over the next ve years, we intend to efciently

    invest over 1.4 billion in the region to meet the challenges

    posed by the move to a low carbon economy, changes in the

    pattern of demand for electricity and the needs of servicing an

    ageing network.

    Longer-term, we foresee a number of signicant future

    challenges for the industry which could radically change both

    the networks we own and the way they are operated. We plan

    to produce a longer-term outlook report later this year which

    will set out our views to 2050.

    1. Welcome

    Our plans are based on delivering against the recently

    concluded price control negotiated with Ofgem for the 2010-

    2015 period and incorporating initiatives based on feedback

    gained at previous stakeholder workshops.

    Our plans are based on achieving several simultaneous targets

    in terms of the performance of the network, its condition

    and utilisation, as well as meeting all our legal and statutory

    responsibilities. This document sets out our plan in terms of

    the planned investment by driver, detailing the rationale for

    each and the resulting plans.

    We would be delighted to hear your views. If you wish to

    contact us, a number of different ways are listed at the back

    of this document.

    Steve Johnson

    Chie Executive Ofcer

    Welcome to Electricity North WestsInvestment Plan Statement for 2010 2015.

    The aim of this document is to explain our

    role in the energy industry and detail what

    assets we own. It will then outline how we

    manage our assets and our resulting network

    investment plan for the 2010 2015 period.

    3Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    4/16

    2. The Electricity Supply Industry

    The electricity industry in Great Britain is structuredinto four main groups;

    The generators, who own the major power stations and

    produce electricity from a variety of fuel sources.

    The National Grid, who own and operate the 400kV and

    275kV transmission network that links the major power

    stations and transports electricity in bulk across the UK.

    The 14 Distribution Network Operators (DNOs), who own

    and operate the remaining electricity network, connectingthe remaining generators and the national grid to every

    electricity customer in the UK.

    The suppliers, who buy the electricity produced by the

    generators, sell that electricity to their customers and

    pay the network operators for the transportation of that

    electricity across their networks.

    The electricity market is regulated by the Gas and Electricity

    Markets Authority (the Authority), which governs and acts

    through the Ofce of Gas and Electricity Markets (Ofgem).

    In the electricity market, suppliers contract with generators

    (for wholesale power) and with transmission and distribution

    network businesses (for delivery services), in order that they

    can provide energy to nal consumers. Distribution operators

    are directly regulated by Ofgem and their charges for use

    of their networks are subject to a ve-year price control

    mechanism.

    We are one of the fourteen DNOs and a private limited

    company. We are owned by a consortium of funds controlledby the Commonwealth Bank of Australia and IIF International

    Holding GP Ltd which is a constituent of JP Morgan

    Infrastructure Investments Fund.

    We have an indirect nancial relationship with customers

    as we charge suppliers for the use of our network and the

    suppliers in turn charge their customers the total cost for all

    elements in the supply chain. We account for approximately

    15% of the nal bill for electricity for domestic consumers.

    We use these revenues to operate and maintain the network,

    together with delivering an investment programme of renewal

    and expansion as detailed in this document.

    4 Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    5/16

    Our network comprises of the following key assets:

    Over 13 000km of overhead lines

    Almost 44 000km of underground cables

    Almost 84 000 items of switchgear

    Over 34 000 transformers

    Through this network we deliver over 25 TWh of electricityeach year to over 2.4 million customers across 12 500 square

    kilometres of North West England.

    Our network covers a diverse range of terrain and customer

    mix from isolated farms in Cumbria, to areas of heavy industry,

    urban populations and city centres as shown in the map.

    Our network assets range from large transformers to

    individual services. All these assets are held in a register so

    that we can manage ongoing maintenance through their lives

    and up until they are programmed for replacement.

    The investment programme is therefore managed through

    different types of projects from bulk programmes for thereplacement of high volume low value assets through to

    bespoke large projects for work at single sites.

    In delivering the investment programme we manage

    thousands of individual projects ranging in value up to

    tens of millions of pounds.

    On average, the network performs such that a customer

    experiences a power cut every two years and is without

    electricity for less than one hour every year (99.99% reliability)

    Blackpool

    Preston

    Blackburn

    Burnley

    Manchester

    Macclesfield

    Wigan

    Bolton RochdaleOldham

    Ashton

    Barrow

    Lancaster

    Kendal

    Workington

    Whitehaven

    Carlisle

    Stockport

    3. Our Assets and Key Facts

    We operate a distribution network built of overhead lines,underground cables, transformers, switchgear and ancillary

    equipment.

