Network Evolution – PSTN in Transition Moderator Brian Daly Core Network & Government/Regulatory Standards, AT&T Labs Panelists Richard Ejzak, Director, Corporate Standards, Alcatel-Lucent Carroll Gray-Preston, Senior Director, Technology & Planning, GENBAND Mike Nawrocki, Director, Wireline Standards, Verizon

Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

Network Evolution –PSTN in Transition

ModeratorBrian DalyCore Network & Government/Regulatory Standards, AT&T Labs

PanelistsRichard Ejzak, Director, Corporate Standards, Alcatel-LucentCarroll Gray-Preston, Senior Director, Technology & Planning, GENBANDMike Nawrocki, Director, Wireline Standards, Verizon

Page 2: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

PSTN TransitionBrian K. Daly, ModeratorAT&T Labs – Network Technologies

Page 3: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Network Evolution Objectives

Activities

Develop Detailed Requirements & 

Recommendations for Focus Group Report

Provide Targeted Analysis & 

Recommendations to FCC’s Technological 

Advisory Council (TAC) Working Group

3

Page 4: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

ATIS Focus Group Overview

• During 2012, the PSTN Focus Group developed the PSTN Transition Assessment and Recommendations.• Presented to ATIS Board & the Technology and Operations

Council• High level conclusions shared with FCC TAC in Dec.

• Focus Group has completed work but is available to re-engage, as necessary.• FCC is launching a new task force to address IP Transition

(policy, economic, legal, technical…)

4

Page 5: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

FCC TAC PSTN Transition• In 2011 and 2012, the FCC TACs have made a number of

recommendations for effecting the transition from the PSTN.• Total of seven Study Areas:

• Copper Retirement (Re-Use)• PSTN User Impacts• Interconnection• Database Transition• Numbering (User/Service/App Identifiers)• Quality of Service• Robustness and Public Safety

• Consolidated recommendations to the FCC in three areas:• Databases and Identifiers• QoS and Interconnection• Robustness and Public Safety

• Focus for 2013+ should be planning for transition

5

Page 6: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

TAC Communication Process

6

Page 7: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

PSTN Transition Subteams

7

Application Services

• PSTN Services in Transition

• New Services • Successor

Networks• Protocol Issues• Evolving

Applications environment

• PSTN Services in Transition

• New Services • Successor

Networks• Protocol Issues• Evolving

Applications environment

Access

• End user access issues

• Alternative accesses

• Customer Expectations

• CPE Stranding• User-related

Regulations

• End user access issues

• Alternative accesses

• Customer Expectations

• CPE Stranding• User-related

Regulations

Transport

• End-to-end Communication

• Interconnect Models

• Routing• Authentication• QoS, Security• Emerging

Technologies

• End-to-end Communication

• Interconnect Models

• Routing• Authentication• QoS, Security• Emerging

Technologies

Numbering

• Addressing• Administration• Numbering

Authentication• ENUM

capabilities• Databases

• Addressing• Administration• Numbering

Authentication• ENUM

capabilities• Databases

Chaired by GENBAND

Chaired by Ericsson

Chaired by Alcatel Lucent

Chaired by Neustar

Page 8: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

8

Sub-Team’s Scope of Focus

Access

End UserDevices/Clients

Wireless RAN

Wireline Access

WiFi/Femto

Transport

IP/MPLS/Optical Core

Application Services

Regulatory P

olicy

CommunicationServices

Border/Media Gateways

Session Control

PolicyMgmt

Applications

Ad-HocEmergency Networks

Wireless Packet Core

Session Interconnect

End-End Multi-service QoS

PSTN Equivalence

Services

EmergencyServices (E911,

priority)

OTT & OTT/NSP Services

Network APIs

Define by: Network domains Key issue areas

Numbering/Addressing

Essential UniversalServices

InternetPeering/Transit

Lawful Intercept

Stranded TTY, Alarm, etc.

