Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Social Monitoring Report
Semi-Annual Report
Project Number: 44219-014
Loan/Grant: 3139/3721/0397
January to June 2020
Nepal: South Asia Subregional Economic Cooperation
Power System Expansion Project
(On-grid)
Prepared by Nepal Electricity Authority
Submission date: July 2020
This Social Monitoring Report is a document of the borrower. The views expressed herein do
not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may
be preliminary in nature. Your attention is directed to the "terms of use" section of this website.
In preparing any country program or strategy, financing any project, or making any designation
of or reference to a particular territory of geographic area in this document, the Asian
Development Bank does not intend to make any judgments as to the legal or other status of
any territory or area.
Social Monitoring Report
Semi Annual Monitoring Report
January-June 2020
(Loan No. 3139/ Grant No. 0397)-NEP: South Asia Sub-regional Economic Cooperation (SASEC) Power System Expansion Project
Prepared by: Nepal Electricity Authority, Nepal for the Asian Development Bank. Reviewed and supervised by: Project Supervision Consultant (Power Grid Corporation of India Ltd. in association M/s Jade Consult) This Social Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
July 2020
Semi-annual Social Safeguard Monitoring Report January-June, 2020
1 SASEC-PSEP NEA-PSC-ESSD
ACRONYMS AND ABBREVIATIONS
ADB Asian Development
Bank
AP Angle Point
APs Affected Peoples
CDC Compensation
Determination
Committee
CDO Chief District Officer
CF Community Forest
CFUGs Community Forest User
Groups
CSR Corporate Social
Responsibility
CTEVT Council for Technical
Education and
Vocational Training
DKTLP Dana-Kushma 220kV
Transmission Line
Project
Semi-annual Social Safeguard Monitoring Report January-June, 2020
2 SASEC-PSEP NEA-PSC-ESSD
DMD Deputy Management
Directorate
EIB European Investment
Bank
EM Entitlement Matrix
ESMU Environmental and
Social Management Unit
ESSD Environment and Social
Studies Department
GoN Government of Nepal
GRC Grievance Redress
Committee
ha hectare
HH Household
IEE Initial Environmental
Examination
IP Indigenous People
IPP Indigenous People’s
Plan
IR Involuntary Resettlement
Semi-annual Social Safeguard Monitoring Report January-June, 2020
3 SASEC-PSEP NEA-PSC-ESSD
KNBTLP Kushma-New Butwal
220kV Transmission
Line Project
kV kilovolt
MKTLP Marsyangdi-Kathmandu
220kV Transmission
Line Project
NEA Nepal Electricity
Authority
PAF Project Affected Family
PAP Project Affected People
PCP Public Communication
Policy, 2011
PMD Project Management
Directorate
PSC Project Supervision
Consultant
PCC Plain Cement Concrete
RAP Resettlement Action
Plan
Semi-annual Social Safeguard Monitoring Report January-June, 2020
4 SASEC-PSEP NEA-PSC-ESSD
RIPP Resettlement and
Indigenous People’s
Plan
RM Rural Municipality
RP Resettlement Plan
RoW Right of Way
SASEC South Asia Sub-
Regional Economic
Cooperation
SPS Safeguard Policy
Statement
TL Transmission Line
UMBTLP Udipur-Markichowk-
Bharatpur 220kV
Transmission Line
Project
VDC Village Development
Committee
Semi-annual Social Safeguard Monitoring Report January-June, 2020
5 SASEC-PSEP NEA-PSC-ESSD
TABLE OF CONTENTS 1. THE PROJECT DETAILS ................................................................................................................... 6
1.1 Background of the project ................................................................................................................. 7
1.2 Physical Progress of the Project Activities ....................................................................................... 8
1.3 Reporting Period ............................................................................................................................. 10
1.4 Monitoring Requirements and Frequency of Submission ............................................................... 10
1.5 Scope of Semi-Annual Monitoring Report ...................................................................................... 10
2. CHANGES IN PROJECT SCOPE AND ADJUSTED SAFEGUARD MEASURES .......................... 11
3. QUALITATIVE AND QUANTITATIVE DATA .................................................................................... 11
4. MONITORING PARAMETERS/INDICATORS AND METHODS ..................................................... 11
5. SEMI-ANNUAL MONITORING RESULTS ....................................................................................... 12
5.1 Documentation and Approval ......................................................................................................... 12
5.2 Land Acquisition and Compensation Distribution ........................................................................... 12
5.2.1 Rate Fixation for Land Acquisition ............................................................................................... 13
5.2.2 Compensation for Acquired Land ................................................................................................ 15
5.2.3 Compensation Distribution for Structure Loss ............................................................................. 17
5.2.4 Compensation Distribution for Crop, Tree and Fodder Loss ....................................................... 19
5.2.5 Compensation Distribution for Fruits Loss. .................................................................................. 19
5.2.6 Progress on Assistance to Vulnerable Households..................................................................... 20
5.2.7 Additional Assistant to the PAFs .................................................................................................. 21
5.2.8 Major Issues associated with Land Acquisition and Compensation ............................................ 21
5.2.9 Safeguard Implementation Progress ........................................................................................... 22
5.2.10 Livelihood Restoration Program ................................................................................................ 23
5.2.11 Impact on Indigenous People (IPs)............................................................................................ 26
5.3 Monitoring Results compared against IR and IPs Safeguards ....................................................... 31
6. GRIEVANCE REDRESSAL MECHANISM ....................................................................................... 40
7. PUBLIC CONSULTATION AND PARTICIPATION AND INFORMATION DISCLOSURE ............... 40
8. CORRECTIVE ACTIONS FOR NON-COMPLIANCE AND MAJOR GAPS ..................................... 41
9. RECOMMENDATION FOR MONITORING ADJUSTMENT ............................................................ 41
10. INSTITUTIONAL ARRANGEMENT FOR MONITORING ............................................................... 41
10.1 Central Level Arrangement ........................................................................................................... 41
10.1.1Environment and Social Studies Department (ESSD)................................................................ 41
10.1.2 Central Level Line Agencies ...................................................................................................... 42
10.2 Project Level Arrangement ........................................................................................................... 42
10.2.1 Project Management Directorate, NEA (PMD Office)................................................................ 42
10.2.2 Project Manager......................................................................................................................... 42
10.2.3. Environment and Social Monitoring Unit (ESMU)..................................................................... 42
10.2.4 Project Supervision Consultant (PSC) ....................................................................................... 43
11. Impacts of COVID-19 in the project implementation ...................................................................... 43
Semi-annual Social Safeguard Monitoring Report January-June, 2020
6 SASEC-PSEP NEA-PSC-ESSD
LIST OF TABLES
Table 1: Physical Progress of the sub-projects ...................................................................... 8
Table 2: Scope of Semi-Annual Monitoring Report .............................................................. 11
Table 3: Details of Land Acquisition .................................................................................... 12
Table 4: Compensation Distribution Status .......................................................................... 15
Table 5: Major issues associated with land acquisition and compensation in project sites .. 21
Table 6: Status of Safeguard implementation progress ....................................................... 23
Table 7 : Resettlement Impact and Impacts on IPs ............................................................. 27
Table 8: Compliance Monitoring Results in terms of Involuntary Resettlement Safeguards . 32
Table 9: Monitoring Results in terms of Indigenous Peoples Safeguards ............................ 37
Table 10: Corrective actions for non-compliance ................................................................. 41
Annexture: Status of Compliance with Loan Covenants
Semi-annual Social Safeguard Monitoring Report January-June, 2020
7 SASEC-PSEP NEA-PSC-ESSD
1. THE PROJECT DETAILS
1.1 Background of the project
Asian Development Bank (ADB) approved the South Asia Sub-Regional Economic
Cooperation (SASEC) Power System Expansion Project on July 4, 2011 and signed the
loan/grant/project agreement with the Government of Nepal (GoN) on July 11, 2014. Nepal
Electricity Authority (NEA) has received financial assistance from the ADB with co-financing
from Norway and loan from European Investment Bank (EIB) for Implementation of above
project. However, the safeguard implementation and monitoring cost shall be borne by NEA.
The project will contribute to Nepal’s energy development objectives by (i) scaling up the on-
grid and off-grid renewable energy supply, (ii) facilitating cross-border power exchange, (iii)
increasing access to renewable energy in rural areas, (iv) building capacity for on-grid and off-
grid power sector development, and (v) utility scale solar photovoltaic project development.
The project targets the strengthening and expansion of transmission and distribution systems
that will enable Nepal to further benefit from power trading and development of its abundant
hydropower resources. Transmission network strengthening and expansion, in conjunction
with current hydropower generation development, is a precondition to reducing load shedding
and increased cross border electricity trade.
The transmission line corridors and distribution system expansion projects are listed below:
1. Kali Gandaki Corridor:
• Dana – Kushma 220kV transmission line (length: 38.85km).
• Kushma – New Butwal 220kV transmission line (length: 88km)
• New Butwal – Bardaghat 220kV transmission line (length:21km)
• Construction of grid substations: 100MVA (33.33MVA X 3 single phase unit),
220kV/132kV at each of Dana and Kushma substation and 25MVA, three phase,
132kV/33kV at Dana and 100MVA, 3 phase, 220kV/132kV at New Butwal along Kali
Gandaki Corridor.
2. Marsyangdi Corridor:
• Udipur–Markichowk–Bharatpur 220kV transmission line (length: 64.45 km), and
substation at Khudi, switchyard at Udipur, Markichowk substation, and bay extension
at Bharatpur
• Manang–Khudi–Udipur 220kV transmission line (length:45km), and associated
substations at Manang and bay extension at Khudi
3. Marsyangdi to Kathmandu:
• Marki Chowk – Matatirtha 220kV transmission line, and associated bay extension at
Matatirtha (length: 82km)
Semi-annual Social Safeguard Monitoring Report January-June, 2020
8 SASEC-PSEP NEA-PSC-ESSD
• Construction of 480MVA, 220kV/132kV grid substations along Marsyangdi–
Kathmandu route
4. Power distribution network improved:
Construction and or Upgrading of 410km of 33kV, 545km of 11kV and 725km of 400V
distribution lines, 216MVA, 33/11kV Substations, and 20MVA distribution substations in The
East, Central and West regions.
• Lot 1: Distribution System expansion in eastern and central Nepal
• Lot 2: Distribution System expansion in western Nepal
• Lot 3: Up-gradation of distribution networks.
1.2 Physical Progress of the Project Activities
The summary of physical progress of packages during the period of January-June, 2020 are
described in the below Table-1 and Tower Foundation and Tower Erection details has been
attached in Annexure 1.
Table 1: Physical Progress of the sub-projects
SN Sub-Projects Status of Project Activities
Kali Gandaki Corridor:
1 Dana–
Kushma
220kV
Transmission
Line and
substations at
Dana and
Kushma
Khurkot (Kushma) Substation and Access Road
Tower Foundation work, LM tower work, Firewall work has been completed.
Equipment foundation work and stringing work for both 220kV and 132kV
has been completed
Control office building finishing work, Transit camp, Cable trench work on
progress.
Control office building’s ground floor switchyard work is ongoing
Dana Substation
Tower Foundation work, ICT foundation work and LM tower work completed.
Stringing work for both 220kV and 132kV completed.
Ground floor switchyard work. Transit camp concrete work and control office building finishing work on progress.
Tower Footing (Angle Points)
In DKTLP, total 110 tower foundation and 108 tower erections have been completed. Total 37 Kilometer of stringing work has been completed till this reporting period.
In Parbat District, 56 tower foundations and 56 tower erections have been completed.
In Myagdi District, 54 tower foundations and 52 tower erections have been completed.
Details of the tower foundations have been kept safely with project.
2 Kushma– New
Butwal 220kV
TL
New Butwal (Badera) Substation
The transformer setup, Power control building, Residential building, Guest
building, Earthing, Access road PCC & RCC, Boundary wall fencing are in
progress.
Tower Footing (Angle Points)
Semi-annual Social Safeguard Monitoring Report January-June, 2020
9 SASEC-PSEP NEA-PSC-ESSD
In KNBTLP, total 94 tower foundation and 20 tower erections have been completed and 12 tower foundations & 3 tower erections are in progress till this reporting period.
In Palpa district, total 41 tower foundation and 5 tower erection works has been completed and 1 tower foundation work is in progress till this reporting period.
In Syangja district, total 13 tower foundation work have been completed and 5 tower foundation work are under progress till this reporting period.
In Parbat district, total 40 tower foundation and 15 tower erections work have been completed. Similarly, 6 tower foundation and 3 tower erection work are in progress till this reporting period.
Details of tower foundation & erection work have been attached kept safely with
project.
Marsyangdi–Kathmandu 220kV transmission line and substations at Matatirtha and Markichowk
3 Marsyangdi
Kathmandu
220kV
Transmission
Line and
substations at
Matatirtha and
Markichowk
Matatirtha Substation
Construction of control building up to foundation beam, B-type building upto plinth level has been completed and rebar work above plinth level in progress, PCC at water tank site work completed.
Construction of sharewall at transformer installation site, Column work at Gantry point, C-type building upto plinth level, drainage systems on progress.
Markichowk Substation
Construction of gantry foundation work completed for 220kV and 132kV, PCC for D & T Type Building completed.
RCC works of C type & D type Building, equipment foundation & transformer’s foundation works are in progress in various stages of construction.
(Note*: The progress activities of Matatirtha substation is same as mentioned in December, 2019 .No additional work progress has been achieved so far in this reporting period as the contractor has left the work since December, 2019.)
**MKTLP Project Manager Office has published a bid invitation notice on 23 June, 2020 for the Design, Supply, and Installation and Commissioning of 220 kV Air insulated Substation (AIS) in Matatirtha, Kathmandu and 220kV Gas Insulated Substation (GIS) in Markichowk, Marsyangdi. Bid invitation notice have been kept safely with project.
Tower Footing (Angle Points)
In MKTLP, total 227 tower foundations have been completed and 226 tower erection work have been completed till this reporting period. Total 74km of stringing work has been completed till this reporting period.
In Dhading District, 139 tower foundation and 139 tower erections have been completed. Stringing work has been completed in 48.47 km span till this reporting period.
In Chitwan District, 29 tower foundations and 29 tower erections have been completed. Total 9km stringing work has been completed in Chitwan. Stringing work is ongoing from AP 58 to AP 57 in Chitwan district.
In Gorkha District, 51 tower foundation and 50 tower erection have been completed. Total 16km stringing work has been completed in Gorkha.
In Tanahun District, 4 tower foundations and 4 tower erections have been completed. Total 900m stringing work has been completed in Tanahun
Semi-annual Social Safeguard Monitoring Report January-June, 2020
10 SASEC-PSEP NEA-PSC-ESSD
In Kathmandu District, 4 tower foundationand 4 tower erections have been completed. Stringing work has been completed.