    5Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    6/16

    4.1.1 CUSTOMER CONNECTIONS

    New buildings require new electricity connections and, where

    appropriate, enhancements to the existing network. Customer

    connections are a competitive market area with a number of

    different organisations providing alternative quotations for

    new connections to our network.

    Most connections however are

    ultimately adopted as part of our

    network. The size of this

    investment programme is

    dependent upon requests from

    customers for supply and therefore

    subject to economic conditions.

    When work is undertaken to

    provide new supplies most of

    this is paid for by the customer

    requesting the supply.

    The chart opposite shows the number of new connections to

    our network over a ten year period. The rst ve years of this

    chart are actual gures and the remaining ve years are

    based on forecasts. This highlights the effect of the recenteconomic recession and our forecast for a slow recovery.

    We undertake investment forthree key reasons;

    Expanding and replacing the network (4.1 and 4.2)

    Maintaining and repairing it, and (4.3 and 4.4)

    Supporting activities (4.5)

    Our capital programme aims to expand the network to cater

    for changes in demand for electricity and to provide new

    connections. We term this load-related capital expenditure.

    We are also investing signicant funds in replacing the

    existing assets as they reach the end of their useful life,termed non-load related capital expenditure.

    In addition to these dened programmes we invest in the

    network by undertaking routine maintenance, the repair of

    faults, non operational investment to purchase equipment

    to help us undertake the work and undertake research and

    development activities.

    For the ve year period we are planning to invest around 1.4

    billion across these areas as shown in the chart below. This

    represents a 36% increase over the previous ve year period.

    4. Our Investment Programme

    ENW Investment Plan 2010-2015

    Load Related Plan 2010-2015

    During 2010 2015 we plan to invest over

    400 million on load related projects as shown inthe chart above. This represents a 12% increase

    over the previous 5 years.

    4.1 LOAD RELATED PROGRAMMELoad related investment is undertaken to allow growth of the

    network. This can take a number of forms but is mostly due to

    the connection of new supplies to the network.

    30%

    47%

    4%

    14%

    2%

    2%

    KEY

    Load related

    Non-load related

    Non-operational

    Network Maintenance

    Trees

    R&D

    KEY

    New Connections

    DG Connections

    General Reinforcement

    51%

    18%

    31%

    6 Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    7/16

    We will continue to forecast future investment requirements

    based upon general economic and market information and

    conditions. As part of this we will liaise with housebuilders

    and other stakeholders to better understand market trends.

    We will continue to improve response times to connectors

    requests and continue discussions with our regulator

    regarding pre investment in known development areas.

    During 2010 2015 we plan to invest over 200

    million to connect around 84 000 new supplies.

    4.1.2 GENERAL REINFORCEMENT

    Existing customers change their usage of electricity over time

    with reductions caused by using more efcient equipment, or

    increases caused by doing more or using larger equipment.

    The combined effect of all these individual changes results in

    changing demand patterns on our network. Where increasing

    demand causes our network to approach its capacity limits,

    we will invest to increase the networks capacity.

    Where we provide an electricity supply to customers it has to

    be within a specied voltage range. On the infrequent

    occasions where customers experience voltage outside these

    limits, we will investigate and, where necessary, correct the

    problem within a guaranteed period.

    When we build the investment programme for general

    reinforcement we go through a process of prioritisation.

    This ensures that our investment targets those sites that have

    the greatest need for some form of intervention.

    This prioritisation takes account of a number of factors that

    cover a comparison of demand against rm capacity, the

    amount of time per year the demand is above rm capacity

    and the number of customers.

    New Connections

    During 2010 2015 we plan to invest over 100

    million to reinforce our network.

    0

    5000

    10000

    15000

    20000

    25000

    2005-06

    2006-07

    2007-08

    2008-09

    2009-10

    2010-11

    2011-12

    2012-13

    2013-14

    2014-15

    Within the general reinforcement programme the largest

    single project is the Wigan 132kV Reinforcement project

    (which is expected to cost around 20 million).

    There is a need to reinforce the network in the Wigan area.This will be achieved by building a new large substation in

    the Upholland/Orrell area of Wigan which will be supplied

    by a new circuit to be installed to connect to the national

    grid at Kirkby.