Reliability, Security, …

Outage Reporting

Managed Services

PSTNInterworking

Service/AppInterworking

Unbundled copper loops

BearerInterconnect

Enhanced MMServices

Page 9: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

PSTN Transition Report

• PSTN Transition Assessment and Recommendation report has been completed.

• Evaluated the network’s current state and defines opportunities for new and richer communication capabilities that the successor network will deliver.

• Assessed key issues in the transition across four areas of network evolution: application services, access, numbering, and transport.

• Represents the only comprehensive industry resource outlining the key considerations for decision makers on all aspects of network evolution.

9

Page 10: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

ATIS Focus Group Participants

• Adtran• Alcatel-Lucent• AT&T (co-lead)• Bell Canada• CenturyLink• Cisco• Ericsson• GENBAND

10

• Huawei• JDSU• Juniper• Neustar• Qualcomm• Time Warner Cable• Verizon (co-lead)

Page 11: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

PSTN TransitionTransport Sub-teamRichard EjzakDirectorCorporate StandardsAlcatel-Lucent

Page 12: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Outline

• Transition to IP interconnect• IP interconnect models• Key issues• Simple interconnect business model• Observations• Recommendations

12

Page 13: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

• As the interconnect architecture moves to IP, it becomes flatter, more direct, less tied to geography, in need of more security.

• Many technical options exist due to evolving standards and industry practices.

• Negotiated commercial agreements needed to resolve myriad technical and operational issues.

• Multiple “successor networks” will provide a wide range of services.

Transition to IP Interconnect

13

Page 14: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution – PSTN in TransitionThursday, March 7, 2013

Interconnect Models

14

• Telecom industry models:• ATIS NGN• i3 Forum Bilateral• GSMA IPX (IP eXchange)

• Transit interconnect with support for routing, multilateral hubbing, SLAs, KPIs, QoS

• 3GPP IMS:• Core set of SIP-based

specifications for Inter-IMS NNI, IMS to IP NNI, RAVEL, OMR, etc.

• Other models:• IETF protocols (SIP,

ENUM, RTCweb, ICE,…)

• SIP Connect• WebRTC• Google Talk

Federation, Jingle (XMPP)

• Skype, etc.

Page 15: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution – PSTN in TransitionThursday, March 7, 2013

Additional Interconnect Architectures

15

IM CN subsystem network A IM CN subsystem network B

Ici

Izi

II-NNI

Mx

Ix

MxMx

Mx

TrGW Ix

Mx

TrGW

IBCF

S-CSCF I-CSCF

P-CSCF

S-CSCFI-CSCF

MSC Server enhanced for ICS or SRVCC

Mx

IBCF

Signalling Bearer

ATCF

Mx

ATCF

Mx

MSC Server enhanced for ICS or SRVCC

P-CSCF

MxMx

Mx

Mx

BGCFBGCF

IMS NNI

WebRTCIPX

Page 16: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution – PSTN in TransitionThursday, March 7, 2013

Protocol Interworking Options

16

• Support for video, WB voice, IM, and other advanced services• Variants of SIP, SIP-I, XMPP and proprietary signaling protocols

exist• Addressing/routing (e.g., DNS, ENUM)• Signaling and media security (e.g., IPSec, TLS)• Provider identity and authentication (e.g., bilateral, CA, callback)• Transcoding• Managed vs. unmanaged (internet) transport• QoS (e.g., packet marking)• Fraud and attack (e.g., DOS) detection/prevention• Charging conventions• Bilateral and multilateral interconnect

Page 17: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution – PSTN in TransitionThursday, March 7, 2013

Key Issues

17

• Addressing and routing• Direct interconnect requires access to address resolution

• Security• E.g., Identity verification to control SPAM calling

• QoS• Proliferation of networks using unmanaged transport• Access QoS most important

• Bundling of signaling with media• Most models assume availability of signaling along with media

through managed transit networks to facilitate per-call charging for media transport – facilitated through media anchoring

• Charging• Transition from sending-party-pays to bill-and-keep

Page 18: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution – PSTN in TransitionThursday, March 7, 2013