The details has been kept safely with project.
Marsyangdi Corridor
4 Udipur-
Markichowk-
Bharatpur
220kV TL)
Udipur substation
The tender of Udipur substation which was awarded to Shenzhen Farad
Electric Co. Ltd has been cancelled and it is still in re-tender process now.
The tender of Udipur substation was awarded to L & T Company.
Bharatpur substation
The tender of New Bharatpur substation which was awarded to Shenzhen
Farad Electric Co. Ltd has been cancelled and it is in re-tender process now
The tender of New Bharatpur substation was awarded to L & T Company.
Tower Footing (Angle Points)
In UMBTLP, 15 tower foundation works has been completed at Lamjung district and 5 tower foundation works are in progress in this reporting period. However, erection work has not started yet.
The details have been kept safely with project.
1.3 Reporting Period
The reporting period of this Semi-annual Social Monitoring Report covers the activities
conducted between the months of January-June, 2020.
1.4 Monitoring Requirements and Frequency of Submission
As per loan covenants, semiannual safeguard monitoring report is required to be prepared
and disclosed. The semiannual report is based on the periodical report (Quarterly, Monthly)
prepared by the subprojects, review of approved documents, field information and public
consultation with stakeholders, affected persons, and the relevant project staffs.
1.5 Scope of Semi-Annual Monitoring Report
This monitoring report covers all the information on execution of different
subprojects/components including land acquisition and RIPP implementation activities and
also ensures safeguard provisions and compliance verification, as applicable. The scope of
this semi-annual report includes the project components detailed in Table 2. PSC is
responsible for monitoring and supervision of NEA components only and therefore, the
projects under NEA components only has been considered/ reported in this report.
The distribution system augmentation and expansion project covers 25 distribution substations
in different districts of Eastern, Central and Western parts of Nepal. The total land acquired
for the construction of distribution substations is 129761.81sq.m. There are in total 44 APs,
among which 5 are IPs, 3 Dalits and 14 are women. Altogether, NPR 156,863,554
compensation has been distributed to land owners for the distribution system augmentation
and expansion project in all substations. There are no land issues for the ll distribution
substations.
Semi-annual Social Safeguard Monitoring Report January-June, 2020
11 SASEC-PSEP NEA-PSC-ESSD
Table 2: Scope of Semi-Annual Monitoring Report
SN Sub–Project Components 1 Dana–Kushma 220kV transmission line and associated substations under Kali Gandaki
Corridor 2 Kushma–New Butwal 220kV transmission line and associated substations under Kali Gandaki
Corridor 3 Marsyangdi–Kathmandu 220kV transmission line and associated substations 4 Udipur-Markichowk-Bhartpur 220kV transmission line and associated substation under
Marsyangdi Corridor 5 Power distribution network improved
Lot-1: Distribution System expansion in eastern and central Nepal Lot-2: Distribution System expansion in western Nepal Lot-3: Up-gradation of distribution networks
2. CHANGES IN PROJECT SCOPE AND ADJUSTED SAFEGUARD MEASURES
According to ADB SPS 2009, the Project is categorized as “A” for involuntary resettlement and
“B” for indigenous peoples. The project scope is same as approved.
3. QUALITATIVE AND QUANTITATIVE DATA
This social monitoring report is prepared utilizing both quantitative and qualitative tools and
techniques to draw inference related to safeguard issues and implementation. The
quantitative data are collected to measure the status and change of a specific variable which
are quantifiable such as affected households, acquired land, compensation distribution
status, total structure loss, total crop loss etc.
The qualitative data are also collected in order to identify the issues as well as get detailed
information during the implementation process through observation, open-ended interviews,
meaningful consultation meetings, GRC meetings, discussions, formal meetings with project
staffs, project affected families, local communities, and other stakeholders etc.
4. MONITORING PARAMETERS/INDICATORS AND METHODS
Monitoring method of this semi-annual monitoring report is based on some important
parameters/indicators including: (i) type of impacts due to acquisition, (ii) extent of impacts,
(iii) measures adopted to minimize the impacts, (iv) implementation status of mitigating
measures, (v) consultation and participation, (vi) grievance redressed, (vii) compensation
payment, and (viii) implementation of resettlement and rehabilitation activities.
Various tools were used to collect data and information and to identify issues related to
compensation process which includes: (i) Observation for collection of data and information of
the APs in particular and community as a whole, (ii) Interviews /focused group discussions,
village mapping and data collection utilizing other participatory rule appraisal (PRA
)techniques with affected persons, community members, workers and officials/other
stakeholders to collect data and information, (iii) public consultation meetings with affected
community and officials (iv) formal survey method with CDO, representatives of local elected
bodies & concerned stakeholders.
Semi-annual Social Safeguard Monitoring Report January-June, 2020
12 SASEC-PSEP NEA-PSC-ESSD
5. SEMI-ANNUAL MONITORING RESULTS
This Semi-annual Social Monitoring work is essential for proper implementation of social
safeguard measures. The results of monitoring are summarized in the following sections:
5.1 Documentation and Approval
Combined Resettlement and Indigenous People Plan (RIPP) for the Project was prepared by
NEA and approved by the ADB in June, 2011 at appraisal. The draft of updated RIPP was
submitted to ADB in April, 2018 and substantial revised version of updated RIPP was
submitted.
The household survey for the structure loss household under RoW of MKTLP and RoW of
DKTLP has been completed. The updated RIPP report including update of MKTLP and DKTLP
along with RoW information (information of structure loss HHs) has been prepared and
submitted to ADB in June, 2020. The household survey of Parbat, Palpa and Syangja Districts
has been completed in KNBTLP whereas household survey in remaining districts is ongoing.
Similarly, household survey of Lamjung District has been completed in UMBTLP whereas
household survey in remaining districts is ongoing.
5.2 Land Acquisition and Compensation Distribution
Land acquisition of Dana and Kushma substations under Kali Gandaki Corridor and
Markichowk & Matatirtha substations under Marsyangdi-Kathmandu section has been
completed. Comparatively, the land acquisition data differs from original RIPP, because the
entire land requirement presented in original RIPP was based on estimation. Whereas, this
prepared report is based on actual land acquired after check survey and detailed design. The
compensation distribution for the APs is under process. With regards to land acquisition for
tower foundation, 6.68 ha and 9.93 ha land has been acquired for Dana-Kushma 220kV
subproject under Kali Gandaki corridor and Marsyangdi-Kathmandu 220kV subproject
respectively. The details of proposed land in original RIPP and actual land acquired are
mentioned below in Table 3:
Table 3: Details of Land Acquisition
S.N. Sub-project Components As per original
RIPP (ha)
Achievement till
reporting period
(ha)
1. Kali Gandaki Corridor
1.1 Dana-Kushma 220kV TL (DKTLP) under Kali Gandaki Corridor
Dana Substation 5 5.45
Kushma Substation 10 7.91
Kushma Substation (Addl.) 1.7
Tower Foundation (Dana-Kushma line) 2.97 6.68
Sub-Total 17.97 21.74
1.2 Kushma-New Butwal 220kV TL (KNBTLP)
New Butwal S/S 10 8.55
Tower Foundation (Kushma-New Butwal TL) - 3.255
Sub-Total 10 11.775
1.3 New Butwal-Bardaghat 220kV TL (NBBTLP) 1
1 The details of Land acquisition of NBBTL has not been displayed as construction work has not started yet.
Semi-annual Social Safeguard Monitoring Report January-June, 2020
13 SASEC-PSEP NEA-PSC-ESSD
S.N. Sub-project Components As per original
RIPP (ha)
Achievement till
reporting period
(ha)
Tower Foundation (New Butwal Bardaghat Line) - -
2. Marsyangdi-Kathmandu 220kV TL (MKTLP)
Markichowk Substation 3.5 3.02
Matatirtha Substation 5 6.19
Tower Foundation (Marsyangdi-Kathmandu TL) 5.87 9.93
Sub-Total 14.37 19.14
3. Marsyangdi Corridor
3.1 Udipur-Markichowk-Bharatpur 220kV TL (UMBTL) 2
Udipur Substation 4 5.18
Bharatpur Substation - 2.5
Tower Foundation (Udipur-Markichowk-Bharatpur TL) 4.41 1.53
Sub-Total 8.41 9.21
3.2 Manang-Khudi-Udipur 220kV TL (MKUTL) 3
Manang Substation - -
Khudi Substation - -
Tower Foundation (Manang-Khudi-Udipur TL) - -
Sub-Total - -
4. Samundratar Trishuli 3B Hub TL 132kV (STR3BTL) 4
Samundratar Substation - -
Trishuli 3B Hub Substation - -
Tower Foundation (Samundratar Trishuli 3B Hub TL) - -
Sub-Total - -
Total 50.75 61.883
5.2.1 Rate Fixation for Land Acquisition
The summary of Rate fixation for Land Acquisition are mentioned below:
DKTLP
The CDC fixed the rate for land acquisition in Parbat district on 2074/9/18 (2nd January
2018).
The additional land notice in Myagdi and Parbat districts were published on 2075/04/01
(2018/07/17) and 2075/12/24 (2019/04/07) respectively and rate has been fixed for
those land on 2074/6/2.
The CDC meeting was conducted in Parbat district and notice was published on
2076/2/25 (8th June, 2019) regarding additional 10 land plots of 2 APs (old) for Kushma
substation of Parbat district.
The CDC meeting which was conducted on 5th July 2019 in Parbat district has decided
the additional land for the tower no 4, 15 , 7A, 17, 24 and 25B .
2 The details of Land acquisition of UMBTL has not been displayed for tower foundation as construction work has not been started yet and land has been acquired for Bharatpur substation by NEA. 3 The details of Land acquisition of MKUTL has not been displayed as construction work has not been started yet. 4 The details of Land acquisition of STR3BTL has not been displayed as construction work has not been started yet.
Semi-annual Social Safeguard Monitoring Report January-June, 2020
14 SASEC-PSEP NEA-PSC-ESSD
The CDC meeting has been conducted in Myagdi district on 12th December, 2019
which has decided to start the compensation distribution for Structural loss under RoW.
The CDC meeting has been conducted in Myagdi District on Jan 16th ,2020 which has
decided to structure loss under RoW for Annapurna 6, Ghirchyang tower no 41A to 41
B.
The CDC meeting has been conducted in Parbat district on Jan 22nd ,2020 which has
decided to land compensation for under RoW for Jaljala ward no 1,2,3,4, Parbat from
AP 17 to 26
The CDC meeting has been conducted in Myagdi district on March 3rd, 2020 has
decided to land compensation for under RoW.
The CDC meeting has been conducted in Myagdi district on March 21st, 2020 has
decided structure loss compensation for under RoW for Annapurna 6, Ghirchyang from
tower no 41A to 41 B.
The CDC meeting has been conducted in Myagdi district on 8th May 2020, which has
decided to compensate for AP 43 and 44 for Structural loss under RoW of tower no.
43 and 44.
The CDC meeting has been conducted in Myagdi district on June 24th ,2020 has
decided Additional land acquisition for tower no 42 B
MKTLP
The land acquisition notice for additional land of 3 new APs of four affected land plots
of Chitwan District was published on 2075/9/19 (2019/01/03).
The CDC fixed the rate for land acquisition in Chitwan district on 2075/2/25 (8th June
2018) and in Dhading district on 2074/10/24 (7th February, 2018).
The CDC meeting in Dhading district fixed the rate for land acquisition in Benighat
Rorang Municipality on 2075/5/3 (19th August 2018).
The land acquisition notice for Kathmandu District was published on 2075/08/01 (17th
November 2018).
Public notice for land acquisition has been published in Tanahun on 2075/8/9 (25th
November 2018).
The CDC of Kathmandu district fixed the rate for land acquisition for Kathmandu district
on 2075/10/17 (31st January 2019).
The CDC meeting was conducted in Dhading district on 13th May 2019, regarding
compensation for affected land plots and structures under Right of Ways (ROW) of
Gorkha district.
The land notice of Gorkha district was published in National Newspaper on 2074/1/23
(2017/05/06) and similarly, rate of affected land under RoW in Gorkha district has been
fixed by CDC in 2074/06/02 (2017/09/18).
CDC decided to provide 20% compensation for land along the Right of Way (ROW)
through the project office in Gorkha District.
CDC has also endorsed the structure loss compensation amount under transmission
line RoW.
PMO office has published the notice of affected land plots falling under RoW of
Dhading district on 15 May 2019 in Gorkhapatra National Daily Newspaper.
CDC meeting has been done for Dhading district regarding compensation for affected
land plots in high way crossing point under Right of Ways (ROW) on 2076/04/29
Semi-annual Social Safeguard Monitoring Report January-June, 2020
15 SASEC-PSEP NEA-PSC-ESSD
(14/082019).CDC has decided to provide 20% compensation for land under
transmission line ROW in high way crossing point through the project office.
CDC meeting has been done on 20th January 2020 in Gorkha district regarding the
formation of a subcommittee for losses valuation of AP 74/2 where tower foundation
work has been complected but other work has been halted because of obstacle
creating by household owner.
CDC meeting has been done for Gorkha district regarding structures, trees, crops, and
fodders under the right of way (RoW) on 20th January 2020.
KNBTLP
The CDC was formed in Syangja district under the chair of CDO on 23rd July, 2019
(2076/04/5).
The the valuation of the acquired land of Syangja District was completed on 27th
August, 2019 (2076/05/10).
The land acquisition notice for Syangja has been published in Gorkhapatra on
(2076/03/20).
The land acquisition notice for Parbat has been publishedin Gorkhapatra on 14th
October, 2019 (2076/06/27).
UMBTLP
The land acquisition notice for Lamjung District (UMBTLP) was published on
2075/12/26 (9th April 2019). The CDC fixed the rate for land acquisition in Lamjung
district on 2076/3/19 (4th July, 2019).
All the details of rate fixation and land acquisition notice updated in this period have been kept
safely with project.
5.2.2 Compensation for Acquired Land
The compensation of substations and tower foundation that has been disbursed by concerned
District Administration Office till the reporting period are given in below Table 4. The details of
the compensation distribution till this reporting period have been kept safely with project. It
may be noted that reporting includes only the sub-components where some progress has been
made.