    This scheme is part of a strategy to uprate the capacity of

    the Lancashire area as a whole. Another scheme for a new

    Bulk Supply Point (BSP) at Preston to support the northern

    end of the group was constructed in 2008. In combination,

    the two schemes will relieve Wigan, Wrightington, Leyland

    and Ribble BSPs (serving a total of 247 000 customers)

    which are all currently loaded at the limit of their capacity.

    7Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    8/16

    Our Investment Programme continued

    4.1.3 DISTRIBUTED GENERATION (DG)Climate change and an increase in environmental awareness

    have led to a change in the mix of fuel sources for electricity

    generation and also a change in the scale of generation

    plant. Many new generators are much smaller than traditional

    power stations and therefore connect to the lower voltage

    distribution networks, such as that owned by ourselves, rather

    than the higher voltage transmission network owned by

    National Grid.

    Electricity generators connected to the distribution networks

    are called distributed generation (DG). Most new DG produce

    renewable energy and/or low carbon combined heat and

    power.

    We recognise the importance of the roll out of DG in meeting

    renewables targets and will continue to provide suitable

    network connections to meet the needs of the connectors

    of DG. We will also continue to work with the regulator and

    the rest of the industry on innovative solutions for network

    development to provide a more exible network that can

    accommodate the wide range of connections envisaged in

    some of the future scenarios.

    DG installation capacity (MW) by type 2010-2015

    0

    50

    100

    150

    200

    250

    300

    350

    Micro

    CHP

    (dom

    estic)

    Othe

    r(notCHP)

    Waste

    incineration

    Photovoltaic

    Landfillg

    asand

    biogas

    Biomass(not

    CHP)

    SmallCHP

    (1MW)

    Onsho

    rew

    ind

    Offsho

    rew

    ind

    The size of this investment programme is dependent upon

    requests from customers for supply and therefore subject to

    economic conditions. When work is undertaken to provide new

    supplies most of this is paid for by the customer requesting

    the supply.

    During 2010 2015 we plan to invest around

    80 million to enable the connection of 1GW of

    generation sites to our network.

    The chart below gives a breakdown of DG capacity by

    technology type. This shows the capacity of DG that we expect

    to connect to our network based on proposals by the developers

    of DG sites and our own assessment of the market drivers.

    8 Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    9/16

    4.2 NON-LOAD RELATED PROGRAMMEThe non-load related programme is undertaken for a variety of

    different reasons. A large component of the programme is for

    the replacement of old assets in poor condition. Other parts

    of the non-load programme are for specic improvement

    initiatives.

    There are some programmes that are currently at an

    embryonic stage and as such are not listed separately in

    detail because the spend forecast for the ve years is so low.

    During 2010 2015 we plan to invest about

    680 million on non-load related projects as

    shown in the chart above. This represents a

    52% increase over the previous ve years.

    9%

    70%

    5%

    1%

    2%

    1%1%

    0%

    12%

    KEY

    Asset ReplacementLossesFloodingQoS

    DiversionsEnvironmentVisual AmenitySafetyOperational IT

    Non-Load Related Plan 2010-2015

    0

    200

    400

    600

    800

    1000

    1200

    1920

    1923

    1927

    1931

    1935

    1939

    1943

    1947

    1951

    1955

    1959

    1963

    1967

    1971

    1975

    1979

    1983

    1987

    1991

    1995

    1999

    2003

    2007

    Age prole for high voltage ground mounted circuit breakers

    4.2.1 ASSET REPLACEMENTAll physical network assets have a nite lifespan before they

    become unt for purpose. Our asset replacement investment

    is designed to replace those assets at the end of their life and

    replace them with their modern equivalent in order to maintain

    the networks capacity and performance levels.

    Through good asset management practices, we have

    been able to extend the life of many of our network asset

    components, however we are now in a period where we

    need to replace an increasing number of assets. This reects

    previous historic investment linked to UK economic cycles,

    including the post-war prosperity boom and electrication

    programmes of the 1960s. This can be seen in the chartbelow which shows the age prole of ground mounted high

    voltage circuit breakers.

    We will continue to invest in our network to maintain its

    overall health, continuing our historically good performance

    and safety standards. We will also continue to invest in our

    asset management systems to ensure we improve the timing

    and efciency of any investment we make.

    We continue to review our asset replacement policies,

    particularly with regard to the rebuilding of overhead lines

    to ensure they are resilient to storm conditions and climatic

    change.

    9Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    10/16

    Our Investment Programme continued

    4.2.3 FLOODINGAn increased environmental risk with climate change is that

    of ooding from river or coastal sources. A number of our

    major sites are located near to water sources as they were

    installed at power stations that required water for cooling

    purposes. Our smaller sites are located close to customers,

    many of whom live in homes built on ood plains.