Simplified Business Model

18

• Models evolving to allow separation of service and access providers• Business agreements evolving to separate provision of and charging

for transit service and media transport

Page 19: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution – PSTN in TransitionThursday, March 7, 2013

Observations/Trends

19

• IP interconnect would significantly advance with the availability of an industry-wide address translation and routing solution (e.g., ENUM)

• There is an increasing need for authentication of users and/or service providers to minimize fraud and spam

• The industry is moving from an established interconnection model to multiple models• The models have varying requirements (QoS, security, etc.) and

compensation arrangements• Model diversity breeds innovation but eventually a few dominant models

must prevail• These unique QoS and security requirements will introduce new challenges

and opportunities for managed communication services• The PSTN transition is best served by allowing a gradual evolution of

services and interconnection models• The separation of service provider responsibility for communication services

and IP access is a key driver for new interconnection models• Emerging technologies and services (e.g., OTT, cloud, WebRTC, OMR) will

significantly influence the evolution of interconnection models

Page 20: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution – PSTN in TransitionThursday, March 7, 2013

Recommendations

20

• The industry should agree on a tiered routing architecture based on the carrier registering the user’s TN• LATA routing is unnecessary

• Future interconnect models should support identity authentication of the users and access and service providers• To provide security, compensation support, and fraud/spam control

• Potential future ATIS activities:• Analyze emerging IP interconnection issues:

• Technical issues such as security and QoS• Commercial issues such as the use/need for a multiservice model

• Develop new IP interconnection models with the latest advances• Based on the evolution of existing voice and multi-service models

• Encourage the voluntary convergence of the industry on a minimal set of the most broadly adopted models

Page 21: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

PSTN TransitionApplication Services Sub-teamCarroll Gray-PrestonSenior DirectorTechnology and PlanningGENBAND

Page 22: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

PSTN Applications Services in Transition

Business

Residential

Core Voice

• Emergency Hot Line• Coin (Public Interest

Payphone)• Emergency Alerts• Operator Assisted

Communications• Telecommunication

s Relay Service (TRS)

• Video Relay Service (VRS)

• IP Relay Service

• Emergency Hot Line• Coin (Public Interest

Payphone)• Emergency Alerts• Operator Assisted

Communications• Telecommunication

s Relay Service (TRS)

• Video Relay Service (VRS)

• IP Relay Service

• CLASSSM

• Database Services• Automatic Call

Distributor (ACD)• IVR (Interactive

Voice Response)• Intelligent Network

(IN) Services• Voicemail• Voice Conferencing

• Fax• Alarm System• BRI Services• PRI Services• CAS Trunk Services• Analog Loop Signaling

dependent services

• Fax• Alarm System• BRI Services• PRI Services• CAS Trunk Services• Analog Loop Signaling

dependent services

• Emergency Services• Lawful Intercept• Priority Services• Malicious Call Trace• Portability

• Emergency Services• Lawful Intercept• Priority Services• Malicious Call Trace• Portability

22

Page 23: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Applications Services in Successor Networks

Business

Residential

Core Voice

Content Share

Social Networking

IM/Chat

HD Voice

Consumers will have access to range of new application services

Key principles still apply –Market forces, standardization, self-regulation, and government oversight continue to influence definition

New applications defined today will evolve over time as more broadband services become available and achieve market penetration

23

Page 24: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

24

Assessment Approach

Current State

Standards

Future State

RegulatoryEconomicInterests

PublicSafety

National Security

PSTNApplications

Page 25: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Application Services Categories

25

Sunset Services

This set of services leverage outdated technology and are being/or have been

replaced by alternate mechanisms that provide superior

capability.

Sunset Services

This set of services leverage outdated technology and are being/or have been

replaced by alternate mechanisms that provide superior

capability.

Transitional Services

Due to market penetration, this set of services will require

strategies for ongoing support until such time as it makes commercial

sense to transition.