Table 4: Compensation Distribution Status
SN Sub-project
Components Affected
APs Acquired Land
APs who have
received Compensati
on
Compensation target (NPR)
Compensation paid (NPR)
1. Kaligandaki Corridor
1.1.Dana-Kushma 220kV TL Project under Kali Gandaki Corridor (DKTLP)
i Dana Substation
21 5.45 21 27,118,086 100% paid
Semi-annual Social Safeguard Monitoring Report January-June, 2020
16 SASEC-PSEP NEA-PSC-ESSD
SN Sub-project
Components Affected
APs Acquired Land
APs who have
received Compensati
on
Compensation target (NPR)
Compensation paid (NPR)
ii Kushma Substation
84 7.91 84 149,682,530.81 100% paid
Sub-total (i+ii) 105 13.36 105 176,800,616.81 176,800,616.81
iii Tower Foundation (Myagdi)
87 2.976 68 48,293,147.91 38,398,138
iv Tower Foundation (Parbat)
134 3.708 74 36,668,794.09 16,673,246
v Kushma substation (Addl.)
21 1.7 21 10,239,644 10,239,644
vi RoW (Myagdi)
361 23.2 22 NA 21,300,568.53
vii RoW (Plots) (Parbat)
1451 34 NA 5,204,471
Sub-Total (iii+iv+v+vi+vii)
2054 31.584 219 95,201,586.00 91,816,068
1.2.Kushma-New Butwal 220kV TL Projectunder Kali Gandaki Corridor (KNBTLP)
i New Butwal Substation
6 HHs and 3 private
Companies
8.55 6 HHs and 3
private companies
136,251,875.00 100% paid
ii Tower Foundation (Palpa)
137 3.225 56 12,186,425.92
4,874,570.4
Sub-Total (i+ii) 143 11.805 62 148,438,300.92 141,438,300.92
2. Marsyangdi-Kathmandu
i Markichowk Substation
15 3.024 15 60,768,621.02 100% paid
ii Matatirtha Substation
138 6.19 138 1,106,616,063.
58 100% paid
Sub-Total (i+ii) 153 9.22 153 1,167,384,684.
60 1,167,384,684.
60
Semi-annual Social Safeguard Monitoring Report January-June, 2020
17 SASEC-PSEP NEA-PSC-ESSD
SN Sub-project
Components Affected
APs Acquired Land
APs who have
received Compensati
on
Compensation target (NPR)
Compensation paid (NPR)
iii Tower Foundation (Dhading)
203 6.22 164 90,000,000 97,976,712.68
iv RoW Dhading 1556 143.53 402 NA 116004140.6
v Tower Foundation (Kathmandu)
7 0.166 2 19,000,000 3,435,002
vi Tower Foundation (Gorkha)
90 2.49 71 38,000,000 37,493,901.26
vii RoW Gorkha 622 - 302 NA 86,532,270.1
viii Tower Foundation (Chitwan)
25 1.176 21 15,000,000 12,728,425.00
ix Tower Foundation (Tanahun)
2 0.014 2 274218.75 274,218.75
Sub-Total (iii+iv+v+vi+vii+viii+
ix) 2505 153.596 964 162,274,219
354,444,670.40
3. Marsyangdi Corridor
3.1. Udipur-Markichowk-Bharatpur under Marsyangdi Corridor (UMBTLP)
i Udipur Substation
6 5.18 6 53,925,719.09 100% paid
ii Tower Foundation (Lamjung)
83 1.53 45 59,675,976.56 41,345,405
Sub-Total (i+ii) 89 6.71 51 113,601,695.65 95,271,124.09
5.2.3 Compensation Distribution for Structure Loss
The compensation distribution for Structure loss for the subprojects have been described as
follows:
Semi-annual Social Safeguard Monitoring Report January-June, 2020
18 SASEC-PSEP NEA-PSC-ESSD
DKTLP
Under Tower Foundation
In total 4 APs have been compensated by NPR. 2,999,198 for structure loss under tower
foundation in Parbat district and 8 APs have been compensated by NPR. 10,084,899 for
structure loss under tower foundation in Myagdi district till this reporting period.
Under RoW
In this reporting period, 22 APs have been compensated NPR20891622.63 loss in Myagdi
district and 1 AP has been compensated NPR81425 in Parbat District for structure loss under
RoW till this reporting period.
MKTLP
In MKTLP, there are total 77 APs, 47 APs, 9 APs and 6 APs affected due to structure loss in
Dhading, Gorkha, Chitwan and Tanahun districts respectively under tower foundation and
RoW.
Under Tower Foundation
In this Semi-annual, 4 APs have received structure loss compensation under tower foundation
in Dhading district. Therefore, in total 10 APs have received structure loss compensation, i.e.
NPR 4673443.66/- under tower foundation in Dhading district till this reporting period.
Similarly, in total 3 APs have been compensated NPR 848,218.66 in Gorkha district and 3 APs
have been compensated NPR 1,520,871.41 in Chitwan district for structure loss under tower
foundation till this reporting period. Similarly, 3 Community buildings' owners have been
compensated NPR 1,527,979.95 for structure loss under tower foundation in Chitwan district.
Under RoW
In this reporting period, 5 APs have received compensation NPR3360425.7 in Dhading district,
1 AP has received compensation NPR1855577.75 in Chitwan district and 4 APs have received
compensation NPR3217928.02 in Gorkha district for structure loss under RoW.
Therefore, in total 44 APs out of 74 have received compensation NPR 21242452.26/- under
RoW in Dhading district till this reporting period.
Similarly, 4 APs have received compensation amount NPR 3,175,763.55 for structure loss
under RoW in Chitwan and 4 APs in Gorkha district, have received compensation amount of
NPR 3,217,928.02 for structure loss under RoW. The compensation distribution for 6 APs in
Tanahun District is yet to be distributed.
The details of structure loss compensation has been kept safely with project.
KNBTLP
The structure loss and compensation payment in KNBTLP is not in progress because the
project is enlisting the exact number of structure loss due to tower foundation.
UMBTLP
The structure loss and compensation payment is not in progress because the project is
enlisting the exact number of structure loss due to tower foundation.
Semi-annual Social Safeguard Monitoring Report January-June, 2020
19 SASEC-PSEP NEA-PSC-ESSD
5.2.4 Compensation Distribution for Crop, Tree and Fodder Loss
The Compensation distribution for crop loss in each subproject has been described as follows:
DKTLP
In this reporting period, 91 APs have received crop loss compensation in DKTLP. Altogether
total 155 APs have received compensation NPR 1690097.67 in Parbat district and 28 APs
have received compensation NPR 644219.20 in Myagdi district for crop loss till this reporting
period.
Similarly, in this reporting period, 82 APs have received compensation i.e. NPR 2038008.29
in Parbat district and 76 APs have received compensation amounting to NPR 3838631.46 in
Myagdi district for tree loss. Therefore, till the reporting period 82 APs amounting to NPR
2038008.29 and 76 APs amounting to NPR 3838631.46 for the trees loss compensation in
Parbat District and Myagdi District respectively.
MKTLP
In this reporting period, 50 APs and 23 APs have been compensated for crop loss in Dhading
and Chitwan districts. Therefore, till this reporting period, total 385 APs have been
compensated NPR 7,939,598.07/- in Dhading district, 65 APs have been compensated NPR
670,907 in Gorkha district and 37APs have been compensation of NPR 1,537,605 in Chitwan
district for crop loss.
Similarly, in this reporting period 18 APs have been compensated for tree loss in Gorkha
districts.
Therefore, altogether 7 APs have received tree loss compensation NPR 2,172.18 and 31 APs
have received fodder tree loss compensation NPR 1,447,100 in Chitwan district and 18APs
have received compensation NPR825000 for tree loss in Gorkha district till the reporting
period.
The details of crop loss compensation distribution has been attached in Annexure 6 (kept
safely with project) and the details of tree loss and fodder tree loss compensation distribution
has been attached in Annexure 7( kept safely with project).
KNBTLP
The crop loss and compensation payment is not in progress because the project is enlisting
the exact number of loss due to tower foundation.
UMBTLP
In this reporting period, total 2 HHs have received crop loss compensation NPR 43000 under
Tower Foundation in Lamjung district.
5.2.5 Compensation Distribution for Fruits Loss.
DKTLP
The fruits loss and compensation payment is not in progress because the project is enlisting
the exact number of loss due to tower foundation.
MKTLP
In MKTLP, total 159 APs and 14 APs are affected due to fruits loss in Dhading and Chitwan
districts respectively.
Semi-annual Social Safeguard Monitoring Report January-June, 2020
20 SASEC-PSEP NEA-PSC-ESSD
In this reporting period, 3 APs have been compensated for fruits loss in Dhading district.
Therefore, in total 114 APs have received fruits tree loss compensation NPR 3,518,908/-in
Dhading district till the reporting period. Similarly, 3 APs have been compensated NPR
186,480 in Chitwan districts for fruits loss till this reporting period.
45 APs and 11 APs are yet to be compensated for fruits loss in Dhading and Chitwan districts
respectively as compensation distribution are still in progress.
The details of fruit tree loss compensation distribution has been kept safely with project.
KNBTLP
The fruits loss and compensation payment is not in progress because the project is enlisting
the exact number of loss due to tower foundation.
UMBTLP
The fruits loss and compensation payment is not in progress because the project is enlisting
the exact number of loss due to tower foundation.
5.2.6 Progress on Assistance to Vulnerable Households
DKTLP
In Parbat District, among interviewed HHs under Tower Foundation, 57 APs have been
identified as vulnerable groups among them 17 are Dalits, 5 are IPs, 16 are women headed,
3 are disabled and 25 are below poverty line during RIPP update where mentioned numbers
are non-additive.
Similarly, in Myagdi District, among interviewed HHs under Tower Foundation, 42 APs have
been identified as vulnerable group among them 2 are Dalits, 28 are IPs, 9 are women headed,
8 are below poverty line and 2 are disabled persons during RIPP update where mentioned
numbers are non-additive.
Similarly, in Myagdi and Parbat districts, among interviewed HHs under RoW, 17 APs have
been identified as vulnerable group among them, 15 are IPs, 1 is Dalit, 4 are below poverty
line and 3 are woman headed during RIPP update where mentioned numbers are non-
additive.
The assistance to vulnerable households has not yet been released till this reporting period.
In this reporting period, household survey and data analysis of affected people due to
additional land in Myagdi and Parbat districts of 15 APs and 4 APs in respective districts has
been completed.
MKTLP
In Dhading District, among interviewed HHs, 75 APs have been identified as vulnerable groups
among them 8 are dalit, 49 are IPs, 16 are women headed, 8 are disabled and 9 are below
poverty line during RIPP update where mentioned numbers are non-additive.
In Gorkha District, among interviewed HHs, 35 APs have been identified as vulnerable group
among them 8 are dalit, 15 are IPs, 3 are women headed, 10 are below poverty line and 7 are
disabled during RIPP update where mentioned numbers are non-additive.
In Chitwan district, among interviewed HHs, 18 APs have been identified as vulnerable groups
among them 18 are IPs, 6 are women headed and 1 is disabled during RIPP update where
mentioned numbers are non-additive. In this reporting period due to additional land in Chitwan
district 4 APs have been increased.
Semi-annual Social Safeguard Monitoring Report January-June, 2020
21 SASEC-PSEP NEA-PSC-ESSD
Similarly, in Kathmandu district, among interviewed HHs, 5 APs are identified as vulnerable
groups among them 5 are IPs and 1 is disabled during RIPP update where mentioned numbers
are non-additive.
KNBTLP
Household’s survey of the known APs has been just completed and data analysis is in
progress.
UMBTLP
In Lamjung district, out of 83 APs, 26 APs are identified as IPs and 20 APs are identified as
woman headed.
5.2.7 Additional Assistant to the PAFs
During this semi-annual monitoring period, the APs are yet to receive additional assistance,
however, the APs who are eligible to get additional assistance under tower foundation are
finalized and are being distributed. This assistance includes livelihood rehabilitation,
transportation assistance, vulnerable assistance etc., as per approved entitlement matrix of
the RIPP.
5.2.8 Major Issues associated with Land Acquisition and Compensation
The report on major issues associated with land acquisition and compensation in the
subprojects have been described separately as follows in Table 5:
Table 5: Major issues associated with land acquisition and compensation in project sites
SN Major Issues
DKTLP
1 The problem in Annapurna-6, Pokharebagar at 6 APs of Tower foundation has been solved.
One of the affected, Pokharebagar Dhan Bahadur Baruwal whose residential building is
affected by RoW (43 Ap–44 AP) is still demanding for revaluation of his building and
demanding the homestead land in the same vicinity. The issue is in the process of solving by
project. CDC has already determined his losses due to the Transmission Line activities, but
he is denying to receive/accept the money.
2 The stringing work had been stopped by the people of Kushma 2, Pang due to AP1 to AP1C
ROW issues as the affected people are demanding high compensation from the project. This
issue has been already solved by the project and the stringing work has been completed.
3 The affected people at Dana Substation stopped the construction activities of substation on
2077/3/10. Meeting was conducted at CDO office on 2077/3/14 to address their demands and
the work has been resumed after the negotiation was done between the project and local
people. Now the local people are in the process to submit the financial and technical proposal
to the project as per their demands.
MKTLP
4 At AP74/2, total of 9.5 Ropani land is impacted by tower foundation including RoW of a single
household at Gorkha- 14. PAFs have demanded either to provide land for land or to pay full
compensation (not only 20% as per CDC) of affected land under RoW. The issue has been
under discussion in second and third level GRC. Asubcommittee, led by Assistant Chief District
Semi-annual Social Safeguard Monitoring Report January-June, 2020
22 SASEC-PSEP NEA-PSC-ESSD
SN Major Issues
Officer has been formed by the CDC meeting which was held on 2076/10/06 to investigate the
losses of concerned PAFs.
KNBTLP
5 At AP 56A, PAFs have demanded to put iron ganger on the wall for security, which is under
consideration in project office and technical studies are going on to address the demand which
is still in the process of solving by NEA
6 At AP58B/0, PAF Mr. Lila Bahadur Rana has demanded security of his house which is at
sloppy area and also demanded for compensation of cowshed. It is still in process of solving.
7 The issue regarding Baglung has not been solved yet. The technical committee appointed by
the MoEWRI is still working on the technical possibilities of the alternative route suggested by
the locals taking engineering, environmental, social, administrative and economical aspects
into consideration for the submission of report to the Ministry. The project is taking initiation to
solve through ministry level.
8 PAF of AP 16, 16A & 17 Manomaya Kunwar of Phalewas-11 Parbat has denied digging up
Approach Road, PAF Manomaya has demanded to construct the wall. This problem was
sorted through interaction with concerned stakeholders and affected people which in process
of addressing the demand.
9 Approach Road construction has not been started yet in AP 43C & 44 due to high demand of
PAF. They are demanding to construct wall all along the Approach Road. This is in the process
of addressing.