    We have identied those major sites at risk of ooding and are

    delivering an ongoing programme to improve ood defences

    at those sites. We are working locally and nationally with a

    number of environmental agencies to ensure our modelling is

    up to date with the latest available information and that our

    plans are prioritised accordingly.

    During 2010 2015 we plan to invest around

    7 million to protect those sites most at risk of

    ooding.

    When we dene the investment programme for asset

    replacement we go through a process of prioritisation.

    This ensures that our investment targets those parts of

    the network that have the greatest need for some form of

    intervention. This prioritisation takes account of a number

    of factors that cover safety to the public and our personnel,

    condition of the assets, environment, operating history,

    previous faults on the same type of asset, availability

    of spare parts and local knowledge.

    During 2010 2015 we plan to invest around

    470 million on the replacement of poor

    condition assets.

    4.2.2 LOSSES

    Electricity owing through a conductor generates heat, whilst

    a transformer can generate both heat and noise. This results

    in approximately 5% of the electricity entering our network

    being lost. Although these losses cannot be totally eliminated,

    they can be reduced by installing more expensive plant and

    equipment that is designed to operate with lower losses.

    During 2010 2015 we plan to invest around

    2 million to install equipment as a trial that will

    reduce losses at two key substations.

    10 Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    11/16

    4.2.4 QUALITY OF SUPPLYQuality of supply investment is undertaken with the aim

    of improving the overall quality of service experienced by

    customers.

    This will be achieved by investing in projects that can reduce

    the number of customers affected by faults, reduce the length

    of time customers are off supply in the event of a fault and

    also reducing the likelihood of faults on the network.

    In addition we are planning to undertake specic investment

    to improve the service received by those customers who

    experience the worst reliability on the network. These are

    generally located in very rural locations and at the end of long

    overhead line networks.

    The quality of supply experienced by customers is measured

    based on the number of interruptions (CI) to supply and the

    length of time customers are without supply, or customer

    minutes lost (CML).

    It should be noted that the programme of planned asset

    replacement will impact this performance due to the required

    network outages when replacing assets. These forecasts

    exclude for the effect of planned outages, which for the

    ve years to 2015 reect the increased programme we are

    planning for the replacement of overhead lines. With the effect

    of planned work excluded, the underlying change to CI and

    CML performance is a 6% improvement.

    During 2010 2015 we plan to invest around

    4 million on projects that will improve the service

    experienced by customers, particularly to speed up

    supply restoration following a fault.

    0

    10

    20

    30

    40

    50

    60

    2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

    4.2.5 VISUAL AMENITYIn 2005, a specic limited programme of undergrounding

    overhead lines, identied by regional stakeholders, within

    statutory National Parks and Areas of Outstanding Natural

    Beauty commenced.

    Funding for this programme was allowed by Ofgem up to a

    value of 5 million following their customer willingness to pay

    survey and a review of the various environmental obligations

    placed upon the industry.

    The two photographs below show an example of such a

    project before and after investment.

    15 year CI CML performanceWe support this initiative as a model of public-

    private partnership and have planned for its

    continuance at a level equivalent to the current

    programme in 2010 2015. This is around

    7 million during the ve years.

    4.2.6 DIVERSIONS

    Sometimes when development work is planned for either

    building or new road developments, our network assets

    may be in the path of these developments. Assets therefore

    need to be diverted to an alternative location to allow these

    developments to proceed. We plan for this type of work based

    on historical trends and any known large projects.

    Diversions projects mostly involve diverting underground

    cables and occasionally overhead lines and substations.

    During 2010 2015 we plan to invest around30 million on diversions activities.

    4.2.7 ENVIRONMENT

    Environmentally-driven investment takes place to ensure

    compliance with environmental legislation. We plan to invest

    to guard against oil leakage from our sites and to mitigate

    noise where appropriate.

    During 2010 2015 we plan to invest around

    12 million on environmental projects.

    11Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    12/16

    Our Investment Programme continued

    4.2.9 OPERATIONAL ITThe operational IT programme is aimed at the replacement

    and improvement of those IT systems that are used for

    the real time control of the network. The ability to operate

    the network remotely offers benets in terms of the security

    of supplies and is used to minimise disruptions experienced

    by customers.