Transitional Services

Due to market penetration, this set of services will require

strategies for ongoing support until such time as it makes commercial

sense to transition.

Successor Network Services

Services definitively supported in successor

networks driven by regulatory, social policy,

or market forces.

Successor Network Services

Services definitively supported in successor

networks driven by regulatory, social policy,

or market forces.

Current set of PSTN applications

Page 26: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Summary • Significant number of current applications will be supported in both

Transitional and Successor Networks, although they may be implemented or delivered in alternate forms.

• Solutions exist to support most legacy PSTN functions in next generation networks (currently in transitional phase).

• Relatively equal distribution of Services evolving to Successor Networks driven by regulatory considerations (e.g. emergency calling) vs. market demand.

• Recommendations for further study: • Calling number and name delivery privacy regulation • Portability

26

For most applications, business drivers will determine which applications migrate and how they do so

Page 27: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

PSTN TransitionMike NawrockiDirectorWireline StandardsVerizon

Page 28: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Access – Key Considerations

28

Voice grade channels

(no mobility)

Fixed lines (no mobility)

Access Voice Service Provider

Carrier-provided line power

Subscriber side signaling Availability

Stranding of CPE(Analog phones, fax,

alarm, PBXs, etc.)

Loss of central office power

Robustness

Page 29: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Access Summary

• Stranded CPE should be treated as an economic issue (not a policy issue), and in most cases consumers are voluntarily making the transition to better solutions.

• Removal of C.O. provided line powering is also an economic issue – emergency powering can be provided as a feature.

• Reliability and robustness in the future network are less dependent on underlying access network and can be engineered to various levels.

29

Page 30: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Numbering and Network Evolution

30

Interconnection & Routing

Legacy Rate Centers & LATAs

Numbering

Geographic Linkage

Future of PSTN Names

IP-routable addresses

Page 31: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Numbering – Addressing & Authentication

The industry should address the following open issues:•Addressing:

• Administrative information exchange • Discovery• Mutual authentication• Consider a TDM-to-IP addressing solution that conserves

numbering resources

•Numbering Authentication: • Ensure that telephone numbers on IP networks are secured

against spoofing

31

Page 32: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Telephone Number Administration

The industry should investigate the following issues:• Consider introducing expanded geographic area codes for

traditional communications service.

• Consider breaking the linkage between geography of the TN and geography of the point of interconnection.

• Closely monitor number allocation and utilization.

• Assess the implications of direct consumer registration of TNs.

• Eliminate number allocation and assignment based on rate centers and LATAs.

32

Page 33: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Recommendations for ATISATIS should perform the following actions (with the ATIS Packet Technologies and Systems Committee (PTSC) taking the lead and coordination function):•Analyze the IP interconnection recommendations and determine the need for new specifications.

•Analyze the impact of emerging technologies and services (e.g., OTT, cloud, WebRTC, OMR) on future interconnection.

•Examine the impact on commercial issues, including the potential enhancements for multiservice support.

•Encourage the voluntary convergence of the industry on a minimal set of the most broadly-adopted models of interconnection.

33

Page 34: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution ‐ PSTN in TransitionThursday, March 7, 2013

Next Steps

• Transition responsibility for specific work items to ATIS PTSC.

• Continue to promote the PSTN Transition Report to key industry stakeholders.

• Work of PSTN Transition focus group is complete, but team will stay responsive to government & industry requests.

34

Page 35: Network Evolution – PSTN in Transitionzttechsol.com/newSite3/wp-content/uploads/2018/04/PSTNwebinar_030713.pdfNetwork Evolution –PSTN in Transition Thursday, March 7, 2013 Protocol

ATIS Board of Directors’ MeetingOctober 20, 2011

Network Evolution – PSTN in TransitionThursday, March 7, 2013

35

Thank you for attendingNetwork Evolution – PSTN in Transition

Visit the ATIS Document Center to purchase a copy of the

PSTN Transition Focus Group Assessment and Recommendations

www.atis.org/docstore