10 Due to the excavation of 37 E and 37 F for the construction of foundation there had been a
deep ditch in Syangja. Because of this reason, soil has been eroded and affected the
foundation of the bridge of Seti Beni. Local People demanded to clean the soil as soon as
possible. Message was delivered to Contractor and Project Official to solve this issue as soon
as possible. So the issue has been solved as soil has been cleaned which was demanded by
local people.
11 At AP 49/0, PAFs & community people have demanded to manage access road from north
side of tower pad which has been stopped from 1 year because of project & contractor were
late tor designing wall for the access road.
UMBTLP
12 Affected persons in AP33A at Dordi 2 Archalbot are demanding compensation of trees and re-
determination of land compensation. Regarding the issue several meeting were conducted
between the project, PSC, Safeguard Team and the APs. Project has agreed to provide
compensation of trees and APs has also agreed to start the construction work.
13 Community people in AP44, AP45/2 and AP46 of Rainas-6 Dhamilikuwa are demanding re-
determination of land compensation and determination of RoW compensation as earliest.
14 Community people of Palungtar -4 and 5 are still demanding to shift the alignment from
Thatipokhari market area due to the plan of smart city and scope of paragliding in that area.
They have submitted the letter to Nepal electricity authority Kathmandu and Ministry of Energy,
water resources and Irrigation.
5.2.9 Safeguard Implementation Progress
The status of safeguard implementation progress is given in below Table 6( kept safely with
project).
Semi-annual Social Safeguard Monitoring Report January-June, 2020
23 SASEC-PSEP NEA-PSC-ESSD
Table 6: Status of Safeguard implementation progress
SN Subprojects Status
Kali Gandaki Corridor
1 Dana-Kushma 220kV
transmission line, and
substations at Dana
and Kushma
Conducted GRC and Public consultation meetings
Conducted the meeting at CDO office Beni Myagdi for
Annapurna -6 Pokhrebagar issues again.
2 Kushma-New Butwal
220kV transmission
line, and substation at
New Butwal
Conducted Public consultation meeting.
Informed and managed documentation of PAFs for receiving
compensation process by project.
Check survey & cadastral survey is remaining from AP 82 to
Badera SS. whereas Cadastral survey has also completed
and report has been received in Syangja district (But some
landowner details are missing).
Compensation distribution is going on in Palpa district
Visited PAFs for consultation for the clearance of tower pad
foundation.
Crop and fruit loss data collection is ongoing.
Marsyangdi-Kathmandu 220kV transmission line and substations at Matatirtha and
Markichowk
3 Marsyangdi -
Kathmandu 220kV
transmission line and
substations at
Matatirtha and
Markichowk
Conducted Consultation and GRC meetings.
Construction work of Shatighat (Cremation place) for
Indigeneous people (Tamang &Gurung community is in
progress) at Thakre-8.
Compensation is being provided to APs against loss of private
land, houses/sheds, crops and trees.
Sewing and Knitting training for project affected HH is being
conducted to 21 female participants in Dhading district.
Marsyangdi Corridor
4 Udipur-Markichowk-
Bharatpur 220kV
transmission line and
substation at Udipur
GRC and public meetings have been conducted.
Household survey has been completed for tower pad in
Lamjung district
Cadastral survey is completed in Lamjung district
Cadastral survey is completed from AP 62 to AP 79 of Gorkha
district. Other process is ongoing at Gorkha and cadrastel
survey is ongoing in Tanahun district.
Tree marking work is ongoing at Gorkha district and completed
in Chitwan District.
Tree marking (Chhapan) work is ongoing at Lamjung Distrist.
5.2.10 Livelihood Restoration Program
For any loss of livelihood, restoration measures have been identified in the updated RIPP.
ESSD has been planning to implement livelihood restoration and enhancement skill
development training as a part of safeguard measures of the project. The proposed training
will be conducted following the curriculum of Council for Technical Education and Vocational
Training (CTEVT) level 1 skill training. PSC consultant will facilitate the trainings.
DKTLP
Semi-annual Social Safeguard Monitoring Report January-June, 2020
24 SASEC-PSEP NEA-PSC-ESSD
The Agriculture Productivity Intensification Program for the project affected families has
been completed on 2nd March, 2019 in DKTLP. The total 80 affected family members have
been beneficiated by the Seasonal and off seasonal vegetable farming training.
Two months computer training for the project affected families at Beni, Myagdi district has
been completed. Total 16 participants have been enrolled in Computer training in which
13 were female and 3 were male.
Similarly, Electrician, and Tailoring training have been also completed in the month of
August 2019 which had started since 9th May 2019 at Barnath hostel, Beni, Myagdi district
in DKTLP. There were total 16 male participants enrolled in the Electrician training. There
were total 20 female participating in the tailoring training.
Two months computer training for the project affected families at Beni, Myagdi district
which was started in the month of April 2019 has been completed in the month of October
2019.Total 16 participants have been enrolled in Computer training in which 13 were
female and 3 were male.
1 Month Driving has been completed in Parbat district which was started on 25th
November 2018 and completed on 23rd December, 2018. Total 25 people participated the
training, among them 20 were male, 5 were female, 2 were IPs and 2 were dalits.
Remaining trainings are in the process of implementation.
MKTLP
In MKTLP, skill development training on Beautician has been completed in Dhading district
in 23rdJanuary, 2019 (2075/10/9) which was started from 19thNovember 2018 (2075/08/3).
Total 30 female participants had enrolled in the training but only 26 participants
successfully completed the training course. Among them, 9 are IPs and 1 is Dalit.
In MKTLP, under mitigation measure total 5 training events of 7 days long training of
seasonal and off seasonal vegetable farming has been completed. Two events were
completed in the month of December 2018 (in Siddhalek RM-3, Salangghat and Siddhalek
RM-7; Pipaltar of Dhading district) and 3 were completed in the month of January, 2019 in
Ghyalchowk village of Gandaki RM-3, Gorkha, Yangkot, Gorkha and Ichchhakamana RM,
Chitwan. Altogether 100 project affected people had participated in vegetable farming
training. Among them 53 were male, 47 were female, 31 were IPs and 13 were Dalit.
In MKTLP, health and sanitation training program was conducted for 60 project labors in
substation of Markichowk and Matatirtha and labor working on transmission line to make
them aware about health and sanitation in the month of February, 2019. Total 3 programs
were conducted. One program was conducted in Matatirtha Substation on 19th February,
2019 for 24 workers for one day. Another program was conducted in Dharke on 20th
February for 16 workers. Similarly, training was conducted in Markichowk substation,
Tanahun of MKTLP on 21st February, 2019 for 20 workers for one day.
In MKTLP, Tailoring training was conducted in MKTLP from 5th March 2019 for 20 women
(project affected families) at Gyaja village of Sahidlakhan RM-3, Gorkha, which has been
completed on 3rd May, 2019
Similarly, total three training events on forest and wildlife conservation training has been
provided to community forest user groups of Gorkha, Chitwan and Dhading districts from
ESSD during this month (May, 2019). Each of the training program was of 2 days where
total 60 participants were trained from 4 community forest, 3 leasehold forest of Gorkha
and Chitwan districts and 8 different CFs of Dhading district.
Semi-annual Social Safeguard Monitoring Report January-June, 2020
25 SASEC-PSEP NEA-PSC-ESSD
In MKTLP, total seven training events of NTFPs Training has been implemented and also
has been completed during the month May, 2019 and altogether 148 participants
participated from 8 CF and 3 LF of Gorkha and Chitwan district and 14 affected Community
Forests from Dhading district. Each of the training programs was of 3 days.
In MKTLP, three training events of 7 days Agriculture productivity Intensification Trainings
have been implemented during the month June, 2019. One training event was conducted
in Dhading district. Total 22 participants participated in this training event where female
and IPs participants were 14 & 5 respectively. Whereas 59 participants have been
participated from Ghyalchowk 7 and 8 ward of Gandaki Rural Municipality of Gorkha
district.
Driving training which was started from 9th June 2019 for 12 PAFs of Gorkha district under
skill development program has been completed on 15th July 2019. 30 days training was
delivered to PAFs aiming to enhance and restore the livelihood of the affected
household/people. All 12 participants were indigenous peoples (IPs).
Similarly, 2 months (60 days) long basic Computer training has been also completed in
Gorkha, Tanahun and Chitwan districts on 15th July 2019 which had been implemented
from 15th May, 2019 for 8 PAFs. 6 Aps out of 8 participants were IPs.
Likewise, 2 months (60 days) long basic computer training course has been conducted
from 26th May 2019 to28th July 2019 in Dhading district. 25 participants successfully
completed the training course. 7 Male and 18 Female participants participated in the
training program. Among them 5 were dalits and 9 were IPs.
Driving training which was started from 20th November 2019 for 5 PAFs of Tanahun and
Gorkha district under skill development program, which will be completed on 19th
December, 2019. Total 30 days training has been delivered to PAFs aiming to enhance
and restore the livelihood of the affected household/people in the area.
In Dhading, 7 days Agriculture productivity and Crop Intensification Trainings has been
implemented from 22nd to 28thDecember, 2019.Total 24 participants participated in this
training event where female participants were 9 and Dalit participants were 2.
30 days driving training has been implemented from 20th November, 2019 to 19th
December, 2019 for 5 PAFs of Tanahu and Gorkha district under skill development
program. A total of 5 men have participated in the training among them 2 were IPs and 3
were Dalits.
Similarly, 2 months Tailoring training which started from 4th December, 2019 has been
completed in February, 2020. Total 11 PAFs of Gorkha and Tanahu districts have
participated the training. All of the participants were female in the training and among them
7 are Dalits, 3 are IPs, and 1 is from other caste group.
One month (30 days) driving training has been implementing to the project HHs from 19th
March, 2020 in Chitwan district. A total of 8 participants are participating in this training.
Program. (The driving training program has been resumed from 23rd June 2020 in Chitwan
district which was halted due to Covid-19. Social distancing norms have been followed
throughout the training because of COVID-19 pandemic)
2 months (60 days) long basic tailoring training course has been implemented to the project
affected HHs from14th February, 2020 in Dhading district. Total 21 female participants are
participating in this training among them 1 is dalit and 15 are IPs. (The training program
has halted because of Covid-19 lockdown)
Semi-annual Social Safeguard Monitoring Report January-June, 2020
26 SASEC-PSEP NEA-PSC-ESSD
KNBTLP
IN KNBTLP, One day social awareness program scheduled for this month has been halted
due to the outbreak of Corona Virus COVID-19 which will be conducted in next reporting
period.
The details of livelihood restoration program has been kept safely with project.
5.2.11 Impact on Indigenous People (IPs)
At Dana substation under Kali Gandaki Corridor, out of 21 APs, 18 are IPs. Likewise, at
Khurkot substation (additional land 1.7 ha affected households of 21), out of 105 APs none
are IPs.
In Myagdi district, out of 73 interviewed APs, 26 are IPs and in Parbat, out of 131interviewed
APs, 5 are IPs of Dana-Kusma 220kV Transmission Line under Kaligandaki Corridor at the
time of household survey for Updated RIPP. Similarly, for structure under RoW in Myagdi
district out of 18 interviewed APs, are15 IPs and in Parbat district, out of 2 interviewed APs,
there are no IPs at the time of household survey for Updated RIPP.
Out of total 138 APs, 25 are IPs in Matatirtha substation and all 15 APs are IPs in Markichowk
substation of Marsyangdi-Kathmandu 220kV Transmission Line project.
In Dhading, out of 162 interviewed APs, 48 are IPs; in Chitwan, out of 20 interviewed APs, 18
are IPs, in Gorkha, out of 65 interviewed APs, 15 are IPs, in Kathmandu out of 5 interviewed
APs, 5 are IPs and in Tanahun out of 2 interviewed APs, 1 is IP of Marsyangdi-Kathmandu
220kV transmission line project. Similarly, for structure under RoW in Dhading district out of
71 interviewed APs, 29 are IPs, in Gorkha out of 40 interviewed APs, 12 are IPs, in Chitwan
district out of 7 interviewed APs, all 7 are IPs and in Tanahun out of 6 interviewed APs, all 6
are IPs at the time of household survey for Updated RIPP.
Similarly, out of 18 interviewed APs, 15 are IPs under RoW in Maygdi and Parbat districts at
the time of household survey for Updated RIPP.
At Udipur substation under Marsyangdi Corridor, out of 6 APs, 3 are IPs. In Lamjung district,
out of 83 APs, 26 are IPs of Udipur-Markichowk-Bharatpur 220kV Transmission Line under
Marsyangdi Corridor at the time of household survey for Updated RIPP.
100% compensation has been disbursed in Dana Substation, Kushma Substation, New-
Butwal substation and Udipur substation. IPs are provided full compensation of their affected
assets and other assistance as per entitlement matrix. Details are presented in the Table 7
below.
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
27
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
Ta
ble
7 :
Res
ett
lem
en
t Im
pac
t an
d Im
pa
cts
on
IP
s
SN
N
am
e o
f P
roje
cts
T
ota
l A
Ps
In
terv
iew
ed
AP
s
du
rin
g R
IPP
up
date
To
tal A
ffec
ted
IP
s
am
on
g in
terv
iew
ed
AP
s
du
rin
g U
pd
ate
d R
IPP
To
tal IP
s (
rec
eiv
ed
co
mp
en
sati
on
) R
em
ark
s
1.
Kali G
an
da
ki
Co
rrid
or
1.1
Dan
a-K
ush
ma
22
0kV
TL
Pro
jec
t u
nd
er
Kali G
an
daki
Co
rrid
or
i.
Dana
S/S
21
18
18
1
00%
com
pe
nsation
ha
s
bee
n
dis
burs
ed
ii.
Ku
shm
a S
/S
84
0
0
The
re
has
be
en
no
aff
ecte
d
IPs
in
Kushm
a S
/S.
iii
Tow
er
in M
ya
gd
i
(Land)
87
71
2
8
35
3
5 IP
s ha
ve re
ce
ived
co
mp
ensa
tio
n
an
d r
em
ain
ing a
re in
pro
gre
ss
iv.
Tow
ers
in P
arb
at
(Land)
134
1
30
5
3
3 IP
s h
ave rece
ived
com
pe
nsatio
n a
nd
rem
ain
ing a
re in p
rogre
ss
R
oW
in M
ya
gdi
(Land)
361
R
oW
in P
arb
at
(Land)
1451
4
v.
Str
uctu
res u
nder
RoW
(Myag
di)
21
18
1
5
14
Str
uctu
res u
nder
RoW
(Parb
at)
2
2
0
0
vi
Ku
shm
a S
/S
(Ad
ditio
na
l)
21
20
0
0
The
re
has
be
en
no
aff
ecte
d
IPs
in
Add
l. K
ushm
a S
/S.