    BT Group PLC are migrating their existing network toa system known as 21st Century Network. This new

    network will be unable to offer guaranteed times for

    the transfer of data signals. Our control and protective

    systems require a level of certainty in the time taken for a

    signal to transfer from our control centre to a substation

    on the network so that we can continue to safely and

    securely operate our networks.

    In order to maintain these signal transmission times we

    will construct our own data network over which we have

    total control. This will be done by providing a new bre

    system where signal transmission times are well within

    the specication of the protective systems.

    4.2.8 SAFETYWe operate a safe and efcient network. We have a strong

    safety record and we will continue to invest appropriately

    to maintain that record.

    Most of our safety related investment over the next ve years

    is to ensure our overhead lines maintain safe horizontal and

    vertical clearances in line with the Electricity Safety Quality

    and Continuity Regulations (ESQCR) 2002.

    We operate within a modern social environment. Unfortunately,

    there is an increasing trend of vandalism and other anti social

    behaviour in and around our substations. With the recent rapid

    increase in world metal prices we, like all other utility

    companies, have seen a signicant increase in the theft of

    metalwork from our substations. Our major sites may also be

    considered a suitable target for some terrorist organisations.

    We will continue to invest in an ongoing programme of security

    strengthening at identied sites. We will also continue to work

    with community partners to reduce anti social behaviour

    around our installations and reduce the value of our

    equipment to thieves.

    During 2010 2015 we plan to invest over

    80 million on projects to improve safety.

    During 2010 2015 we plan to invest almost

    60 million on operational IT projects.

    12 Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    13/16

    4.4 TREESOne of the main external impacts

    on our overhead lines is trees.

    We have a routine programme of

    vegetation management where

    we cut and prune trees growing

    in the vicinity of the overhead lines

    to maintain public safety and to

    reduce the risk of trees causing

    faults on the lines. We believe we

    may be beginning to see early

    climate change effects, in that the

    growing season is extending and that the number and severityof storms may be on the increase.

    We are working with the rest of the industry to update historic

    practices and develop enhancements such as resilience,

    where more trees are managed to reduce the risk posed by

    falling trees in heavy storm conditions.

    During 2010 2015 we plan to invest over

    26 million on projects to maintain clearances

    from trees.

    4.5 NON OPERATIONAL PROGRAMME

    The non-operational programme aims to deliver projects in

    areas that will support delivery of the operational investment

    and management of the business.

    During 2010-2015 we are planning to invest in the following:

    Accommodation and maintenance of our buildings

    Improvement of existing IT and the introduction of new

    systems

    Tools to maintain existing stocks and introduce new tools

    and instruments to improve working practices, customer

    service and safety

    The replacement of 500 vehicles out of a eet of around

    750 ranging from cars and small vans to large trucks and

    specialist vehicles

    By having the right balance of these resources in place

    we will optimise the way we are set up and operate to be

    able to efciently deliver the investment programme during

    2010 2015.

    During 2010 2015 we plan to invest almost

    60 million on non-operational projects.

    4.3 NETWORK MAINTENANCE4.3.1 INSPECTIONS & MAINTENANCE

    We routinely inspect and maintain the assets that make up our

    network to ensure they remain safe and continue to provide a

    high level of service.

    Occasionally some assets need to be turned off to do this

    safely which may result in an interruption to supply. Where

    this is necessary, we give customers at least two days notice

    of the interruption and its length to allow them to make any

    alternative arrangements they feel are necessary.

    We will also continue to invest in training and systems to

    ensure inspection information is efciently collected and used

    to continually improve the management of the network.

    During 2010 2015 we plan to invest over

    110 million on inspecting and maintaining

    the existing network assets.

    4.3.2 FAULTS

    Occasionally faults occur on parts of our network caused

    either by deterioration or by a number of outside inuences.

    Fortunately loss of supply is an infrequent occurrence. We

    have a network availability of over 99.99% with, on average,

    a customer experiencing one power cut every two yearsand being without electricity for about two hours for each

    occurrence. As these are averages, most customers receive

    a better service but some customers do unfortunately

    receive worse.

    Dedicated teams respond to faults when notied either by

    customer calls or by alarms generated by the network itself.

    These teams attempt to identify the source of the problem,

    restore supplies to customers as quickly as possible and then

    repair the network back to normal.

    In an average twelve month period we respond to around

    14 000 faults, averaging forty to fty faults per day.

    During 2010 2015 we expect to invest about

    95 million on work to rectify faults across the

    range of network assets.