Su
b-T
ota
l (A
) 2182
2
41
6
6
74
1.2
Ku
sh
ma
-Ne
w B
utw
al
un
de
r K
ali
Gan
daki
Co
rrid
or
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
28
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
SN
N
am
e o
f P
roje
cts
T
ota
l A
Ps
In
terv
iew
ed
AP
s
du
rin
g R
IPP
up
date
To
tal A
ffec
ted
IP
s
am
on
g in
terv
iew
ed
AP
s
du
rin
g U
pd
ate
d R
IPP
To
tal IP
s (
rec
eiv
ed
co
mp
en
sati
on
) R
em
ark
s
vii
New
Butw
al S
/S
6 A
Ps a
nd 3
Pri
vate
Com
pa
nie
s5
0
0
viii
T
ow
ers
in P
alp
a
137
1
28
7
4
41
T
ota
l 13
1 A
ps, 74 IP
s a
nd
41 IP
s h
ave
rece
ived c
om
pe
nsatio
n fro
m p
roje
ct.
Su
b-T
ota
l (B
) 1
46
1
28
7
4
41
2.
Mars
yan
gd
i-K
ath
man
du
220
kV
TL
(M
KT
LP
)
ix
Mark
icho
wk S
/S
15
15
15
1
00%
com
pe
nsation
ha
s
bee
n
dis
burs
ed
.
x
Ma
tatirt
ha S
/S
138
25
25
1
00%
com
pe
nsation
ha
s
bee
n
dis
burs
ed
.
xi
Tow
ers
in K
TM
(Land)
7
5
6
2
2
IPs
have
receiv
ed
lan
d
com
pensation a
mou
nt
an
d r
em
ain
ing
are
in
pro
gre
ss.
xii
Tow
ers
in D
ha
din
g
(Land)
203
1
64
4
9
46
164
hhs
have
re
ce
ived
lan
d
com
pensation
NP
R 9
79
76
712
.68
/-till
this
re
port
ing
peri
od.A
ltog
eth
er
46
IP
s
an
d
10
D
alit
h
ave
re
ce
ived
la
nd
com
pensation a
mo
unt.
xiii
T
ow
ers
in C
hitw
an
(Land)
26
20
2
1
17
Com
pensation h
as b
een r
eceiv
ed b
y
21
HH
s a
mon
g w
hic
h 1
7 H
Hs a
re I
Ps
an
d r
em
ain
ing a
re in
pro
gre
ss
5 N
am
e l
ist
of
3 P
riva
te c
om
pa
nie
s:
1.
Ka
lig
an
da
ki
Ce
me
nt
Ud
hy
og
Pv
t. L
td.
2.
Ind
ren
i C
rush
er
Ud
hy
og
Pv
t. L
td.
3.
Asi
an
Ce
me
nt
Pv
t. L
td.
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
29
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
SN
N
am
e o
f P
roje
cts
T
ota
l A
Ps
In
terv
iew
ed
AP
s
du
rin
g R
IPP
up
date
To
tal A
ffec
ted
IP
s
am
on
g in
terv
iew
ed
AP
s
du
rin
g U
pd
ate
d R
IPP
To
tal IP
s (
rec
eiv
ed
co
mp
en
sati
on
) R
em
ark
s
xiv
T
ow
ers
in G
ork
ha
(Land)
90
71
4
4
41
70
HH
s
have
receiv
ed
lan
d
com
pensation.
41 I
Ps have r
eceiv
ed
com
pensationa
nd
re
main
ing
are
in
pro
gre
ss
xv
Tow
ers
in
Tan
ahun
(Land)
2
2
1
0
2
HH
s
have
re
ce
ived
la
nd
com
pensation a
mong
th
em
one
is IP
s.
xvi
Ro
W in
Dha
din
g
(Land)
1556
N
A
NA
1
31
402
H
Hs
have
rece
ived
lan
d
com
pensation
un
de
r R
oW
N
PR
11
6,0
04,1
40
.62/-
till
this
re
po
rtin
g
pe
rio
d.
xvii
Ro
W in
Gork
ha
(Land)
622
-
- 1
24
3
02H
Hs
ha
ve
re
ce
ived
lan
d
com
pensationu
nd
er
RoW
xviii
Str
uctu
res u
nder
TF
and R
oW
(Chitw
an)
9
7
7
7 I
Ps h
ave r
ece
ive
d c
om
pe
nsatio
n f
or
str
uctu
re
loss
and
re
ma
inin
g
are
in
pro
gre
ss
xix
Str
uctu
res u
nder
TF
and R
oW
(Dh
ad
ing)
85
49
28
44 H
Hs h
ave r
eceiv
ed
str
uctu
re l
oss
com
pensation
NP
R
21
24245
2.2
6/-
un
der
Ro
W till
th
is r
ep
ort
ing
peri
od. 2
1
HH
s w
ere
IP
s a
nd 3
HH
we
re d
alit
Sim
ilarly,
10
H
Hs
have
re
ceiv
ed
str
uctu
re loss c
om
pensatio
n u
nder
TF
NP
R
46
73
443.6
6
till
this
re
po
rtin
g
pe
rio
d. 7
HH
s w
ere
IP
S.
xx
Str
uctu
res u
nder
TF
and R
oW
(Gork
ha
)
47
16
3
8
AP
s
have
re
ce
ive
d
co
mp
ensa
tio
n
un
der
Tow
er
pa
d fo
r str
uctu
re lo
ss,
am
on
g w
hic
h 3
is IP
and re
ma
inin
g a
re
in p
rogre
ss
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
30
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
SN
N
am
e o
f P
roje
cts
T
ota
l A
Ps
In
terv
iew
ed
AP
s
du
rin
g R
IPP
up
date
To
tal A
ffec
ted
IP
s
am
on
g in
terv
iew
ed
AP
s
du
rin
g U
pd
ate
d R
IPP
To
tal IP
s (
rec
eiv
ed
co
mp
en
sati
on
) R
em
ark
s
Su
b-
To
tal (C
) 2800
2
62
233
4
39
3.
Mars
yan
gd
i C
orr
ido
r
3.1
Ud
ipu
r-M
ark
ich
ow
k-B
hara
tpu
r 220
kV
TL
(U
MB
TL
P)
xviii
U
dip
ur
Su
bsta
tion
6
3
3
100%
com
pe
nsation
ha
s
bee
n
dis
burs
ed
.
xix
T
ow
er
in L
am
jung
83
26
17
46
HH
s
have
rece
ive
d
the
com
pensation
of
NR
s
41
3454
05
in
La
mju
ng d
istr
ict.
Su
b-
To
tal (D
) 89
29
20
Gra
nd
To
tal
5217
6
31
386
5
74
Semi-annual Social Safeguard Monitoring Report January-June, 2020
31 SASEC-PSEP NEA-PSC-ESSD
5.3 Monitoring Results compared against IR and IPs Safeguards
The Compliance status against Loan Covenants related to resettlement and Indigenous
People safeguards has been kept safely with project.
The overall details of Monitoring Results compared against IR and IPs Safeguards for all the
subprojects have been described in Table 8 and Table 9 below:
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
32
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
Tab
le 8
: C
om
pli
an
ce
Mo
nit
ori
ng
Resu
lts
in
term
s o
f In
vo
lun
tary
Res
ett
lem
en
t S
afe
gu
ard
s
SN
M
on
ito
rin
g
As
pects
Ind
icato
rs
Co
mp
lian
ce
Sta
tus
DK
TL
P
MK
TL
P
KN
BT
LP
U
MB
TL
P
1
Deliv
ery
o
f
En
titl
em
en
ts
Entitlem
ents
d
isburs
ed
, com
pare
d
with
no. an
d c
ate
go
ry o
f lo
sses s
et out
in t
he E
ntitlem
ent
matr
ix.
Dis
burs
em
en
ts a
ga
inst tim
elin
es
Identificatio
n o
f th
e d
ispla
ce
d p
ers
ons
losin
g l
and t
em
pora
rily
, e.g
. th
rou
gh
so
il d
isposa
l, b
orr
ow
pits, co
ntr
acto
rs’
ca
mps,
be
en inclu
de
d
Re
sto
ration
of
socia
l in
frastr
uctu
re
and
serv
ices.
Pro
gre
ss
on
inco
me
an
d
livelih
ood
resto
ratio
n
activitie
s
be
ing
imp
lem
ente
d a
s s
et
ou
t in
the
inco
me
resto
ratio
n p
lan
, fo
r e
xa
mple
, utiliz
ing
repla
ce
me
nt
lan
d,
co
mm
en
cem
ent
of
pro
duction
, th
e n
o.
of
the
dis
pla
ce
d
pers
on
s tr
ain
ed in
em
plo
ym
ent
with
jobs,
Mic
ro-c
redit
dis
burs
ed
, no
. o
f
incom
e-g
en
era
ting
activitie
s a
ssis
ted.
Qua
lity o
f n
ew
plo
ts a
nd
issue o
f la
nd
titles
Bein
g c
om
plie
d w
ith
:
Co
mp
ensatio
n
dis
trib
ution
in
M
yagd
i
and
Pa
rbat
dis
tric
ts
unde
r tr
ansm
issio
n
line
and
Ro
W
are
in
pro
gre
ss.
Socia
l
safe
gu
ard
m
easure
s fo
r
the
AP
s
are
at
vari
ous
sta
ge
of
imp
lem
enta
tio
n.
In
DK
TL
P,
skill
develo
pm
en
t tr
ain
ing
pro
gra
m
on
safe
ty
for
lab
ore
rs;
ele
ctr
icia
n,
tailo
ring,
co
mpu
ter,
drivin
g
tra
inin
gs
ha
ve
been
con
du
cte
d
an
d
imp
lem
ente
d.
Bein
g c
om
plie
d w
ith:
Com
pensation
dis
trib
utio
n in
Dh
ad
ing
,
Gork
ha
, C
hitw
an
,
Kath
ma
ndu
an
d
Tana
hun
und
er
transm
issio
n l
ines a
nd
Ro
W a
re in
pro
gre
ss.
Socia
l safe
gua
rd
measure
s fo
r th
e A
Ps
are
at
vario
us s
tage o
f
imp
lem
enta
tion.
In M
KT
LP
, tr
ain
ing o
n
Co
mp
ute
r,
dri
vin
g,
tailo
ring
, A
gricu
ltu
re
pro
ductivity
an
d
Cro
p
Inte
nsific
atio
n
have
be
en
co
nd
ucte
d
an
d
imp
lem
ente
d.
Bein
g C
om
plie
d w
ith
:
Co
mp
ensatio
n
dis
trib
ution
fo
r N
ew
-
Butw
al
su
bsta
tion
has b
een
com
ple
ted
and
co
mpe
nsation
dis
trib
ution
is
ong
oin
g
in
Palp
a
dis
tric
t un
der
tow
er
pad
. T
he
check
su
rve
y
&
cada
str
al
su
rve
y
of
transm
issio
n
line
is
rem
ain
ing fro
m A
P82
to
su
b-s
tation
a
t
Bad
era
Bein
g C
om
plie
d w
ith:
Com
pensa
tion
dis
trib
ution
fo
r U
dip
ur
su
bsta
tion
has
be
en
co
mp
lete
d
and
co
mp
ensatio
n
dis
trib
ution
is
ong
oin
g
in
Lam
jung
dis
tric
t
und
er
tow
er
pa
d.
2
Co
ns
ult
ati
on
an
d
Gri
evan
ces
Co
nsu
ltations
org
aniz
ed
as
sched
ule
d i
nclu
din
g m
eeting
s,
gro
up
dis
cussio
ns a
nd c
om
mu
nity a
ctivitie
s.
Know
ledge
of
entitlem
en
ts
by
the
dis
pla
ce
d p
ers
ons.
Use
of
the
gri
evance
red
resses
mechan
ism
by th
e d
isp
lace
d p
ers
ons.
Bein
g c
om
plie
d w
ith
:
2 G
RC
m
eetings an
d 4
Pu
blic
C
onsu
lta
tio
n
meetings
have
bee
n
con
ducte
d
in
this
rep
ort
ing p
erio
d.
Bein
g c
om
plie
d w
ith:
4 G
RC
me
eting
s a
nd 5
Pub
lic
Co
nsu
ltatio
n
meetings
have
b
ee
n
conducte
d
in
this
report
ing p
eri
od.
Bein
g c
om
plie
d w
ith
4 G
RC
mee
ting
s a
nd
16
Pub
lic
Con
sultation
meetings h
ave
be
en
Bein
g C
om
plie
d w
ith
:
3 G
RC
mee
tin
gs a
nd 2
Pub
lic
Co
nsultation
meetings
have
be
en
co
nducte
d
in
this
report
ing p
eri
od.
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
33
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
SN
M
on
ito
rin
g
As
pects
Ind
icato
rs
Co
mp
lian
ce
Sta
tus
DK
TL
P
MK
TL
P
KN
BT
LP
U
MB
TL
P
Info
rmation o
n th
e re
solu
tion o
f th
e
grie
van
ces.
Info
rmation o
n t
he i
mple
menta
tio
n o
f
the s
ocia
l p
rep
ara
tion p
hase.
Imp
lem
enta
tio
n o
f sp
ecia
l m
easure
s
for
Ind
ige
no
us P
eop
les
co
nducte
d
in
this
rep
ort
ing p
erio
d.
3
Co
mm
un
ica
tio
n
an
d
Part
icip
ati
on
Perc
enta
ge
of
wom
en
ou
t of
tota
l
part
icip
an
ts.
No
. of
meetings
exclu
siv
ely
w
ith
wo
me
n.
No.
of
me
eting
s
exclu
siv
ely
w
ith
vu
lnera
ble
gro
ups.
No
. of
me
eting
s a
t ne
w s
ite
s.
No
. of
me
eting
s betw
ee
n hosts
and
the d
isp
laced
pe
rso
ns.
Level
of
part
icip
ation i
n m
eetings (
of
wo
me
n, m
en
, a
nd
vu
lne
rable
gro
up
s).
Level o
f in
form
atio
n c
om
munic
ate
d—
ade
quate
or
ina
de
quate
.
Info
rmation d
isclo
su
re.
Tra
nsla
tion of
info
rmatio
n d
isclo
sure
in t
he lo
cal la
ngu
ag
es
Bein
g c
om
plie
d w
ith
:
In
DK
TL
P,
4
pub
lic
con
sulta
tio
ns
were
con
ducte
d
in
this
rep
ort
ing
peri
od
wh
ere
87
peo
ple
p
art
icip
ate
d.
Am
on
g
all
the
part
icip
an
ts,
2
(2.2
9%
)
were
D
alit
s
and
4
(5.7
4%
) w
ere
wo
men
. N
o
IPs p
art
icip
ate
d.
The
info
rma
tio
n
was
deliv
ere
d
in
Nep
ali
lan
gu
age.
Bein
g c
om
plie
d w
ith:
In
MK
TL
P,
5
pu
blic
co
nsu
lta
tio
ns
we
re
co
nducte
d
in
this
rep
ort
ing p
erio
d w
he
re
51 p
eo
ple
part
icip
ate
d.
Am
ong
all
the
part
icip
an
ts,
8
(15
.68%
) w
ere
IP
s,
12
(23
.52%
) w
ere
D
alit
s
and
24
(47
.05%
) w
ere
wo
me
n.
The
in
form
atio
n
was
de
livere
d
in
Nep
ali
lan
gua
ge
.
Bein
g c
om
plie
d w
ith
:
In K
NB
TL
P, 1
6 p
ublic
co
nsu
lta
tio
ns
we
re
co
nducte
d
in
this
rep
ort
ing
pe
riod
whe
re
199
p
eop
le
part
icip
ate
d.
Am
ong
all
the p
art
icip
an
ts,
8
(4.0
2%
) w
ere
IP
s,
6
(3.0
1%
) w
ere
D
alit
s
and
2
5
(12
.56
%
)
were
wo
men
.
The
info
rma
tion
was
deliv
ere
d
in
Ne
pa
li
lan
gu
age.
Bein
g C
om
plie
d w
ith
:
In
UM
BT
LP
, 2
pu
blic
co
nsu
lta
tio
ns
were
co
nducte
d
in
this
report
ing p
erio
d w
here
25 p
eo
ple
pa
rtic
ipate
d.
Am
ong
all
the
part
icip
an
ts,
1
(4%
)
we
re
wo
me
n.
No
IP
s
and
Dalit
part
icip
ate
d.
The
in
form
ation
was
deliv
ere
d
in
Ne
pa
li
lan
gua
ge.
4
Bu
dg
et
an
d
Tim
e F
ram
e
Lan
d
acq
uis
itio
n
and
re
settle
ment
sta
ff
ap
po
inte
d
an
d
mo
bili
zed
on
sched
ule
for
the f
ield
and o
ffic
e w
ork
.
Ca
pacity
build
ing
an
d
train
ing
activitie
s c
om
ple
ted o
n s
ch
ed
ule
.
Bein
g c
om
plie
d w
ith
:
The
com
pen
satio
n
for
acq
uire
d la
nd
ha
s b
ee
n
dis
burs
ed
to
A
Ps un
der
Su
bsta
tio
n
an
d
un
der
tow
er
foun
datio
n
are
Bein
g c
om
plie
d w
ith:
The
co
mp
ensatio
n
for
acquire
d
land
ha
s
be
en
dis
burs
ed
to A
Ps
un
der
Substa
tio
n
an
d
tow
er
found
ation
are
Bein
g c
om
plie
d w
ith
:
The
com
pen
sation
for
the
aff
ecte
d
peo
ple
u
nd
er
su
bsta
tion has b
een
dis
burs
ed a
nd u
nder
Bein
g c
om
plie
d w
ith:
The com
pe
nsa
tio
n fo
r
the a
ffecte
d h
ouse
ho
ld
und
er
su
bsta
tion
ha
s
bee
n
dis
burs
ed
and
co
mp
ensatio
n
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
34
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
SN
M
on
ito
rin
g
As
pects
Ind
icato
rs
Co
mp
lian
ce
Sta
tus
DK
TL
P
MK
TL
P
KN
BT
LP
U
MB
TL
P
Achie
vin
g
resettle
ment
imp
lem
enta
tion activitie
s a
gain
st
the
agre
ed im
ple
menta
tio
n p
lan.
Fund
s a
llocation fo
r re
se
ttle
ment
to
resettle
me
nt ag
encie
s o
n t
ime.
Re
ceip
t of
sche
dule
d
funds
by
resettle
me
nt off
ices.
Fund
s d
isbu
rse
me
nt
accord
ing t
o t
he
resettle
me
nt p
lan
.
Socia
l pre
para
tio
n
ph
ase
as
pe
r
sched
ule
.
Lan
d
acq
uis
itio
n
and
occup
atio
n
in
tim
e for
imp
lem
enta
tion.
bein
g
com
pe
nsa
ted
as
per th
e e
ntitlem
ent m
atr
ix
of
resett
lem
ent
an
d
ind
ige
nous p
eo
ple
p
lan
.
The A
Ps u
nde
r R
oW
are
bein
g
com
pe
nsa
ted
as
per
the d
ecis
ion
mad
e b
y
Com
pe
nsa
tion
Dete
rmin
atio
n
Com
mitte
e
(CD
C).
Sim
ilarly,
AP
s
for
str
uctu
re l
oss,
cro
p l
oss,
fruits l
oss,
tre
e l
oss a
nd
gra
ss
loss
are
b
ein
g
com
pensa
ted a
s p
er
the
decis
ion
ma
de
by
Com
pe
nsa
tion
Dete
rmin
atio
n
Com
mitte
e (
CD
C).
be
ing
com
pensate
d a
s
per
the
entitle
men
t
matr
ix
of
resett
lem
en
t
an
d in
dig
en
ous p
eo
ple
pla
n.
Th
e
AP
s
und
er
Ro
W
are
b
ein
g
com
pensate
d
as
per
the d
ecis
ion m
ade
b
y
Co
mp
ensatio
n
De
term
ina
tio
n
Co
mm
itte
e
(CD
C).
Sim
ilarl
y,
AP
s
for
str
uctu
re
loss,
cro
p
loss,
fruits
loss,
tre
e
loss a
nd
gra
ss loss a
re
be
ing
com
pensate
d a
s
pe
r th
e d
ecis
ion
mad
e
by
Com
pen
satio
n
De
term
ina
tio
n
Co
mm
itte
e (
CD
C).
tow
er
fou
nd
ation a
re
bein
g
com
pen
sate
d
in
Palp
a
dis
tric
t as
per
the
entitlem
en
t
matr
ix
of
resettle
me
nt
and
ind
ige
nous
pe
op
le
pla
n.
The
ch
eck
su
rve
y
of
transm
issio
n
line
rou
te is c
om
ple
ted in
this
rep
ort
ing p
erio
d.
dis
trib
ution
is
ong
oin
g
in L
am
jung d
istr
ict
for
tow
er
pad
as per
the
entitle
me
nt
ma
trix
of
resettle
me
nt
and
ind
ige
nous
pe
op
le
pla
n.
5
Liv
elih
oo
d
an
d
Inc
om
e
Re
sto
rati
on
No
. o
f d
ispla
ced
p
ers
ons un
der
the
rehab
ilita
tio
n p
rog
ram
s (
wo
men
, m
en,
and
vu
lnera
ble
gro
ups).
No
. o
f d
ispla
ced
pers
ons
who
receiv
ed
voca
tiona
l tr
ain
ing (
wo
men,
men,
and
vuln
era
ble
gro
up
s).
Typ
es
of
tra
inin
g
an
d
no.
of
part
icip
an
ts in e
ach.
Bein
g c
om
plie
d w
ith
:
Sa
fety
T
rain
ing
has
been
pro
vid
ed
to
11
8
lab
ore
rs.
16 m
ale
part
icip
ants
enro
lled
in
the
Ele
ctr
icia
n t
rain
ing
in
Myagd
i.
Bein
g c
om
plie
d w
ith:
12
AP
s
(all
IPs)
part
icip
ate
d
in
drivin
g
train
ing
in
Go
rkh
a.
8
AP
s
(2
IPs)
part
icip
ate
d
in
2
mon
ths
(60
d
ays)
lon
g
basic
Bein
g c
om
plie
d w
ith
One
da
y
socia
l
aw
are
ne
ss
pro
gra
m
schedu
led
for
this
month
ha
s
be
en
halted
du
e
to
the
outb
reak
of
Coro
na
Vir
us
CO
VID
-19
whic
h
will
be
Not C
om
plie
d w
ith
:
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
35
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
SN
M
on
ito
rin
g
As
pects
Ind
icato
rs
Co
mp
lian
ce
Sta
tus
DK
TL
P
MK
TL
P
KN
BT
LP
U
MB
TL
P
No
. a
nd
perc
enta
ge
o
f dis
pla
ced
pers
on
s
covere
d
un
der
livelih
ood
pro
gra
ms
(wom
en,
men,
and
vu
lnera
ble
gro
ups).
No.
of
dis
pla
ced p
ers
ons w
ho h
ave
resto
red
th
eir
in
co
me a
nd
liv
elih
oo
d
patt
ern
s
(wom
en,
men,
and
vu
lnera
ble
gro
ups).
No. o
f ne
w e
mp
loym
en
t activitie
s.
Exte
nt
of
part
icip
atio
n
in
rehab
ilita
tio
n p
rogra
ms.
Exte
nt
of
part
icip
ation in
vocatio
nal
train
ing
pro
gra
ms.
De
gre
e
of
satisfa
ctio
n
with
sup
port
receiv
ed f
or
livelih
ood
pro
gra
ms.
Perc
enta
ge o
f su
cce
ssfu
l e
nte
rprise
s
bre
akin
g
even
(wo
me
n,
men,
and
vu
lnera
ble
gro
ups).
Perc
enta
ge
of d
isp
laced
pe
rso
ns w
ho
impro
ve
d t
heir
in
com
e (
wo
men,
me
n,
and
vu
lnera
ble
gro
ups)
Pe
rce
nta
ge
of
dis
pla
ced
pers
on
s
wh
o i
mpro
ved
th
eir s
tandard
of
livin
g
(wom
en
, m
en, and
vuln
era
ble
gro
ups)
No
. o
f d
isp
laced
pers
ons
with
repla
ce
me
nt a
gricu
lture
lan
d (
wom
en
,
men,
and
vuln
era
ble
gro
up
s)
Qua
ntity
of
lan
d o
wned
/con
tracte
d b
y
dis
pla
ce
d p
ers
ons (
wo
me
n,
men
an
d
20
fem
ale
part
icip
ate
d
in
the
tailo
ring
train
ing
in
Myagd
i.
16 p
art
icip
ants
ha
ve
been
e
nro
lled
in
Com
pu
ter
train
ing i
n
whic
h
13
were
fem
ale
a
nd
3
were
ma
le in
Mya
gdi.
25
pe
ople
part
icip
ate
d
in
drivin
g
train
ing
(2
0
ma
le, 5 fe
ma
le, 2 IP
s
and
2
dalit
s)
in
Pa
rba
t
Rem
ain
ing
tr
ain
ings
are
in t
he p
rocess o
f
imp
lem
enta
tio
n.
Com
pute
r tr
ain
ing
in
Gork
ha
,
Tan
ah
un
a
nd
Chitw
an
25 A
Ps (
7 m
en a
nd
18
wo
me
n)
part
icip
ate
d
in
2
mon
ths
(60
d
ays)
lon
g
basic
com
pute
r tr
ain
ing
in D
had
ing
dis
tric
t.
5 A
Ps (
2Ip
s a
nd 3
Dalit
s)
enro
lled
in
30
da
ys
drivin
g
train
ing
in
Tan
ah
un
an
d
Go
rkh
a
11
AP
s
(7
Dalit
s
and 3
IP
s)
enro
lled
in
2
mo
nth
s
tailo
rin
g t
rain
ing i
n
Go
rkh
a
an
d
Tan
ah
u d
istr
icts
.
24 A
Ps (
9 w
om
en
& 2
Da
lits)
enro
lled
in
7
days
Agricu
lture
pro
du
ctivity
an
d
Cro
p
Inte
nsific
atio
n
con
ducte
d
in
next
rep
ort
ing p
erio
d.
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
36
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
SN
M
on
ito
rin
g
As
pects
Ind
icato
rs
Co
mp
lian
ce
Sta
tus
DK
TL
P
MK
TL
P
KN
BT
LP
U
MB
TL
P
vu
lnera
ble
gro
ups)
No. of
househo
lds
with a
gricu
ltura
l e
qu
ipm
ent
Tra
inin
gs
in
Dhad
ing
1
mo
nth
drivin
g
has
bee
n
imp
lem
en
ted
in
Chitw
an
dis
tric
t
where
8
A
Ps
part
icip
ate
d.
2 m
onth
s ta
ilorin
g
train
ing
has
bee
n
imp
lem
en
ted
fo
r
21 fe
ma
le.
6
Ben
efi
t
Mo
nit
ori
ng
No
tice
able
ch
an
ges
in
patte
rns
of
occup
atio
n,
pro
ductio
n,
an
d r
eso
urc
e
use
com
pa
red
to
the
pre
-pro
ject
situation
.
No
tice
able
ch
an
ges
in
incom
e
and
expend
iture
patt
ern
s c
om
pare
d to t
he
pre
-pro
ject
situ
ation.
Ch
an
ge
s
in
key
so
cia
l an
d
cultu
ral
para
mete
rs
rela
tin
g
to
livin
g
sta
ndard
s.
Ch
an
ge
s
occu
rred
fo
r vuln
era
ble
gro
ups.
Ben
efitin
g
fro
m
the
pro
ject
by
the
dis
pla
ce
d p
ers
ons.
Bein
g c
om
plie
d w
ith
:
Ben
efit
mon
itori
ng
ca
n’t
be
done
ye
t be
ca
use
pro
ject
is s
till
in t
he
initia
l
con
str
uctio
n
ph
ase
an
d
Liv
elih
ood
an
d
Incom
e
Resto
ration
p
rogra
m
is
ongo
ing.
Ben
efits
fr
om
the i
nte
rve
ntion
sha
ll b
e
ana
lyzed
once
the
inte
rven
tio
n
accru
es
som
e m
atu
rity
.
Bein
g c
om
plie
d w
ith:
Ben
efit
mo
nito
rin
g
can’t
be
done
ye
t
be
cause p
roje
ct
is s
till
in
the
in
itia
l
constr
uction
ph
ase
an
d
Liv
elih
ood
an
d
Inco
me
R
esto
ratio
n
pro
gra
m
is
on
go
ing
.
Ben
efits
fr
om
th
e
inte
rven
tion
sh
all
be
an
aly
zed
once
th
e
inte
rven
tion
accru
es
som
e m
atu
rity
.
Bein
g c
om
plie
d w
ith
:
Be
nefit
mo
nito
ring
can
’t
be
do
ne
ye
t
because
pro
ject
is
still
in
the
initia
l
con
str
uctio
n
pha
se
and
Liv
elih
ood
and
Incom
e
Resto
ration
pro
gra
m is
o
ng
oin
g.