    13Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    14/16

    4.6 R&DWe are investing signicant amounts of time and money in

    a variety of research and development programmes funded

    under Ofgems Innovation Funding Initiative. Since 2004 we

    have invested over 6 million in a range of projects that are

    designed to enhance the performance of our network in

    a variety of ways. We are planning to increase our R&D

    investment during 2010-2015 under Ofgems new Low

    Carbon Networks Fund scheme as we prepare the way for

    electricity distribution networks to help deliver the low carbon

    electricity system that is required to meet national climate

    change objectives.

    There are two Tiers to the Low Carbon Network Fund:

    the First Tier of the Fund allows us to manage the small scale

    deployment of new technologies and the Second Tier is for

    large agship Smart Grid Projects.

    Our research and development projects cover three primary

    activities. Asset Management, Quality of Supply and Smart

    Grids.

    Under Asset Management we have a number of projects that

    are, for example, researching new ways to manage our asset

    base from investing in biodegradable alternatives to mineral

    insulating oil, developing new techniques to better understand

    the condition and ageing of network assets and investigatinghow we may be able to deliver more capacity from our network

    by understanding and quantifying the cooling effects of wind

    and weather on our assets to avoid upgrading where possible.

    We have a number of projects under Quality of Supply. We are

    developing a range of instruments that can detect and locate

    defects on our underground cable network before the defect

    turns into a fault and customers are disconnected. We are

    also developing a device for intermittent cable faults, the Fuse

    Restorer, that can automatically replace a standard fuse into

    a faulted circuit to restore supplies and then send a text

    message to an engineer to tell them the location of the fault

    and the type of fault event.

    For Smart Grids we are developing a number of projects,

    funded by the First Tier of the Low Carbon Networks Fund,

    delivering new technologies including the UKs rst super-

    conducting fault current limiter installed on our network at

    Bamber Bridge near Preston. This can assist with the

    connection of large amounts of local renewable energy

    generation to allow us to reduce our reliance on fossil fuels

    for electricity generation. In addition we will develop proposals

    and seek funding from the Second Tier of the Low Carbon

    Networks Fund to manage Smart Grid Projects in the NW.

    During 2010 2015 we plan to invest up to

    30 million on R&D projects

    Our Investment Programme continued

    4.7 PROGRAMME DELIVERABLESOur programme aims to replace and refurbish a range of

    existing network assets, install new assets, restore assets

    back to service following faults and continue maintaining

    assets in order to manage network capacity and maintain

    the condition, performance and safety of the network.

    Additional network assets will result from the DG and

    Customer Connections programmes but these cannot be

    accurately quantied in advance as these depend on exactly

    what supplies are requested, but more importantly where and

    also on what network capacity may already be available there.

    During the ve years, excluding Connections and DistributedGeneration, we are planning to undertake some form of

    intervention (replace/refurbish/install new) on:

    Over 5 300 items of switchgear

    Over 1 400 transformers

    Almost 5 500km of overhead lines

    Almost 1 000km of underground cables

    Additionally as part of the ongoing maintenance programme

    we will:

    Respond to around 14 000 faults annually on the network

    Inspect 176 000 spans of overhead line and undertake

    tree cutting to maintain safe clearances for 75 000 spans

    Continue to undertake routine scheduled maintenance

    of the network assets in accordance with our Codes of

    Practice

    We forecast that this investment will allow us to manage

    the condition and utilisation of our network. Over the next

    ve years, we will be measuring this through a range of

    indicators comprising Health Indices (HIs) and Fault rates for

    specied asset types, and Load Indices (LIs) for the loading of

    network elements. This is in accordance with Ofgems newly

    introduced Network Outputs regime for 2010-2015.

    14 Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    15/16

    5. Contact Us

    We are interested in views onthis document and our future

    plans, including whether there

    are any areas you feel we have

    missed, or other priorities and

    factors we should consider.

    YOU CAN:

    Write to us at the following address:

    Head of External Communications

    Electricity North West

    304 Bridgewater Place

    Birchwood Park

    Warrington

    WA3 6XG

    E-mail us at the following address:

    [email protected]

    Or via the link on our website which also includes details

    of previous stakeholder events:

    www.enwl.co.uk

    We look forward to hearing your views!

    15Electricity North West Network Investment Plan 2010 to 2015

  • 8/2/2019 Network Investment Plan

    16/16

    Electricity North West

    304 Bridgewater Place

    Birchwood Park

    Warrington

    WA3 6XG

    [email protected]

    www.enwl.co.uk