Be
nefits
fr
om
th
e
inte
rven
tio
n sha
ll be
ana
lyzed
o
nce
th
e
inte
rven
tio
n
accru
es
som
e m
atu
rity
.
Not C
om
plie
d w
ith
:
Constr
uction
wo
rks
has ju
st sta
rted
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
37
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
Tab
le 9
: M
on
ito
rin
g R
esu
lts in
term
s o
f In
dig
en
ou
s P
eo
ple
s S
afe
gu
ard
s
SN
M
on
ito
rin
g
Asp
ects
Ind
icato
rs
Co
mp
lia
nce
Sta
tus
DK
TL
P
MK
TL
P
KN
BT
LP
U
MB
TL
P
1
Dem
og
rap
hic
Baseli
ne
Th
e n
o. of
affecte
d I
ndig
en
ous P
eo
ple
s (
IP)
by c
ate
gory
of
imp
act,
ge
nder,
ag
e,
hab
itat
(vill
age
etc
.),
inco
me
, sta
tus a
nd p
ositio
n
No. o
f ho
useho
lds w
ith h
an
dic
ap
pe
d,
eld
erly o
r in
valid
me
mbers
No. o
f fe
ma
le h
ead
ed
ho
use
ho
lds
No. o
f vuln
era
ble
ho
use
hold
s (
poor,
eld
erly)
No. o
f ho
useho
lds b
y e
thn
ic g
roup
No. o
f b
irth
s a
nd d
ea
ths
Be
ing c
om
plie
d w
ith:
RIP
P
of
DK
TLP
section
has
be
en
pre
pare
d/u
pdate
d
and
has
be
en
subm
itte
d t
o A
DB
.
Bein
g c
om
plie
d w
ith
:
RIP
P
of
MK
TL
P
se
ction
ha
s
be
en
pre
pare
d/u
pdate
d a
nd
has b
ee
n s
ub
mitte
d t
o
AD
B.
Bein
g C
om
plie
d w
ith
:
Househ
old
su
rvey
has
be
en
com
ple
ted
in
Palp
a,
Pa
rbat
an
d
Syan
gja
d
istr
icts
wh
ere
as
house
hold
su
rve
y.
Da
ta a
naly
sis
is o
ngo
ing
for
RIP
P u
pda
te.
Be
ing C
om
plie
d w
ith
Cen
sus
surv
ey
and
Househ
old
surv
ey h
as
been
co
mp
lete
d
for
tow
er
pa
d i
n L
am
jun
g
dis
tric
t. D
ata
an
aly
sis
is
ong
oin
g
for
RIP
P
upda
te.
2
Co
nsu
ltati
on
an
d
part
icip
ati
on
No.
of
consu
ltatio
n
an
d
part
icip
ation
activitie
s t
ha
t occur—
me
eting
s,
info
rma
tio
n
dis
se
min
atio
n,
bro
ch
ure
s;
flyers
, tr
ain
ing
Perc
enta
ge
of
IP w
om
en
a
s part
icip
ants
;
no
. o
f m
ee
ting
s e
xclu
siv
ely
with I
P w
om
en
Perc
enta
ge
of
vuln
era
ble
IP
gro
ups
repre
sente
d
/ a
tte
nd
ing
meetings;
no.
of
meetings
exclu
siv
ely
w
ith
vu
lnera
ble
IP
gro
ups.
La
ng
ua
ges u
sed a
t m
ee
tin
gs
Goo
d
faith
ne
gotiatio
ns—
reco
rdin
g
of
pro
ce
ss,
part
icip
ants
, lo
ca
tio
ns,
corr
espo
nde
nce
Bro
ad
co
mm
un
ity
sup
port
—re
cord
of
pro
ce
sses,
part
icip
an
ts,
locations
and
ag
ree
men
t obta
ine
d
Consulta
tion
an
d p
art
icip
ation
pro
gre
ss
aga
inst p
lan
an
d b
udg
et
Be
ing C
om
plie
d w
ith:
In
DK
TL
P,
4
pu
blic
consulta
tio
ns
were
cond
ucte
d
in
this
repo
rtin
g
peri
od
where
87
pe
op
le
part
icip
ate
d.
Am
ong
all
the p
art
icip
an
ts,
2
(2.2
9%
) w
ere
D
alit
s
and 4
(5
.74
%)
were
wom
en.
No
IP
s
part
icip
ate
d.
Nep
ali
lan
gua
ge w
as
used
as
a
ma
jor
me
diu
m
for
com
mu
nic
atio
n
and
in p
ublic
con
sultation
Bein
g C
om
plie
d w
ith:
In
MK
TLP
, 5
pu
blic
con
sulta
tio
ns
we
re
con
ducte
d
in
this
repo
rtin
g p
eri
od w
he
re
51 p
eop
le p
art
icip
ate
d.
Am
on
g
all
the
part
icip
an
ts,
8
(15.6
8%
) w
ere
IP
s,
12
(23.5
2%
) w
ere
D
alit
s
and 2
4 (
47.0
5%
) w
ere
wom
en
.
Ne
pa
li la
ngu
age
w
as
used
as
a
majo
r
med
ium
fo
r
co
mm
un
ication
a
nd
in
pub
lic
co
nsu
ltation
Bein
g C
om
plie
d w
ith
:
In
KN
BT
LP
, 1
6
pu
blic
consu
lta
tio
ns
were
conducte
d
in
this
report
ing
pe
rio
d
where
19
9 p
eo
ple
part
icip
ate
d.
Am
ong
all
the
pa
rtic
ipan
ts,
8
(4.0
2%
)
we
re
IPs,
6
(3.0
1%
)
we
re
Dalit
s
an
d
25
(12.5
6 %
) w
ere
wom
en
.
Nepa
li la
ng
uag
e
was
used a
s a
majo
r m
ed
ium
for
com
mun
icatio
n a
nd
in
pub
lic
co
nsulta
tion
meetings
pa
rtic
ipan
ts
are
fr
om
m
ixed
repre
senta
tio
n
such a
s B
ein
g C
om
plie
d w
ith
In U
MB
TL
P,
2 p
ub
lic
consulta
tio
ns
were
cond
ucte
d
in
this
repo
rtin
g
perio
d
where
2
5
pe
ople
part
icip
ate
d.
Am
on
g
all
the part
icip
ants
, 1
(4%
) w
ere
wo
men
. N
o
IPs
an
d
Dalit
part
icip
ate
d.
Nep
ali
lan
gu
age
was
used
as
a
majo
r
me
diu
m
for
com
mu
nic
atio
n a
nd in
pub
lic
consu
lta
tio
n
me
etin
gs
pa
rtic
ipants
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
38
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
SN
M
on
ito
rin
g
Asp
ects
Ind
icato
rs
Co
mp
lia
nce
Sta
tus
DK
TL
P
MK
TL
P
KN
BT
LP
U
MB
TL
P
me
etin
gs
part
icip
an
ts a
re f
rom
mix
ed r
epre
senta
tion
such a
s I
Ps,
wom
en,
Dalit
, O
BC
etc
meetings
part
icip
ants
are
fr
om
m
ixed
rep
resenta
tio
n
su
ch
as IP
s,
wom
en
, D
alit
,
OB
C e
tc
IPs,
wo
men
, D
alit
, O
BC
etc
are
fr
om
m
ixe
d
repre
se
nta
tio
n
such
as I
Ps,
wo
men,
Da
lit,
OB
C e
tc
3
Mit
igati
on
Measu
res
Pro
gre
ss o
f im
ple
menta
tio
n o
f m
itig
atio
n /
be
ne
ficia
l m
easu
res a
ga
inst pla
n
No.
of
activitie
s
that
occu
r/com
ple
ted
—
such
as c
on
str
uction
, liv
elih
ood r
esto
ratio
n,
dis
burs
em
en
ts, tr
ain
ing
Perc
enta
ge
pro
gre
ss a
ga
inst
tim
elin
es a
nd
bu
dg
et
Be
ing c
om
plie
d w
ith:
ES
SD
h
as
cond
ucte
d
diffe
rent
tra
inin
gs f
or
the A
Ps
under
tow
er
fou
ndation.
Imple
me
nta
tio
n
of
rem
ain
ing
S
kill
Develo
pm
ent
tra
inin
gs
are
in
pro
gre
ss
Bein
g c
om
plie
d w
ith
:
ES
SD
h
as
co
ndu
cte
d
the
diffe
rent
train
ings
for
the
AP
s
un
der
tow
er
foun
datio
n.
.Im
ple
men
tation
of
rem
ain
ing
S
kill
Develo
pm
ent
train
ing
s
are
in
pro
gre
ss.
Not C
om
plie
d w
ith:
HH
s
surv
ey
and
cadastr
al
has no
t be
en
com
ple
ted
und
er
Ro
W
so,
IPs
or
aff
ecte
d
dis
adva
nta
ged
p
eop
le
ha
ve n
ot
be
en f
inaliz
ed
un
der
Ro
W to
co
ndu
ct
train
ing
Not
Co
mp
lied w
ith:
HH
s
surv
ey
and
cada
str
al
has
not
been
co
mp
lete
d
under
Ro
W s
o,
IPs o
r
affecte
d
dis
ad
va
nta
ged p
eople
have
n
ot
bee
n
fina
lize
d
unde
r R
oW
to c
ond
uct tr
ain
ing
Se
mi-a
nn
ua
l S
ocia
l S
afe
gu
ard
Mo
nitoring
Repo
rt
Jan
ua
ry-J
une
, 2
02
0
39
S
AS
EC
-PS
EP
NE
A-P
SC
-ES
SD
SN
M
on
ito
rin
g
Asp
ects
Ind
icato
rs
Co
mp
lia
nce
Sta
tus
DK
TL
P
MK
TL
P
KN
BT
LP
U
MB
TL
P
4
Gri
evan
ce
Red
res
s
Tota
l n
o.
of
peo
ple
/gro
ups
usin
g
the
gri
eva
nce
re
dre
ss p
roce
dure
.
No.
of
dis
tin
ct
pe
ople
/gro
up
s.
An
y I
P g
roup
with s
ign
ific
antly m
ore
grie
vances?
How
m
any
tim
es
has
a
househ
old
subm
itte
d t
he s
am
e g
rieva
nce?
No. of
grieva
nces r
esolv
ed
?
Le
ng
th o
f tim
e t
ake
n t
o b
e r
esolv
ed
?
Types
of
gri
eva
nce
cate
gorie
s
and
pre
va
lence
Be
ing C
om
plie
d w
ith:
In
DK
TLP
, 2
GR
C
me
etin
gs
were
cond
ucte
d
in
this
repo
rtin
g
peri
od
where
26
pe
op
le
part
icip
ate
d.
6
gri
evances
have
been
receiv
ed
in
th
is
rep
ort
ing
peri
od
am
on
g w
hic
h 2
have
been
solv
ed
.
Bein
g C
om
plie
d w
ith:
In
MK
TL
P,
3
GR
C
meetings
we
re
co
nducte
d
in
this
rep
ort
ing p
erio
d w
he
re
36 p
eo
ple
part
icip
ate
d.
5
grie
va
nces
ha
ve
bee
n
receiv
ed
in
th
is
rep
ort
ing
pe
riod
am
on
g w
hic
h a
re in
the
pro
cess o
f solv
ing.
Bein
g C
om
plie
d w
ith:
In
KN
BT
LP
, 4
G
RC
meeting
was c
on
ducte
d
in th
is re
port
ing
peri
od
wh
ere
5
5
peop
le
pa
rtic
ipate
d.
6 grie
van
ces h
as b
een
re
ceiv
ed
in
this
re
port
ing p
eri
od a
mo
ng
w
hic
h
2
gri
evances
ha
ve
be
en
so
lve
d
and
re
st are
in the
pro
cess o
f solv
ing
.
Be
ing C
om
plie
d w
ith:
In
UM
BT
LP
, 3
GR
C
me
etin
g
was
cond
ucte
d
in
this
repo
rtin
g
perio
d
where
4
9
pe
ople
part
icip
ate
d.
2
gri
evan
ces
have
been re
ce
ived in
th
is
report
ing
peri
od
wh
ich
are
in th
e p
rocess o
f
solv
ing
.
5
Imp
lem
en
tati
on
Pro
ble
ms
Identifie
d
de
lays—
(d
ays,
cost)
due
to
pe
rso
nn
el, c
apa
city,
insuff
icie
nt fu
nd
s,
etc
.
No.
of
tim
es
imple
menta
tio
n
sched
ule
revis
ed
No
pro
ble
ms
we
re
ide
ntifie
d
duri
ng
this
perio
d.
No
pro
ble
ms w
ere
ide
ntifie
d d
uri
ng
th
is
peri
od.
No
pro
ble
ms
were
ide
ntifie
d
duri
ng
this
perio
d.
No p
rob
lem
s w
ere
ide
ntifie
d d
uri
ng
th
is
perio
d.
Semi-annual Social Safeguard Monitoring Report January-June, 2020
40 SASEC-PSEP NEA-PSC-ESSD
6. GRIEVANCE REDRESSAL MECHANISM
Land Acquisition Act, 1977 encourages forming Grievance Redress Committee (GRC) to
solve the grievances related to the acquisition that may be submitted in land acquisition
process. PMU issued the letter to MC/RMC for formation of GRC. In DKTLP, in this reporting
period, 2 GRC meetings were conducted where 26 people participated, among them 23 were
men and 3 were women. Similarly, in MKTLP, 4 GRC meetings (1 was virtual meeting due to
COVID-19) were conducted where 36 people participated among which 40 were men and 2
were women. In KNBTLP, 4 GRC meetings were conducted where 55 people participated
among which 45 were men and 10 were women. In UMBTLP, 3 GRC meetings were
conducted where 49 people participated among which 45 were men and 4 were women. Total
6, 5, 6 and 2 grievances have been received in DKTLP, MKTLP, KNBTLP and UMBTLP
respectively out of which 2, 0, 2 and 0 grievances have been resolved respectively. The
remaining grievances are under process of resolving. The details of Grievance Redress
Committee Meeting Matrix and its minutes have been kept safely with project.
In DKTLP, among previously recorded 6 grievances, 4 unsolved grievances are still in the
process of solving. In MKTLP, previously recorded 5 grievances, all 5 are still in process of
solving. In KNBTLP previously recorded 6 grievances, 4 unsolved grievances are still in
process of solving. In UMBTLP previously recorded 2 grievances are still in process of solving.
The details of Recorded grievances have been kept safely with project).and letters related to
the Recorded grievances have been kept safely with project of this report.
7. PUBLIC CONSULTATION AND PARTICIPATION AND INFORMATION
DISCLOSURE
While implementing the RIPP, meaningful consultation program with project-affected people
was carried out, in line with requirements pertaining to receive compensation and
compensation determination procedure. The meaningful consultation ensures the presence of
different categories of representatives (i.e. representative sampling) in the consultation
process so as to obtain a balanced public opinion, equitable and non-discriminatory
participation, provide transparent and factual information with prior information about the
project, systematic documentation of the process, public disclosure of relevant parts etc. The
consultations in instant case were so designed that these basic criteria of a truly participative
and meaningful consultation process is meet in its letter and spirit.
In this reporting period, a total of 87 people participated in 4 public consultation meetings at
DKTLP among which 82 participants were men and 5 participants were women. Similarly, a
total of 51 people participated in 5 public consultation meetings at MKTLP among which, 27
participants were men and 24 participants were women. In KNBTLP, 16 public consultations
were conducted where 199 people participated among which 174 were men and 25 were
women. In UMBTLP, 2 public consultation were conducted where total 25 people participated
among which 21 were men and 1 was woman. In the meeting, discussion was made with the
participants regarding the skill training development training objectives, training venue and
convenient time for training. Similarly, all the necessary information about the project and its
merit demerits were dissipated well in advance to address information asymmetry in target
group. Besides these, consultation with Municipality and Rural Municipality representatives
have also been carried out to discuss on project activities and to resolve the problem related
Semi-annual Social Safeguard Monitoring Report January-June, 2020
41 SASEC-PSEP NEA-PSC-ESSD
with project activities. The public, CFUGs, business owners, affected people and local level
leaders were informed about the project activities. The consultation also focused on
entitlement matrix of the project and compensation receiving procedure. The techniques were
observation, consultation meetings, interviews and structured questionnaires. These
consultations provided inputs for identification of the needs of the communities and the
relevant stakeholders. The detail of public consultation matrix and minutes of public
consultation have been kept safely with project .
The consulted people were informed about different aspects of the projects and likely about
resettlement impacts and mitigation measures. They were also informed about the (i) process
of assessing resettlement and confirming the scope of impacts (ii) process of compensation
determination in accordance to the Land Acquisition Act 1977 and provisions of compensation
and other assistance made in the Entitlement Matrix (iii) Mitigation measures including
livelihood restoration and enhancement programs for PAF.
8. CORRECTIVE ACTIONS FOR NON-COMPLIANCE AND MAJOR GAPS
Following corrective actions are required in order to improve the monitoring activities, which
has been presented in Table 10:
Table 10: Corrective actions for non-compliance
SN Issues Corrective actions Responsibility Remarks 1 Delay in implementation of
RIPP entitlement matrix
Entitlement provisioned in
entitlement matrix to be
provided to affected HHs soon.
PMO Office
9. RECOMMENDATION FOR MONITORING ADJUSTMENT
The monitoring of social safeguard activities and implementation will be continued during the
project implementation. For this monthly report there was no any recommendation to be
suggested from the field.
Provide assistances for APs as per entitlement matrix of RIPP: It is necessary to provide
assistance for APs as per RIPP entitlement matrix. PSC should provide necessary guidance
to PMO office.
Rate fixing of private land, tree, structure under RoW: Compensation rate for the loss of
private land, tree, structure to be fixed soon in DKTLP and provided to affected people. Delay
in such activity might cause disturbances in stringing work.
10. INSTITUTIONAL ARRANGEMENT FOR MONITORING
10.1 Central Level Arrangement
10.1.1Environment and Social Studies Department (ESSD)
The scope of ESSD engagement based on MOU signed with PMD and ESSD is given here
below:
• ESSD shall mobilize environmental/social staff to the site for the environmental
management.
• ESSD will establish site based ESMU offices.
Semi-annual Social Safeguard Monitoring Report January-June, 2020
42 SASEC-PSEP NEA-PSC-ESSD
• ESSD shall work in coordination with the PSC safeguard specialists to avoid any
duplication of jobs.
• ESSD shall be responsible for implementation of environmental, social measures
including GESI.
• ESSD shall be responsible for compliances and impact monitoring, assist project for
grievances handling.
• ESSD shall assist implementation of resettlement plan.
10.1.2 Central Level Line Agencies
The central level line agencies such as Ministry of Energy, Ministry of Forest and Department
of Electricity Development have responsibility for the monitoring of project activities concerning
Environmental and Social Management, Mitigation and Monitoring Plan. ESSD is coordinating
with central level line agencies regarding the monitoring work. As the concerned line agency,
Department of Forest is responsible for the implementation of forestation program as per the
Procedural Guideline for the Use of Forest Land 2063.
10.2 Project Level Arrangement
10.2.1 Project Management Directorate, NEA (PMD Office)
The PMD office is overall responsible for the implementation of RIPP. It is also deputed a
Senior Environment Specialist (SES) and a Senior Social Safeguards specialist (SSS) in the
PMD office for Safeguard implementation and monitoring works of the SASEC TL Projects.
The responsibility of safeguard specialist to cooperate with and provide guidance to the social
safeguards teams of NEA on all tasks related in updating and finalizing the Resettlement and
Indigenous Peoples Plan (RIPP), to provide guidance to NEA’s concerned staff responsible
for social safeguards for detailed census surveys of affected persons and update the list of
affected and displaced persons, to provide required training (in –house and on-the job) to the
enumerators and surveyors to carry out the census survey and work closely with the NEA
team to involve them in the project planning from the initial period.
10.2.2 Project Manager
The Kali Gandaki Corridor (Dana-Kushma Section) and Marsyangdi-Kathmandu section
Project 220 kV TL Project Manager Office has been established under the organizational setup
of PMD. The Project Manager will be responsible for establishment of Compensation
Determination Committee (CDC). He will be responsible to coordinate valuation by the
valuation committee (CDC) and finalization of compensation packages, to provide necessary
guidance in the classification, and development of all social safeguards documents, including
the provision of training in the development and implementation of RIPP, to prepare Update
land acquisition and resettlement impact assessment based on all available data on land
acquisition as per the detailed layout for each subproject and collect additional data as
required and to make sure the allocation of necessary budget for the implementation of the
program. He will be responsible for the overall coordination of the work and make final decision
on environmental, social and public concern issues.
10.2.3. Environment and Social Monitoring Unit (ESMU)
Environment and Social Monitoring Unit has been established under ESSD umbrella for day
to day environmental and social monitoring of the project (One in Dana-Kushma Section,
Semi-annual Social Safeguard Monitoring Report January-June, 2020
43 SASEC-PSEP NEA-PSC-ESSD
where it has one Environmental Safeguard Officer and one Social Safeguard Officer) , (One
in Marsyangdi- Kathmandu section, where it has two Environmental Safeguard Officers and
Two Social Safeguard Officers ), (One in Kushma New Butwal Section, where it has one
Environmental Safeguard Officer and one Social Safeguard Officer) and (One in Udipur-
Markichok Section where it has one Environmental Safeguard Officer and one Social
Safeguard Officer) in coordination of work with PAFs, local communities, Rural
Municipality/Municipality and district level line agencies. The unit has site office for day to day
monitoring of the social and environmental impacts and responsible for submitting the
compliance monitoring reports to ESSD.
10.2.4 Project Supervision Consultant (PSC)
The project supervision consultant will have social safeguard specialist. They will be
responsible for updating/ finalizing the RIPP based on the final engineering design and check
survey to be done by the construction contractor. This will be done in close coordination with
PMU/PIU. The consultant will further assist in overall supervision of the projects and ensure
all plans are implemented in a smooth and timely manner in accordance with the provisions
of the RIPP. They will also prepare and implement training and capacity development
programs for resettlement and indigenous planning for the PIU and PMU of NEA and their
concerned staff and will closely work with the PMU and PIUs to ensure displaced persons and
compensated before the construction activities. The PSC safeguard specialist will also be
responsible for assisting NEA for preparation of monitoring reports.
11. Impacts of COVID-19 in the project implementation
COVID-19 is a disease caused by a new strain of coronavirus. ‘CO’ stands for corona, ‘VI’ for
virus, and ‘D’ for disease. Formerly, this disease was referred to as ‘2019 novel coronavirus’
or ‘2019-nCoV.’ The COVID-19 virus is a new virus linked to the same family of viruses as
Severe Acute Respiratory Syndrome (SARS) and some types of common cold. (WHO, 2019).
The outbreak of coronavirus disease (COVID-19) has been declared a Public Health
Emergency of International Concern (PHEIC) and the virus has now spread to many countries
and territories.
A high-level coordination committee for COVID-19 prevention and control in Nepal was formed
under the coordination of honorable deputy prime minister and defense minister on 1st March
2020. High level inter-ministerial Committee chaired by Deputy Prime Minister has been
restructured as the Corona Crisis Management Centre (CCMC). The Incident Command
System of the MoHP has been activated for COVID-19 response. (WHO, April 2020). GoN,
on 23rd March 2020, taking cognizance of the evolving global situation and recourse to the
Infectious Disease Act 2020, decided to lockdown the country effective from 24th March 2020
which was extended several times looking at the severe situation caused due to COVID-19 all
across the country and the world. Government of Nepal decided to ease the lockdown
adopting a phased approach from 12th June 2020. In the first phase of 21 days, GON allowed
shops to open and vehicles to operate under the odd-even rule. However, public places,
institutions and events with higher intensity of congregation which includes schools, colleges,
shopping malls, party palaces, conferences, sports activities etc. remained closed.
Due to Corona Virus outbreak all around world including Nepal, implementation phase of
SASEC project has also been affected especially in the field/sites which includes construction
Semi-annual Social Safeguard Monitoring Report January-June, 2020
44 SASEC-PSEP NEA-PSC-ESSD
work, public consultation and GRC meetings, compensation distribution, CDC meetings etc.
From the month of April, 2020 to June, 2020, the progress work had been halted to some
extent but however, virtual consultation meetings had been conducted, compensation
distribution was also carried out in some areas (which has been mentioned in report as well
as in annexures) in appropriate situation and grievances were also recorded in DKTLP. So for
past three months (April-June, 2020), the implementation phase of the project has been
adversely impacted. However, few project activities have also been carried out taking
necessary safety precautions by safeguard officers, stakeholders and project itself.
Semi-annual Social Monitoring Report January-June, 2019
SASEC-PSEP NEA-ESSD-PSC
Annexure-2: Status of Compliance with Loan Covenants
Sch. Para
No. Description
Current
Status
4. 9. The Borrower shall ensure that no Works contract which involves involuntary resettlement impacts is awarded,
until the Borrower and NEA have prepared and submitted to ADB the final RIPP based on the Project’s
detailed design, and obtained ADB’s clearance of such RIPP.
Being
complied
4. 10. The Borrower shall ensure that no Works contract which involves impacts on indigenous peoples is awarded
until the Borrower and NEA have prepared and submitted to ADB the final RIPP, and obtained ADB’s
clearance of such RIPP.
Being
complied
5. 7. The Borrower shall establish and maintain, or cause NEA and AEPC to establish and maintain, a grievance
redress mechanism acceptable to ADB for the purpose of addressing any grievances arising out of the Project,
including those from affected peoples concerning land acquisition, environment and any other social issues in
a timely manner.
Being
complied
5. 12. The Borrower shall ensure, or cause NEA and AEPC, as applicable, to ensure, that all land and all rights-of-
way required for the Project, each Subproject and all Project facilities are made available to the Works
contractor in accordance with the schedule agreed under the related Works contract and all land acquisition
and resettlement activities are implemented in compliance with (a) all applicable laws and regulations of the
Borrower relating to land acquisition and involuntary resettlement; (b) the Involuntary Resettlement
Safeguards; (c) the RF (for Subprojects); and (d) all measures and requirements set forth in the RIPP, as
appropriate, and any corrective or preventative actions set forth in the Safeguards Monitoring Report.
Being
Complied
5. 13. Without limiting the application of the Involuntary Resettlement Safeguards or the RIPP, the Borrower shall
ensure, or cause NEA to ensure, that no physical or economic displacement takes place in connection with the
Project until:
(a) compensation and other entitlements have been provided to affected people in accordance with the RIPP,
as appropriate; and
(b) a comprehensive income and livelihood restoration program has been established in accordance with the
RIPP, as appropriate.
Being
Complied
5. 14. The Borrower shall ensure, or cause NEA and AEPC to ensure, as applicable, that the preparation, design,
construction, implementation and operation of the Project, each Subproject and all project facilities comply with
(a) all applicable laws and regulations of the Borrower relating to indigenous peoples; (b) the Indigenous
Peoples Safeguards; and (c) the IPPF (for Subprojects); and (d) all measures and requirements set forth in the
RIPP, as appropriate, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.
Being
Complied
Semi-annual Social Monitoring Report January-June, 2019
SASEC-PSEP NEA-ESSD-PSC
Sch. Para
No. Description
Current
Status
5. 15. The Borrower shall ensure that Part 3 of the Project does not have any indigenous peoples or involuntary
resettlement impacts, all within the meaning of SPS. In the event that Part 3 of the Project does have any such
impact, the Borrower shall take all steps to ensure that the Project complies with (a) the applicable laws and
regulations of the Borrower; (b) the SPS; and (c) the IPPF and the RF, as applicable.
Being
Complied
5. 16. The Borrower shall make available, or cause NEA and AEPC to make available, necessary budgetary and
human resources to fully implement the EMP and the RIPP.
Being
Complied
5. 17. The Borrower shall ensure, or cause NEA and AEPC to ensure, that all bidding documents and contracts for
Works contain provisions that require contractors to:
(a) comply with the measures relevant to the contractor set forth in the IEE, the EMP and the RIPP (to the
extent they concern impacts on affected people during construction), and any corrective or preventative actions
set forth in a Safeguards Monitoring Report;
(b) make available a budget for all such environmental and social measures;
(c) provide the Borrower with a written notice of any unanticipated environmental, resettlement or indigenous
peoples risks or impacts that arise during construction, implementation or operation of the Project that were not
considered in the IEE, the EMP and the RIPP;
(d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to
transport materials and construction; and
(e) Reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition
upon the completion of construction.
Being
Complied
5. 18. The Borrower shall do the following or cause NEA and AEPC to do the following:
(a) submit semiannual Safeguards Monitoring Reports to ADB and disclose relevant information from such
reports to affected persons promptly upon submission;
(b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation
or operation of the Project that were not considered in the IEE, the EMP, and the RIPP, promptly inform ADB of
the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action
plan;
(c) report any actual or potential breach of compliance with the measures and requirements set forth in the
EMP and the RIPP promptly after becoming aware of the breach.
Being
Complied